Prefabricated pier bearing platform and pier
Through the block prefabricated design and connection structure of the prefabricated pier cap, the existing technology problems of high energy consumption and difficulty in transportation and hoisting of the bridge pier cap are solved, convenient assembly and efficient construction are achieved, and construction costs are reduced.
Patent Information
- Application Number
- CN202323494309.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-12-21
- Publication Date
- 2024-10-29
- Estimated Expiration
- 2033-12-21
AI Technical Summary
The existing bridge pier cap construction method has high energy consumption, a lot of labor, and large environmental pollution, and the overall prefabricated method has many problems during transportation and hoisting.
The block prefabrication design of the prefabricated pier cap is adopted, and the connection between the prefabricated blocks and the prefabricated connecting blocks simplifies the on-site processing procedures, reduces the difficulty of transportation and hoisting, and uses structures such as grouting sleeves and connecting steel bars to achieve convenient assembly.
It achieves convenient assembly and efficient transportation and hoisting of bridge pier caps, reduces the difficulty of on-site processing, improves construction efficiency and ease of use, and reduces construction costs.
Smart Images

Figure CN221919502U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of bridge construction, in particular to a prefabricated bridge pier cap and a bridge pier having the prefabricated bridge pier cap. Background Art
[0002] In the related technologies, bridge pier caps are mostly constructed by on-site casting, which has the disadvantages of high energy consumption, high labor, high requirements for on-site construction, and great environmental pollution. However, since the foundation of bridge pier caps is mostly large-sized and large-volume concrete structure, if the overall prefabrication method is adopted, there are also many problems in the transportation and hoisting process, and there is room for improvement. Utility Model Content
[0003] The utility model aims to solve at least one of the technical problems existing in the prior art. To this end, one purpose of the utility model is to provide a prefabricated bridge pier cap, the prefabricated blocks and prefabricated connecting blocks are easy to transport, hoist and assemble, which is conducive to reducing on-site processing procedures and reducing processing difficulty.
[0004] According to the prefabricated pier cap of the embodiment of the utility model, it includes: two prefabricated blocks separated from each other, each of the two prefabricated blocks is provided with a first connecting part on one side facing each other; a prefabricated connecting block, the prefabricated connecting block is arranged between the two prefabricated blocks, the prefabricated connecting block is provided with a second connecting part corresponding to the prefabricated blocks, and the second connecting part is connected and matched with the first connecting part.
[0005] According to the prefabricated pier cap in the embodiment of the utility model, by arranging the prefabricated pier cap to be connected by prefabricated blocks and prefabricated connecting blocks, block prefabrication of the prefabricated pier cap can be realized, which is convenient for transportation and lifting, and the connection process between the prefabricated blocks and the prefabricated connecting blocks is simple, which can reduce on-site processing procedures, reduce processing difficulty, and improve the convenience of use of the prefabricated pier cap.
[0006] According to the prefabricated pier cap in some embodiments of the utility model, one of the first connection part and the second connection part is a first grouting sleeve, and the other is a connecting steel bar, and the connecting steel bar is inserted into and connected to the first grouting sleeve.
[0007] According to the prefabricated pier caps of some embodiments of the utility model, the prefabricated blocks are provided with contact planes cooperating with the prefabricated connecting blocks, the connecting steel bars are provided on the contact planes, and the extending directions of the connecting steel bars are provided perpendicularly to the contact planes.
[0008] According to the prefabricated pier cap in some embodiments of the present invention, at least one of the side walls of the prefabricated blocks and the prefabricated connecting blocks facing each other is provided with a concave-convex structure.
[0009] According to some embodiments of the prefabricated pier cap of the utility model, the prefabricated block includes a base, a first connecting member and a second connecting member, the first connecting member and the second connecting member are both arranged in the base, at least a portion of the first connecting member protrudes above the base and is used to be connected to the pier column, and the second connecting member forms a grouting space open in the height direction, and the grouting space is used to accommodate the pile foundation steel bars of the pile foundation.
