Gantry type offshore wind power pile foundation

By setting up the portal frame and anchoring structure around the offshore wind power monopile foundation, combined with the bonding technology of high-strength grouting materials and auxiliary piles, the stability and construction difficulty of the offshore wind power monopile foundation in the deep sea environment are solved, and the problem is achieved. A more economical and stable offshore wind power foundation installation.

CN221919504UActive Publication Date: 2024-10-29POWERCHINA HUADONG ENG CORP LTD
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202323209418.7
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-11-28
Publication Date
2024-10-29
Estimated Expiration
2033-11-28

AI Technical Summary

Technical Problem

The existing offshore wind power monopile foundation has poor stability in the deep-sea environment, and the conventional jacket foundation is complex and expensive to manufacture, making it difficult to meet the construction requirements of large deep-sea units.

Method used

The gantry type offshore wind power pile foundation is used. By setting up the gantry frame and anchoring structure around the single pile foundation, and using the cooperation of high-strength grouting material, auxiliary piles and sleeves to achieve stable installation on the seabed, and through reinforcement Ring plates enhance structural strength.

Benefits of technology

It effectively reduces the impact of the single pile foundation, reduces the use of steel and the amount of welding, improves the economy and stability of construction, and avoids the manufacturing complexity of the jacket foundation and fatigue problems in the splash zone.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221919504U_ABST
    Figure CN221919504U_ABST
Patent Text Reader

Abstract

The utility model relates to a portal type offshore wind power pile foundation. The utility model is suitable for the technical field of offshore wind power equipment. According to the technical scheme, the portal type offshore wind power pile foundation is characterized in that the portal type offshore wind power pile foundation is provided with a single pile foundation, a plurality of portal frames are evenly arranged at the bottom of the single pile foundation in the circumferential direction of the single pile foundation, and anchoring structures anchored into the seabed surface are arranged at the ends, away from the single pile foundation, of the portal frames. Thus, after the single-pile foundation is arranged on the seabed surface, the anchoring structures evenly arranged around the single-pile foundation are anchored in the seabed surface, and the single-pile foundation is stably installed on the seabed surface through the anchoring structures.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to a portal-type offshore wind power pile foundation, which is applicable to the technical field of offshore wind power equipment. Background Art

[0002] At present, the offshore wind power industry has developed rapidly in China, and about 70% of the offshore wind farms built at home and abroad have adopted single pile foundations. At present, offshore wind power projects often use larger power wind turbines to save costs, and with the development of near-shore wind power, wind farms are increasingly developing in the deep sea. With the increase of upper wind turbine loads, and the shallow surface layer in some coastal areas is mostly silty soft soil, although the pure single pile foundation is simple in process, the single pile foundation is often large in diameter, resulting in high steel consumption and difficulty in pile sinking. Conventional offshore single pile foundation construction equipment cannot meet the construction requirements. At present, in response to the above situation, jacket foundations are often used to improve the stability of single pile foundations. However, the use of conventional jacket foundations has defects such as many production nodes, greater fatigue problems in the splash zone, and greater difficulty in processing and manufacturing.

[0003] Therefore, there is an urgent need to research and develop a wind turbine foundation type that is suitable for deep sea and large-scale offshore wind power environments and has better economic benefits. Utility Model Content

[0004] The technical problem to be solved by the present invention is: In order to solve the above technical problem, the present invention provides a portal type offshore wind power pile foundation.

[0005] The technical solution adopted by this utility model is a gantry-type offshore wind turbine pile foundation, characterized by a single pile foundation, a plurality of gantry frames evenly arranged along the circumference of the single pile foundation at the bottom of the single pile foundation, and anchoring structures anchored into the seabed surface at the ends of the gantry frames away from the single pile foundation. Thus, after the single pile foundation is arranged on the seabed surface, the anchoring structures evenly arranged around the single pile foundation are anchored into the seabed surface, thereby achieving a stable installation of the single pile foundation on the seabed surface.

