Asphalt pavement structure treated by fog sealing layer

By applying fog seal layer treatment on asphalt pavement, combined with micro-piles and water collection well drainage systems, the problems of drainage system blockage and high construction difficulty are solved, and long-life, low-cost, and low-impact maintenance effects of asphalt roads are achieved.

CN221798045UActive Publication Date: 2024-10-01TIBET TIANSHUN ROAD & BRIDGE ENG CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420271733.8
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-02-04
Publication Date
2024-10-01
Estimated Expiration
2034-02-04

AI Technical Summary

Technical Problem

The existing asphalt pavement drainage system is prone to clogging, construction quality control is difficult and costly, and the micro-surface is prone to spalling.

Method used

The asphalt pavement structure treated with fog seal layer includes cushion layer, base layer and surface layer. Micro piles are set in the base layer, the top layer is coated with emulsified asphalt seal layer, the surface layer is coated with silicon asphalt fog seal layer, water collection wells and drainage holes. Combined with the drainage system, the fog seal layer penetrates into the voids and cracks of the surface layer, and the silicone asphalt has good permeability and adhesion.

Benefits of technology

It extends the service life of asphalt roads, improves the stability and anti-deformation performance of the pavement, reduces traffic impact, reduces later maintenance costs, enhances sealing performance, and prevents damage to the pavement caused by water accumulation.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221798045U_ABST
    Figure CN221798045U_ABST
Patent Text Reader

Abstract

The asphalt pavement structure treated by the fog sealing layer comprises a cushion layer, a base layer and a surface layer, micro piles are arranged in the base layer at intervals; the top surface of the base layer is coated with an emulsified asphalt seal layer; the top surface of the surface layer is fully coated with a fog sealing layer; the fog sealing layer is made of silicon asphalt and permeates into gaps and / or cracks and / or capillary pores of the surface layer; water-collecting wells are respectively arranged at the top of the cushion layer and on two sides of the base layer and the surface layer at intervals; drain pipes are connected between the lower parts of adjacent water-collecting wells in the longitudinal axial direction of the road and between the lower parts of corresponding water-collecting wells in the transverse axial direction of the road; a strip-shaped base is mounted on the base layer on the outer side of the water collecting well; a strip-shaped mounting opening is formed in one side, close to the road center line, of the strip-shaped base; concrete vertical road teeth are mounted at the strip-shaped mounting openings; drainage hole channels are formed in the concrete vertical road teeth at intervals. The utility model solves the technical problems that the traditional drainage system is easy to block, the drainage is not timely, the construction quality control difficulty is high, the construction cost is high and the micro-surfacing is easy to peel off due to the adoption of an ultra-thin wearing layer in an asphalt pavement structure.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model belongs to the technical field of building engineering, in particular to an asphalt pavement structure treated with a fog seal layer. Background Art

[0002] During the use of asphalt pavement, under the combined effects of vehicle wheel load and rain, the asphalt in the asphalt mixture gradually ages and its adhesion decreases, and the road surface is prone to looseness, potholes, etc. On the other hand, if the road construction quality is not well controlled and the compaction is insufficient, the road surface will be damaged prematurely; if the road drainage is not timely, it will also cause damage inside, etc. If the above-mentioned diseases are not handled in time, the road performance will decline rapidly, greatly shortening the service life of the road.

[0003] Therefore, asphalt concrete roads must have a reasonable drainage system and effective preventive maintenance measures. The existing road drainage system is particularly prone to blockage. Once the drainage channel is blocked, it will affect the drainage effect and cause rapid water accumulation. Preventive maintenance measures include ultra-thin wear layer, micro-surfacing, fog seal layer, etc. Among them, the ultra-thin wear layer has the best actual application effect, but there are problems such as difficulty in construction quality control and high project cost. It is suitable for situations where the surface damage is relatively serious; the micro-surfacing project cost is slightly lower, but it is prone to peeling. Utility Model Content

[0004] The purpose of the utility model is to provide an asphalt pavement structure treated with a fog seal layer, in order to solve the technical problems that the traditional drainage system is easy to be blocked, the drainage is not timely, the asphalt pavement structure uses an ultra-thin wearing layer, the construction quality control is difficult, the project cost is high, and the micro-surface is prone to peeling.

[0005] To achieve the above purpose, the utility model adopts the following technical solutions.