[0010] According to the prefabricated pier cap of some embodiments of the utility model, the second connecting member includes an embedded corrugated pipe, the embedded corrugated pipe is penetrated in the base and forms the grouting space, the base is provided with grouting holes, the grouting holes penetrate the base along the height direction, the bottom wall of the prefabricated block is used to support on the pile foundation and define a grouting channel with the pile foundation, and the grouting hole is connected with the grouting space through the grouting channel.
[0011] According to some embodiments of the prefabricated pier cap of the utility model, the second connecting member includes a plurality of the embedded corrugated pipes, and the plurality of the embedded corrugated pipes are arranged at intervals around the grouting holes; the first connecting member includes a plurality of pier column steel bars, and the plurality of the pier column steel bars are arranged at intervals around the grouting holes and staggered with the embedded corrugated pipes in the radial direction.
[0012] According to the prefabricated pier cap in some embodiments of the present invention, each of the prefabricated blocks has two second connecting members, and the two second connecting members are respectively located on both sides of the corresponding first connecting member.
[0013] According to the prefabricated pier cap in some embodiments of the utility model, the prefabricated connecting block extends along the first direction and has its two ends respectively connected to the two prefabricated blocks, the two second connecting members of the same prefabricated block are respectively arranged on both sides of the corresponding first connecting member along the second direction, and the first direction is arranged perpendicular to the second direction.
[0014] The utility model also provides a bridge pier.
[0015] The pier according to the embodiment of the utility model comprises: a pier column, a pile foundation and a prefabricated pier cap according to any of the above embodiments, the pile foundation is provided with pile foundation steel bars, the prefabricated pier cap is supported on the pile foundation and connected to the pile foundation steel bars, and the pier column is supported on the prefabricated pier cap and connected to the prefabricated pier cap.
[0016] The bridge piers according to the embodiments of the utility model are formed by arranging a prefabricated bridge pier cap which is connected by prefabricated blocks and prefabricated connecting blocks. This can realize block prefabrication of the prefabricated bridge pier cap, which is convenient for transportation and hoisting. The connection process between the prefabricated blocks and the prefabricated connecting blocks is simple, which can reduce on-site processing procedures, reduce processing difficulty, and improve the convenience of using the prefabricated bridge pier cap, which is beneficial to improving the construction efficiency of the bridge piers and reducing construction costs.
[0017] Additional aspects and advantages of the present invention will be given in part in the following description, and in part will become apparent from the following description, or will be learned through the practice of the present invention. BRIEF DESCRIPTION OF THE DRAWINGS
[0018] The above and / or additional aspects and advantages of the present invention will become apparent and easily understood from the description of the embodiments in conjunction with the following drawings, in which:
[0019] Figure 1 is a schematic diagram of a bridge pier according to an embodiment of the utility model;
[0020] Figure 2 It is a schematic diagram of the installation of a prefabricated bridge pier cap according to an embodiment of the utility model;
[0021] Figure 3 is a schematic diagram of a prefabricated connection block according to an embodiment of the utility model;
[0022] Figure 4 It is a schematic diagram of the installation of the prefabricated bridge pier cap and the pile foundation according to the embodiment of the utility model;
[0023] Figure 5 is a schematic diagram of the installation of a prefabricated bridge pier cap according to another embodiment of the utility model;
[0024] Figure 6 It is a schematic diagram of the installation of a prefabricated pier cap and a pier column according to an embodiment of the utility model.