[0006] The anchoring structure comprises a first sleeve fixedly mounted on the end of the portal frame, a first auxiliary pile being arranged in the first sleeve, the first auxiliary pile being anchored into the seabed surface below the first sleeve, and the first auxiliary pile and the first sleeve being fixedly connected via a first fixing structure. In this way, after the single pile foundation is arranged on the seabed surface, the first sleeve fixedly mounted on the portal frame is arranged on the seabed surface around the single pile foundation, the first auxiliary pile is passed through the first sleeve and then anchored into the seabed surface below the first sleeve, and a first fixing structure is arranged between the first auxiliary pile and the first sleeve, so as to fix the first sleeve and the first auxiliary pile in connection, thereby achieving a stable support function for the single pile foundation by cooperating with the anchoring structures evenly arranged around the single pile foundation.

[0007] The first adhesive structure comprises a high-strength grouting material filled between the first sleeve and the first auxiliary pile. A first grouting pipe is provided on the inner wall of the first sleeve to evenly fill the high-strength grouting material between the first sleeve and the first auxiliary pile. A first grouting packer is provided at the bottom of the first sleeve to prevent the high-strength grouting material from leaking from the bottom of the first sleeve. Thus, after the first auxiliary pile is passed through the first sleeve and anchored into the seabed, the high-strength grouting material is evenly filled into the first sleeve and the first auxiliary pile through the first grouting pipe. After the high-strength grouting material solidifies, it bonds the first sleeve and the first auxiliary pile. The first grouting packer, disposed at the bottom of the first sleeve, effectively prevents the high-strength grouting material from leaking from the bottom of the first sleeve during the grouting process.

[0008] A first guide groove is provided on the inner wall of the top surface of the first sleeve, so as to facilitate the insertion of the first auxiliary pile into the first sleeve.

[0009] The anchoring structure includes a second auxiliary pile fixedly mounted on the end of the portal frame, a second sleeve anchored on the seabed at a position corresponding to the second auxiliary pile, the second auxiliary pile inserted into the second sleeve, and the second auxiliary pile and the second sleeve fixedly connected via a second fixing structure. Thus, before the single pile foundation is placed on the seabed, the second sleeve is pre-anchored into the seabed at a position corresponding to each second auxiliary pile. When the single pile foundation is placed on the seabed, the second auxiliary pile fixedly mounted on the single pile foundation is extended into the second sleeve, and the second sleeve is fixedly connected to the second auxiliary pile by the second fixing structure.

[0010] The second adhesive structure comprises a high-strength grouting material filled between the second sleeve and the second auxiliary pile. A second grouting pipe is provided on the outer wall of the second auxiliary pile to evenly fill the high-strength grouting material between the second sleeve and the second auxiliary pile. A second grouting packer is provided at the bottom of the second auxiliary pile to prevent leakage of the high-strength grouting material from the bottom of the second auxiliary pile. Thus, after the second auxiliary pile is passed through the second sleeve and anchored into the seabed, the high-strength grouting material is evenly filled into the second sleeve and the second auxiliary pile through the first grouting pipe. After the high-strength grouting material solidifies, it bonds the second sleeve and the second auxiliary pile. The second grouting packer, positioned at the bottom of the second sleeve, effectively prevents leakage of the high-strength grouting material from the bottom of the second sleeve during grouting.

[0011] A second guide groove is provided on the inner wall of the bottom surface of the second auxiliary pile, so as to facilitate the insertion of the second auxiliary pile into the second sleeve.

[0012] The portal frame is a reinforced concrete structure having a cast concrete body and a reinforcement plate arranged in the concrete body, thereby enhancing the structural strength of the portal frame.

[0013] A portal frame top reinforcement ring plate is fixedly installed outside the monopile foundation above the portal frame, thereby enhancing the structural strength of the portal frame installed on the monopile foundation.

