Simple conduit well cementation device for petroleum drilling
By mixing cement powder and water on the ground and sending it into the conduit through a grouting pipe, a simple cementing device solves the problem of insufficient mixing of cement powder and annulus liquid, achieves efficient sealing of the conduit, and reduces costs and risks. Improved construction efficiency.
Patent Information
- Application Number
- CN202420256389.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-02-01
- Publication Date
- 2024-10-29
- Estimated Expiration
- 2034-02-01
AI Technical Summary
In the existing sealing methods for oil drilling ducts, the cement powder is not fully mixed with the annulus liquid, resulting in poor sealing effect and increased construction risks and costs. Moreover, the traditional pumping cement slurry method is expensive and inefficient.
A simple cementing device for oil drilling conduits is designed. A cement mixing tank is used to stir cement powder and water on the ground. The evenly mixed cement slurry is sent into the annulus of the conduit through a grouting pipe. The density difference is used to gradually replace the liquid to form an effective Seal.
It achieves efficient sealing of the conduit, reduces construction costs and time costs, reduces the risk of formation collapse, and achieves the same cementing quality as traditional methods without waiting.
Smart Images

Figure CN221920916U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to a cementing device, in particular to a simple cementing device for a pipe used for oil drilling, belonging to the technical field of oil drilling cementing equipment. Background Art
[0002] In oil drilling construction, drilling from the depth of zero is called the first drilling, or the first drilling for short. In order to seal the loose strata in the shallow surface, prevent the shallow surface well wall collapse and wellhead collapse during the first drilling construction, which will lead to the instability of the drilling rig, and create wellhead conditions for the first drilling to install the wellhead blowout preventer and water outlet pipe, etc., it is generally necessary to drill a large wellbore before the first drilling, and put in a first drilling pipe with a size of tens of meters or larger than the first drilling wellbore for sealing.
[0003] Because the well depth is relatively shallow, in order to save costs, reduce construction intensity and improve construction convenience, a simple and quick method is generally adopted. The cement powder is poured into the annulus of the catheter manually, and the cement powder is mixed and solidified with the liquid in the annulus by natural sedimentation to complete the sealing of the catheter.
[0004] The simple cementing method of cement powder pouring has the following problems: 1. Since the cement powder is not fully mixed with water on the ground, it is poured directly into the annulus of the pipe manually. The cement powder sinks by gravity and cannot be effectively mixed with the liquid in the annulus to form slurry, resulting in poor bonding between the annulus and the first and second interfaces after solidification;
[0005] 2. The conventional cement slurry was not injected into the water hole for circulation displacement. The annulus of the catheter was mixed with cement slurry and water. The cement slurry with good fluidity was not formed to replace the liquid in the annulus of the catheter. The catheter section could not be effectively sealed only by relying on the natural mixing effect of cement powder and annular liquid.
[0006] 3. Cement powder may not settle to the bottom of the well by its own weight, resulting in excessive slurry, poor sealing, gaps, and poor cement bonding at the casing shoe. During the lower opening construction, there are often abnormal conditions such as cement falling off, drilling fluid overflow, and formation collapse in the casing section, which leads to cement stuck in the lower opening, environmental pollution caused by drilling fluid overflow at the wellhead, difficulty in drilling and leakage caused by formation collapse in the casing section, and other abnormal phenomena, which greatly increase the risk of lower construction.
[0007] If the casing sealing needs to achieve a better sealing effect, it is generally necessary to send a cement truck from a professional cementing company to the well, and use a pumping method to pump cement slurry into the water holes of the casing in a positive circulation to replace the annular liquid to complete the sealing of the casing. The cost of sending a cement truck from a professional cementing company to the well is generally high. In addition to the cement truck and ash tank truck, an operator is also required, which is costly. Generally, the cost of going to the well is RMB 10,000 per time plus the cost of raw materials, and the construction timeliness is poor. Both parties have to wait and cooperate for a long time, and the cost, time cost, and labor intensity are all high. Utility Model Content
[0008] The purpose of this section is to summarize some aspects of the embodiments of the utility model and briefly introduce some preferred embodiments. Some simplifications or omissions may be made in this section and the specification abstract and utility model name of this application to avoid blurring the purpose of this section, specification abstract and utility model name, and such simplifications or omissions cannot be used to limit the scope of the utility model.
[0009] In view of the above problems and / or the problems existing in the prior art, the present utility model is proposed.
[0010] The utility model aims to overcome the problems existing in the prior art and provide a simple cementing device for a pipe used in oil drilling, which has a simple structure, high operating efficiency, good sealing effect, and saves time and construction cost.
