Double-pile-casing structure for cast-in-place pile hole forming
Through the combination of stone filling layer and positioning structure, using technologies such as sliding and threaded connection, the dynamic adjustment and positioning of the casing gap is realized, which solves the problem of poor positioning effect in the existing technology and improves the efficiency of cast-in-place pile hole formation. The practicality of the casing structure.
Patent Information
- Application Number
- CN202420403124.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-04
- Publication Date
- 2024-10-15
- Estimated Expiration
- 2034-03-04
AI Technical Summary
The existing double casing structure for forming holes for cast-in-place piles cannot be effectively adjusted according to the difference in casing gaps, resulting in poor positioning effect and reducing the practicality of the double casing structure for forming holes for cast-in-place piles.
It adopts the stone filling layer, the main component and the positioning structure, including the slidingly connected first casing, the lower positioning component and the upper positioning component, and realizes the dynamic adjustment and adjustment of the casing gap through the threaded cylinder, limit blocks, bearings, springs and other components. position.
Through the cooperation of the stone filling layer and the positioning structure, the positioning mechanism can be adjusted according to the different diameters of the outer casing and the inner casing to ensure the expected positioning effect and improve the practicality of the double casing structure for bored piles.
Smart Images

Figure CN221837585U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of cast-in-place piles, in particular to a double casing structure for bored cast-in-place piles. Background Art
[0002] Bored cast-in-place piles refer to piles that are made by forming pile holes in the foundation soil at the construction site through mechanical drilling, steel pipe squeezing or manual excavation, and placing steel cages inside and pouring concrete. Depending on the hole-forming method, cast-in-place piles can be divided into several categories, such as sunken pipe cast-in-place piles, bored cast-in-place piles and excavated cast-in-place piles.
[0003] According to the Chinese patent with the authorized publication number CN217399619U, a double casing structure for bored piles is disclosed, wherein the inner end of a positioning block abuts against the outer side wall of an inner casing, the outer end of the positioning block is provided with a slit with an opening facing downward, and the top of the outer casing is inserted into the slit, thereby the inner casing and the top of the outer casing are positioned by the positioning block, and at the same time, the outer end of a positioning ring is docked with the bottom of the outer casing, and the inner end of the positioning ring abuts against the outer side wall of the inner casing, thereby the inner casing and the bottom of the outer casing are positioned.
[0004] In the actual use of the above scheme, the sizes of the positioning ring and the positioning block are generally fixed, so that it is only applicable to the case of one casing gap. During use, the diameters of the outer casing and the inner casing are generally different, so that the casing gap generally changes. Therefore, the double casing structure for bored pile holes cannot effectively adjust the positioning mechanism according to the different casing gaps, and may not achieve the expected positioning effect. The double casing structure has great limitations, which reduces the practicality of the existing double casing structure for bored pile holes. Utility Model Content
[0005] In view of the deficiencies in the prior art, the present application provides a double casing structure for bored piles, which has the advantages of being able to effectively adjust the casing gap according to actual conditions, thereby solving the problem of low practicality of the existing double casing structure for bored piles.
[0006] In order to achieve the above-mentioned purpose of being able to effectively adjust the casing gap according to actual conditions, the present application provides the following technical solutions: a double casing structure for bored pile holes, comprising a stone filling layer, a main body assembly installed at the bottom of the stone filling layer, and a positioning structure installed inside the stone filling layer to position the casing for bored pile holes;
[0007] The positioning structure includes a first casing slidably connected to the inside of the rock filling layer, a lower positioning assembly installed inside the first casing for positioning the bottom of the casing, a second casing slidably installed inside the lower positioning assembly, and an upper positioning assembly installed inside the first casing for positioning the top of the casing;
[0008] The upper positioning assembly includes two threaded cylinders respectively slidably connected to the left and right walls of the first casing, two stop blocks respectively fixed to the top and bottom of the threaded cylinder, a screw threadedly connected to the inside of the threaded cylinder, two rotating blocks respectively fixed to the opposite ends of the two screws, a bearing rotatably connected to the outside of the screw, and two stop rods respectively fixed to the top and bottom of the bearing; the stop rod and the bearing are used to ensure that the screw rotates in place
[0009] By adopting the above technical solution, the tops of the outer casing and the inner casing can be effectively positioned and fixed according to different casing gaps.