[0025] Reference numerals:
[0026] Pier 1000,
[0027] Prefabricated bridge pier cap 100, first direction F1, second direction F2,
[0028] Prefabricated block 1, base 11, grouting hole 111, first connecting piece 12, pier column steel bar 121, second connecting piece 13, embedded corrugated pipe 131, grouting space 132, contact plane 14,
[0029] Prefabricated connection block 2, first grouting sleeve 21, concave-convex structure 3, grouting channel 4,
[0030] The pier column 200 , the second grouting sleeve 201 , the pile foundation 300 , the pile foundation reinforcement 301 , the grouting plate 400 , and the annular support block 500 . DETAILED DESCRIPTION
[0031] The embodiments of the present invention are described in detail below, and examples of the embodiments are shown in the accompanying drawings, wherein the same or similar reference numerals throughout represent the same or similar elements or elements having the same or similar functions. The embodiments described below with reference to the accompanying drawings are exemplary and are only used to explain the present invention, and cannot be understood as limiting the present invention.
[0032] Hereinafter, a prefabricated pier cap 100 according to an embodiment of the present invention will be described with reference to the accompanying drawings.
[0033] like Figure 1-Figure 6 As shown, the prefabricated pier cap 100 according to the embodiment of the utility model includes: two prefabricated blocks 1 and a prefabricated connecting block 2 separated from each other, and the two prefabricated blocks 1 are respectively provided with a first connecting part on one side facing each other; the prefabricated connecting block 2 is arranged between the two prefabricated blocks 1, and the prefabricated connecting block 2 is provided with a second connecting part corresponding to the prefabricated block 1, and the second connecting part is connected and matched with the first connecting part.
[0034] In this way, the prefabricated pier cap 100 can be prefabricated in blocks, which is convenient for transportation and hoisting, and the connection process between the prefabricated blocks 1 and the prefabricated connecting blocks 2 is simple, which can reduce on-site processing procedures and reduce processing difficulty.
[0035] For example, refer to Figure 1-Figure 2 As shown, the pier 1000 includes a prefabricated pier cap 100, a pier column 200 and a pile foundation 300. The prefabricated pier cap 100 includes two prefabricated blocks 1. The two prefabricated blocks 1 are arranged spaced apart. Each prefabricated block 1 is supported on at least one pile foundation 300 and is used to support a pier column 200. The two prefabricated blocks 1 are respectively provided with a first connecting portion on one side facing each other.
[0036] The prefabricated bridge pier cap 100 further includes a prefabricated connection block 2, which is arranged between two prefabricated blocks 1, and the two ends of the prefabricated connection block 2 along the length direction are respectively against the two prefabricated blocks 1, and the prefabricated connection block 2 is provided with a second connection part, which is arranged opposite to the first connection part. When the prefabricated block 1 is installed to the prefabricated connection block 2, the second connection part can be connected and matched with the first connection part, and the joint between the prefabricated connection block 2 and the prefabricated block 1 can be glued by structural adhesive. In this way, the convenient assembly of the prefabricated bridge pier cap 100 can be achieved.
[0037] According to the prefabricated pier cap 100 of the embodiment of the utility model, by setting the prefabricated pier cap 100 to be connected by a prefabricated block 1 and a prefabricated connecting block 2, the block prefabrication of the prefabricated pier cap 100 can be realized, which is convenient for transportation and lifting, and the connection process between the prefabricated block 1 and the prefabricated connecting block 2 is simple, which can reduce the on-site processing procedures, reduce the processing difficulty, and improve the convenience of use of the prefabricated pier cap 100.
[0038] In some embodiments of the present invention, one of the first connection portion and the second connection portion is the first grouting sleeve 21 , and the other is a connecting steel bar, which is passed through and connected to the first grouting sleeve 21 .
[0039] For example, refer to Figure 2-Figure 3 As shown, the first connection part can be set as the first grouting sleeve 21, and the second connection part can be set as the connecting steel bar; or, the first connection part can be set as the connecting steel bar, and the second connection part can be set as the first grouting sleeve 21, and the present application does not limit this. When the prefabricated block 1 is installed to the prefabricated connection block 2 along the length direction of the prefabricated connection block 2, the connecting steel bar can be inserted into the first grouting sleeve 21, and then the connecting slurry can be poured into the first grouting sleeve 21, so that the prefabricated block 1 can be connected to the prefabricated connection block 2. In this way, the convenient assembly of the prefabricated pier cap 100 can be achieved.