[0006] An asphalt pavement structure treated with a fog seal layer comprises a cushion layer, a base layer and a surface layer which are arranged in sequence from bottom to top; the cushion layer is laid on a soil base; the base layer is paved with cement-stabilized graded crushed stone, and micro piles are arranged at intervals in the base layer; a gap is left between the bottom of the micro pile and the bottom surface of the base layer, and a gap is left between the top of the micro pile and the top surface of the base layer; an emulsified asphalt seal layer is applied to the top surface of the base layer; the surface layer is laid above the base layer; a fog seal layer is fully applied on the top surface of the surface layer; the fog seal layer is made of silicon asphalt, and the fog seal layer penetrates into the gaps and / or cracks and / or pores of the surface layer; water collection wells are arranged at intervals on the top of the cushion layer and on both sides of the base layer and the surface layer along the longitudinal axis of the road; the top of the water collection well is aligned with the top surface of the surface layer Adaptable, a grille manhole cover is installed at the wellhead of the water collection well; drainage pipes are connected between the lower parts of the water collection wells adjacent to each other in the longitudinal direction of the road and between the lower parts of the water collection wells corresponding to each other in the transverse direction of the road; a strip base is installed on the base layer outside the water collection well; the strip base is arranged along the longitudinal direction of the road, and the top surface of the strip base does not exceed the top surface of the surface layer; a strip installation opening is opened on the side of the strip base close to the center line of the road; a concrete curb is installed at the strip installation opening; the top surface of the concrete curb exceeds the top of the surface layer, and drainage channels are spaced apart along the longitudinal direction of the road on the concrete curb at a position corresponding to the top of the surface layer; the drainage channels are staggered with the water collection well, and the drainage channels guide the accumulated water on the surface layer into the green belt arranged outside the road surface.

[0007] Preferably, the cushion layer is paved with cement-stabilized stone chips, and the thickness of the cushion layer is not less than 20 cm.

[0008] Preferably, the surface layer includes a lower layer, a middle surface layer and an upper layer arranged in sequence from bottom to top; the lower layer is laid on the emulsified asphalt sealing layer, and the thickness of the lower layer is not less than 7 cm; a lower emulsified asphalt tack coat oil layer is coated on the top of the lower layer; the middle surface layer is laid on the lower emulsified asphalt tack coat oil layer, and the thickness of the middle surface layer is not less than 6 cm; an upper emulsified asphalt tack coat oil layer is coated on the top of the middle surface layer; the upper layer is laid on the upper emulsified asphalt tack coat oil layer.

[0009] Preferably, the base layer is paved with cement-stabilized graded gravel, and the thickness of the base layer is not less than 25 cm.

[0010] Preferably, the micro pile is prefabricated, and a steel cage is arranged inside the micro pile.

[0011] Preferably, the top surface of the fog seal layer is provided with a transverse slope to guide the surface water on the road into the water collection well and / or drainage channel.

[0012] Compared with the prior art, the utility model has the following characteristics and beneficial effects.

[0013] 1. The utility model sprays a layer of asphalt pavement curing agent evenly on the asphalt pavement, which can seal the fine cracks inside the asphalt on the one hand, and improve the activity of asphalt in asphalt concrete on the other hand, increase the bonding force between concrete aggregates, and achieve the purpose of extending the service life of the asphalt pavement. It is most suitable for early implementation of asphalt pavement aging, and has the advantages of low engineering cost and good application effect. In addition, the fog seal layer is simple to construct, and can be constructed at room temperature, even at 0℃, and can be used in both cold and hot climates. Traffic can be opened 2-3 hours after construction, and the impact on traffic is small.

[0014] 2. The utility model arranges a mist seal layer on the top of the surface layer. The silicone asphalt of the mist seal layer has good wettability with the asphalt mixture, does not form a film on the road surface, and can quickly penetrate into the mixture. Under normal circumstances, the penetration depth can reach more than 4 cm. On the one hand, it can increase the adhesion of the aggregate in the asphalt mixture, and on the other hand, it can effectively fill the fine cracks and partial gaps between the aggregates to achieve a water-tightening effect. The road surface can resist the erosion of gasoline, water and other chemicals, and the protective effect is more significant for roads such as airport runways that are easily damaged by fuel.

[0015] 3. The utility model sets a layer of fog seal on the top of the surface layer, which not only improves the stability of the road surface, enhances the stability and anti-deformation and distortion performance of asphalt concrete, but also reduces the damage caused by repeated freeze-thaw cycles and reduces the burst damage of pores or gaps caused by wheel movement in a humid environment. In addition, the use of the fog seal can restore the original road surface to a neat matte black appearance, creating a good visual experience for drivers and improving driving safety.