[0010] Furthermore, the lower positioning assembly includes two telescopic rods respectively fixed to the left and right inner walls of the first protective tube, two trapezoidal blocks respectively fixed to the opposite ends of the two telescopic rods, and two springs respectively fixed to the left and right inner walls of the first protective tube.
[0011] By adopting the technical solution, the bottoms of the outer casing and the inner casing can be positioned according to different casing gaps.
[0012] Furthermore, the main body component includes a silt layer fixed to the bottom of the rock filling layer, a soil layer fixed to the bottom of the silt layer, and a hard rock layer fixed to the bottom of the soil layer.
[0013] By adopting the above technical scheme, the main structure of the bored pile construction is achieved.
[0014] Furthermore, a bottom hole is opened on the top of the hard rock layer, a lower hole is opened on the top of the soil layer, a middle hole is opened on the top of the silt layer, and an upper hole is opened on the top of the stone filling layer.
[0015] By adopting the above technical solution, the upper section hole, the middle section hole, the lower section hole and the bottom section hole are arranged from top to bottom to form a cast-in-place pile hole.
[0016] Furthermore, the second protective tube is slidably connected to the interior of the middle hole, and positioning grooves are provided on both left and right sides of the second protective tube.
[0017] By adopting the above technical solution, it is ensured that the second casing can protect the wall of the middle hole and facilitate the positioning and fixing of the top of the second casing.
[0018] Furthermore, the inner left wall and the inner right wall of the first protective tube are both provided with mounting grooves, and the spring is located on the outer side of the telescopic rod.
[0019] By adopting the above technical solution, it is convenient to install the spring and the telescopic rod and ensure that the spring can undergo expected effective deformation.
[0020] Furthermore, the limiting rod is an L-shaped rod, and one end of the limiting rod away from the bearing is fixed to the outer side of the first casing.
[0021] By adopting the above technical solution, it is ensured that the bearing is fixed by the limiting rod.
[0022] Furthermore, one side opposite to the two threaded barrels passes through the first protective barrel and extends to the inside of the first protective barrel, and the outer side of the threaded barrel is equal to the diameter of the positioning groove.
[0023] By adopting the above technical solution, it is ensured that the threaded tube can enter the interior of the first protective tube and be plugged into the positioning groove to achieve positioning and fixing of the tops of the first protective tube and the second protective tube.
[0024] Compared with the prior art, the present invention provides a double casing structure for bored piles, which has the following beneficial effects:
[0025] The double casing structure for bored pile drilling, through the coordinated use of the stone filling layer, the main body component and the positioning structure, can effectively adjust the positioning mechanism in actual use to produce different casing gaps according to the different diameters of the outer casing and the inner casing, thereby ensuring that the expected positioning effect of the outer casing and the inner casing can be achieved, thereby improving the practicality of the double casing structure for bored pile drilling. BRIEF DESCRIPTION OF THE DRAWINGS
[0026] Figure 1 This is a schematic diagram of the structure of this application;
[0027] Figure 2 It is a partial enlarged schematic diagram of the A part in the structure of the utility model;
[0028] Figure 3 It is a three-dimensional schematic diagram of the threaded barrel connection structure in the structure of the utility model.
