Fabricated concrete column steel-encased full-bolt-connection replaceable joint

By presetting the outer steel and cantilever beams on the concrete columns, combined with full bolt connections and friction plates, the complex construction and durability problems of traditional concrete column-steel beam connection nodes are solved, and efficient, reliable connections and seismic performance are achieved. Reduced environmental impact.

CN221798714UActive Publication Date: 2024-10-01SHANGHAI KELDE TECHNOLOGY CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420222561.5
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-01-30
Publication Date
2024-10-01
Estimated Expiration
2034-01-30

AI Technical Summary

Technical Problem

The construction of traditional concrete column-steel beam connection nodes is complicated and requires professional technology and equipment. When the nodes are damaged or need to be replaced, it is time-consuming and labor-intensive. There are also problems of stress concentration, corrosion, fatigue and looseness, which affect durability and environmental sustainability.

Method used

The prefabricated concrete columns are wrapped with steel and are fully bolted to connect replaceable nodes. By presetting the wrapped steel and screw rods before pouring the concrete columns, cantilever beams and H-shaped steel are installed after pouring, and full bolted connections and friction plates are used to realize the joints. Strength and earthquake resistance, easy installation and maintenance.

Benefits of technology

It improves the bending resistance and shear resistance of the joint, reduces stress concentration, enhances durability, simplifies construction and maintenance, and meets the requirements of sustainable development.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221798714U_ABST
    Figure CN221798714U_ABST
Patent Text Reader

Abstract

The utility model discloses an assembly type concrete column encased steel full bolt connection replaceable joint which comprises encased steel arranged at the outer end of a reinforcement cage. The screw rod vertically penetrates through the encased steel and the reinforcement cage, and then concrete is poured to fix the encased steel and the reinforcement cage; the cantilever beam is movably mounted on the outer side of the encased steel, sleeves the lead screw and is fixedly connected with the lead screw through a bolt; and the H-shaped steel is fixedly connected with the end part of the cantilever beam through a cover plate assembly and a connecting plate by adopting bolts, and friction plates are arranged between the cover plate assembly and the H-shaped steel as well as between the cover plate assembly and the cantilever beam. The joint is used for rapidly installing the H-shaped steel on the concrete outer column, the bending resistance and shearing resistance of the concrete column can be improved through the encased steel, meanwhile, bolt connection is adopted, and the joint has the advantages of being convenient to disassemble and assemble, reliable in connection and the like.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of construction, in particular to an assembled concrete column with steel-clad exterior and fully bolted connection and replaceable node. Background Art

[0002] Traditional concrete column-steel beam connection nodes usually require on-site welding or bolting. The construction process is complicated and requires professional welding technology and equipment. In addition, the on-site construction time is long, which increases the construction period of the project. At the same time, once the node is damaged or needs to be replaced, the entire node needs to be dismantled and reinstalled, which is time-consuming and labor-intensive, and may cause secondary damage to the surrounding structure. The design of traditional concrete column-steel beam connection nodes may cause stress concentration, among which stress concentration is prone to occur in welding parts such as welds and connecting plates, reducing the strength and stability of the overall node. At the same time, welding or bolting connections are prone to corrosion, fatigue and loosening in welding heat-affected zones, bolt holes and other parts, reducing the durability of the node. The traditional concrete column-steel beam connection nodes require more welding materials and energy consumption, which has a certain impact on the environment and does not meet the requirements of sustainable green development.

[0003] After searching, it was found that the Chinese utility model patent with the patent publication number "CN210529936U" disclosed a steel tube concrete column-I-beam connection node, including a steel tube concrete column, a beam-column node connection block, an I-beam, an I-shaped diagonal support, a connection plate, tension bolts and bolts. The steel tube concrete column-I-beam connection node with strong energy dissipation capacity is connected by an I-beam and a steel tube concrete column through a beam-column node connection block; the I-shaped diagonal support connects the steel tube concrete column on one side and connects the beam-column node connection block and the I-beam on the other side. The steel tube concrete column, I-beam, beam-column node connection block, I-shaped diagonal support and connection plate are all processed with reserved holes to facilitate later connection. The components involved in the utility model can all be prefabricated in the factory, which has the advantages of protecting the environment, improving the quality of components and ensuring the accuracy of components. The beam-column form of the steel tube concrete column and the I-beam adopted in the utility model well meets the requirements of strong columns and weak beams, and has good seismic performance.

