Gas pipeline compensator cladding body
By designing the gas pipeline compensator covering body and using the outer covering structure and bolt connection, the safety hazards of hot welding operations and the problem of low maintenance efficiency have been solved, an efficient and safe maintenance process has been achieved, and economic and safety risks have been reduced. .
Patent Information
- Application Number
- CN202323627438.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-12-29
- Publication Date
- 2024-10-15
- Estimated Expiration
- 2033-12-29
AI Technical Summary
During the use of existing gas pipeline compensators, there are safety hazards in hot welding operations, reduced tool life, low maintenance efficiency, and easy damage during replacement, resulting in economic losses and safety risks.
A gas pipeline compensator covering body is designed. It adopts an outer covering structure and uses bolted connections instead of welding. It is combined with a lubricating oil pump, nitrogen purge and sealing system to achieve welding-free repairs and perform maintenance on the outside to reduce internal corrosion. Contact with sexual substances.
It improves the repair efficiency of the gas pipeline compensator, shortens the maintenance time, reduces the cost of spare parts and operation risks, avoids safety accidents caused by hot welding operations, and ensures the safety of maintenance personnel.
Smart Images

Figure CN221839176U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of pipeline compensators, in particular to a gas pipeline compensator sheath. Background Art
[0002] Coke oven gas is widely used in many links of steel production, so the stability of coke oven gas pipeline network is very important. Pipeline compensators are essential accessories in the pipeline system to compensate for pipeline deformation caused by temperature changes. They can withstand a certain positive or negative pressure and require regular maintenance. Once damaged during long-term use, the pipeline needs to be stopped before it can be replaced as a whole, resulting in greater economic losses.
[0003] In addition, the current disassembly and replacement of compensators have the following technical difficulties: (1) There are safety hazards in welding and hot work in the gas area; (2) Direct contact with the strong acid solution in the gas pipeline reduces the service life of the tools and endangers the health of personnel; (3) The preparation time before disassembly of the compensator is long, and the maintenance efficiency is low; (4) The replacement operation of the compensator is easy to damage the protective layer on the inside of the pipeline. Utility Model Content
[0004] The technical task of the utility model is to provide a gas pipeline compensator covering body to improve work efficiency, reduce spare parts cost and lower operation risk in view of the above deficiencies in the prior art.
[0005] The utility model solves the technical problem by a technical solution: a gas pipeline compensator sheath, comprising an upper sheath shell and a lower sheath shell; the characteristic is that the upper sheath shell and the lower sheath shell both comprise a half sheath, a reducer flange, a stuffing box outer ring and a plane flange; the half sheath shell is welded with the reducer flanges on both sides, and the inner diameter of the reducer flange is the same as the outer diameter of the gas pipeline; the stuffing box outer ring is welded on the outer side of the reducer flange, and the inner diameter of the stuffing box is larger than the outer diameter of the gas pipeline; the plane flange is welded with the half sheath section and the reducer flange section; the lower sheath shell is fixed with a lubricating oil pump on the side of the plane flange, and the lubricating oil pump delivers grease through an oil supply line; the upper sheath shell is provided with two opening flanges, which are respectively inserted into a CO concentration detector and a nitrogen pipeline; the stuffing box pressure flange is fixed with the stuffing box outer ring by bolts; the stuffing box outer ring, the reducer flange and the stuffing box pressure flange are combined into a stuffing box, and the seal and the oil separator ring between the two seals are arranged in the stuffing box.
[0006] Furthermore, two tapered holes are provided on two obliquely opposite sides of the planar flange, and two positioning pins are installed in the tapered holes.
[0007] Furthermore, a plurality of reinforcing ribs are welded on the above-mentioned plane flange.
[0008] Furthermore, the lower enclosure shell is provided with a guide rod on a plane in contact with the upper enclosure shell.
[0009] Furthermore, the lubricating oil pump is divided into two oil supply passages through the main lubricating oil passage and the three-way joint to transport grease to both sides.
[0010] Furthermore, a sewage valve is installed at the bottom of the lower shell body.
[0011] Furthermore, a plurality of lifting rings are welded on both sides of the upper enclosure shell and both sides of the lower enclosure shell.
[0012] Furthermore, the control unit of the nitrogen pipeline is electrically connected to the CO concentration detector.
