Cantilever construction cast-in-place support
By burying pre-embedded tie rods and pre-embedded steel rods in the bridge pier, combined with the steel pipe columns on the left and right sides, a bracket is formed to support the transverse main beam, which solves the problems of large steel consumption and slow construction speed of conventional brackets, and achieves a reduction in the number of steel pipes and improvement of construction efficiency.
Patent Information
- Application Number
- CN202420202817.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-01-29
- Publication Date
- 2024-10-29
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
Conventional beam-column supports have the problems of large steel consumption, complex structure, slow construction speed, long construction period, and poor economic benefits.
Pre-embedded tie rods and pre-embedded steel rods are embedded in the pier, and a row of steel pipe columns is set up on the left and right sides. The embedded steel rods support the transverse main beams. The pre-embedded tie rods exert a pulling force on the steel pipe columns, reducing the number of steel pipes and improving construction efficiency.
The number of steel pipes is reduced, the economic benefits are improved, the construction period is shortened, the safety risks of high-altitude operations on high piers are reduced, and the construction progress is accelerated.
Smart Images

Figure CN221919032U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of building engineering, in particular to a cantilever construction cast-in-place bracket. Background Art
[0002] Conventional beam-column support layout forms are to arrange two rows of steel pipe columns on the mileage side of the pier body, and arrange transverse main beams on the top of the steel pipe columns. The transverse main beams serve as the support of the longitudinal distribution beams. The longitudinal distribution beams are arranged on the upper part of the transverse main beams. The template system is laid on the longitudinal distribution beams, and the two rows of steel pipe columns are fixed by longitudinal column inter-column diagonal braces. This support form has the problems of large steel consumption, complex support structure, slow construction speed, long construction period, waste of manpower and material resources, and poor economic benefits. Utility Model Content
[0003] The purpose of the utility model is to overcome the deficiencies in the above-mentioned prior art and to provide a cantilever construction cast-in-place bracket, in which pre-buried tie rods and pre-buried steel bars are embedded in the pier, and a row of steel pipe columns are arranged on each side of the pier. The pre-buried steel bars and the two rows of steel pipe columns form a bracket for supporting the transverse main beam. The pre-buried tie rods exert a pulling force on the steel pipe columns on the left and right sides of the pier to keep the steel pipe columns stable. The pre-buried steel bars support the transverse main beam upward by supporting the steel pipes. The bracket of the utility model reduces the number of steel pipes and improves the economic benefits.
[0004] To achieve the above-mentioned purpose, the technical solution adopted by the utility model is: a cantilever construction cast-in-place bracket includes a pier, a steel pipe column, an embedded steel rod and an embedded tie rod arranged on a bearing platform, a transverse main beam is arranged on the top of the pier, and the number of the steel pipe columns is multiple, and the multiple steel pipe columns are arranged in two rows and respectively arranged on the left and right sides of the pier, and a wall connection piece is arranged between each of the steel pipe columns and the pier, the embedded steel rod is buried in the upper part of the pier, and the left and right ends of the embedded steel rod both pass through the pier horizontally and leave a distance between the side walls of the pier, and the left and right ends of the embedded steel rod are provided with supporting steel pipes, which extend upward and are pressed against the transverse main beam, and the embedded tie rods are buried in the inside of the pier and connected to the wall connection piece.
[0005] Preferably, the embedded tie rods include a first embedded tie rod and a second embedded tie rod, the first embedded tie rods are arranged on the upper side of the second embedded tie rods, the number of the first embedded tie rods and the second embedded tie rods are the same and both are multiple, the multiple first embedded tie rods are located at the same height and are horizontally arranged, the multiple second embedded tie rods are located at the same height and are horizontally arranged, and each of the first embedded tie rods is provided with an external plate at its left and right ends near the piers and each of the second embedded tie rods is provided with an external plate at its left and right ends near the piers, and the external plate is a square structure and is close to the outer wall of the pier.
[0006] Preferably, there are multiple wall connecting members, one end of each of the wall connecting members is connected to the steel pipe column, and one end of each of the wall connecting members away from the steel pipe column is connected to an external plate.