[0014] A portal frame bottom reinforcement ring plate is fixedly installed outside the monopile foundation below the portal frame, thereby enhancing the structural strength of the portal frame installed on the monopile foundation.

[0015] The beneficial effects of the present invention are as follows: in the present invention, the single pile foundation is arranged on the seabed surface, and the portal structure is set near the mud surface, which can effectively reduce the impact on the single pile foundation; in the present invention, the auxiliary piles are matched with the sleeve shaft holes and are bonded by high-strength grouting material. Compared with the jacket foundation, the steel structure has fewer nodes, the middle single column and the steel pipe pile are both cylindrical, and the welding amount is relatively small. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] Figure 1 It is a structural elevation diagram of Example 1 in the present utility model.

[0017] Figure 2 This is a schematic plan view of the arrangement of three portal frames outside a single pile foundation in Example 1 of the present invention.

[0018] Figure 3 This is a schematic plan view of the arrangement of four portal frames outside a single pile foundation in Example 1 of the present invention.

[0019] Figure 4 It is a structural elevation diagram of Example 2 of the present utility model.

[0020] Figure 5 This is a schematic plan view of the arrangement of three portal frames outside a single pile foundation in Example 2 of the present invention.

[0021] In the figure: 1. Single pile foundation; 2. Anchoring structure; 3. Gantry frame; 3-1. Reinforcement plate; 3-2. Concrete body; 4. First auxiliary pile; 5. First sleeve; 5-1. First guide groove; 5-2. First grouting pipe; 5-3. First grouting packer; 6. Second auxiliary pile; 6-1. Second guide groove; 6-2. Second grouting pipe; 6-3. Second grouting packer; 7. Second sleeve; 8-1. Gantry top reinforcement ring plate; 8-2. Gantry bottom reinforcement ring plate; 9. Wind turbine tower; 10. Foundation platform. DETAILED DESCRIPTION

[0022] The present invention will be further described in detail below with reference to the accompanying drawings and through examples. The following examples are provided to explain the present invention, but the present invention is not limited to the following examples.

[0023] Example 1: This example is a gantry-type offshore wind turbine pile foundation, comprising a monopile foundation 1 arranged on the seabed. The top surface of the monopile foundation 1 is connected to the upper wind turbine tower 9 via a flange, and a foundation platform 10 is welded to the outer wall of the upper portion of the monopile foundation 1 on land.

[0024] In this embodiment, a plurality of gantry frames 3 are fixedly mounted on the side wall at the lower end of the monopile foundation 1. Each gantry frame 3 needs to be evenly arranged outside the monopile foundation 1 in the circumferential direction of the monopile foundation 1. The gantry frame 3 is a reinforced concrete structure having a cast concrete body 3-2 and a reinforcement plate 3-1 arranged within the concrete body 3-2. The reinforcement plate 3-1 at one end of the gantry frame 3 is welded to the outer wall of the monopile foundation 1, and a first sleeve 5 is fixedly welded to the other end of the gantry frame 3. A gantry top reinforcement ring plate 8-1 is fixedly welded to the outer wall of the monopile foundation 1 at a position above the gantry frame 3, and a gantry bottom reinforcement ring plate 8-2 is fixedly welded to the outer wall of the monopile foundation 1 at a position below the gantry frame 3.

[0025] In this embodiment, a first auxiliary pile 4 is arranged within a first sleeve 5 fixedly mounted on the portal frame 3. The auxiliary pile passes through the first sleeve 5 and is anchored into the seabed. After the first auxiliary pile 4 is anchored into the seabed, a high-strength grouting material is poured between the first auxiliary pile 4 and the first sleeve 5 to bond the first auxiliary pile 4 to the first sleeve 5.

