Rotary blowout preventer for tunnel surrounding rock drilling construction

By using rotating blowout preventers in tunnel drilling construction, and utilizing the sealing structure of fixed components and rotating components, the problem of groundwater injection is solved and the stability of the construction environment and drilling quality are ensured.

CN221838291UActive Publication Date: 2024-10-15CHINA RAILWAY SOUTHWEST SCI RES INST CO LTD
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202420703746.8
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-04-08
Publication Date
2024-10-15
Estimated Expiration
2034-04-08

AI Technical Summary

Technical Problem

During the tunnel anchoring construction process, groundwater leakage problems are often encountered when drilling, causing water jets to affect the construction environment and cause construction to be suspended.

Method used

A rotating blowout preventer for tunnel drilling construction in surrounding rock is designed, which includes a fixed component and a rotating component. By installing a fixed pipe and a sleeve at the drilling hole position, and using a combination of rubber sleeve and sealing ring, groundwater is prevented from spraying outward. out.

Benefits of technology

It effectively prevents groundwater from ejecting outward from the borehole opening, ensuring the smooth progress of drilling construction, and improves the quality and stability of the borehole through the centering mechanism.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221838291U_ABST
    Figure CN221838291U_ABST
Patent Text Reader

Abstract

The utility model discloses a rotary blowout preventer for tunnel surrounding rock drilling construction, and relates to the tunnel drilling construction technology, the rotary blowout preventer comprises a fixed assembly and a rotary assembly, the fixed assembly comprises a fixed pipe, a discharge pipe and a sleeve, one end of the discharge pipe is fixedly connected with the side wall of the fixed pipe, the discharge pipe is communicated with the interior of the fixed pipe, and the sleeve is connected with the rotary assembly. One end of the sleeve is rotatably arranged in one end of the fixed pipe in a penetrating manner; the rotating assembly comprises a connecting disc and a rubber sleeve which are coaxially arranged, one end of the connecting disc is fixedly connected with the large-diameter end of the rubber sleeve, the connecting disc is in threaded connection with the end, away from the fixing pipe, of the sleeve, and the rubber sleeve is coaxially arranged in the sleeve; a first sealing ring is arranged between the sleeve and the fixed pipe, and a second sealing ring is arranged between the rubber sleeve and the sleeve; when in use, the rotary blowout preventer is mounted at a position corresponding to a drilling hole position on a surrounding rock, and underground water can be effectively prevented from being sprayed outwards if leaking underground water is drilled during drilling construction, so that the drilling construction process is ensured to be smoothly carried out.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of tunnel drilling construction, in particular to a rotary blowout preventer for tunnel surrounding rock drilling construction. Background Art

[0002] In tunnel engineering, anchor rods are often needed to stabilize and reinforce the surrounding rock. Before installing the anchor rods, drilling construction needs to be carried out in the surrounding rock at the location where the anchor rods are to be installed. During the tunnel anchoring construction process, the number of anchor rods that need to be installed, that is, the number of anchor rod holes that need to be drilled, is large and the hole depth is deep. The geological environment in the tunnel surrounding rock is complex, and groundwater leakage is often drilled during the drilling process, causing the groundwater to spray out from the borehole, causing a huge impact on the construction environment, and even causing the construction to be suspended. Construction can only be continued after the water is drained. Utility Model Content

[0003] The utility model aims to provide a rotary blowout preventer for tunnel surrounding rock drilling construction, which is installed at a position corresponding to the drilling hole position on the surrounding rock. If leakage groundwater is drilled during drilling construction, it can effectively prevent the groundwater from spraying out, avoid affecting the construction environment, and ensure the smooth progress of the drilling construction process.