[0004] However, this technical solution requires pre-opening multiple connection holes on the steel tube concrete column and the I-shaped steel beam. Since the insertion of bolts generally requires nuts to fix them, when the bolts pass through the connection holes, it is difficult to ensure that the other end of the bolts passes through the concrete column (that is, the length of the bolts cannot fully pass through the steel tube concrete column), resulting in low connection strength. If there are some smaller vibrations (such as earthquakes), it is easy to cause falling off. Utility Model Content

[0005] Therefore, in order to solve the above-mentioned deficiencies, the utility model provides a prefabricated concrete column external steel-clad fully bolted replaceable node, which is achieved by pre-arranging external steel at the outer end of the steel cage and passing through a screw rod before pouring the concrete column. After pouring the concrete, the screw rod on the outside of the external steel can facilitate the installation of H-shaped steel, effectively ensuring the installation strength. At the same time, through the cantilever beam and the cover plate and friction plate connected to the H-shaped steel, the outward movement of the node plastic hinge can be achieved under large earthquake and super-large earthquake conditions, and self-resetting friction energy dissipation can be achieved at the connection between the cantilever extension beam section and the H-shaped steel beam.

[0006] The utility model is implemented by constructing a prefabricated concrete column outer steel-clad fully bolted replaceable node, including outer steel-clad, arranged at the outer end of the steel cage;

[0007] The screw rod vertically penetrates the outer steel and the steel cage and then pours concrete to fix it;

[0008] A cantilever beam is movably mounted on the outside of the outer steel and is sleeved on the outside of the screw rod and fixed by bolts; and

[0009] The H-shaped steel is fixed to the end of the cantilever beam by bolts through a cover plate assembly and a connecting plate, and a friction plate is arranged between the cover plate assembly and the H-shaped steel and between the cover plate assembly and the cantilever beam.

[0010] As described above, in order to improve the bending, shear and other mechanical properties of concrete components, the technical solution adopts the method of external steel cladding to strengthen the outer surface of the concrete column-steel beam connection area. The external steel cladding adopts steel plates, which work together with the concrete columns to improve the overall performance of the node connection area.

[0011] In order to facilitate quick installation and ensure that some parts can be replaced after being damaged by an earthquake, this technical solution uses full bolt connection on the outer end of the outer steel, providing a detachable connection method with the advantages of easy disassembly and assembly and reliable connection.

[0012] Compared with the traditional concrete column-steel beam connection node structure connection technology, the prefabricated concrete column steel-encased full bolt connection has the following advantages:

[0013] Strengthen the core area: The external steel cladding will further strengthen the concrete in the core area to prevent oblique shear failure of the concrete columns at the connection.

[0014] Outward displacement of plastic hinge: The use of all-bolt self-resetting friction energy dissipation connection nodes makes the plastic hinge of the beam-column node appear at the joint of the extended cantilever beam, realizing the outward displacement of the plastic angle of the beam-column node. At the same time, the self-resetting friction energy dissipation improves the seismic performance of the beam-column connection node.

[0015] Reduce stress concentration: Fully bolted connections can disperse the stress at the connection, thereby reducing stress concentration and improving the overall performance and stability of the structure.

[0016] Improved durability: Since the connection nodes are fully bolted, corrosion and fatigue problems in the welding heat affected zone and bolt holes can be reduced, thereby improving the durability of the nodes.

[0017] Easy to maintain and replace: Since the connection nodes are fully bolted, when a component of the node is damaged or needs to be replaced due to an earthquake, it can be repaired and replaced by simply removing the bolts without affecting the structure of other parts.

[0018] Fast construction: The use of precast concrete columns can save on-site construction time and improve construction efficiency.