[0026] In this embodiment, a first grouting pipe 5-2 is provided on the inner wall of the first sleeve 5, and the first grouting pipe 5-2 extends from the top of the first sleeve 5 to the bottom of the first sleeve 5. When high-strength grouting material is poured between the first auxiliary pile 4 and the first sleeve 5 through the first grouting pipe 5-2, the high-strength grouting material will be evenly filled from the bottom of the first sleeve 5 to the top of the first sleeve 5.

[0027] Furthermore, to prevent leakage of high-strength grouting material from the bottom of the first sleeve 5 during the process of pouring high-strength grouting material between the first sleeve 5 and the first auxiliary pile 4, a first grouting packer 5-3 is fixedly installed on the inner wall of the bottom of the first sleeve 5. In this way, by bonding the first auxiliary piles 4 anchored in the seabed to the first sleeve 5 fixedly installed on the monopile foundation 1, the first auxiliary piles 4 arranged around the monopile foundation 1 provide stable support for the monopile foundation 1.

[0028] Furthermore, in this embodiment, a first guide groove 5 - 1 is provided on the top inner wall of the first sleeve 5 to facilitate the installation of the first auxiliary pile 4 in the first sleeve 5 and to guide it.

[0029] The arrangement method of this embodiment is:

[0030] The first sleeve 5 is fixedly mounted on the portal frame 3, and a plurality of portal frames 3 are evenly fixedly mounted on the monopile foundation 1 along the circumferential direction of the monopile foundation 1;

[0031] The monopile foundation 1 is sunk to the seabed, and the first sleeves 5 are respectively arranged on the seabed around the monopile foundation 1;

[0032] Pass the first auxiliary pile 4 through the first sleeve 5 and anchor it into the seabed;

[0033] The high-strength grouting material is evenly filled between the first sleeve 5 and the first auxiliary pile 4 through the first grouting pipe 5-2. After the high-strength grouting material solidifies, the first sleeve 5 and the first auxiliary pile 4 are bonded to achieve stable installation of the single pile foundation 1 on the seabed.

[0034] Example 2: This example is a gantry-type offshore wind power pile foundation, which is substantially the same as Example 1. The differences between Example 2 and Example 1 are:

[0035] In this embodiment, the anchoring structure 2 provided at the end of the portal frame 3 is a second auxiliary pile 6 fixedly installed at the end of the portal frame 3 and a second sleeve 7 anchored in the seabed surface.

[0036] In this embodiment, a second grouting pipe 6-2 is provided on the outer wall of the second auxiliary pile 6, extending from the top to the bottom of the second auxiliary pile 6. Thus, after the second auxiliary pile 6 is inserted into the second sleeve 7, high-strength grouting material is poured between the second auxiliary pile 6 and the second sleeve 7 through the second grouting pipe 6-2. After the high-strength grouting material solidifies, the second auxiliary pile 6 and the second sleeve 7 are bonded together.

[0037] Furthermore, in this embodiment, a second grouting packer 6 - 3 is installed on the outer wall of the bottom of the second auxiliary pile 6 to prevent the high-strength grouting material from leaking from between the second sleeve 7 and the second auxiliary pile 6 .

[0038] Furthermore, in this embodiment, a second guide groove 6 - 1 is provided on the outer wall of the bottom surface of the second auxiliary pile 6 to facilitate the installation of the second auxiliary pile 6 in the second sleeve 7 and to guide it.

[0039] The arrangement method of this embodiment is:

[0040] The second auxiliary pile 6 is fixedly installed on the portal frame 3, and a plurality of portal frames 3 are evenly fixedly installed on the single pile foundation 1 along the circumferential direction of the single pile foundation 1;

[0041] Anchor each second sleeve 7 into the seabed surface at a position corresponding to the second auxiliary pile 6;

[0042] The monopile foundation 1 is lowered to the seabed surface, and the second auxiliary piles 6 are moved to positions corresponding to the second sleeves 7;

[0043] Insert the second auxiliary pile 6 into the second sleeve 7;

[0044] The high-strength grouting material is evenly filled between the second sleeve 7 and the second auxiliary pile 6 through the second grouting pipe 6-2. After the high-strength grouting material solidifies, the second sleeve 7 and the second auxiliary pile 6 are bonded to achieve stable installation of the single pile foundation 1 on the seabed.