[0011] In order to solve the above technical problems, the utility model provides a simple cementing device for a pipe for oil drilling, including a pipe located in an open wellbore, the lower end of the pipe is inserted into the soil layer at the bottom of the well, a grouting pipe is inserted into the annulus between the outer periphery of the pipe and the inner wall of the wellbore, the lower end of the grouting pipe is close to the bottom of the wellbore, the upper end of the grouting pipe is connected to the outlet pipeline of a grouting pump, the inlet pipeline of the grouting pump is connected to the bottom valve outlet of a cement mixing tank, the cement mixing tank is located on one side of the drilling platform, a stirring shaft is provided along the axis of the cement mixing tank, the upper end of the stirring shaft is connected to the output end of a stirring motor, and a stirring blade is provided at the lower end of the stirring shaft.
[0012] Furthermore, the grouting pipe is a 2-inch oil pipe.
[0013] Furthermore, the outer diameter of the catheter is 339.7 mm.
[0014] Furthermore, the wellbore is drilled by a scraper with a diameter of 425 mm.
[0015] Furthermore, a reamer with a diameter of 473 mm is provided above the scraper.
[0016] Furthermore, the volume of the cement mixing tank is greater than the annular volume around the conduit.
[0017] Compared with the prior art, the utility model has achieved the following beneficial effects: 1. A cement slurry mixing device is set on the ground, and the cement powder and water mixed therein are mixed evenly by a stirring motor, which can effectively mix into a uniform cement slurry compared with the method of manually pouring cement powder into the annulus;
[0018] 2. The mixed cement slurry is sent to the bottom of the annulus of the pipe through the grouting pipe. The cement slurry gradually pushes the annulus liquid out of the wellhead from bottom to top by utilizing the density difference. Compared with the traditional method, the annulus of the pipe can be filled with cement slurry, and the annulus liquid will not be mixed into the cement slurry, which can form an effective sealing of the pipe.
[0019] 3. It can effectively fill the catheter shoe with cement slurry, which reduces the risk of ground collapse and cement stone collapse at the lower catheter shoe compared with the shortcomings of traditional methods;
[0020] 4. Compared with cement truck cementing method, it can achieve the same cementing quality, but the cost is extremely low, and there is no need to wait, saving time and investment costs. BRIEF DESCRIPTION OF THE DRAWINGS
[0021] In order to more clearly illustrate the technical solutions of the embodiments of the present utility model, the following will briefly introduce the drawings required for the description of the embodiments. Obviously, the drawings described below are only some embodiments of the present utility model. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative labor. The drawings are only provided for reference and explanation, not for limiting the present utility model. Among them:
[0022] Figure 1 This is a schematic diagram of the structure of a simple cementing device for a pipe used in oil drilling according to the utility model;
[0023] Figure 2 This is a state diagram after the cementing of the utility model is completed;
[0024] In the figure: 1. An open wellbore; 2. A guide tube; 3. A cement mixing tank; 3a. Agitator blades; 4. A bottom valve; 5. A grouting pump; 6. A grouting pipe; 7. A drilling platform. DETAILED DESCRIPTION
[0025] In the following description of the utility model, the terms "upper", "lower", "front", "back", "left", "right", "inside", "outside", etc. indicate directions or positional relationships based on the directions or positional relationships shown in the accompanying drawings. They are only for the convenience of describing the utility model and simplifying the description, and do not mean that the device must have a specific direction.
[0026] In order to make the technical means, creative features, objectives and effects of the present invention easier to understand, the present invention is further described below with reference to specific figures. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of them.
[0027] Unless otherwise defined, all technical and scientific terms used herein have the same meaning as those commonly understood by those skilled in the art of the present invention. The terms used in the specification of the present invention are only for the purpose of describing specific embodiments and are not intended to limit the present invention.
[0028] like Figure 1 As shown, the utility model of the simple cementing device for oil drilling with a conduit includes a conduit 2, a cement mixing tank 3, a grouting pump 5 and a grouting pipe 6. The conduit 2 is located in an open wellbore 1. The drilling platform, the open wellbore 1 and the conduit 2 are all coaxial. The lower end of the conduit 2 is inserted into the soil layer at the bottom of the well to close the lower end. The cement mixing tank 3 is placed on one side of the drilling platform. A stirring shaft is provided along the axis of the cement mixing tank 3. The upper end of the stirring shaft is connected to the output end of the stirring motor. The lower end of the stirring shaft is provided with a stirring blade 3a, which is convenient for mixing cement powder and mixing water evenly.
