Hot air device and coating machine with same

By installing a drainage mechanism in the hot air device of the coating machine, the problem of condensed water accumulation in the steam pipe is solved, the steam quality and the accuracy of the pressure gauge are improved, the preheating time is shortened, and the practicality of the hot air device is improved.

CN221814709UActive Publication Date: 2024-10-11YABAO PHARMA GRP CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202323265565.6
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-11-30
Publication Date
2024-10-11
Estimated Expiration
2033-11-30

AI Technical Summary

Technical Problem

During the shutdown period of the existing coating machine, condensation water is easily formed in the steam pipe, resulting in low steam quality, easy adhesion of the drug, long preheating time, and inaccurate pressure gauge readings, which affects the practicality of the hot air device.

Method used

A hot air device is designed, including a hot air cabinet and a drainage mechanism. By arranging a first valve body and a second valve body at the steam inlet, the accumulated water is discharged to the condensation pool when the steam flows, thereby increasing the steam saturation, and before starting the machine. Drainage, reduce water hammer, improve steam quality and pressure gauge accuracy.

Benefits of technology

It effectively improves the steam quality, shortens the preheating time of the hot air device, reduces the number of defective products, avoids the problem of inaccurate pressure gauge readings, and improves the practicality of the hot air device.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221814709U_ABST
    Figure CN221814709U_ABST
Patent Text Reader

Abstract

The utility model belongs to the technical field of coating machines, and particularly discloses a hot air device and a coating machine with the same. In the hot air device, a steam inlet of a hot air cabinet is communicated with a steam source through a first pipe fitting, so that steam can be transmitted into the hot air cabinet from the steam source; the communicating position of the second pipe fitting and the first pipe fitting is arranged on the side, away from the hot air cabinet, of the first valve body, the second valve body is installed on the first pipe fitting, the first valve body is closed, the second valve body is opened before the hot air cabinet works, accumulated water in the first pipe fitting can be discharged into the second pipe fitting in the flowing process of steam, the steam quality is improved, and the service life of the hot air cabinet is prolonged. The preheating and preparation time of air in the hot air cabinet before the coating machine body is started is shortened, the number of defective products is reduced, in addition, the water hammer phenomenon occurring when the water content in the first pipe fitting is large can be avoided, the phenomenon that reading is inaccurate when a meter hand of a pressure meter abnormally swings is avoided, and the coating machine quality is improved. And the practicability of the hot air device is effectively improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of coating machines, in particular to a hot air device and a coating machine having the same. Background Art

[0002] The coating machine is an efficient, energy-saving, safe and clean mechatronic equipment for coating Chinese and Western medicines, tablets, pills, micropellets, small pills, water pills, dripping pills, granule pills, etc. with sugar coating, organic film coating, water-soluble film coating, and slow-release and controlled-release coating. The coating machine is widely used in the pharmaceutical, chemical, food and other industries.

[0003] The existing coating machines in the pharmaceutical industry are mainly composed of a coating machine body, a hot air device and an exhaust device. The air inlet of the hot air cabinet in the hot air device is connected to the steam source, so that the steam can enter the hot air cabinet to heat the air, thereby generating hot air. The air outlet of the hot air cabinet is connected to the air inlet of the coating machine body, so that the hot air can enter the coating machine body to carry out the coating drying operation. The air inlet of the exhaust cabinet in the exhaust device is connected to the air outlet of the coating machine body, so that the hot air can be recovered after completing the coating process.

[0004] However, during the period when the coating machine is shut down, condensation water is likely to form inside the pipes containing steam in the hot air device and accumulate inside the pipes, resulting in a low saturation of the steam used to heat the air, that is, a low steam quality. When this part of the steam enters the coating machine body for drug coating operations, it is likely to cause the drugs to stick, become cottony, or even become scrapped. In addition, water hammer is likely to occur in the steam pipe, causing the needle of the pressure gauge to swing abnormally. At the same time, due to the low steam quality, the preheating time of the hot air cabinet is longer, resulting in insufficient practicality of the hot air device. Utility Model Content

[0005] Therefore, the technical problem to be solved by the utility model is that in the prior art, condensed water is easily formed inside the pipeline during the shutdown of the coating machine, which affects the effect of drug coating, causes the needle of the pressure gauge to swing abnormally, and easily prolongs the preheating time, resulting in insufficient practicality of the hot air device.