[0007] Preferably, there are a plurality of pre-embedded steel bars, and a pre-embedded steel bar is provided on the upper side of each of the first pre-embedded tie rods.
[0008] Preferably, the first embedded tie rods and the second embedded tie rods are both precision-rolled threaded steel embedded tie rods.
[0009] Compared with the prior art, the utility model has the following advantages:
[0010] 1. The utility model embeds pre-buried tie rods and pre-buried steel bars in the pier, and a row of steel pipe columns are arranged on the left and right sides of the pier respectively. The pre-buried steel bars and the two rows of steel pipe columns form a bracket for supporting the transverse main beam. The pre-buried tie rods exert a pulling force on the steel pipe columns on the left and right sides of the pier to keep the steel pipe columns stable. The pre-buried steel bars support the transverse main beam upward by supporting the steel pipes. The bracket of the utility model reduces the number of steel pipes and improves the economic benefits.
[0011] 2. The utility model embeds pre-buried tie rods in the bridge piers to fix the steel pipe columns on the left and right sides of the bridge piers, thereby improving the construction efficiency of the supporting structure, shortening the construction period and reducing the labor intensity of the staff.
[0012] 3. The utility model uses steel rods instead of steel pipe columns as the support points of the crossbeam, thus reducing a row of steel pipe columns, which not only saves the amount of steel pipes, but also reduces the safety risks of high-altitude operations on high piers, speeds up the construction progress, and shortens the construction period.
[0013] The present invention is further described in detail below through the accompanying drawings and embodiments. BRIEF DESCRIPTION OF THE DRAWINGS
[0014] Figure 1 It is a structural schematic diagram of the utility model.
[0015] Figure 2 for Figure 1 Enlarged structural diagram at A in the middle.
[0016] Description of reference numerals:
[0017] 1—bridge pier; 2—steel pipe column; 3—embedded steel rod;
[0018] 4—first embedded tie rod; 5—second embedded tie rod; 6—wall connection piece;
[0019] 7—external connecting plate; 8—supporting steel pipe; 9—capping platform;
[0020] 10—Transverse main beam. DETAILED DESCRIPTION
[0021] like Figure 1 As shown, the utility model includes a pier 1, a steel tube column 2, an embedded steel rod 3 and an embedded tie rod. The pier 1 is arranged on a cap 9 and a transverse main beam 10 is arranged on the top of the pier 1. There are multiple steel tube columns 2, and the multiple steel tube columns 2 are arranged in two rows on the left and right sides of the pier 1 respectively. A wall connecting piece 6 is arranged between each steel tube column 2 and the pier 1. The embedded steel rod 3 is buried in the upper part of the pier 1 and the left and right ends of the embedded steel rod 3 are horizontally passed through the pier 1 and a distance is left between the side wall of the pier 1. Support steel pipes 8 are arranged on the left and right ends of the embedded steel rod 3. The support steel pipe 8 extends upward and is pressed against the transverse main beam 10. The embedded tie rod 4 is buried in the inside of the pier 1 and is connected to the wall connecting piece 6.
[0022] The cast-in-place bracket of the utility model is mainly used for 0# blocks. A row of steel pipe columns 2 is respectively arranged on the left and right sides of the pier 1, and the number of the two rows of steel pipe columns 2 is the same. Each steel pipe column 2 is formed by welding a plurality of steel pipes end to end according to the height of the pier 1. The two ends of each steel pipe column 2 are respectively connected to the pedestal 9 and the transverse main beam 10. The distance between two adjacent steel pipe columns 2 in each row is adjusted according to the position of the embedded tie rod. A steel pipe column 2 is respectively arranged on the left and right sides of the embedded tie rod, and the embedded tie rod is connected to the steel pipe column 2 through a wall connecting member 6, one end of the wall connecting member 6 is connected to the embedded tie rod, and the end of the wall connecting member 6 away from the embedded tie rod is connected to the steel pipe column 2. The steel pipe columns 2 on both sides of the pier 1 generate opposite forces on the embedded tie rod through the wall connecting member 6, and the steel pipe columns 2 are controlled by the embedded tie rod to support the transverse main beam 10, thereby improving the stability of the steel pipe columns 2. The embedded steel rod 3 on the upper part of the pier 1 supports the transverse main beam 10 upward through the supporting steel pipe 8. The embedded steel rod 3 and the steel pipe column 2 together form an upward supporting effect on the transverse main beam 10. There are multiple supporting steel pipes 8, which are I-beams. The multiple supporting steel pipes 8 are respectively arranged on the upper part of the embedded steel rod 3 located on the outer side of the pier 1. The multiple supporting steel pipes 8 can be neatly arranged on the upper side of the embedded steel rod 3, or arranged according to a certain pattern.