[0016] 4. The utility model sets a layer of fog seal layer on the top of the surface layer. Wear-resistant materials and reducing materials are added to the silicone asphalt of the fog seal layer, and its good permeability and waterproof properties make the original road surface achieve super strong sealing performance. In addition, the fog seal layer can permanently seal the holes, pores and cracks ≤3mm of the asphalt road surface, thereby giving the asphalt road an internal waterproof and moisture-proof mechanism (the water-facing surface and the water-receiving surface). When there is water on the road surface, it can be blocked outside the road surface structure by the fog seal layer, so that the accumulated water flows to the drainage channel or the water well. The combination of blocking and drainage reduces the damage to the road surface caused by accumulated water.

[0017] 5. The utility model arranges micro piles at intervals in the cushion layer, and the micro piles and the cement-stabilized graded gravel of the base layer jointly bear the load transferred from the surface layer, thereby improving the bearing capacity of the base layer. At the same time, the bottom surface of the base layer exceeds the bottom of the micro piles, and the top surface of the base layer exceeds the top surface of the micro piles, so that the load can be evenly transferred from the base layer to the cushion layer, avoiding concentrated load transfer.

[0018] 6. The utility model sets water collection wells on both sides of the road, and sets drainage channels at intervals along the longitudinal axis of the road at the top of the concrete curb corresponding to the surface layer; the double drainage can quickly drain rainwater on the road surface to prevent rainwater from being retained on the road surface to form water accumulation and waterlogging; at the same time, the utility model connects drainage pipes between the lower parts of the water collection wells adjacent to each other in the longitudinal axis of the road and between the lower parts of the water collection wells corresponding to each other in the transverse axis of the road. The water collection wells on both sides of the drainage system are connected, so that the accumulated water in the water collection wells on both sides can be quickly collected. BRIEF DESCRIPTION OF THE DRAWINGS

[0019] The utility model is further described in detail below in conjunction with the accompanying drawings.

[0020] Figure 1 It is a schematic diagram of the cross-sectional structure of the asphalt pavement structure treated with a fog seal layer between adjacent water collection wells of the utility model.

[0021] Figure 2 It is a schematic diagram of the cross-sectional structure of the asphalt pavement structure treated with a fog seal layer at a water collection well of the utility model.

[0022] Figure numbers: 1-cushion, 2-base, 3-surface layer, 3.1-upper layer, 3.2-middle surface layer, 3.3-lower layer, 3.4-lower emulsified asphalt tack layer, 3.5-upper emulsified asphalt tack layer, 4-soil base, 5-micro piles, 6-emulsified asphalt seal layer, 7-mist seal layer, 8-water collection well, 9-grating manhole cover, 10-drainage pipe, 11-strip base, 12-strip installation port, 13-concrete curb, 14-drainage duct, 15-green belt, 16-cement mortar undercover. DETAILED DESCRIPTION

[0023] like Figure 1-2As shown, the asphalt pavement structure treated with a fog seal layer comprises a cushion layer 1, a base layer 2 and a surface layer 3 arranged in sequence from bottom to top; the cushion layer 1 is laid on a soil base 4; the base layer 2 is paved with cement-stabilized graded crushed stone, and micro piles 5 are arranged at intervals in the base layer 2; a spacing is left between the bottom of the micro pile 5 and the bottom surface of the base layer 2, and a spacing is left between the top of the micro pile 5 and the top surface of the base layer 2; an emulsified asphalt seal layer 6 is applied to the top surface of the base layer 2; the surface layer 3 is laid on top of the base layer 2; a fog seal layer 7 is fully applied on the top surface of the surface layer 3; the fog seal layer 7 is made of silicone asphalt, and the fog seal layer 7 penetrates into the gaps and / or cracks and / or pores of the surface layer 3; water collection wells 8 are arranged at intervals along the longitudinal axis of the road on the top of the cushion layer 1 and on both sides of the base layer 2 and the surface layer 3; the top of the water collection well 8 is adapted to the top surface of the surface layer 3, and a grid is installed at the wellhead of the water collection well 8 A grating manhole cover 9; a drainage pipe 10 is connected between the lower parts of the water collection wells 8 adjacent to each other in the longitudinal direction of the road and between the lower parts of the water collection wells 8 corresponding to each other in the transverse direction of the road; a strip base 11 is installed on the base layer 2 outside the water collection well 8; the strip base 11 is arranged along the longitudinal direction of the road, and the top surface of the strip base 11 does not exceed the top surface of the surface layer 3; a strip installation opening 12 is opened on the side of the strip base 11 close to the center line of the road; a concrete curb 13 is installed in the strip installation opening 12; the top surface of the concrete curb 13 exceeds the top of the surface layer 3, and drainage channels 14 are arranged at intervals along the longitudinal direction of the road at the position corresponding to the top of the surface layer 3, and a cement mortar undercover 16 is arranged at the bottom of the concrete curb 13; the drainage channel 14 is staggered with the water collection well 8, and the drainage channel 14 guides the accumulated water on the surface layer 3 into the green belt 15 arranged outside the road surface.