[0040] In some embodiments of the present invention, the prefabricated block 1 is provided with a contact plane 14 cooperating with the prefabricated connecting block 2 , the connecting steel bars are provided on the contact plane 14 , and the extending direction of the connecting steel bars is perpendicular to the contact plane 14 .
[0041] For example, refer to Figure 2 As shown, a contact plane 14 can be provided on one side of the prefabricated block 1 facing the prefabricated connection block 2, and the contact plane 14 is used to cooperate with the end wall of the prefabricated connection block 2 along the length direction. A connecting steel bar protruding outward is provided on the contact plane 14, and the extending direction of the connecting steel bar is perpendicular to the contact plane 14, and a first grouting sleeve 21 is provided on the prefabricated connection block 2, and the first grouting sleeve 21 is extended and arranged along the length direction of the prefabricated connection block 2. When the prefabricated block 1 is installed to the prefabricated connection block 2 along the length direction of the prefabricated connection block 2, the connecting steel bar can be inserted into the first grouting sleeve 21 to be connected to the prefabricated connection block 2.
[0042] It can be understood that by setting the side wall of the prefabricated block 1 and the prefabricated connecting block 2 as the contact plane 14, and arranging the first grouting sleeve 21 on the prefabricated connecting block 2, the structure of the prefabricated block 1 can be simplified, the processing difficulty of the prefabricated block 1 can be reduced, and the practicality of the prefabricated pier cap 100 can be improved.
[0043] In some embodiments of the present invention, a plurality of connecting steel bars may be provided, and the plurality of connecting steel bars are arranged along the width direction of the prefabricated connecting block 2 (i.e. Figure 2 Alternatively, the connecting steel bars may be provided in a plurality, and the plurality of connecting steel bars may be arranged in a height direction (i.e. Figure 1 Alternatively, the connecting steel bars can be arranged in multiple groups, and the multiple groups of connecting steel bars are arranged in a spaced manner along the width direction of the prefabricated connecting block 2, each group of connecting steel bars is multiple, and the multiple connecting steel bars in the same group are arranged in a spaced manner along the height direction. This application does not limit this. This is conducive to meeting different working conditions.
[0044] In some embodiments of the utility model, at least one of the side walls of the prefabricated block 1 and the prefabricated connecting block 2 facing each other is provided with a concave-convex structure 3, and the concave-convex structure 3 is used to form a shear key with the structural adhesive. Specifically, the concave-convex structure 3 can be provided on the side wall of the prefabricated block 1 facing the prefabricated connecting block 2; or the concave-convex structure 3 can be provided on the side wall of the prefabricated connecting block 2 facing the prefabricated block 1; or the concave-convex structure 3 can be provided on the side walls of the prefabricated block 1 and the prefabricated connecting block 2 facing each other.
[0045] Through the above arrangement, the force-bearing surface between the prefabricated blocks 1 and the prefabricated connecting blocks 2 can be increased, which is beneficial to improving the connection reliability between the prefabricated blocks 1 and the prefabricated connecting blocks 2 and improving the reliability of the prefabricated pier cap 100.
[0046] In some embodiments of the utility model, the prefabricated block 1 includes a base 11, a first connecting member 12 and a second connecting member 13. The first connecting member 12 and the second connecting member 13 are both arranged in the base 11. At least part of the first connecting member 12 protrudes above the base 11 and is used to be connected to the pier column 200. The second connecting member 13 forms a grouting space 132 open in the height direction. The grouting space 132 is used to accommodate the pile foundation steel bars 301 of the pile foundation 300.
[0047] For example, refer to Figure 2 As shown, the prefabricated block 1 includes a base 11, a first connecting member 12 and a second connecting member 13. The base 11 is cast by concrete. The first connecting member 12 and the second connecting member 13 are both arranged in the base 11. At least part of the first connecting member 12 protrudes above the base 11. The first connecting member 12 can be constructed as a metal member. The first connecting member 12 is used to connect with the pier column 200 to fix the pier column 200 on the prefabricated block 1.