[0004] The purpose of this utility model is achieved through the following technical solutions:

[0005] A rotary blowout preventer for tunnel surrounding rock drilling construction, comprising a fixed component and a rotating component, the fixed component comprising a fixed pipe, a discharge pipe and a sleeve, one end of the discharge pipe is fixedly connected to the side wall of the fixed pipe, the discharge pipe is communicated with the interior of the fixed pipe, and one end of the sleeve is rotatably penetrated into one end of the fixed pipe; the rotating component comprises a coaxially arranged connecting disk and a rubber sleeve, the connecting disk is in a circular ring shape, the rubber sleeve is in a hollow conical column shape, one end of the connecting disk is fixedly connected to the large diameter end of the rubber sleeve, the connecting disk is threadedly connected to one end of the sleeve away from the fixed pipe, and the rubber sleeve is coaxially arranged in the sleeve; a first sealing ring is arranged between the sleeve and the fixed pipe, and a second sealing ring is arranged between the rubber sleeve and the sleeve.

[0006] Furthermore, the fixing assembly also includes a centering mechanism, which includes three or more centering devices evenly distributed in a circle, and the centering device includes a centering tube, a centering rod, a screw and a steel ball. The centering tube is arranged along the radial direction of the fixing tube, one end of the centering tube passes through the outer wall of the fixing tube and is fixedly connected to the fixing tube, the other end of the centering tube is threadedly connected to the screw, one end of the screw extends into the centering tube and is rotatably connected to one end of the centering rod, the centering rod is slidably arranged in the centering tube, and the other end of the centering rod is rotatably provided with the steel ball.

[0007] Specifically, one end of the fixed tube is detachably connected to a bearing seat, the sleeve is inserted into the bearing seat, the sleeve and the bearing seat are connected via a bearing, and the first sealing ring is arranged between the sleeve and the bearing seat.

[0008] Specifically, the rotating assembly also includes a rigid connecting tube, which is fixedly sleeved on the large diameter end of the rubber sleeve, one end of which is fixedly connected to the connecting disk, the connecting tube is arranged in the sleeve, and the second sealing ring is arranged between the connecting tube and the sleeve.

[0009] Specifically, the rotating assembly further comprises a rigid guide cylinder, the guide cylinder is fixedly inserted into the large diameter end of the rubber sleeve, and one end of the guide cylinder is fixedly connected to the connecting disk.

[0010] Specifically, a flange is fixedly provided at one end of the fixing pipe away from the sleeve.

[0011] The beneficial effects of the utility model are:

[0012] The rotary blowout preventer for tunnel surrounding rock drilling construction includes a fixed component and a rotating component, wherein the fixed component includes a fixed pipe, a discharge pipe and a sleeve, one end of the fixed pipe is fixedly installed on the wall of the tunnel surrounding rock, the discharge pipe is connected to the side wall of the fixed pipe and can be used to guide the discharge of slag and water, and one end of the sleeve can be rotatably inserted into the other end of the fixed pipe; the rotating component includes a coaxially arranged connecting plate and a rubber sleeve, one end of the connecting plate is fixedly connected to the large diameter end of the rubber sleeve, and one end of the drill rod can be connected to the drill bit after passing through the connecting plate and the rubber sleeve in sequence. When in use, the drilling equipment moves the drill rod to a position aligned with the axis of the fixed pipe, and extends the drill bit into the fixed pipe, so that the rotation of the drill rod can drive the connecting plate to rotate together through the rubber sleeve, and during the rotation process, the connecting plate can be threadedly connected to one end of the sleeve away from the fixed pipe, and then the sleeve, the rubber sleeve and the drill rod rotate together during the drilling process of the drill rod. A first sealing ring is provided between the sleeve and the fixed pipe, and a second sealing ring is provided between the rubber sleeve and the sleeve. Combined with the sliding sealing effect between the rubber sleeve and the drill rod, the groundwater can be effectively prevented from spraying outward from the hole mouth along the axis of the borehole during the entire drilling process, avoiding its impact on the construction environment and ensuring the smooth progress of the drilling process. After drilling a hole, the drill rod can be reversed to separate the rotating assembly from the fixed assembly, and the drilling equipment can move the drill rod and the rotating assembly together to the next hole for drilling, and the operation process is also relatively convenient.