[0013] Furthermore, a sealing groove is provided on the end surface where the plane flange of the lower enclosure shell contacts the upper enclosure shell, and both ends extend to the inner ring of the outer ring of the stuffing box; the sealing groove is filled with a flange seal.
[0014] Compared with the prior art, the utility model has the following outstanding beneficial effects:
[0015] 1. The utility model changes the operation mode of directly replacing the compensator, reducing the cost of spare parts;
[0016] 2. Improve the efficiency of gas pipeline compensator repair work and shorten the maintenance time;
[0017] 3. Eliminate welding and fire operations in gas areas to avoid combustion, explosion and poisoning accidents. BRIEF DESCRIPTION OF THE DRAWINGS
[0018] Figure 1 It is a structural schematic diagram of the utility model.
[0019] Figure 2 yes Figure 1 Schematic diagram of the left side.
[0020] Figure 3 It is a top view structural schematic diagram of the utility model.
[0021] Figure 4 yes Figure 3 A partial enlarged view of point A.
[0022] Figure 5 yes Figure 3 A partial enlarged view of point B.
[0023] Figure 6 It is a schematic diagram of a half left view of the utility model.
[0024] Among them: 1. cladding; 2. reducing flange; 3. outer ring of stuffing box; 4. flat flange; 5. positioning pin; 6. guide rod; 7. lifting ring; 8. CO concentration detector; 9. nitrogen pipeline; 10. electric control switch; 11. gas pipeline; 12. lubricating oil pump; 13. main lubricating oil circuit; 14. drain valve; 15. three-way joint; 16. oil supply oil circuit; 17. reinforcing ribs; 18. packing flange; 19. distributor; 20. lubricating pipeline; 21. lubricating oil channel; 22. oil distributor ring; 23. seal; 24. sealing groove; 25. flange seal; 26. stuffing box; 27. compensator; 28. lower lifting ring; 29. reversing valve. DETAILED DESCRIPTION
[0025] The present invention is further described below in conjunction with the accompanying drawings and specific embodiments of the specification. In the following, only certain exemplary embodiments are briefly described. As those skilled in the art will appreciate, the described embodiments may be modified in various ways without departing from the spirit or scope of the embodiments of the present invention. Therefore, the drawings and descriptions are considered to be exemplary and non-restrictive in nature.
[0026] In the following embodiments, unless otherwise clearly specified and limited, the terms "installed", "connected", "connected", "fixed" and the like should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection, an electrical connection, or a communication; it can be a direct connection, or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements. For those of ordinary skill in the art, the specific meanings of the above terms in the embodiments of the present utility model application can be understood according to the specific circumstances.
[0027] It should be understood that the terms "center", "longitudinal", "lateral", "length", "width", "thickness", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", "clockwise", "counterclockwise", "axial", "radial", "circumferential", "end", "side" and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the embodiments of the utility model application and simplifying the description, and do not indicate or imply that the referred device or element must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on the embodiments of the utility model application.
[0028] The utility model solves the problem of compensator damage by using an outer sheath, avoiding the need to replace the compensator. Its installation method is changed from welding to bolt connection, which ensures the stability of the connection while eliminating the safety hazards caused by welding and hot work. The entire maintenance process only requires the assembly of the sheath and is carried out on the outside of the gas pipeline, shortening the maintenance time while preventing maintenance personnel and tools from contacting corrosive substances in the pipeline.
[0029] like Figure 1-3 As shown, the utility model is a gas pipeline compensator sheath, comprising an upper sheath shell and a lower sheath shell.
[0030] The upper enclosure shell and the lower enclosure shell both include a half enclosure shell 1 , a reducing flange 2 , a stuffing box outer ring 3 and a plane flange 4 .
[0031] The half cladding 1 is welded to the reducer flanges 2 on both sides, and the inner diameter of the reducer flanges 2 is the same as the outer diameter of the gas pipeline 11. The outer ring 3 of the stuffing box is welded on the outside of the reducer flange 2, and its inner diameter is larger than the outer diameter of the gas pipeline 11. Evenly distributed and equal-sized bolt holes are drilled on the outer end face. The plane flange 4 is welded to the section of the half cladding 1 and the section of the reducer flange 2 along the generatrix direction of the half cladding 1. The plane flange 4 is provided with two tapered holes on the diagonally opposite sides, and two locating pins 5 are installed in the tapered holes. A plurality of reinforcing ribs 17 are welded on the plane flange 4 to keep the relative position of the plane flange 4 and the half cladding 1 stable.