[0048] The second connecting member 13 extends in the height direction, and a grouting space 132 is formed on the second connecting member 13. The grouting space 132 extends in the height direction and is open at both ends. The grouting space 132 is arranged opposite to the pile foundation 300 and is used to accommodate the pile foundation steel bars 301. When the pile foundation steel bars 301 extend to the grouting space 132, the connecting slurry can be poured into the grouting space 132 to realize the connection between the pile foundation 300 and the prefabricated block 1.
[0049] Through the above arrangement, the connection stability between the prefabricated pier cap 100 and the pier column 200 and the pile foundation 300 can be improved, and the reliability of the prefabricated pier cap 100 is improved.
[0050] In some embodiments of the utility model, the second connecting member 13 includes a pre-embedded corrugated pipe 131, which is inserted into the base body 11 and forms a grouting space 132. The base body 11 is provided with a grouting hole 111, which penetrates the base body 11 along the height direction. The bottom wall of the prefabricated block 1 is used to support on the pile foundation 300 and defines a grouting channel 4 with the pile foundation 300. The grouting hole 111 is connected to the grouting space 132 through the grouting channel 4.
[0051] For example, refer to Figure 2 and Figure 4 As shown, the second connecting member 13 includes a pre-embedded bellows 131, which extends in the height direction and penetrates the base 11, and a grouting space 132 is formed in the pre-embedded bellows 131. The base 11 is provided with a grouting hole 111, which is spaced apart from the pre-embedded bellows 131 and penetrates the base 11 in the height direction. The prefabricated block 1 can be supported on the pile foundation 300 at intervals by the annular support block 500, so that the bottom wall of the prefabricated block 1, the top wall of the pile foundation 300 and the annular support block 500 can jointly define a grouting channel 4, and the grouting hole 111 is connected to the grouting space 132 through the grouting channel 4.
[0052] Specifically, when the prefabricated blocks 1 are supported on the pile foundation 300 at intervals, the connection slurry can be introduced into the grouting holes 111, and the connection slurry can flow into the grouting channel 4 along the grouting holes 111, and the connection slurry flows along the grouting channel 4 to flow into the grouting space 132, and fills up the grouting space 132 upward, thereby connecting the pile foundation steel bars 301 to the prefabricated blocks 1. It should be noted that an annular slurry retaining plate 400 can be sleeved on the outside of the pile foundation 300, and the slurry retaining plate 400 is used to cover the gap between the prefabricated blocks 1 and the pile foundation 300 to prevent leakage of the connection slurry.
[0053] Through the above arrangement, the connection slurry can completely fill the grouting space 132, so as to improve the connection reliability between the connection steel bars and the prefabricated blocks 1, and improve the installation stability of the prefabricated pier cap 100.
[0054] In some embodiments of the utility model, a roughening area may be provided at the top wall of the pile foundation 300 corresponding to the grouting channel 4; or a roughening area may be provided at the bottom wall of the prefabricated block 1 corresponding to the grouting channel 4; or a roughening area may be provided at the top wall of the pile foundation 300 corresponding to the grouting channel 4, and a roughening area may be provided at the bottom wall of the prefabricated block 1 corresponding to the grouting channel 4. Through the above arrangement, the inner diameter of the grouting channel 4 can be increased, which is conducive to the flow of the connecting slurry.
[0055] In some embodiments of the utility model, the second connecting member 13 includes a plurality of pre-embedded corrugated pipes 131, which are arranged at intervals around the grouting hole 111; the first connecting member 12 includes a plurality of pier column steel bars 121, which are arranged at intervals around the grouting hole 111 and are staggered with the pre-embedded corrugated pipes 131 in the radial direction.
