Composite polyurethane heat preservation steel pipe

By introducing the combined structure of snap ring, traction ring, drawbar and bolt into the polyurethane insulated steel pipe, the problem of time-consuming and laborious connection is solved, and the closed-cell structure of the polyurethane material improves the corrosion resistance and insulation effect, achieving rapid disassembly. Installation and efficient insulation.

CN221880544UActive Publication Date: 2024-10-22HEILONGJIANG TENGSHUN PIPE IND CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202323612767.3
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-12-28
Publication Date
2024-10-22
Estimated Expiration
2033-12-28

AI Technical Summary

Technical Problem

The existing polyurethane insulated steel pipe lacks a connecting device. When connecting, it needs to be heated and left to wait for foaming to complete, which is time-consuming and labor-intensive, and lacks a quick disassembly and assembly function.

Method used

A composite polyurethane insulated steel pipe is designed, which adopts a combined structure of a snap ring, a traction ring, a drawbar and a bolt. It realizes quick connection and disassembly by rotating the bolt and sliding the traction ring, drawbar and pressure block, and connects the outer tube and the inner tube. Polyurethane insulation pipes are installed between them to improve corrosion resistance and insulation effect.

Benefits of technology

It realizes the quick connection and disassembly of polyurethane insulated steel pipes, improves installation efficiency, and reduces heat conduction and convection through the closed-cell structure of polyurethane materials, enhancing corrosion resistance and thermal insulation effects.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221880544U_ABST
    Figure CN221880544U_ABST
Patent Text Reader

Abstract

The utility model discloses a composite polyurethane heat preservation steel pipe, which relates to the technical field of heat preservation steel pipes, comprises an outer pipe, and is characterized in that a clamping ring is fixedly arranged at the side end of the outer pipe, and three pressing blocks are uniformly and rotatably arranged at the side end of the clamping ring; a traction ring is mounted on the outer side wall of the outer pipe on one side of the clamping ring in a sliding manner; wherein three threaded holes are uniformly formed in the side end of the traction ring, and three traction rods are uniformly and fixedly mounted at the side end of the traction ring; wherein the side ends of the three traction rods are rotationally connected with the side ends of the pressing blocks correspondingly, and three bolts are evenly and rotationally installed at the positions, located on one sides of the traction rods, of the side end of the traction ring; wherein the three bolts are installed in three threaded holes formed in the side end of the traction ring correspondingly, a fixing ring is fixedly installed at the side end, located on the opposite face of the clamping ring, of the outer pipe, and a heat preservation pipe is fixedly installed on the inner side wall of the outer pipe.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of heat-insulating steel pipes, in particular to a composite polyurethane heat-insulating steel pipe. Background Art

[0002] The urban heating system consists of three parts: heat source, heat network and heat users. The urban heating system is a heating network that uses centralized heat sources to supply heat energy for production or life to heat energy users through facilities such as heating pipelines. The heating network is composed of countless insulated steel pipes, which supply hot water from the heat source to heat energy users.

[0003] At present, there is a polyurethane insulated steel pipe (such as patent number: CN206504021 U) disclosed, which includes a steel pipe body, the outer surface of the steel pipe body is sprayed with an epoxy powder anti-corrosion coating, the outer surface of the epoxy powder anti-corrosion coating is sprayed with an adhesive layer, the outer surface of the adhesive layer is sprayed with a polyethylene anti-corrosion coating, and the inner wall of the steel pipe body is pasted with an insulation layer, and the material of the insulation layer is polyurethane. The beneficial effects of the utility model are simple structure and strong practicality.

[0004] However, in the process of implementing the above technical scheme, it was found that there are at least the following technical problems: the existing polyurethane insulated steel pipe lacks a connecting device. When connecting, it is necessary to heat the ends of the two polyurethane insulated pipes to a molten state, wrap the insulation sleeve or insulation board between the two pipe ends, and ensure a tight fit while waiting for the polyurethane foaming to be completed. Generally, it takes more than 30 minutes to stand for foaming. After completion, check whether there are voids or gaps at the interface. If there are any, they need to be repaired or re-foamed. This connection method is time-consuming and labor-intensive. Utility Model Content

[0005] 1. Technical issues to be solved

[0006] In view of the deficiencies in the prior art, the utility model provides a composite polyurethane insulated steel pipe to solve the problem that the existing polyurethane insulated steel pipe lacks a connecting device. When connecting, the pipe ends of the two polyurethane insulated pipes need to be heated to a molten state, and an insulation sleeve or an insulation board needs to be wrapped between the two pipe ends to ensure a tight fit while waiting for the polyurethane foaming to be completed. Generally, it needs to be left to stand for more than 30 minutes after the foaming is completed, and then check whether there are voids or gaps at the interface. If so, it needs to be repaired or re-foamed. This connection method has the technical problem of being time-consuming and labor-intensive.