[0032] The lower housing is fixed with a lubricating oil pump 12 on the side of the flat flange 4, and a guide rod 6 is provided on the plane in contact with the upper housing. The guide rod 6 can determine the relative position of the flange holes before the upper housing and the lower housing are assembled, so as to prepare for the subsequent alignment of the flange holes. The lubricating oil pump 12 is divided into two oil supply oil passages 16 through the main lubricating oil passage 13 and the three-way joint 15 to transport grease to both sides. A drain valve 14 is installed at the bottom of the lower housing to remove water and debris in the housing.
[0033] The upper cladding shell of the cladding 1 is welded with hanging rings 7 on both sides, and is provided with two opening flanges, into which a CO concentration detector 8 and a nitrogen pipeline 9 are inserted respectively. The CO concentration detector 8 is inserted into the cladding through the flange hole to monitor the CO concentration and feedback an electrical signal. At the same time, the nitrogen pipeline 9 is inserted into the cladding through the flange hole, and the electric control switch 10 of the nitrogen pipeline is connected to the electrical signal of the CO concentration detector. The on-off and opening size of the nitrogen pipeline 9 are controlled by the electrical signal sent by the CO concentration detector 8.
[0034] Nitrogen is injected into the cladding through the nitrogen pipeline 9, so that the inner wall of the cladding and the outer wall of the gas pipeline are in a nitrogen atmosphere, so as to prevent the gas leaking from the compensator 27 from corroding the inner wall of the cladding and the outer wall of the gas pipeline. When the nitrogen is sufficient, the CO concentration is lower than the threshold, and the CO concentration detector 9 sends an electrical signal to control the electric control switch 10 to reduce or turn off the nitrogen injection; when the nitrogen is insufficient, the CO concentration is higher than the threshold, and the CO concentration detector sends an electrical signal to control the electric control switch 10 to increase the nitrogen injection.
[0035] A plurality of lower suspension rings 28 are welded on both sides of the lower enclosure. The position and number of suspension points can be changed according to the installation form of the compensator 27. In this embodiment, there are four suspension points, which shows the horizontal arrangement of the gas pipeline compensator 27.
[0036] like Figure 2 As shown, the stuffing box flange 18 is fixed to the stuffing box outer ring 3 by bolts. The grease from the oil supply line 16 is sent to the distributor 19 through the reversing valve 29, and is transported from the distributor 19 to the lubricating oil channel 21 through the lubricating pipeline 20, and finally lubricates the seal 23 through the oil dividing ring 22 between the two seals.
[0037] like Figure 3 As shown in the figure (for clarity, the oil separator ring, seal and two flange seals in the seal groove in one side of the stuffing box in the figure above are abbreviated), the stuffing box outer ring 3, the reducer flange 2 and the stuffing box flange 18 are combined into a stuffing box 26, and the seal 23 and the oil separator ring 22 between the two seals are arranged in the stuffing box. The seal 23 is uniformly squeezed by the stuffing box flange 18 and expands radially to fill the entire stuffing box 26. The parts on both sides of the cladding body that contact the gas pipeline adopt the above-mentioned soft connection method, which can not only play a sealing role between the cladding body and the gas pipeline, but also compensate for the relative movement of the gas pipeline.
[0038] A sealing groove 24 is provided on the end surface where the plane flange 4 of the lower package shell contacts the upper package shell, and both ends extend to the inner ring of the stuffing box outer ring 18. The sealing groove 24 is filled with a flange seal 25 to prevent the exchange of substances inside and outside the package body.
[0039] In the process of troubleshooting the leakage of the gas pipeline compensator, first add the flange seal 25 in the seal groove 24, then use the crane to lift the lower package shell to the designated position below the compensator and fix it, then lift the upper package shell to the top of the lower package shell, and use the guide rod 6 to assist the crane to work, so that the upper package shell is lifted to form a match with the lower package shell. Pre-tighten the flange bolts in the bolt holes, then install the positioning pins 5 that play the role of flange positioning, and fully tighten the flange bolts. Fill a single seal 23 in the stuffing box 26, then put in the oil distribution ring 22, and then put in a seal 23, and finally evenly press the packing flange 18 through the bolts, fix it on the outer ring 3 of the stuffing box, and connect the distributor 19 to the lubricating oil channel 21. The CO concentration monitor 8 connected to the sensor device is inserted into the package through the flange hole, and then the nitrogen pipeline 9 with the electric control switch 10 is connected to the nitrogen source and then inserted into the package. After fully tightening all bolts, the fault handling is completed.