[0045] The above is only a preferred specific implementation method of the present invention, but the protection scope of the present invention is not limited to this. Any technician familiar with the technical field within the technical scope disclosed by the present invention can make equivalent replacements or changes based on the technical solution and utility model concept of the present invention, which should be covered by the protection scope of the present invention.

Claims

1. A portal type offshore wind power pile foundation, characterized by: A single pile foundation (1) is provided, a plurality of portal frames (3) are evenly arranged at the bottom of the single pile foundation (1) along the circumferential direction of the single pile foundation (1), and an anchoring structure (2) anchored in the seabed surface is arranged at the end of the portal frame (3) away from the single pile foundation (1).

2. A gantry type offshore wind power pile foundation according to claim 1, characterized in that: The anchoring structure (2) comprises a first sleeve (5) fixedly mounted on the end of the portal frame (3); a first auxiliary pile (4) is arranged in the first sleeve (5); the first auxiliary pile (4) is anchored in the seabed surface below the first sleeve (5); the first auxiliary pile (4) and the first sleeve (5) are fixedly connected via a first fixing structure.

3. A gantry type offshore wind power pile foundation according to claim 2, characterized in that: The first fixing structure comprises a high-strength grouting material filled between the first sleeve (5) and the first auxiliary pile (4); a first grouting pipe (5-2) is arranged on the inner wall of the first sleeve (5) for evenly filling the high-strength grouting material between the first sleeve (5) and the first auxiliary pile (4); and a first grouting packer (5-3) is arranged at the bottom of the first sleeve (5) for preventing the high-strength grouting material from leaking from the bottom of the first sleeve (5).

4. A portal type offshore wind power pile foundation according to claim 2, characterized in that: A first guide groove (5-1) is provided on the inner wall of the top surface of the first sleeve (5).

5. The portal type offshore wind power pile foundation according to claim 1, characterized in that: The anchoring structure (2) comprises a second auxiliary pile (6) fixedly mounted on the end of the portal frame (3); a second sleeve (7) is anchored at a position corresponding to the second auxiliary pile (6) on the seabed surface; the second auxiliary pile (6) is inserted into the second sleeve (7); and the second auxiliary pile (6) and the second sleeve (7) are fixedly connected via a second fixing structure.

6. A portal type offshore wind power pile foundation according to claim 5, characterized in that: The second fixed bonding structure comprises a high-strength grouting material filled between the second sleeve (7) and the second auxiliary pile (6); a second grouting pipe (6-2) is arranged on the outer wall of the second auxiliary pile (6) for evenly filling the high-strength grouting material between the second sleeve (7) and the second auxiliary pile (6); and a second grouting packer (6-3) is arranged at the bottom of the second auxiliary pile (6) for preventing the high-strength grouting material from leaking from the bottom of the second auxiliary pile (6).

7. The portal type offshore wind power pile foundation according to claim 5, characterized in that: A second guide groove (6-1) is provided on the outer wall of the bottom surface of the second auxiliary pile (6).

8. The portal type offshore wind power pile foundation according to claim 1, characterized in that: The portal frame (3) is a reinforced concrete structure, comprising a cast concrete body (3-2) and a reinforcing plate (3-1) arranged in the concrete body (3-2).

9. The portal type offshore wind power pile foundation according to claim 1, characterized in that: A portal top reinforcement ring plate (8-1) is fixedly installed outside the single pile foundation (1) above the portal frame (3).

10. The portal type offshore wind power pile foundation according to claim 1, characterized in that: A portal bottom reinforcement ring plate (8-2) is fixedly installed outside the single pile foundation (1) below the portal frame (3).

Citation Information

Cited By

  • Gantry type offshore wind power pile foundation

    CN117488861A