[0007] (II) Technical solution

[0008] In order to achieve the above objectives, the present invention is implemented through the following technical solutions:

[0009] A composite polyurethane insulated steel pipe comprises an outer pipe, a clamping ring is fixedly installed on the side end of the outer pipe, three pressure blocks are evenly rotatably installed on the side end of the clamping ring, a traction ring is slidably installed on the outer side wall of the outer pipe located on one side of the clamping ring; three threaded holes are evenly opened on the side end of the traction ring, three traction rods are evenly fixedly installed on the side end of the traction ring; the side ends of the three traction rods are respectively rotatably connected to the side ends of the pressure blocks, and three bolts are evenly rotatably installed on the side end of the traction ring located on one side of the traction rod; the three bolts are respectively installed in the three threaded holes opened on the side end of the traction ring, a fixing ring is fixedly installed on the side end of the outer pipe located on the opposite side of the clamping ring, an insulation pipe is fixedly installed on the inner side wall of the outer pipe, and an inner pipe is fixedly installed on the inner side wall of the insulation pipe.

[0010] Preferably, a second sealing ring is fixedly mounted on the side end of the fixing ring located on the opposite side of the outer tube.

[0011] Preferably: a first sealing gasket is fixedly mounted on the side end of the clamping ring.

[0012] (III) Beneficial effects

[0013] 1. When installing the pipeline, first rotate the three bolts so that the traction ring can slide along the outer wall of the outer tube, pull the traction ring backward, and make the traction ring drive the traction rod to slide backward. When the traction rod slides backward, pull the side end of the pressure block to make the pressure block rotate around the connection between the pressure block and the clamping ring, open the closed loop formed by the three pressure blocks, and then align the fixing ring of another insulated steel pipe with the clamping ring, push the traction ring forward, make the traction ring drive the traction rod to slide forward, so that the pressure block rotates in the opposite direction to form a closed loop composed of three pressure blocks, which presses the fixing ring tightly against the side end of the clamping ring. When the pressure block presses the fixing ring, the threaded hole at the side end of the traction ring just corresponds to the through hole on the outer wall of the outer tube, tighten the bolts to complete the connection, and drive the sliding of the traction rod through the traction ring to make the pressure block rotate, complete the pressing or releasing of the fixing ring, and achieve the effect of quick disassembly and assembly of the insulated steel pipe.

[0014] 2. The outer pipe and the inner pipe are made of DP steel, which can greatly increase the corrosion resistance. An insulation pipe made of polyurethane is installed between the outer pipe and the inner pipe. Because the polyurethane material has a closed-cell structure, it can effectively prevent heat conduction and heat convection, thereby reducing heat loss and waste. When the heating water flows inside the inner pipe, the insulation pipe will play a role in insulation. Through the superposition of the outer pipe, the insulation pipe and the inner pipe, the three-layer structure of the pipeline is completed, achieving both high corrosion resistance and insulation effect. BRIEF DESCRIPTION OF THE DRAWINGS

[0015] The above description is only an overview of the technical solution of the utility model. In order to more clearly understand the technical means of the utility model and implement it according to the contents of the specification, the following is a detailed description of the preferred embodiments of the utility model in conjunction with the accompanying drawings.

[0016] Figure 1 It is a structural diagram of the utility model;

[0017] Figure 2 It is a structural diagram of the utility model;

[0018] Figure 3 It is a structural diagram of the utility model;

[0019] Figure 4 It is a structural diagram of the utility model.