[0013] The above-mentioned fixing assembly also includes a centering mechanism, which has three or more centering devices evenly distributed on the circumference of the fixing tube. The centering device includes a centering tube, a centering rod, screws and steel balls. By tightening the screws of each centering device, the end of the centering rod can push the centering rod toward the center of the fixing tube until the steel ball at the end of the centering rod presses against the drill rod, which can effectively center and support the drill rod and ensure the quality of the drilling construction. BRIEF DESCRIPTION OF THE DRAWINGS

[0014] Figure 1 This is a schematic diagram of the overall structure of a rotary blowout preventer for tunnel surrounding rock drilling construction according to the utility model;

[0015] Figure 2 This is a schematic cross-sectional view of a rotary blowout preventer for tunnel surrounding rock drilling construction according to the utility model;

[0016] Figure 3 This is a schematic diagram of the structure of a fixed component in a rotary blowout preventer for tunnel surrounding rock drilling construction according to the utility model;

[0017] Figure 4 This is a schematic diagram of the structure of a rotating assembly in a rotary blowout preventer for tunnel surrounding rock drilling construction according to the utility model;

[0018] In the figure, 10-fixed component, 11-fixed pipe, 12-discharge pipe, 13-sleeve, 14-first sealing ring, 15-second sealing ring, 16-flange, 17-bearing seat, 18-bearing, 20-rotating component, 21-connecting pipe, 22-rubber sleeve, 23-connecting tube, 24-guide tube, 31-centering tube, 32-centering rod, 33-screw, 34-steel ball. DETAILED DESCRIPTION

[0019] The technical solution of the present utility model is further described in detail below in conjunction with the accompanying drawings, but the protection scope of the present utility model is not limited to the following.

[0020] like Figures 1 to 4As shown, a rotary blowout preventer for tunnel surrounding rock drilling construction includes a fixed component 10 and a rotating component 20. The fixed component 10 includes a fixed pipe 11, a discharge pipe 12 and a sleeve 13. One end of the discharge pipe 12 is fixedly connected to the side wall of the fixed pipe 11, and the discharge pipe 12 is communicated with the inside of the fixed pipe 11. One end of the sleeve 13 is rotatably inserted into one end of the fixed pipe 11. The rotating component 20 includes a coaxially arranged connecting plate 21 and a rubber sleeve 22. The connecting plate 21 is annular, and the rubber sleeve 22 is hollow conical columnar. One end of the connecting plate 21 is fixedly connected to the large diameter end of the rubber sleeve 22. The connecting plate 21 is threadedly connected to one end of the sleeve 13 away from the fixed pipe 11, and the rubber sleeve 22 is coaxially arranged in the sleeve 13. A first sealing ring 14 is arranged between the sleeve 13 and the fixed pipe 11, and a second sealing ring 15 is arranged between the rubber sleeve 22 and the sleeve 13.

[0021] When the rotary blowout preventer for tunnel surrounding rock drilling construction is in use, the fixed component 10 and the rotating component 20 are in a separated state, and construction preparation is carried out:

[0022] In terms of the fixing assembly 10, the end of the fixing pipe 11 away from the sleeve 13 is fixedly installed on the tunnel surrounding rock (in specific implementation, the fixing pipe 11 is fixedly sleeved with a flange 16 at the end and is installed on the surrounding rock by bolts), and the fixing pipe 11 is aligned with the axis of the hole to be drilled during installation. During drilling construction, the fixing assembly 10 can be installed at each hole to be drilled where there is a risk of groundwater leakage.

[0023] As for the rotating assembly 20, it is installed on the drilling equipment. The drilling equipment includes a carrier, a propulsion beam, a rock drill, a drill rod and a drill bit. The propulsion beam is installed on the carrier and can be transported to any position by the carrier and the propulsion direction can be adjusted. The rock drill can be slidably arranged on the propulsion beam. One end of the drill rod is connected to the output end of the rock drill, and the other end of the drill rod is connected to the drill bit. In the rotating assembly 20, the small diameter end of the rubber sleeve 22 is adapted to the diameter of the drill rod (the rubber sleeve 22 is selected in size, and its small diameter end can hold the drill rod to a certain extent, and the two can slide relative to each other but are difficult to rotate relative to each other). Its size is smaller than the diameter of the drill bit, so one end of the drill rod needs to be inserted from the large diameter end of the rubber sleeve 22 into the small diameter end and then connected to the drill bit.