[0029] In the figure: 1, stone filling layer; 200, main body component; 201, silt layer; 202, soil layer; 203, hard rock layer; 204, bottom hole; 205, lower hole; 206, middle hole; 207, upper hole; 300, positioning structure; 301, first casing; 302, second casing; 303, lower positioning component; 3031, telescopic rod; 3032, mounting groove; 3033, trapezoidal block; 3034, spring; 304, positioning groove; 305, upper positioning component; 3051, threaded tube; 3052, limit block; 3053, screw; 3054, rotating block; 3055, bearing; 3056, limit rod. DETAILED DESCRIPTION
[0030] The technical solutions in the embodiments of the present application will be clearly and completely described below in conjunction with the drawings in the embodiments of the present application. Obviously, the described embodiments are only part of the embodiments of the present application, rather than all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without making creative work are within the scope of protection of the present application.
[0031] See also Figure 1-3 The utility model provides a technical solution: a double casing structure for bored pile hole forming, comprising a stone filling layer 1, a main body component 200 installed at the bottom of the stone filling layer 1, and a positioning structure 300 installed inside the stone filling layer 1 for positioning the casing for bored pile hole forming. Through the coordinated use of the stone filling layer 1, the main body component 200 and the positioning structure 300, in the actual use process, different casing gaps can be generated according to the different diameters of the outer casing and the inner casing, and the positioning mechanism can be effectively adjusted to ensure that the expected positioning effect of the outer casing and the inner casing can be achieved, thereby improving the practicality of the double casing structure for bored pile hole forming.
[0032] In this embodiment, the main body component 200 is a structure of a bored pile body.
[0033] like Figure 1 and Figure 2 As shown, the main body component 200 includes a silt layer 201 fixed to the bottom of the rock-fill layer 1 , a soil layer 202 fixed to the bottom of the silt layer 201 , and a hard rock layer 203 fixed to the bottom of the soil layer 202 .
[0034] It should be noted that a bottom hole 204 is opened on the top of the hard rock layer 203, a lower hole 205 is opened on the top of the soil layer 202, a middle hole 206 is opened on the top of the silt layer 201, and an upper hole 207 is opened on the top of the stone filling layer 1, which are the main structures of the bored pile construction.
[0035] In addition, the second casing 302 is slidably connected inside the middle hole 206, and the upper hole 207, the middle hole 206, the lower hole 205 and the bottom hole 204 are arranged from top to bottom to form a cast-in-place pile hole.
[0036] In this embodiment, the positioning structure 300 is a structure for positioning the casing used for bored pile drilling.
[0037] like Figure 1 , Figure 2 and Figure 3As shown, the positioning structure 300 includes a first casing 301 slidably connected to the inside of the rock filling layer 1, a lower positioning component 303 installed inside the first casing 301 for positioning the bottom of the casing, a second casing 302 slidably installed inside the lower positioning component 303, and an upper positioning component 305 installed inside the first casing 301 for positioning the top of the casing.
[0038] It should be noted that positioning grooves 304 are provided on both the left and right sides of the second protective tube 302 to facilitate positioning and fixing the top of the second protective tube 302 .
[0039] In addition, the diameter of the middle hole 206 is larger than the diameter of the lower hole 205, and the diameter of the upper hole 207 is larger than the diameter of the middle hole 206, ensuring that the bottom of the first casing 301 can be in close contact with the stone filling layer 1, and ensuring that the bottom of the second casing 302 can be in close contact with the top of the soil layer 202, so as to perform preliminary positioning.
[0040] In this embodiment, the lower positioning assembly 303 is a structure for positioning the bottom of the outer casing and the inner casing.
[0041] like Figure 1 and Figure 2 As shown, the lower positioning assembly 303 includes two telescopic rods 3031 respectively fixed to the inner left and right walls of the first protective tube 301, two trapezoidal blocks 3033 respectively fixed to the opposite ends of the two telescopic rods 3031, and two springs 3034 respectively fixed to the inner left and right walls of the first protective tube 301.
[0042] It should be noted that the inner left wall and the inner right wall of the first protective tube 301 are both provided with installation grooves 3032, which are convenient for installing the spring 3034 and the telescopic rod 3031. The spring 3034 is located outside the telescopic rod 3031 to ensure that the spring 3034 can undergo the expected effective deformation.