[0019] Environmentally friendly: Compared with the welding materials and energy consumption required by traditional welding technology, the prefabricated concrete column steel-clad full bolt connection technology has less impact on the environment and is more in line with the requirements of sustainable development. BRIEF DESCRIPTION OF THE DRAWINGS

[0020] The accompanying drawings are used to provide a further understanding of the present invention and constitute a part of the specification. Together with the specific implementation of the present invention, they are used to explain the present invention, but do not constitute any limitation to the present invention. In the accompanying drawings:

[0021] Figure 1 It is a cross-sectional schematic diagram of the utility model;

[0022] Figure 2 It is a schematic diagram of the top view of the outer and inner steel cladding and the screw rod assembly of the utility model;

[0023] Figure 3 It is a schematic diagram of the front view of the outer and inner steel cladding and the screw rod combination of the utility model;

[0024] Figure 4 It is a schematic diagram of the cantilever beam in the utility model in a side view direction;

[0025] Figure 5 It is a schematic diagram of the front view of the combination of the outer steel cladding, the screw rod and the cantilever beam in the utility model;

[0026] Figure 6 It is a schematic diagram of the cantilever beam in the utility model in the front view direction;

[0027] Figure 7 It is a schematic diagram of the friction plate in the utility model when viewed from above;

[0028] Figure 8 It is a schematic diagram of the front view of the connecting plate in the utility model;

[0029] Fig. 9 It is a schematic diagram of the upper cover plate in the utility model when viewed from above;

[0030] Fig.10 It is a schematic diagram of the lower cover plate in the utility model when viewed from above;

[0031] In the figure: 1. Outer steel; 2. Screw rod; 3. Cantilever beam; 4. Upper cover plate; 5. Friction plate; 6. Connecting plate; 7. Lower cover plate; 8. H-shaped steel. DETAILED DESCRIPTION

[0032] The technical solution of the present invention is further described in detail below through specific embodiments and in combination with the accompanying drawings; it should be understood that the implementation methods described herein are only used to illustrate and explain the present invention, and are not intended to limit the present invention in any way; the accompanying drawings in the present invention are only used to assist in the description of the embodiments and to facilitate understanding, and are not intended to limit the present invention in any way.

[0033] It should be noted that the structures, proportions, sizes, etc. illustrated in the drawings of this specification are only used to match the contents disclosed in the specification so that people familiar with this technology can understand and read them, and are not used to limit the conditions under which the present invention can be implemented. Any structural modification, change in proportional relationship or adjustment of size should still fall within the scope of the technical contents disclosed in the present invention without affecting the effects and purposes that can be achieved by the present invention.

[0034] As described in the background technology, most existing concrete columns and beams are fixed together by welding, wherein stress concentration is prone to occur in welding parts such as welds and connecting plates, reducing the strength and stability of the overall node; while some are fixed by bolt connections, which is not convenient for bolt insertion and fixing by nuts, and thus the connection strength cannot be guaranteed.

[0035] Based on the above reasons, Figure 1 As shown, the utility model provides a prefabricated concrete column outer steel-clad fully bolted connection replaceable node, including an outer steel-clad 1, which is arranged at the outer end of the steel cage;

[0036] The screw rod 2 vertically penetrates the outer steel 1 and the steel cage and then pours concrete to fix it;

[0037] A cantilever beam 3 is movably mounted on the outside of the outer steel 1 and is sleeved on the outside of the screw rod 2 and fixed by bolts; and

[0038] The H-shaped steel 8 is fixed to the end of the cantilever beam 3 by bolts through the cover plate assembly and the connecting plate 6. A friction plate 5 is arranged between the cover plate assembly and the H-shaped steel 7 and between the cover plate assembly and the cantilever beam 3.

[0039] As described above, in order to improve the bending, shear and other mechanical properties of concrete components, the technical solution adopts the method of external steel cladding to strengthen the outer surface of the concrete column-steel beam connection area. The external steel cladding adopts steel plates, which work together with the concrete columns to improve the overall performance of the node connection area.

[0040] In order to facilitate quick installation and ensure that some parts can be replaced after being damaged by an earthquake, this technical solution uses full bolt connection on the outer end of the outer steel, providing a detachable connection method with the advantages of easy disassembly and assembly and reliable connection.