[0006] To this end, the utility model provides a hot air device, comprising:

[0007] A hot air mechanism, the hot air mechanism comprising a hot air cabinet and a first valve body, the hot air cabinet is provided with a steam inlet, the steam inlet is connected to a steam source through a first pipe, the first valve body is installed on the first pipe, and the first valve body is arranged close to the steam inlet;

[0008] The first drainage mechanism includes a second pipe fitting and a second valve body, one end of the second pipe fitting is connected to the first pipe fitting, and the connecting point is arranged on a side of the first valve body away from the hot air cabinet, the other end of the second pipe fitting is connected to the condensation water pool, and the second valve body is installed on the second pipe fitting.

[0009] Optionally, the above-mentioned hot air device further includes:

[0010] A third valve body is installed on the first pipe fitting, and the third valve body is arranged on a side of the connection between the second pipe fitting and the first pipe fitting away from the first valve body.

[0011] Optionally, the above-mentioned hot air device further includes:

[0012] A pressure detection component is installed on the first pipe, and the pressure detection component is located on a side of the third valve body away from the hot air cabinet.

[0013] Optionally, the hot air device mentioned above,

[0014] The pressure detection component is selected as an electric contact pressure gauge, and the electric contact pressure gauge is communicatively connected with the controller.

[0015] Optionally, the hot air device mentioned above,

[0016] The hot air cabinet also includes a condensed water outlet;

[0017] The hot air device also includes a second drainage mechanism, which includes a third pipe fitting and a fourth valve body. Both ends of the third pipe fitting are respectively connected to the condensate outlet and the condensate pool, and the fourth valve body is installed on the third pipe fitting.

[0018] Optionally, the hot air device mentioned above,

[0019] The condensed water outlet and the steam inlet are both arranged on the top of the hot air cabinet along the height direction.

[0020] Optionally, the hot air device mentioned above,

[0021] The fourth valve body is selected as a steam trap.

[0022] Optionally, the hot air device mentioned above,

[0023] The second drainage mechanism further includes a fifth valve body, which is installed on the third pipe member and is arranged in parallel with the steam trap.

[0024] Optionally, the hot air device mentioned above,

[0025] The first valve body and the second valve body are selected as stop valves.

[0026] A coating machine comprises the above-mentioned hot air device.

[0027] The technical solution provided by the utility model has the following advantages:

[0028] The utility model provides a hot air device, which includes a hot air mechanism and a first drainage mechanism. The hot air mechanism includes a hot air cabinet and a first valve body, the hot air cabinet is provided with a steam inlet, the steam inlet is connected to a steam source through a first pipe, the first valve body is installed on the first pipe, and the first valve body is arranged close to the steam inlet; the first drainage mechanism includes a second pipe and a second valve body, one end of the second pipe is connected to the first pipe, and the connection point is arranged on a side of the first valve body away from the hot air cabinet, the other end of the second pipe is connected to a condensed water pool, and the second valve body is installed on the second pipe.

[0029] The hot air device of this structure uses a first pipe fitting to connect the steam inlet of the hot air cabinet with the steam source, so that steam can be transmitted from the steam source to the inside of the hot air cabinet; by adding a second pipe fitting and a second valve body, specifically, by setting the connection point between the second pipe fitting and the first pipe fitting on the side of the first valve body away from the hot air cabinet, the second valve body is installed on the first pipe fitting, and the first valve body is closed and the second valve body is opened before the hot air cabinet works. During the flow of steam, the accumulated water inside the first pipe fitting can be discharged into the second pipe fitting, thereby improving the saturation of steam that subsequently enters the hot air cabinet, that is, improving the steam quality, reducing the preheating time and preparation time of the air in the hot air cabinet before the coating machine body is started, and at the same time, the number of defective products obtained after coating can be reduced. In addition, the water hammer phenomenon that occurs when the water content in the first pipe fitting is high can be avoided, thereby avoiding the phenomenon of inaccurate readings caused by abnormal swing of the pressure gauge needle, effectively improving the practicality of the hot air device. BRIEF DESCRIPTION OF THE DRAWINGS

[0030] In order to more clearly illustrate the specific implementation methods of the utility model or the technical solutions in the prior art, the drawings required for use in the specific implementation methods or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are some implementation methods of the utility model. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0031] Figure 1 A schematic diagram of the structure of a hot air device provided in an embodiment of the utility model;

[0032] Description of reference numerals:

[0033] 11-hot air cabinet; 111-steam inlet; 112-condensate outlet; 12-first valve body; 13-first pipe fitting;

[0034] 21-second pipe fitting; 22-second valve body;

[0035] 31-third valve body; 32-pressure detection member;

[0036] 41-third pipe fitting; 42-fourth valve body; 43-fifth valve body;

[0037] 51-steam source; 52-condensation water pool. DETAILED DESCRIPTION

[0038] The technical solution of the utility model will be described clearly and completely below in conjunction with the accompanying drawings. Obviously, the described embodiments are part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments of the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0039] In the description of the present invention, it should be noted that the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer", etc., indicating the orientation or positional relationship, are based on the orientation or positional relationship shown in the drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as limiting the present invention. In addition, the terms "first", "second", and "third" are used for descriptive purposes only, and cannot be understood as indicating or implying relative importance.