[0056] For example, refer to Figure 2 and Figure 4 As shown, the second connecting member 13 includes a plurality of pre-embedded corrugated pipes 131, which are arranged at intervals around the grouting hole 111, and each pre-embedded corrugated pipe 131 is formed with a grouting space 132. When the prefabricated block 1 is supported on the pile foundation 300, the grouting hole 111 can be connected to the grouting spaces 132 of the plurality of pre-embedded corrugated pipes 131 through the grouting channel 4, and the distance between the grouting hole 111 and each pre-embedded corrugated pipe 131 is the same. In this way, it can be ensured that each grouting space 132 can be filled with the connecting slurry, thereby improving the connection reliability between the pile foundation 300 and the prefabricated block 1.
[0057] At the same time, if Figure 2 As shown, the first connecting member 12 may include a plurality of pier column steel bars 121, and the pier column 200 may be provided with a plurality of second grouting sleeves 201, respectively, and the plurality of pier column steel bars 121 may be respectively inserted into the corresponding second grouting sleeves 201 and connected to the pier column 200 through the connecting grout. Among them, a plurality of pier column steel bars 121 may be arranged spaced apart around the grouting hole 111, and the pier column steel bars 121 may be staggered with the embedded corrugated pipe 131 in the radial direction, such as being arranged on the radial inner side of the embedded corrugated pipe 131. Through the above arrangement, the pile foundation 300 may be opposite to the pier column 200 in the height direction, so as to realize the arrangement mode in which a single pile foundation 300 supports a single pier column 200.
[0058] In some embodiments of the present invention, Figure 5As shown, each prefabricated block 1 has two second connecting members 13, which are used to be connected to the corresponding pile foundations 300 respectively, and the two second connecting members 13 are respectively located on both sides of the corresponding first connecting member 12, and the first connecting member 12 is used to be connected to the corresponding bridge pier column 200. It should be noted that the base 11 is provided with a grouting hole 111 corresponding to each second connecting member 13. Through the above arrangement, the arrangement mode in which two pile foundations 300 jointly support the same bridge pier column 200 from both sides can be realized.
[0059] In some embodiments of the present invention, the prefabricated connecting block 2 extends along the first direction F1 and is connected to two prefabricated blocks 1 at both ends. The two second connecting members 13 of the same prefabricated block 1 are respectively arranged on both sides of the corresponding first connecting member 12 along the second direction F2, and the first direction F1 is arranged perpendicular to the second direction F2.
[0060] For example, refer to Figure 5 As shown, the first direction F1 is perpendicular to the second direction F2. For example, the first direction F1 can be set to Figure 5 The left and right directions shown in FIG. 1 and the second direction F2 is set to Figure 5 The longitudinal direction of the prefabricated connection block 2 may be arranged to extend along the first direction F1, and the two ends of the prefabricated connection block 2 along the first direction F1 are respectively connected to the two prefabricated blocks 1. At the same time, two second connection members 13 of the same prefabricated block 1 may be arranged respectively on both sides of the corresponding first connection member 12 along the second direction F2.
[0061] Through the above arrangement, the prefabricated pier cap 100 can be constructed as an I-shaped structure, which can improve the design rationality of the prefabricated pier cap 100 and help reduce the processing difficulty of the prefabricated pier cap 100.
[0062] The utility model also provides a bridge pier 1000.
[0063] like Figure 1 As shown, the pier 1000 according to the embodiment of the utility model comprises: a pier column 200, a pile foundation 300 and a prefabricated pier cap 100 according to any of the above embodiments, the pile foundation 300 is provided with pile foundation steel bars 301, the prefabricated pier cap 100 is supported on the pile foundation 300 and connected to the pile foundation steel bars 301, and the pier column 200 is supported on the prefabricated pier cap 100 and connected to the prefabricated pier cap 100.
[0064] According to the pier 1000 of the embodiment of the utility model, by setting a prefabricated pier cap 100 composed of a prefabricated block 1 and a prefabricated connecting block 2, the block prefabrication of the prefabricated pier cap 100 can be realized, which is convenient for transportation and lifting, and the connection process between the prefabricated block 1 and the prefabricated connecting block 2 is simple, which can reduce the on-site processing procedures, reduce the processing difficulty, and improve the convenience of use of the prefabricated pier cap 100, which is beneficial to improving the construction efficiency of the pier 1000 and reducing the construction cost.