[0020] Legend: 1. Outer tube; 2. Clamping ring; 3. Traction ring; 4. Traction rod; 5. Pressure block; 6. First sealing gasket; 7. Fixing ring; 8. Insulation tube; 9. Inner tube; 11. Bolt; 12. Second sealing ring. DETAILED DESCRIPTION

[0021] The embodiment of the present application provides a composite polyurethane insulated steel pipe, which effectively solves the problem of the existing polyurethane insulated steel pipe lacking a connecting device. When connecting, the pipe ends of the two polyurethane insulated pipes need to be heated to a molten state, and the insulation sleeve or insulation board needs to be wrapped between the two pipe ends to ensure a tight fit and wait for the polyurethane foaming to be completed. Generally, it needs to be left to stand for more than 30 minutes. After the foaming is completed, check whether there are voids or gaps at the interface. If there are any, they need to be repaired or re-foamed. This connection method has the technical problem of being time-consuming and labor-intensive. When installing the pipeline, first rotate the three bolts so that the traction ring can slide along the outer wall of the outer pipe, pull the traction ring backward, and let the traction ring drive the traction rod to slide backward. When the traction rod slides backward, it will pull the side end of the pressing block to rotate around the connection between the pressing block and the clamping ring, open the closed loop formed by the three pressing blocks, and then align the fixing ring of the other insulated steel pipe with the clamping ring, push the traction ring forward, and the traction ring The ring drives the traction rod to slide forward, so that the pressure block rotates in the opposite direction to form a closed loop composed of three pressure blocks, which presses the fixing ring tightly against the side end of the clamping ring. When the pressure block presses the fixing ring, the threaded hole at the side end of the traction ring just corresponds to the through hole on the outer wall of the outer tube. The connection is completed by tightening the bolts, and the traction rod is driven to slide by the traction ring to rotate the pressure block to complete the pressing or releasing of the fixing ring, thereby achieving the effect of rapid disassembly and assembly of the insulated steel pipe. The outer and inner pipes are made of DP steel material, which can greatly increase the corrosion resistance. An insulation pipe made of polyurethane is installed between the outer and inner pipes. Because the polyurethane material has a closed-cell structure, it can effectively prevent heat conduction and heat convection, thereby reducing heat loss and waste. When the heating water flows inside the inner pipe, the insulation pipe will play a role of insulation. Through the superposition of the outer pipe, the insulation pipe and the inner pipe, the three-layer structure of the pipeline is completed, achieving both high corrosion resistance and insulation effect.

[0022] Example

[0023] like Figure 1, Figure 2 , Figure 3 and Figure 4 As shown, the technical solution in the embodiment of the present application effectively solves the existing polyurethane insulated steel pipe, which lacks a connecting device. When connecting, the pipe ends of the two polyurethane insulated pipes need to be heated to a molten state, and the insulation sleeve or insulation board needs to be wrapped between the two pipe ends, and it is ensured to be tightly fitted and wait for the polyurethane foaming to be completed. Generally, it takes more than 30 minutes to stand for the foaming. After the foaming is completed, check whether there are cavities or gaps at the interface. If there are any, they need to be repaired or re-foamed. This connection method is time-consuming and labor-intensive. The overall idea is as follows:

[0024] In view of the problems existing in the prior art, the utility model provides a composite polyurethane insulated steel pipe, including an outer tube 1, a clamping ring 2 is fixedly installed on the side end of the outer tube 1, three pressing blocks 5 are evenly rotatably installed on the side end of the clamping ring 2, and a traction ring 3 is slidably installed on the outer wall of the outer tube 1 on one side of the clamping ring 2.

[0025] Three threaded holes are evenly opened on the side end of the traction ring 3, and three traction rods 4 are evenly fixedly installed on the side end of the traction ring 3; the side ends of the three traction rods 4 are rotatably connected to the side ends of the pressure block 5 respectively, and three bolts 11 are evenly rotatably installed on the side end of the traction ring 3 located on one side of the traction rod 4; the three bolts 11 are respectively installed in the three threaded holes opened on the side end of the traction ring 3.

[0026] A fixing ring 7 is fixedly installed on the side end of the outer tube 1 located on the opposite side of the clamping ring 2, an insulation tube 8 is fixedly installed on the inner wall of the outer tube 1, an inner tube 9 is fixedly installed on the inner wall of the insulation tube 8, a second sealing ring 12 is fixedly installed on the side end of the fixing ring 7 located on the opposite side of the outer tube 1, and a first sealing gasket 6 is fixedly installed on the side end of the clamping ring 2.

