Connecting structure of ultrahigh building steel beam and core tube

By using embedded steel plates and embedded parts combined with threaded connections and limiters in ultra-high buildings, a quick and stable connection between the steel beam and the core tube is achieved, which solves the problems of low efficiency and space interference in traditional construction and improves efficiency. Construction efficiency and connection strength.

CN221878387UInactive Publication Date: 2024-10-22CHINA CONSTR SECOND ENG BUREAU LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420358566.0
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-02-27
Publication Date
2024-10-22
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

In the construction of ultra-high buildings, the traditional embedded structure of steel beams and core tubes needs to be welded and adjusted in advance, resulting in low construction efficiency and large installation space requirements. It is easy to interfere with the core tube steel structure, making construction more difficult.

Method used

Embedded steel plates and embedded parts fixed at the ends of steel beams are used to achieve rapid installation and positioning through threaded connections, stoppers and elastic centering components, which facilitates on-site assembly, avoids the need for position adjustment of steel beams, and uses raised parts and Reinforcements increase connection strength.

Benefits of technology

It simplifies the connection process between steel beams and core tubes, improves construction efficiency, reduces installation space requirements, avoids the need to adjust the position of steel beams, and enhances connection stability and welding convenience.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221878387U_ABST
    Figure CN221878387U_ABST
Patent Text Reader

Abstract

The utility model discloses an ultrahigh building steel beam and core tube connecting structure which comprises an embedded steel plate fixedly installed at the end of a steel beam and a plurality of embedded parts arranged on the embedded steel plate, a plurality of threaded holes are formed in the embedded steel plate, one end of each embedded part is provided with a threaded connecting part, and the threaded connecting parts are connected to the threaded holes; a lug boss is arranged at the other end of the embedded part and is poured in the core tube; a limiting piece is arranged on one side of the embedded steel plate, and one end of the limiting piece makes contact with the steel beam. The structure is simple and compact, convenient to install and operate and good in connection stability, the steel beam does not need to be adjusted after installation, the construction efficiency is improved, and the application prospect is wide.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of construction connection between a super-high building steel beam and a core tube, and in particular to a connection structure between a super-high building steel beam and a core tube. Background Art

[0002] At present, super-high buildings occupy part of the construction market, and their structural forms are becoming increasingly diversified. Due to construction cost reasons, the structural form of full reinforced concrete structure + intermediate steel structure truss reinforcement layer is still favored. The reinforced concrete floor has a simple structural form, uses an aluminum formwork system, and adopts a construction deployment of simultaneous casting of vertical and horizontal structures. In order to keep the construction pace the same as other floors and improve quality and efficiency, the additional steel structure truss reinforcement layer in the middle needs to focus on solving the construction difficulties caused by differences in structural forms. A super-high building has 61 floors above ground, a total building height of 268m, and a single-floor area of ​​about 3,000 ㎡. The overall structure is a fully reinforced concrete structure, with the 29th floor being a steel truss reinforcement layer. The horizontal structure of the truss layer adds exposed steel beams instead of concrete beams. The steel beams and the core tube are fixed with anchor plates + anchor bars. When installing the steel beams, a support frame needs to be erected to support the steel beams to form a stable structure. The embedded structure is installed on site at the end of the steel beam to connect it to the core tube. Traditional embedded structures are usually welded at the ends of the steel beams in advance. The advance welding method requires construction before the construction of the core tube's steel structure. When the core tube's steel structure is built and the angle of the steel beam is adjusted, the embedded structure is overlapped on the core tube, reducing construction efficiency. In addition, the existing embedded structures are all one-piece structures, which require a certain amount of installation space during installation and may interfere with the core tube's steel structure, increasing construction difficulty. Utility Model Content

[0003] The utility model aims to provide a connection structure between a super-high building steel beam and a core tube, which has a simple and compact structure, is easy to install and operate, has good connection stability, does not require adjustment of the steel beam after installation, improves construction efficiency, and has broad application prospects.