[0041] Specifically, the screw rod 2 is tied to the steel cage.

[0042] Specifically, a hole is opened on the surface of the outer steel 1 for inserting the screw rod 2 , and the screw rod 2 is connected to the inner surface of the outer steel 1 by welding.

[0043] The outer steel can be square or round, and the lead screw is a round rod.

[0044] Specifically, the cross-intersecting connection parts of the screw rods 2 are connected by welding.

[0045] Specifically, the cantilever beam 3 is cast steel, and a bolt hole is provided on one end of the cantilever beam 3 for the screw rod 2 to pass through. The other end of the cantilever beam 3 is a flange plate and a web plate, and bolt holes are provided on the flange plate and the web plate for maintaining connection with the cover plate assembly and the connecting plate 6.

[0046] The bolt hole of the cantilever beam 3 passes through the screw rod 2 (the screw rod is provided with an external thread) and is then tightened with a nut.

[0047] Specifically, the connecting plate 6 is a low yield point steel connecting plate, and a concave arc is provided on the outer side surface of the connecting plate 6 at the connection position between the cantilever beam 3 and the H-shaped steel 7.

[0048] Specifically, the cover plate assembly includes an upper cover plate 4 and a lower cover plate 7, which are respectively covered on the upper and lower sides of the flanges of the cantilever beam 3 and the H-shaped steel 8 and connected by bolts. The friction plate 5 is arranged on the contact portion between the cover plate assembly 4 and the cantilever beam 3 and the H-shaped steel 8.

[0049] The cantilever beam 3 and the H-shaped steel 8 are connected through the connecting plate 6, the cover plate assembly, and the friction plate 5 through a high-strength bolt pair, wherein the upper cover plate 4 is respectively located on the outer sides of the upper and lower flanges of the splicing, and the order of the components at the splicing is the upper cover plate 4, the friction plate 5, the upper flange of the cantilever beam 3 and the H-shaped steel 8, the lower cover plate 8, the web of the cantilever beam 3 and the H-shaped steel 8, the middle section of the cantilever beam 3 and the H-shaped steel 8 is connected through the connecting plate 6 and a high-strength bolt pair, and the lower end part is similar to the above-mentioned splicing order.

[0050] Specifically, a circular hole is respectively opened on one side of the upper cover plate 4 and the friction plate 5, and the circular hole position corresponds to the H-shaped steel 8, and an oblong hole is opened on the other side, and the oblong hole position corresponds to the cantilever beam 3. The lower cover plate 4 is evenly provided with circular holes connected to the cantilever beam 3 and the H-shaped steel 8.

[0051] Specifically, the friction plate 5 is built with SMA shape memory alloy.

[0052] The purpose of the above two paragraphs is to improve the mechanical properties, stability and reliability of the prefabricated concrete column-H-beam connection node under earthquake action, reduce the risk of structural collapse and damage under earthquake action, and realize the functions of plastic hinge outward movement, centralized controllable node damage, and recoverable friction energy consumption. Among them, the upper cover plate and the lower cover plate at the connection between the cantilever beam 3 and the H-shaped steel 8 are connected by an oblong hole on one side and a single circular hole on the other side. At the same time, a friction plate 5 with built-in SMA shape memory alloy is provided between the upper and lower flanges and the cover plate at the connection. This design aims to realize the outward movement of the node plastic hinge under large and super-large earthquake conditions, and realize self-resetting friction energy consumption at the connection between the cantilever beam and the H-beam. Thereby improving the seismic performance of the entire beam-column connection node, increasing the toughness and stability of the structure, and realizing the functions of controllable node damage and easy replacement after an earthquake.