[0043] In this embodiment, the upper positioning assembly 305 is a structure for positioning and fixing the tops of the outer casing and the inner casing.
[0044] like Figure 1 and Figure 3 As shown, the upper positioning assembly 305 includes two threaded cylinders 3051 respectively slidably connected to the left and right walls of the first protective cylinder 301, two limit blocks 3052 respectively fixed to the top and bottom of the threaded cylinder 3051, a screw 3053 threadedly connected to the inside of the threaded cylinder 3051, two rotating blocks 3054 respectively fixed to the opposite ends of the two screws 3053, a bearing 3055 rotatably connected to the outside of the screw 3053, and two limit rods 3056 respectively fixed to the top and bottom of the bearing 3055; the limit rod 3056 and the bearing 3055 are used to ensure that the screw 3053 rotates in place.
[0045] It should be noted that the limiting rod 3056 is an L-shaped rod, and one end of the limiting rod 3056 away from the bearing 3055 is fixed to the outer side of the first casing 301, ensuring that the bearing 3055 is fixed by the limiting rod 3056, thereby ensuring that the screw 3053 can effectively rotate in place through the action of the limiting rod 3056 and the bearing 3055.
[0046] In addition, one side of the two threaded barrels 3051 passes through the first casing 301 and extends to the interior of the first casing 301, ensuring that the threaded barrel 3051 can enter the interior of the first casing 301 and thereby be plugged into the positioning groove 304 to achieve positioning and fixation of the tops of the first casing 301 and the second casing 302. The outer side of the threaded barrel 3051 is equal to the diameter of the positioning groove 304, making the connection between the threaded barrel 3051 and the positioning groove 304 more stable.
[0047] The working principle of the above embodiment is:
[0048] The upper hole 207 is drilled in the rock filling layer 1 by a pump suction reverse circulation drilling rig equipped with a roller cutter drill bit, the middle hole 206 is drilled by a pump suction reverse circulation drilling rig equipped with a roller cutter drill bit, the lower hole 205 is drilled in the soil layer 202 by a rotary drilling rig, and the bottom hole 204 is drilled in the hard rock layer 203 by a rotary drilling rig. The bottom of the upper hole 207 is located above the silt layer 201, and the top of the middle hole 206 is placed in the rock filling layer 1, connected to the bottom of the upper hole 207. The bottom of the middle hole 206 is located at the bottom of the silt layer 201, and the upper hole 207, the middle hole 206, the lower hole 205 and the bottom hole 204 are arranged from top to bottom to form a cast-in-place pile hole, and then the first casing 301 is placed in the upper hole 207, and then the rotating block 3054 is rotated to drive the screw 3053 to rotate. Under the action of the bearing 3055 and the limit rod 3056, the screw 3053 rotates stably in place, and the threaded barrel 3051 selects the thrust and the limit block 3054 on the internal thread. 52, the outer side of the screw rod 3053 is moved left and right to adjust, so that the threaded tube 3051 enters the first casing 301, and then the second casing 302 is placed in the middle hole 206. In the process of the second casing 302 moving downward, it pushes the two trapezoidal blocks 3033 to move to the opposite side. At this time, the spring 3034 is in a compressed state. Therefore, under the action of the restoring elastic force of the spring 3034, the two trapezoidal blocks 3033 preliminarily position the second casing 302. After the second casing 302 is adjusted into place, the rotating block 3054 is rotated in the opposite direction to allow the threaded tube 3051 to enter the interior of the positioning groove 304, thereby positioning the second casing 302 and improving the stability of the double casing structure. When use is completed, the rotating block 3054 is rotated again to separate the threaded tube 3051 from the positioning groove 304, and the first casing 301 and the second casing 302 can be pulled out more conveniently through the casing gaps therein.