[0029] A bottom valve 4 is installed at the bottom outlet of the cement mixing tank 3, and the outlet of the bottom valve 4 is connected to the inlet pipeline of the grouting pump 5. The outlet pipeline of the grouting pump 5 is connected to the upper end of the grouting pipe 6 through a high-pressure hose or oil. The grouting pipe 6 is inserted from top to bottom into the annulus between the outer periphery of the guide tube 2 and the inner wall of the wellbore, and the lower end of the grouting pipe 6 is close to the bottom of the wellbore. The grouting pipe 6 adopts the 2-inch oil pipe commonly used on the construction site, which is convenient for local materials and reduces procurement costs.
[0030] The volume of the cement mixing tank 3 is larger than the annular volume of the outer periphery of the conduit, so that the cement slurry can be fully prepared at one time without pausing during the grouting process, thereby ensuring that the cement slurry maintains good fluidity. After the grouting is completed, it is convenient to pull out the grouting pipe 6 before the cement slurry thickens.
[0031] The size of each component of the device of the utility model can be appropriately sized according to the actual situation on site. The requirements of the cement slurry mixing device of the utility model are described below in combination with cementing operations with different sizes of conduits.
[0032] Embodiment: If a Φ425mm scraper + Φ473mm reamer is used for one-opening construction, 2-5 Φ339.7mm conduits are lowered after the pilot hole is advanced. When the conduits are in place and filled with water, a male threaded plug is first used to seal the top of the conduits. The pilot hole annular clearance is 66.65mm, and the grouting pipe 6 uses a 2-inch oil pipe. When cementing, first mix cement powder and water in a certain proportion in a cement mixing tank 3 to achieve the cement slurry density and volume required for surface cementing construction.
[0033] The cement slurry is mixed in the cement mixing tank 3 into a cement slurry with a specific gravity of 1.85-1.90g / cm³. The pilot hole is generally made of water mixed with soil slurry with a density of 1.03-1.05g / cm³. The bottom valve 4 at the lower outlet of the cement mixing tank 3 is opened, and the grouting pump 5 is turned on. The grouting pump 5 injects high-density cement slurry into the grouting pipe 6, and flows into the bottom of the catheter annulus along the grouting pipe 6. As the high-density cement slurry continues to flow in, the pilot hole liquid is continuously squeezed upward by relying on the density difference until it is completely replaced out of the ground. The catheter annulus is completely filled with cement slurry, and after solidification, cement stone with a certain hardness is formed, thereby completing the sealing of the pilot hole cement slurry. Figure 2 shown.
[0034] The above description is only the preferred feasible embodiment of the utility model, which shows and describes the basic principle, main features and advantages of the utility model, but does not limit the scope of patent protection of the utility model. The technicians in this industry should understand that the utility model is not limited by the above embodiments. In addition to the above embodiments, the utility model can also have other implementation modes without departing from the spirit and scope of the utility model. The utility model will also have various changes and improvements. All technical solutions formed by equivalent replacement or equivalent transformation fall within the scope of protection required by the utility model. The scope of protection required by the utility model is defined by the attached claims and their equivalents. The technical features not described in the utility model can be achieved by or using existing technologies, which will not be repeated here.
Claims
1. A simple cementing device for a pipe used in oil drilling, comprising a pipe located in an open wellbore, It is characterized in that The lower end of the conduit is inserted into the soil layer at the bottom of the well, a grouting pipe is inserted into the annulus between the outer periphery of the conduit and the inner wall of the wellbore, the lower end of the grouting pipe is close to the bottom of the wellbore, the upper end of the grouting pipe is connected to the outlet pipeline of the grouting pump, the inlet pipeline of the grouting pump is connected to the bottom valve outlet of the cement mixing tank, the cement mixing tank is located on one side of the drilling platform, a stirring shaft is provided along the axis of the cement mixing tank, the upper end of the stirring shaft is connected to the output end of the stirring motor, and the lower end of the stirring shaft is provided with a stirring blade.
2. The simple cementing device for pipe used in oil drilling according to claim 1, Features: The grouting pipe is a 2-inch oil pipe.
3. The simple cementing device for pipe used in oil drilling according to claim 1, Features: The outer diameter of the catheter is 339.7 mm.
4. The simple cementing device for pipe used in oil drilling according to claim 1, Features: The wellbore is drilled by a scraper with a diameter of 425 mm.
5. The simple cementing device for pipe used in oil drilling according to claim 4, Features: A reamer with a diameter of 473 mm is arranged above the scraper.
6. The simple cementing device for pipe used in oil drilling according to any one of claims 1 to 5, Features: The volume of the cement mixing tank is greater than the annular volume around the conduit.