[0040] In the description of the present invention, it should be noted that, unless otherwise clearly specified and limited, the terms "installation", "connection" and "connection" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0041] In addition, the technical features involved in the different embodiments of the present invention described below can be combined with each other as long as they do not conflict with each other.

[0042] Example 1

[0043] This embodiment provides a hot air device, such as Figure 1, including a hot air mechanism and a first drainage mechanism. The hot air mechanism includes a hot air cabinet 11 and a first valve body 12. The hot air cabinet 11 is provided with a steam inlet 111, which is connected to a steam source 51 through a first pipe 13. The first valve body 12 is installed on the first pipe 13 and is arranged close to the steam inlet 111. The first drainage mechanism includes a second pipe 21 and a second valve body 22. One end of the second pipe 21 is connected to the first pipe 13, and the connection point is arranged on a side of the first valve body 12 away from the hot air cabinet 11. The other end of the second pipe 21 is connected to the condensation water pool 52, and the second valve body 22 is installed on the second pipe 21.

[0044] The hot air device of this structure uses the first pipe 13 to connect the steam inlet 111 of the hot air cabinet 11 with the steam source 51, so that the steam can be transmitted from the steam source 51 to the inside of the hot air cabinet 11; by adding the second pipe 21 and the second valve body 22, specifically, by setting the connecting point between the second pipe 21 and the first pipe 13 on the side of the first valve body 12 away from the hot air cabinet 11, installing the second valve body 22 on the first pipe 13, closing the first valve body 12 and opening the second valve body 22 before the hot air cabinet 11 works, and steam flows in the process of The accumulated water inside the first pipe fitting 13 can be discharged into the second pipe fitting 21, thereby improving the saturation of steam entering the hot air cabinet 11 later, that is, improving the steam quality, reducing the preheating time and preparation time of the air in the hot air cabinet 11 before starting the coating machine body, and at the same time reducing the number of defective products obtained after coating. In addition, the water hammer phenomenon that occurs when the water content in the first pipe fitting 13 is high can be avoided, thereby avoiding the phenomenon of inaccurate readings caused by abnormal swinging of the needle of the pressure gauge, and effectively improving the practicality of the hot air device.

[0045] The hot air device provided in this embodiment is as follows: Figure 1 As shown, the third valve body 31 is also included. At this time, the third valve body 31 is installed on the first pipe 13, and the third valve body 31 is arranged at a side of the connection between the second pipe 21 and the first pipe 13 away from the first valve body 12.

[0046] It can be explained that the hot air device provided in this embodiment further includes a pressure detection member 32. The pressure detection member 32 is installed on the first pipe member 13, and the pressure detection member 32 is located on a side of the third valve body 31 away from the hot air cabinet 11.

[0047] Furthermore, in this embodiment, there is no limitation on the type of the pressure detection member 32. In order to warn the operator in time, the pressure detection member 32 is selected as an electric contact pressure gauge, which is connected to the controller for communication, and the controller is also connected to an early warning member such as an audible and visual alarm. At this time, the electric contact pressure gauge converts the measured pressure inside the first pipe member 13 into a pressure signal and transmits it to the controller. After receiving the pressure signal, the controller converts it into an early warning signal and transmits it to the audible and visual alarm, so that the audible and visual alarm prompts the operator in terms of sound and brightness.

[0048] The hot air device provided in this embodiment is as follows: Figure 1 As shown, the hot air cabinet 11 also includes a condensate outlet 112; the hot air device also includes a second drainage mechanism, the second drainage mechanism includes a third pipe fitting 41 and a fourth valve body 42, the two ends of the third pipe fitting 41 are respectively connected to the condensate outlet 112 and the condensate pool 52, and the fourth valve body 42 is installed on the third pipe fitting 41.

[0049] It can be explained that, in the hot air device provided in this embodiment, the condensed water outlet 112 and the steam inlet 111 are both arranged at the top of the hot air cabinet 11 along the height direction.

[0050] It can be explained that, in the hot air device provided in this embodiment, the fourth valve body 42 is selected as a steam trap, specifically a lever float type steam trap.