[0065] In some embodiments of the utility model, a mortar cushion layer is sandwiched between the pier column 200 and the prefabricated pier cap 100, and the thickness of the mortar cushion layer is not less than 2 mm. For example, the thickness of the mortar cushion layer can be set to 2.5 mm; or, the thickness of the mortar cushion layer can be set to 3 mm; or, the thickness of the mortar cushion layer can be set to 3.5 mm, and this application does not limit this. Through the above settings, the connection reliability between the pier column 200 and the prefabricated pier cap 100 can be improved, and the overall performance of the pier 1000 can be improved.
[0066] Specifically, the manufacturing method of the bridge pier 1000 is as follows:
[0067] Step 1: Designing the cap template according to the structure and size of the prefabricated pier cap 100.
[0068] Step 2: Carry out prefabrication, binding and connection procedures of the cap steel bars (such as connecting steel bars and pier column steel bars 121, etc.) of the prefabricated bridge pier cap 100, erect the cap formwork, and take temporary disconnection measures for the cap steel bars in the joints between the prefabricated blocks 1 and the prefabricated connecting blocks 2.
[0069] Specifically, the steel bars can be processed first according to the length of the disconnected cap steel bars, and then the corresponding cap steel bars can be temporarily connected by temporary mechanical connection or binding, and then the layout and positioning can be carried out.
[0070] Step 3: Prefabricated blocks 1 and prefabricated connecting blocks 2 are manufactured in the foundation formwork, that is, the pouring, vibrating and curing processes of concrete are completed.
[0071] Step 4: transport the prefabricated block 1 and the prefabricated connecting block 2 to the site, connect the prefabricated block 1 with the prefabricated connecting block 2 to form a prefabricated pier cap 100, hoist, adjust and position the prefabricated pier cap 100 so that the pile foundation steel bars 301 extend into the first grouting sleeve 21. At this time, connecting slurry can be introduced into the first grouting sleeve 21 through the grouting hole 111 and maintained to connect the prefabricated pier cap 100 with the pile foundation 300.
[0072] Step 5: After the connection slurry in the first grouting sleeve 21 is solidified, the pier column 200 is hoisted so that the plurality of pier column steel bars 121 can be respectively inserted into the plurality of second grouting sleeves 201 of the pier column 200, and then the connection slurry is poured into the second grouting sleeves 201 to connect the prefabricated pier cap 100 with the pier column 200. It should be noted that the pier column 200 can be prefabricated or cast on site. Thus, the processing of the bridge can be completed.
[0073] In the description of the present invention, it should be understood that the terms "center", "longitudinal", "lateral", "length", "width", "thickness", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", "clockwise", "counterclockwise", "axial", "radial", "circumferential" and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the referred device or element must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on the present invention.
[0074] In the description of the present invention, "first feature" or "second feature" may include one or more of the features.
[0075] In the description of the present invention, "plurality" means two or more.
[0076] In the description of the present invention, a first feature being “above” or “below” a second feature may include that the first and second features are directly in contact with each other, or may include that the first and second features are not in direct contact but are in contact with each other via another feature therebetween.
[0077] In the description of the present invention, a first feature “above”, “over” and “above” a second feature includes the first feature being directly above and obliquely above the second feature, or simply means that the first feature is horizontally higher than the second feature.
[0078] In the description of this specification, the description with reference to the terms "one embodiment", "some embodiments", "illustrative embodiments", "examples", "specific examples", or "some examples" means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the utility model. In this specification, the schematic representation of the above terms does not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described can be combined in any one or more embodiments or examples in a suitable manner.
[0079] Although the embodiments of the present invention have been shown and described, those skilled in the art will appreciate that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the claims and their equivalents.