[0023] like Figure 1 , Figure 2 As shown, the embedded tie rods include a first embedded tie rod 4 and a second embedded tie rod 5. The first embedded tie rod 4 is arranged on the upper side of the second embedded tie rod 5. The number of the first embedded tie rod 4 and the second embedded tie rod 5 is the same and both are multiple. The multiple first embedded tie rods 4 are located at the same height and are horizontally arranged. The multiple second embedded tie rods 5 are located at the same height and are horizontally arranged. An external plate 7 is arranged at the left and right ends of each of the first embedded tie rod 4 and the second embedded tie rod 5 near the pier 1. The external plate 7 is a square structure and is close to the outer wall of the pier 1.
[0024] The first pre-embedded tie rod 4 and the second pre-embedded tie rod 5 are both made of finely rolled threaded steel. The first pre-embedded tie rod 4 is arranged near the top of the pier 1, and the second pre-embedded tie rod 5 is arranged near the bottom of the pier 1. The left and right ends of the first pre-embedded tie rod 4 and the second pre-embedded tie rod 5 are both threaded structures and locked by nuts. The connecting line of the first pre-embedded tie rod 4 and the second pre-embedded tie rod 5 located in the same row is perpendicular to the pedestal 9. The left and right ends of the first pre-embedded tie rod 4 and the second pre-embedded tie rod 5 are respectively connected to the steel pipe column 2 through the wall connecting piece 6. Two wall connecting pieces 6 are connected to each steel pipe column 2 and the two wall connecting pieces 6 are parallel. Through the wall connecting piece 6, the first pre-embedded tie rod 4 and the second pre-embedded tie rod 5 are both formed with the steel pipe column 2 in the horizontal direction to ensure the stability of the steel pipe column 2. According to the height of the pier 1, three or four pre-embedded tie rods can also be arranged, and the steel pipe column 2 can be fixed by multiple pre-embedded tie rods.
[0025] like Figure 1 , Figure 2 As shown, there are multiple wall connecting members 6 , one end of each wall connecting member 6 is connected to the steel pipe column 2 , and one end of each wall connecting member 6 away from the steel pipe column 2 is connected to the external connecting plate 7 .
[0026] The wall connecting member 6 is a steel pipe, and each wall connecting member 6 has the same length. The left and right ends of each wall connecting member 6 are rigidly connected to the steel pipe column 2 and the external connecting plate 7 respectively. The wall connecting member 6 is used to fix the pier 1 to the steel pipe column 2, so that the steel pipe column 2 can stably support the transverse main beam 10.
[0027] There are multiple embedded steel bars 3 , and an embedded steel bar 3 is arranged on the upper side of each first embedded tie rod 4 .
[0028] The embedded steel rod 3 is arranged near the top of the pier 1. The embedded steel rod 3 can be a square steel rod or a round steel rod. If the embedded steel rod 3 is a square steel rod, a plurality of supporting steel pipes 8 can be arranged on the upper side of the embedded steel rod 3, and the transverse main beam 10 can be supported by the plurality of supporting steel pipes 8. If the embedded steel rod 3 is a round steel rod, a plurality of supporting steel pipes 8 can be arranged in a line on the embedded steel rod 3. The transverse main beam 10 is supported by the embedded steel rod 3 and the steel pipe column 2, thereby ensuring the stability of the transverse main beam 10.