[0004] In order to achieve the above purpose, the utility model adopts the following technical solutions:

[0005] A connection structure between a steel beam and a core tube of a super-high building, comprising an embedded steel plate fixedly installed on the end of the steel beam and a plurality of embedded parts arranged on the embedded steel plate, wherein a plurality of threaded holes are arranged on the embedded steel plate, a threaded connection portion is arranged at one end of the embedded part, and the threaded connection portion is connected to the threaded hole; a protrusion is arranged at the other end of the embedded part, and the protrusion is cast in the core tube; a limiting part is arranged on one side of the embedded steel plate, and one end of the limiting part is in contact with the steel beam.

[0006] Preferably, a connection space is provided on the raised portion, and a reinforcement piece is detachably provided on the connection space.

[0007] Preferably, welding grooves are provided on the top and bottom of the embedded steel plate.

[0008] Preferably, the limiting member is a limiting block fixedly mounted on the side of the embedded steel plate, and when the limiting member is clamped on the steel beam, the top and bottom surfaces of the embedded steel plate and the top and bottom surfaces of the steel beam are flush.

[0009] Preferably, the steel beam is an H-shaped steel.

[0010] Preferably, two limit members are provided, and the two limit members are provided on both sides of the web of the H-shaped steel.

[0011] Preferably, an elastic centering component is detachably mounted on the limiting member, and one end of two elastic centering components are both against the web of the H-shaped steel.

[0012] Preferably, the elastic centering assembly includes a connecting seat detachably connected to the limit member, a sleeve fixedly arranged on the connecting seat, a spring arranged in the sleeve and a support rod slidably installed in the sleeve, the spring is located between the support rod and the bottom of the sleeve, and one end of the support rod is pressed against the web of the H-shaped steel.

[0013] In the utility model, the embedded steel plates and embedded parts are installed by on-site assembly. After the position of the steel beam is fixed and the steel reinforcement structure of the core tube is tied, the connection structure can be quickly installed without adjusting the position of the steel beam relative to the core tube, which reduces the installation space of the connection structure and avoids secondary adjustment of the steel beam. The ends of the embedded parts are provided with protrusions and reinforcements to improve the connection strength with the core tube casting. The limiters and elastic centering components can quickly locate the vertical and horizontal positions of the embedded steel plates, which is convenient for subsequent welding operations. The elastic centering components are reusable and easy to disassemble and assemble. BRIEF DESCRIPTION OF THE DRAWINGS

[0014] Figure 1 It is a schematic diagram of the overall structure of the utility model;

[0015] Figure 2 This is a schematic cross-sectional view of the elastic centering component structure of the utility model;

[0016] In the figure: 1. Steel beam; 2. Embedded steel plate; 3. Embedded parts; 4. Welding groove; 5. Protrusion; 6. Reinforcement; 7. Limiting part; 8. Elastic centering assembly; 80. Connecting seat; 81. Sleeve; 82. Spring; 83. Support rod. DETAILED DESCRIPTION

[0017] The utility model is further described below in conjunction with the accompanying drawings:

[0018] like Figure 1 and Figure 2 The connection structure of a super-high building steel beam and a core tube shown in the figure comprises an embedded steel plate 2 fixedly mounted on the end of the steel beam 1 and a plurality of embedded parts 3 arranged on the embedded steel plate 2. A plurality of threaded holes are arranged on the embedded steel plate 2, and a threaded connection part is arranged at one end of the embedded part 3, and the threaded connection part is connected to the threaded hole by threading. A welding groove 4 is arranged on the top and bottom of the embedded steel plate 2, and the arrangement of the welding groove 4 facilitates welding operation and improves the reliability of welding. In this embodiment, the steel beam 1 is made of H-shaped steel.

[0019] A protrusion 5 is fixedly provided at the other end of the embedded part 3, and the protrusion 5 is cast in the core tube. Specifically, a connection space is provided on the protrusion 5, and a reinforcement member 6 is detachably provided on the connection space. Each reinforcement member 6 passes through a plurality of connection spaces located at the same layer, so as to enhance the stability of the protrusion 5 after the core tube is cast.