[0024] In this embodiment, the cushion layer 1 is paved with cement-stabilized stone chips, and the thickness of the cushion layer 1 is not less than 20 cm.

[0025] In this embodiment, the surface layer 3 includes a lower layer 3.3, a middle surface layer 3.2 and an upper layer 3.1 which are arranged in sequence from bottom to top; the lower layer 3.3 is laid on the emulsified asphalt sealing layer 6, and the thickness of the lower layer 3.3 is not less than 7 cm; a lower emulsified asphalt tack coat oil layer 3.4 is coated on the top of the lower layer 3.3; the middle surface layer 3.2 is laid on the lower emulsified asphalt tack coat oil layer 3.4, and the thickness of the middle surface layer 3.2 is not less than 6 cm; an upper emulsified asphalt tack coat oil layer 3.5 is coated on the top of the middle surface layer 3.2; the upper layer 3.1 is laid on the upper emulsified asphalt tack coat oil layer 3.5.

[0026] In this embodiment, the base layer 2 is paved with cement-stabilized graded crushed stones, and the thickness of the base layer 2 is not less than 25 cm.

[0027] In this embodiment, the micro pile 5 is prefabricated, a steel cage is arranged inside the micro pile 5, and the micro pile 5 is arranged in a plum blossom shape or a rectangular shape.

[0028] In this embodiment, the top surface of the fog seal layer 7 is provided with a transverse slope to guide the road surface water into the water collection well 8 and / or the drainage channel 14. The fog seal layer 7 is applied on the surface layer around the grille manhole cover 9 on both sides of the road.

[0029] In this embodiment, the base layer 2 is laid in layers, the bottom of the micro pile 5 is supported on the cement stabilized graded gravel laid in the lowest layer, and the distance between the top of the micro pile 5 and the top surface of the base layer 2 is adapted to the thickness of the cement stabilized graded gravel laid in the uppermost layer.

[0030] In this embodiment, the base layer 2 uses 4% cement stabilized stone chips, and the compaction degree of the base layer 2 is not less than 96%; the cushion layer 1 uses 5% cement stabilized graded crushed stone, and the compaction degree of the cushion layer 1 is not less than 98%, and the emulsified asphalt sealing layer 6 on the top of the base layer 2 is 1 cm thick.

[0031] In this embodiment, a micropile 5 is also provided at the bottom of the strip base 11; a strip base 11 and a concrete curb 13 are also provided on the side of the green belt 15 away from the road, and the bottom of the concrete curb 13 on this side is also provided with the cement mortar underlay 16.

[0032] In this embodiment, the silicon asphalt used in the fog seal layer 7 is mainly composed of four components, namely two main components and two important additive components. One main component is a hard asphalt-based material treated by a special process, and the other main component is an organic silicon polymer with a composite active ingredient. One additive component is a refined aromatic compound, and the other additive component is a special surfactant with independent intellectual property rights.

[0033] The hard asphalt component in the silicone asphalt of the fog seal layer 7 has good aging resistance, good compatibility with the asphalt in the mixture, and good viscosity and toughness, and can effectively seal fine cracks in the asphalt mixture. The active silicone polymer component in the silicone asphalt of the fog seal layer 7 has high viscosity and strong hydrophobicity, and at the same time, the molecular group is small, which can directly infiltrate into the interior of the asphalt material. On the one hand, silicone improves the adhesion between the components of the asphalt road, which can effectively reduce the separation of the asphalt mixture and the loosening caused by the presence of moisture, and significantly improves the stability and anti-distortion performance of the asphalt pavement. Therefore, the use of silicone asphalt can effectively extend the service life of the asphalt road and greatly reduce the subsequent maintenance costs of the road. The aromatic compounds added to the silicone asphalt of the fog seal layer 7 can supplement the oxidized aromatic components in the original asphalt to effectively improve the activity of the asphalt. The surfactant added to the silicone asphalt of the mist seal layer 7 greatly reduces the surface tension of the curing agent, making the material have better permeability and compatibility with the original asphalt, so that the curing agent can enter the asphalt oil film wrapped around the aggregate, and then give full play to its high viscosity, hydrophobicity, reduction and other effects, fundamentally improving the adhesion between aggregates in the mixture.