[0029] During the construction of the pier 1, the embedded steel rod 3, the first embedded tie rod 4 and the second embedded tie rod 5 are horizontally arranged in the pier 1. The embedded steel rod 3 is located near the top of the pier 1, the first embedded tie rod 4 is located on the lower side of the embedded steel rod 3, and the second embedded tie rod 5 is located near the bottom of the pier 1. After the embedded steel rod 3, the first embedded tie rod 4 and the second embedded tie rod 5 are arranged, the pier 1 is poured with concrete. Then, a row of steel pipe columns 2 are respectively arranged on the left and right sides of the pier 1. The bottom of the steel pipe column 2 is fixedly connected to the pedestal 9, and the top of the steel pipe column 2 is fixedly connected to the transverse main beam 10 through the supporting steel pipe 8. The external connecting plates 7 at the left and right ends of the first embedded tie rod 4 and the second embedded tie rod 5 are both connected to the wall connecting member 6, and the end of the wall connecting member 6 away from the external connecting plate 7 is connected to the steel pipe column 2. The wall connection member 6 makes the steel pipe column 2 and the bridge pier 1 form an integral support structure, which greatly enhances the anti-overturning ability of the support structure. The wall connection member 6 needs to be kept horizontal when connecting the external plate 7 and the steel pipe column 2. A plurality of support steel pipes 8 are arranged on the upper side of the embedded steel rod 3, and the support of the transverse main beam 10 is realized by the support steel pipe 8. The support structure is formed by fixing the steel pipe column 2 with the embedded steel rod 3 and the embedded tie rod, which greatly reduces the number of steel pipes required for the support structure, improves the efficiency of the support structure construction, and shortens the construction period.
[0030] The above is only a preferred embodiment of the present invention and does not constitute any limitation to the present invention. Any simple modification, change and equivalent structural transformation made to the above embodiments according to the technical essence of the present invention shall still fall within the protection scope of the technical solution of the present invention.
Claims
1. A cantilever cast-in-place bracket, Features: The invention comprises a pier (1) arranged on a pedestal (9), a steel tube column (2), an embedded steel rod (3) and an embedded tension rod. A transverse main beam (10) is arranged on the top of the pier (1). There are a plurality of steel tube columns (2), which are arranged in two rows on the left and right sides of the pier (1). A wall connection member (6) is arranged between each of the steel tube columns (2) and the pier (1). The embedded steel rod (3) is embedded in the upper part of the pier (1), and the left and right ends of the embedded steel rod (3) are horizontally passed through the pier (1) and a distance is left between the side wall of the pier (1). The left and right ends of the embedded steel rod (3) are provided with supporting steel pipes (8), which extend upward and are tightly pressed against the transverse main beam (10). The embedded tension rods are embedded in the interior of the pier (1) and are connected to the wall connection member (6).
2. A cantilever cast-in-place bracket according to claim 1, Features: The embedded tie rods include a first embedded tie rod (4) and a second embedded tie rod (5), the first embedded tie rod (4) is arranged on the upper side of the second embedded tie rod (5), the first embedded tie rod (4) and the second embedded tie rod (5) are the same in number and are both multiple, multiple first embedded tie rods (4) are located at the same height and are arranged horizontally, multiple second embedded tie rods (5) are located at the same height and are arranged horizontally, and each of the first embedded tie rods (4) is provided with an external plate (7) at its left and right ends near the pier (1) and each of the second embedded tie rods (5) is provided with a external plate (7) at its left and right ends near the pier (1), and the external plate (7) is a square structure and is closely attached to the outer wall of the pier (1).
3. A cantilever cast-in-place support according to claim 1, Features: There are a plurality of wall connecting members (6), one end of each wall connecting member (6) is connected to a steel pipe column (2), and one end of each wall connecting member (6) away from the steel pipe column (2) is connected to an external connection plate (7).
4. A cantilever cast-in-place support according to claim 2, Features: The number of the embedded steel bars (3) is plural, and an embedded steel bar (3) is arranged on the upper side of each of the first embedded tie rods (4).
5. A cantilever cast-in-place support according to claim 2, Features: The first embedded tie rod (4) and the second embedded tie rod (5) are both precision-rolled threaded steel embedded tie rods.