[0027] Working principle:

[0028] When the traction rod 4 slides backward, the side end of the pressing block 5 will be pulled, so that the pressing block 5 rotates around the connection between the pressing block 5 and the clamping ring 2, and the closed loop formed by the three pressing blocks 5 is opened. Then, the fixing ring 7 of another insulating steel pipe is aligned with the clamping ring 2, and the traction ring 3 is pushed forward, so that the traction ring 3 drives the traction rod 4 to slide forward, so that the pressing block 5 rotates in the opposite direction to form a closed loop composed of three pressing blocks 5. The closed loop presses the fixing ring 7 tightly against the side end of the clamping ring 2. When the pressing block 5 presses the fixing ring 7, the threaded hole at the side end of the traction ring 3 just corresponds to the through hole on the outer wall of the outer tube 1. The bolts 11 are tightened to complete the connection. The sliding of the traction rod 4 driven by the traction ring 3 causes the pressing block 5 to rotate, and the fixing ring 7 is pressed or released, thereby achieving the effect of rapid disassembly and assembly of the insulating steel pipe.

[0029] In the second step, when laying the heating pipes, the pipes need to be laid underground or on wall brackets, and the temperature of the heating water is relatively high, which can easily cause corrosion to the pipes. The outer pipe 1 and the inner pipe 9 are made of DP steel, which can greatly increase the corrosion resistance. An insulation pipe 8 made of polyurethane is installed between the outer pipe 1 and the inner pipe 9. Because the polyurethane material has a closed-cell structure, it can effectively prevent heat conduction and heat convection, thereby reducing heat loss and waste. When the heating water flows inside the inner pipe 9, the insulation pipe 8 will play a role in heat preservation. Through the superposition of the outer pipe 1, the insulation pipe 8 and the inner pipe 9, the three-layer structure of the pipeline is completed, achieving both high corrosion resistance and heat preservation effect.

[0030] Finally, it should be noted that: Obviously, the above embodiments are only examples for clearly explaining the present invention, and are not intended to limit the implementation methods. For ordinary technicians in the relevant field, other different forms of changes or modifications can be made based on the above description. It is not necessary and impossible to list all the implementation methods here. The obvious changes or modifications derived from this are still within the scope of protection of the present invention.

Claims

1. A composite polyurethane insulated steel pipe, comprising an outer pipe (1), characterized in that: A clamping ring (2) is fixedly mounted on the side end of the outer tube (1), three pressing blocks (5) are evenly rotatably mounted on the side end of the clamping ring (2), and a traction ring (3) is slidably mounted on the outer side wall of the outer tube (1) located on one side of the clamping ring (2); The side end of the traction ring (3) is evenly provided with three threaded holes.

2. A composite polyurethane insulated steel pipe as claimed in claim 1, characterized in that: Three traction rods (4) are evenly and fixedly mounted on the side ends of the traction ring (3); The side ends of the three traction rods (4) are rotatably connected to the side ends of the pressing blocks (5) respectively.

3. A composite polyurethane insulated steel pipe as claimed in claim 2, characterized in that: The side end of the traction ring (3) located on one side of the traction rod (4) is evenly rotatably mounted with three bolts (11); The three bolts (11) are respectively installed in three threaded holes opened at the side ends of the traction ring (3).

4. A composite polyurethane insulated steel pipe as claimed in claim 1, characterized in that: A fixing ring (7) is fixedly mounted on the side end of the outer tube (1) located on the opposite side of the clamping ring (2).

5. The composite polyurethane insulated steel pipe according to claim 1, characterized in that: A heat preservation pipe (8) is fixedly mounted on the inner side wall of the outer pipe (1).

6. A composite polyurethane insulated steel pipe as claimed in claim 5, characterized in that: An inner tube (9) is fixedly mounted on the inner side wall of the thermal insulation tube (8).

7. A composite polyurethane insulated steel pipe as claimed in claim 4, characterized in that: A second sealing ring (12) is fixedly mounted on the side end of the fixing ring (7) located on the opposite side of the outer tube (1).

8. The composite polyurethane insulated steel pipe according to claim 1, characterized in that: A first sealing gasket (6) is fixedly mounted on the side end of the clamping ring (2).