[0024] After completing the above construction preparation, the drilling construction can be carried out. During the construction, the drilling equipment is first operated to align the drill bit with the axis of the fixed pipe 11, and the drill bit is inserted into the fixed pipe 11 and the drill rod is rotated. During the rotation process, the connecting plate 21 is rotated under the drive of the rubber sleeve 22 until the threaded tightening of the connecting plate 21 and the sleeve 13 is completed (the tightening process requires manual intervention if necessary, and the sleeve 13 is clamped and fixed by a clamping tool). After that, the drill rod, the rubber sleeve 22, and the sleeve 13 are rotated together to carry out the drilling construction. Due to the provision of the first sealing ring 14, the second sealing ring 15, and the clamping sealing effect between the flexible rubber sleeve 22 and the drill rod, even if the infiltrated groundwater is drilled during the construction, it can be effectively prevented from being ejected outward from the end of the borehole toward the axis of the borehole. Instead, the groundwater and the slag generated by drilling are discharged under the guidance of the discharge pipe 12, thereby avoiding affecting the construction environment and ensuring the smooth progress of the construction process. After the drilling is completed, the drill rod is pulled out and reversed to disengage the fixed component 10 and the rotating component 20 (manual intervention is required if necessary, and the sleeve 13 is slightly fixed by a clamping tool). Driven by the drilling equipment, the rotating component 20 is moved together with the drill rod, drill bit, etc. to another construction hole where the fixed component 10 is installed for drilling construction.

[0025] In the above design, the drill rod, sleeve 13, rubber sleeve 22 and connecting plate 21 rotate together during drilling construction, the second sealing ring 15 is a static sealing environment, and the drill rod and the rubber sleeve 22 are only a sliding sealing environment when the drill rod is pushed forward. The requirements for the seal are low, it is easy to implement, and the sealing effect is reliable.

[0026] Furthermore, the fixing assembly 10 also includes a centering mechanism, which includes three or more centering devices evenly distributed in a circle. The centering device includes a centering tube 31, a centering rod 32, a screw 33 and a steel ball 34. The centering tube 31 is arranged along the radial direction of the fixing tube 11. One end of the centering tube 31 passes through the outer wall of the fixing tube 11 and is fixedly connected to the fixing tube 11. The other end of the centering tube 31 is threadedly connected with the screw 33. The screw 33 extends into one end of the centering tube 31 and is rotatably connected to one end of the centering rod 32. The centering rod 32 is slidably arranged in the centering tube 31, and the other end of the centering rod 32 is rotatably provided with a steel ball 34. During the drilling construction process, tighten the screws 33 of each centering device, and the ends thereof can push the centering rod 32 to move toward the center of the fixing tube 11 until the steel ball 34 at the end of the centering rod 32 presses against the drill rod. Since the fixed tube 11 is fixedly installed on the tunnel surrounding rock wall, the centering mechanism can effectively center and support the drill rod to ensure the quality of drilling construction; the design of the steel ball 34 also prevents interference with the rotation and advancement of the drill rod after centering.

[0027] In specific implementation, one end of the fixed pipe 11 is detachably connected to the bearing seat 17 by bolts, the sleeve 13 is inserted into the bearing seat 17, the sleeve 13 and the bearing seat 17 are connected by the bearing 18, and the first sealing ring 14 is arranged between the sleeve 13 and the bearing seat 17. The fixed pipe 11 and the bearing seat 17 are arranged in a detachable structure, and during the drilling construction process, only the fixed pipe 11 can be installed on the inner wall of the tunnel surrounding rock corresponding to each hole position, and the bearing seat 17 can be used in rotation; in addition, the first sealing ring 14 is a dynamic seal, and this split structure design also facilitates the inspection, replacement and repair of the first sealing ring 14.