[0051] It can be explained that, in the hot air device provided in this embodiment, the second drainage mechanism further includes a fifth valve body 43, the fifth valve body 43 is installed on the third pipe 41, and the fifth valve body 43 is arranged in parallel with the drain valve.

[0052] The hot air device provided in this embodiment is as follows: Figure 1 As shown, the first valve body 12 and the second valve body 22 are selected as stop valves, and the fifth valve body 43 is selected as a stop valve, so as to facilitate the adjustment of the opening degree of each pipe fitting.

[0053] The hot air device provided in the above embodiment can close the first valve body 12 and open the second valve body 22 before starting the coating machine, and then open the air outlet of the steam source 51, that is, after opening the coating steam valve, use the steam flow to transfer the accumulated water inside the first pipe fitting 13 to the second pipe fitting 21, and then discharge it to the condensation water pool 52. After the pressure detection component 32 shows a normal reading, close the second valve body 22 and open the first valve body 12, so that the steam only passes through the first pipe fitting 13 and then enters the hot air cabinet 11 to heat the air. After the air temperature and humidity meet the requirements, the air is transported to the coating machine body to assist in coating the tablets. In the process of heat exchange between steam and air, the fourth valve body 42 is in a normally open state, so that the condensed water generated by the heat exchange is discharged to the condensation water pool 52 through the third pipe fitting 41; the pipeline where the fifth valve body 43 is located is used as a backup pipeline for discharging condensed water, that is, when the fourth valve body 42 is damaged, close the fourth valve body 42 and open the fifth valve body 43.

[0054] Example 2

[0055] This embodiment provides a coating machine, including the hot air device provided in Example 1.

[0056] Obviously, the above embodiments are merely examples for the purpose of clear explanation, and are not intended to limit the implementation methods. For those skilled in the art, other different forms of changes or modifications can be made based on the above description. It is not necessary and impossible to list all the implementation methods here. The obvious changes or modifications derived therefrom are still within the scope of protection of the invention of the utility model.

Claims

1. A hot air device, characterized in that: include: A hot air mechanism, the hot air mechanism comprising a hot air cabinet (11) and a first valve body (12), the hot air cabinet (11) being provided with a steam inlet (111), the steam inlet (111) being connected to a steam source (51) via a first pipe (13), the first valve body (12) being mounted on the first pipe (13), and the first valve body (12) being arranged close to the steam inlet (111); A first drainage mechanism, the first drainage mechanism comprising a second pipe fitting (21) and a second valve body (22), one end of the second pipe fitting (21) being connected to the first pipe fitting (13), and the connecting point being arranged on a side of the first valve body (12) away from the hot air cabinet (11), the other end of the second pipe fitting (21) being connected to a condensation water pool (52), and the second valve body (22) being installed on the second pipe fitting (21).

2. The hot air device according to claim 1, characterized in that: Also includes: A third valve body (31), the third valve body (31) is installed on the first pipe member (13), and the third valve body (31) is arranged on a side of the connection between the second pipe member (21) and the first pipe member (13) away from the first valve body (12).

3. The hot air device according to claim 2, characterized in that: Also includes: A pressure detection component (32), wherein the pressure detection component (32) is installed on the first pipe component (13), and the pressure detection component (32) is located on a side of the third valve body (31) away from the hot air cabinet (11).

4. The hot air device according to claim 3, characterized in that: The pressure detection element (32) is selected as an electric contact pressure gauge, and the electric contact pressure gauge is communicatively connected with the controller.

5. The hot air device according to any one of claims 1 to 4, characterized in that: The hot air cabinet (11) further comprises a condensed water outlet (112); The hot air device also includes a second drainage mechanism, which includes a third pipe fitting (41) and a fourth valve body (42), the two ends of the third pipe fitting (41) are respectively connected to the condensate outlet (112) and the condensate pool (52), and the fourth valve body (42) is installed on the third pipe fitting (41).

6. The hot air device according to claim 5, characterized in that: The condensed water outlet (112) and the steam inlet (111) are both arranged at the top of the hot air cabinet (11) along the height direction.

7. The hot air device according to claim 5, characterized in that: The fourth valve body (42) is selected as a steam trap.

8. The hot air device according to claim 6, characterized in that: The second drainage mechanism further comprises a fifth valve body (43), the fifth valve body (43) is installed on the third pipe member (41), and the fifth valve body (43) is arranged in parallel with the drain valve.

9. The hot air device according to any one of claims 1 to 4, characterized in that: The first valve body (12) and the second valve body (22) are selected as stop valves.

10. A coating machine, characterized in that: The invention comprises the hot air device according to any one of claims 1 to 9.