[0034] The above embodiments are not exhaustive of specific implementation methods, and there may be other embodiments. The purpose of the above embodiments is to illustrate the utility model rather than to limit the protection scope of the utility model. All applications derived from simple changes of the utility model fall within the protection scope of the utility model.

Claims

1. An asphalt pavement structure treated with a fog seal layer, comprising a cushion layer (1), a base layer (2) and a surface layer (3) arranged in sequence from bottom to top; the cushion layer (1) is laid on a soil base (4); characterized in that: The base layer (2) is paved with cement-stabilized graded crushed stone, and micro piles (5) are arranged at intervals in the base layer (2); a distance is left between the bottom of the micro pile (5) and the bottom surface of the base layer (2), and a distance is left between the top of the micro pile (5) and the top surface of the base layer (2); an emulsified asphalt sealing layer (6) is applied on the top surface of the base layer (2); the surface layer (3) is paved above the base layer (2); and a fog sealing layer ( 7); the fog seal layer (7) is made of silicon asphalt, and the fog seal layer (7) penetrates into the gaps and / or cracks and / or pores of the surface layer (3); water collection wells (8) are arranged at intervals along the longitudinal axis of the road on the top of the cushion layer (1) and on both sides of the base layer (2) and the surface layer (3); the top of the water collection well (8) is adapted to the top surface of the surface layer (3), and a grille manhole cover (9) is installed at the wellhead of the water collection well (8); the water collection wells (8) adjacent to each other in the longitudinal axis of the road are provided with a grille cover (9); A drainage pipe (10) is connected between the lower parts of the wells (8) and between the lower parts of the water collecting wells (8) corresponding to the road transverse axis; a strip base (11) is installed on the base layer (2) outside the water collecting well (8); the strip base (11) is arranged along the longitudinal axis of the road, and the top surface of the strip base (11) does not exceed the top surface of the surface layer (3); a strip installation opening (12) is opened on the side of the strip base (11) close to the center line of the road; The opening (12) is provided with a concrete curb (13); the top surface of the concrete curb (13) exceeds the top of the surface layer (3); drainage holes (14) are provided on the concrete curb (13) at positions corresponding to the top of the surface layer (3) along the longitudinal axis of the road; the drainage holes (14) are arranged in a staggered manner with the water collection well (8), and the drainage holes (14) guide the accumulated water on the surface layer (3) into a green belt (15) arranged outside the road surface.

2. The asphalt pavement structure treated with a fog seal layer according to claim 1, characterized in that: The cushion layer (1) is paved with cement-stabilized stone chips, and the thickness of the cushion layer (1) is not less than 20 cm.

3. The asphalt pavement structure treated with a fog seal layer according to claim 1, characterized in that: The surface layer (3) comprises a lower layer (3.3), a middle layer (3.2) and an upper layer (3.1) which are arranged in sequence from bottom to top; the lower layer (3.3) is laid on the emulsified asphalt sealing layer (6), and the thickness of the lower layer (3.3) is not less than 7 cm; a lower emulsified asphalt tack coat oil layer (3.4) is coated on the top of the lower layer (3.3); the middle layer (3.2) is laid on the lower emulsified asphalt tack coat oil layer (3.4), and the thickness of the middle layer (3.2) is not less than 6 cm; an upper emulsified asphalt tack coat oil layer (3.5) is coated on the top of the middle layer (3.2); the upper layer (3.1) is laid on the upper emulsified asphalt tack coat oil layer (3.5).

4. The asphalt pavement structure treated with a fog seal layer according to claim 1, characterized in that: The base layer (2) is paved with cement-stabilized graded crushed stones, and the thickness of the base layer (2) is not less than 25 cm.

5. The asphalt pavement structure treated with a fog seal layer according to claim 1, characterized in that: The micro pile (5) is prefabricated, and a steel cage is arranged inside the micro pile (5).

6. The asphalt pavement structure treated with a fog seal layer according to claim 1, characterized in that: The top surface of the fog seal layer (7) is provided with a transverse slope for guiding the surface water on the road into the water collection well (8) and / or the drainage channel (14).