[0028] In specific implementation, the rotating assembly 20 also includes a rigid connecting tube 23 and a guiding tube 24. The connecting tube 23 is coaxially sleeved outside the guiding tube 24. The large diameter end of the rubber sleeve 22 is fixedly clamped between the connecting tube 23 and the guiding tube 24, thereby enhancing the overall rigidity of the large diameter end of the rubber sleeve 22. One end of the connecting tube 22 is fixedly connected to the connecting disk. The connecting tube 22 is arranged in the sleeve 13. The second sealing ring 15 is arranged between the connecting tube 22 and the sleeve 13, which are also rigid structures, thereby ensuring the sealing performance of the second sealing ring 15. The above-mentioned guiding tube 24 is inserted into the large diameter end of the rubber sleeve, and its end is fixedly connected to the connecting disk. When the drill rod is inserted into the rubber sleeve 22, the drill rod can be guided to avoid direct friction contact between the drill rod and the large diameter end of the flexible rubber sleeve 22.

[0029] The above is only a preferred embodiment of the utility model. It should be understood that the utility model is not limited to the form disclosed herein, and should not be regarded as excluding other embodiments, but can be used in various other combinations, modifications and environments, and can be modified within the scope of the concept described herein through the above teachings or the technology or knowledge of the relevant field. The changes and modifications made by those skilled in the art do not deviate from the spirit and scope of the utility model, and should be within the scope of protection of the claims attached to the utility model.

Claims

1. A rotary blowout preventer for tunnel surrounding rock drilling construction, characterized in that: It includes fixed components and rotating components. The fixing assembly includes a fixing pipe, a discharge pipe and a sleeve, one end of the discharge pipe is fixedly connected to the side wall of the fixing pipe, the discharge pipe is communicated with the interior of the fixing pipe, and one end of the sleeve is rotatably inserted into one end of the fixing pipe; The rotating assembly comprises a coaxially arranged connection disk and a rubber sleeve, wherein the connection disk is in a circular ring shape, and the rubber sleeve is in a hollow conical column shape, one end of the connection disk is fixedly connected to the large diameter end of the rubber sleeve, the connection disk is threadedly connected to the end of the sleeve away from the fixed pipe, and the rubber sleeve is coaxially arranged in the sleeve; A first sealing ring is arranged between the sleeve and the fixing pipe, and a second sealing ring is arranged between the rubber sleeve and the sleeve.

2. A rotary blowout preventer for tunnel surrounding rock drilling construction according to claim 1, characterized in that: The fixing assembly also includes a centering mechanism, which includes three or more centering devices evenly distributed in a circle, and the centering device includes a centering tube, a centering rod, a screw and a steel ball. The centering tube is arranged along the radial direction of the fixing tube, one end of the centering tube passes through the outer wall of the fixing tube and is fixedly connected to the fixing tube, the other end of the centering tube is threadedly connected to the screw, one end of the screw extends into the centering tube and is rotatably connected to one end of the centering rod, the centering rod is slidably arranged in the centering tube, and the other end of the centering rod is rotatably provided with the steel ball.

3. A rotary blowout preventer for tunnel surrounding rock drilling construction according to claim 2, characterized in that: One end of the fixed tube is detachably connected to a bearing seat, the sleeve is inserted into the bearing seat, the sleeve and the bearing seat are connected via a bearing, and the first sealing ring is arranged between the sleeve and the bearing seat.

4. A rotary blowout preventer for tunnel surrounding rock drilling construction according to claim 2, characterized in that: The rotating assembly also includes a rigid connecting tube, which is fixedly sleeved on the large diameter end of the rubber sleeve, one end of which is fixedly connected to the connecting disk, the connecting tube is arranged in the sleeve, and the second sealing ring is arranged between the connecting tube and the sleeve.

5. A rotary blowout preventer for tunnel surrounding rock drilling construction according to claim 4, characterized in that: The rotating assembly further comprises a rigid guide cylinder, which is fixedly inserted into the large diameter end of the rubber sleeve, and one end of the guide cylinder is fixedly connected to the connecting disk.

6. A rotary blowout preventer for tunnel surrounding rock drilling construction according to claim 1, characterized in that: A flange is fixedly sleeved on one end of the fixing pipe away from the sleeve.