[0040] The utility model adopts a split structure, all joint surfaces are sealed with silicone sealing strips, the connection method is bolt connection, and it is provided with internal gas concentration detection and nitrogen purge device, so that the interior of the coating is always in a dry environment to avoid corrosion of equipment due to internal condensed water accumulation. The contact surface between the end of the coating and the pipeline is provided with a sealing lubrication system to ensure that the pipeline can realize the axial movement function. The end sealing flange can be adjusted according to the sealing situation to achieve the sealing purpose, and the function of free fire treatment for compensator corrosion leakage treatment is realized. The operation time of compensator leakage gas treatment is reduced, the manual labor of personnel is reduced, and the operation risk is reduced. The equipment is coated to reduce replacement and improve the availability of the equipment. Safety accidents caused by hot work or gas leakage during the compensator replacement operation are avoided to ensure the safety of the operators.
[0041] It should be noted that matters not described in detail in this embodiment are well-known technologies in the art.
[0042] The above description is only for the purpose of describing the present invention in detail for the specific implementation purpose of the present invention. For those skilled in the art, various obvious changes made to the present invention without departing from the spirit and scope of the present invention are within the protection scope of the present invention.
Claims
1. A gas pipeline compensator sheath, comprising an upper sheath shell and a lower sheath shell; characterized in that: The upper and lower enclosure shells both include a half enclosure, a reducing flange, a stuffing box outer ring and a flat flange; the half enclosure is welded to the reducing flanges on both sides, and the inner ring diameter of the reducing flange is the same as the outer diameter of the gas pipeline; the outer ring of the stuffing box is welded on the outer side of the reducing flange, and its inner ring diameter is larger than the outer diameter of the gas pipeline; the flat flange is welded to the half enclosure section and the reducing flange section; the lubricating oil pump is fixed on the side of the flat flange of the lower enclosure shell, and the lubricating oil pump conveys grease through the oil supply line; two opening flanges are provided on the upper enclosure shell, and the CO concentration detector and the nitrogen pipeline are inserted respectively; the stuffing box pressure flange is fixed to the stuffing box outer ring by bolts; the stuffing box outer ring, the reducing flange and the stuffing box pressure flange are combined into a stuffing box, and the seal and the oil separator ring between the two seals are arranged in the stuffing box.
2. The gas pipeline compensator cladding according to claim 1, characterized in that: The plane flange is provided with two tapered holes on two obliquely opposite sides, and two positioning pins are installed in the tapered holes.
3. The gas pipeline compensator cladding according to claim 1, characterized in that: A plurality of reinforcing ribs are welded on the plane flange.
4. The gas pipeline compensator cladding according to claim 1, characterized in that: The lower enclosure shell is provided with a guide rod on a plane in contact with the upper enclosure shell.
5. The gas pipeline compensator cladding according to claim 1, characterized in that: The lubricating oil pump is divided into two oil supply oil circuits through the lubricating main oil circuit and the three-way joint to transport lubricating grease to both sides.
6. The gas pipeline compensator cladding according to claim 1, characterized in that: A sewage discharge valve is installed at the bottom of the lower shell body.
7. The gas pipeline compensator cladding according to claim 1, characterized in that: A plurality of lifting rings are welded on both sides of the upper enclosure shell and both sides of the lower enclosure shell.
8. The gas pipeline compensator cladding according to claim 1, characterized in that: The electric control switch of the nitrogen pipeline is connected with the electrical signal of the CO concentration detector.
9. The gas pipeline compensator cladding according to claim 1, characterized in that: A sealing groove is arranged on the end surface where the plane flange of the lower enclosure shell contacts the upper enclosure shell, and both ends extend to the inner ring of the outer ring of the stuffing box; the sealing groove is filled with a flange seal.
Citation Information
Cited By
Gas pipeline compensator cladding body
CN117662895A