[0049] Compared with the prior art, the double casing structure for bored pile holes, through the coordinated use of the stone filling layer 1, the main body assembly 200 and the positioning structure 300, can produce different casing gaps according to the different diameters of the outer casing and the inner casing during actual use, and effectively adjust the positioning mechanism to ensure that the expected positioning effect of the outer casing and the inner casing can be achieved, thereby improving the practicality of the double casing structure for bored pile holes and solving the problem of low practicality of the existing double casing structure for bored pile holes.
[0050] The electrical components appearing in the article are all electrically connected to the main controller and the power supply. The main controller can be a conventional known device for control such as a computer, and the existing public power connection technology is not described in detail in the article.
Claims
1. The double casing structure of bored pile is characterized by: It comprises a rock filling layer (1), a main body component (200) installed at the bottom of the rock filling layer (1), and a positioning structure (300) installed inside the rock filling layer (1) for positioning a casing used for bored pile drilling; The positioning structure (300) comprises a first casing (301) slidably connected to the inside of the rock filling layer (1), a lower positioning component (303) installed inside the first casing (301) for positioning the bottom of the casing, a second casing (302) slidably installed inside the lower positioning component (303), and an upper positioning component (305) installed inside the first casing (301) for positioning the top of the casing; The upper positioning assembly (305) comprises two threaded cylinders (3051) respectively slidably connected to the left and right walls of the first protective cylinder (301), two limit blocks (3052) respectively fixed to the top and bottom of the threaded cylinder (3051), a screw rod (3053) threadedly connected to the inside of the threaded cylinder (3051), two rotating blocks (3054) respectively fixed to the opposite ends of the two screw rods (3053), a bearing (3055) rotatably connected to the outside of the screw rod (3053), and two limit rods (3056) respectively fixed to the top and bottom of the bearing (3055); the limit rods (3056) and the bearing (3055) are used to ensure that the screw rod (3053) rotates in place.
2. The double casing structure for bored pile holes according to claim 1 is characterized in that: The lower positioning assembly (303) comprises two telescopic rods (3031) respectively fixed to the inner left side wall and the inner right side wall of the first protective tube (301), two trapezoidal blocks (3033) respectively fixed to the opposite ends of the two telescopic rods (3031), and two springs (3034) respectively fixed to the inner left side wall and the inner right side wall of the first protective tube (301).
3. The double casing structure for bored pile according to claim 1 is characterized in that: The main body component (200) comprises a silt layer (201) fixed to the bottom of the rock filling layer (1), a soil layer (202) fixed to the bottom of the silt layer (201), and a hard rock layer (203) fixed to the bottom of the soil layer (202).
4. The double casing structure for bored pile holes according to claim 3 is characterized in that: A bottom hole (204) is opened on the top of the hard rock layer (203), a lower hole (205) is opened on the top of the soil layer (202), a middle hole (206) is opened on the top of the silt layer (201), and an upper hole (207) is opened on the top of the rock filling layer (1).
5. The double casing structure for bored pile holes according to claim 3 is characterized in that: The second protective tube (302) is slidably connected to the interior of the middle hole (206), and positioning grooves (304) are provided on both left and right sides of the second protective tube (302).
6. The double casing structure for bored pile holes according to claim 2 is characterized in that: The inner left wall and the inner right wall of the first protective tube (301) are both provided with mounting grooves (3032), and the spring (3034) is located outside the telescopic rod (3031).
7. The double casing structure for bored pile holes according to claim 1 is characterized in that: The limiting rod (3056) is an L-shaped rod, and one end of the limiting rod (3056) away from the bearing (3055) is fixed to the outer side of the first casing (301).
8. The double casing structure for bored pile holes according to claim 5 is characterized by: One side opposite to the other of the two threaded barrels (3051) passes through the first protective barrel (301) and extends to the inside of the first protective barrel (301), and the outside of the threaded barrel (3051) is equal to the diameter of the positioning groove (304).
Citation Information
Cited By
Cast-in-situ bored pile casing structure and construction method thereof