[0020] A limiting member 7 is provided on the side where the embedded steel plate 2 contacts the steel beam 1, and one end of the limiting member 7 contacts the steel beam 1. The limiting member 7 is a limiting block fixedly installed on the side of the embedded steel plate 2 by welding. When the limiting member 7 is stuck on the steel beam 1, the top and bottom surfaces of the embedded steel plate 2 and the top and bottom surfaces of the steel beam 1 are flush, which is used to limit the vertical height of the installed embedded steel plate 2. Two limiting members 7 are provided, and the two limiting members 7 are provided on both sides of the web of the H-shaped steel. An elastic centering component 8 is detachably installed on the limiting member 7 through a slide groove and a slider or a fastener. One end of the two elastic centering components 8 are both against the web of the H-shaped steel, which is used to center and limit the lateral position of the installed embedded steel plate 2, thereby improving the efficiency of installation and avoiding repeated adjustments.

[0021] The elastic centering assembly 8 includes a connection seat 80 detachably connected to the stopper 7, a sleeve 81 fixedly arranged on the connection seat 80, a spring 82 arranged in the sleeve 81, and a support rod 83 slidably installed in the sleeve 81, wherein the spring 82 is located between the support rod 83 and the bottom of the sleeve 81, and one end of the support rod 83 is pressed against the web of the H-shaped steel. After installing the embedded steel plate 2, the two elastic centering assemblies 8 are installed one by one on the stopper 7, and the extrusion force of the spring 82 is used to make the embedded steel plate 2 correspond to the horizontal position of the steel beam 1. After the embedded steel plate 2 is spot welded on the steel beam 1, the elastic centering assembly 8 is removed, and then full welding is performed.

[0022] The above embodiments are only some descriptions of the concept and implementation of the utility model, and are not intended to limit the concept and implementation of the utility model. Under the concept of the utility model, technical solutions that have not been substantially changed are still within the scope of protection.

Claims

1. A connection structure between a steel beam and a core tube of a super-high building, comprising an embedded steel plate fixedly mounted on the end of the steel beam and a plurality of embedded parts arranged on the embedded steel plate, characterized in that: A plurality of threaded holes are arranged on the embedded steel plate, a threaded connection portion is arranged at one end of the embedded part, and the threaded connection portion is connected to the threaded hole; a protrusion is arranged at the other end of the embedded part, and the protrusion is cast in the core tube; a limiting member is arranged on one side of the embedded steel plate, and one end of the limiting member is in contact with the steel beam.

2. The connection structure between the super-high building steel beam and the core tube according to claim 1 is characterized in that: A connection space is provided on the raised portion, and a reinforcement piece is detachably provided on the connection space.

3. The connection structure between the super-high building steel beam and the core tube according to claim 1 is characterized in that: Welding grooves are arranged on the top and bottom of the embedded steel plate.

4. The connection structure between the super-high building steel beam and the core tube according to any one of claims 1 to 3, characterized in that: The limiting member is a limiting block fixedly mounted on the side of the embedded steel plate. When the limiting member is clamped on the steel beam, the top and bottom surfaces of the embedded steel plate and the top and bottom surfaces of the steel beam are flush.

5. The connection structure between the super-high building steel beam and the core tube according to claim 4 is characterized in that: The steel beam is an H-shaped steel.

6. The connection structure between the super-high building steel beam and the core tube according to claim 5 is characterized in that: Two limiting members are provided, and the two limiting members are provided on both sides of the web of the H-shaped steel.

7. The connection structure between the super-high building steel beam and the core tube according to claim 6 is characterized in that: An elastic centering component is detachably mounted on the limiting member, and one end of two elastic centering components are both against the web of the H-shaped steel.

8. The connection structure between the super-high building steel beam and the core tube according to claim 7 is characterized in that: The elastic centering component includes a connecting seat detachably connected to the limit member, a sleeve fixedly arranged on the connecting seat, a spring arranged in the sleeve and a support rod slidably installed in the sleeve, the spring is located between the support rod and the bottom of the sleeve, and one end of the support rod is pressed against the web of the H-shaped steel.