[0053] Method of use: First, the outer steel 1, screw rod 2 and concrete steel cage need to be tied and positioned, and then concrete is poured. After completion, the cantilever beam 3 is placed on the outer end of the screw rod 2 and then in contact with the outer steel 1 and the bolts are initially tightened. Next, the H-shaped steel 8 is connected to the cantilever beam 3 through the connecting plate 6, friction plate 5, upper cover plate 4 and lower cover plate 7 using high-strength bolt pairs. Under the action of small and medium earthquakes, the joint between the cantilever beam 3 and the H-shaped steel 8 is in the elastic stage, and the internal shear force is transmitted through the web connection, and the bending moment is transmitted through the upper and lower flange cover plate connection. Under the action of large and super-large earthquakes, a plastic hinge is formed at the joint between the cantilever beam 3 and the H-shaped steel 8. At this time, the connecting plate 6 is damaged, and the upper cover plate 4 connection has relative slippage, dissipating the seismic energy, reducing the seismic response of the overall structure, and thus improving the mechanical properties of the node. At the same time, the outer steel 1 and screw rod 2 strengthen the strength of the core node area of ​​the concrete column to prevent the concrete from being damaged by oblique shear under large and super-large earthquakes.

[0054] Since this technical solution adopts full bolt connection, it is easy to install and disassemble. The outer steel will further strengthen the concrete in the core area to prevent oblique shear failure of the concrete column at the connection. The use of full bolt self-resetting friction energy dissipation connection nodes makes the plastic hinge of the beam-column node appear at the splicing of the extended cantilever beam, realizing the outward displacement of the plastic angle of the beam-column node. At the same time, the self-resetting friction energy dissipation improves the seismic performance of the beam-column connection node. The full bolt connection can disperse the stress at the connection, thereby reducing stress concentration and improving the overall performance and stability of the structure.

[0055] The above description is a detailed description of the preferred feasible embodiment of the utility model, but the embodiment is not used to limit the scope of the patent application of the utility model. All equivalent changes or modified changes completed under the technical spirit suggested by the utility model should fall within the patent scope covered by the utility model.

Claims

1. A replaceable node of an assembled concrete column with steel-clad all-bolt connection, characterized in that: include External steel, set at the outer end of the steel cage; The screw rod vertically penetrates the outer steel and the steel cage and then pours concrete to fix it; A cantilever beam is movably mounted on the outside of the outer steel and is sleeved on the outside of the screw rod and fixed by bolts; and The H-shaped steel is fixed to the end of the cantilever beam by bolts through a cover plate assembly and a connecting plate, and a friction plate is arranged between the cover plate assembly and the H-shaped steel and between the cover plate assembly and the cantilever beam.

2. According to claim 1, a prefabricated concrete column steel-clad fully bolted replaceable node is characterized by: The screw rod is tied to the steel cage.

3. According to claim 1, a prefabricated concrete column steel-clad fully bolted replaceable node is characterized by: The surface of the outer steel cladding is provided with a hole for inserting a screw rod, and the screw rod is connected to the inner surface of the outer steel cladding by welding.

4. According to claim 1, a prefabricated concrete column steel-clad fully bolted replaceable node is characterized by: The cross-intersecting connection parts of the screw rods are connected by welding.

5. According to claim 1, the assembled concrete column steel-clad fully bolted replaceable node is characterized by: The cantilever beam is cast steel, and a bolt hole is provided on one end of the cantilever beam for the screw rod to pass through. The other end of the cantilever beam is a flange plate and a web plate, and bolt holes are provided on the flange plate and the web plate for maintaining connection with the cover plate assembly and the connecting plate.

6. According to claim 1, a prefabricated concrete column steel-clad fully bolted replaceable node is characterized by: The connecting plate is a low yield point steel connecting plate, and a concave arc is arranged on the outer side surface of the connecting plate at the connection position between the cantilever beam and the H-shaped steel.

7. According to claim 1, a prefabricated concrete column steel-clad fully bolted replaceable node is characterized by: The cover plate assembly includes an upper cover plate and a lower cover plate, which are respectively covered on the upper and lower sides of the flanges of the cantilever beam and the H-shaped steel and connected by bolts. The friction plate is arranged on the contact position between the cover plate assembly and the cantilever beam and the H-shaped steel.

8. According to claim 7, a prefabricated concrete column steel-clad fully bolted replaceable node is characterized by: The upper cover plate and the friction plate are respectively provided with circular holes on one side, the circular holes corresponding to the H-shaped steel, and oblong holes corresponding to the cantilever beams on the other side. The lower cover plate is evenly provided with circular holes connected to the cantilever beams and the H-shaped steels.