Claims
1. A prefabricated bridge pier cap (100), characterized in that: include: Two prefabricated blocks (1) are spaced apart, and the two prefabricated blocks (1) are respectively provided with a first connecting portion on one side facing each other; A prefabricated connecting block (2), wherein the prefabricated connecting block (2) is arranged between the two prefabricated sub-blocks (1), and the prefabricated connecting block (2) is provided with a second connecting portion corresponding to the prefabricated sub-block (1), and the second connecting portion is connected and matched with the first connecting portion.
2. The prefabricated bridge pier cap (100) according to claim 1, characterized in that: One of the first connection part and the second connection part is a first grouting sleeve (21), and the other is a connecting steel bar, and the connecting steel bar is inserted and connected in the first grouting sleeve (21).
3. The prefabricated bridge pier cap (100) according to claim 2, characterized in that: The prefabricated block (1) is provided with a contact plane (14) that cooperates with the prefabricated connecting block (2), the connecting steel bars are arranged on the contact plane (14), and the extending direction of the connecting steel bars is arranged perpendicular to the contact plane (14).
4. The prefabricated pier cap (100) according to claim 1, characterized in that: At least one of the side walls of the prefabricated block (1) and the prefabricated connecting block (2) facing each other is provided with a concave-convex structure (3).
5. The prefabricated pier cap (100) according to claim 1, characterized in that: The prefabricated block (1) comprises a base (11), a first connecting member (12) and a second connecting member (13); the first connecting member (12) and the second connecting member (13) are both arranged in the base (11); at least a portion of the first connecting member (12) protrudes above the base (11) and is used to be connected to a pier column (200); the second connecting member (13) forms a grouting space (132) open in a height direction; the grouting space (132) is used to accommodate pile foundation steel bars (301) of a pile foundation (300).
6. The prefabricated pier cap (100) according to claim 5, characterized in that: The second connecting member (13) comprises a pre-buried corrugated pipe (131), the pre-buried corrugated pipe (131) is inserted into the base (11) and forms the grouting space (132), the base (11) is provided with a grouting hole (111), the grouting hole (111) passes through the base (11) in the height direction, the bottom wall of the prefabricated block (1) is used to support on the pile foundation (300) and defines a grouting channel (4) with the pile foundation (300), and the grouting hole (111) is connected with the grouting space (132) through the grouting channel (4).
7. The prefabricated bridge pier cap (100) according to claim 6, characterized in that: The second connecting member (13) comprises a plurality of pre-buried corrugated pipes (131), and the plurality of pre-buried corrugated pipes (131) are arranged at intervals around the grouting hole (111); The first connecting member (12) comprises a plurality of pier steel bars (121), wherein the plurality of pier steel bars (121) are arranged at intervals around the grouting hole (111) and are staggered with the embedded corrugated pipe (131) in the radial direction.
8. The prefabricated pier cap (100) according to claim 5, characterized in that: Each of the prefabricated blocks (1) has two second connecting members (13), and the two second connecting members (13) are respectively located on both sides of the corresponding first connecting member (12).
9. The prefabricated bridge pier cap (100) according to claim 8, characterized in that: The prefabricated connecting block (2) extends along a first direction (F1) and has two ends respectively connected to the two prefabricated blocks (1); the two second connecting members (13) of the same prefabricated block (1) are respectively arranged on both sides of the corresponding first connecting member (12) along a second direction (F2); the first direction (F1) and the second direction (F2) are arranged perpendicularly.
10. A bridge pier (1000), characterized in that: include: A pier column (200), a pile foundation (300) and a prefabricated pier cap (100) according to any one of claims 1 to 9, wherein the pile foundation (300) is provided with pile foundation reinforcement (301), the prefabricated pier cap (100) is supported on the pile foundation (300) and connected to the pile foundation reinforcement (301), and the pier column (200) is supported on the prefabricated pier cap (100) and connected to the prefabricated pier cap (100).