Rectangular steel sleeve for rectangular pipe jacking construction

By designing a rectangular steel sleeve for rectangular pipe jacking construction, and using the base and axial support structure to stabilize the rectangular steel sleeve in the receiving well, the settlement problem during the construction of shallow-buried large-section rectangular pipe jacking is solved, ensuring safe and smooth construction and improving construction efficiency. Efficiency and speed.

CN221920958UActive Publication Date: 2024-10-29CHINA RAILWAY 22ND BUREAU GRP RAIL ENG CO LTD +2
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420610595.1
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-03-27
Publication Date
2024-10-29
Estimated Expiration
2034-03-27

AI Technical Summary

Technical Problem

During the construction of shallow-buried large-section rectangular pipe jacking, due to the influence of geological conditions and construction parameters, settlement errors or failures often occur, which hinders the progress of the project and may cause damage to surrounding buildings and underground facilities, and even cause geological disasters.

Method used

A rectangular steel sleeve for rectangular pipe jacking construction is designed, which includes a base, a rectangular steel sleeve body and an axial support structure. The rectangular steel sleeve body is supported in the concrete layer of the receiving well through the horizontal support part and the limiting part of the base. , and is supported on the wall of the receiving well through the axial support structure at the back. The assembly of multiple pipe sections and back covers and the arrangement of support frames and supports ensure that the rectangular steel sleeve is stable during the construction process.

Benefits of technology

It effectively prevents soil settlement, ensures smooth pipe jacking, improves construction safety and efficiency, simplifies the installation and disassembly process, adapts to narrow space operations, and improves construction speed and efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221920958U_ABST
    Figure CN221920958U_ABST
Patent Text Reader

Abstract

The utility model relates to a rectangular steel sleeve for rectangular pipe jacking construction. The rectangular steel sleeve comprises a base (1); the rectangular steel sleeve body (2) is supported on the base (1); the axial supporting structure (3) is arranged on the back of the rectangular steel sleeve body (2), and the rectangular steel sleeve body (2) is supported on an existing wall of the rectangular pipe jacking construction receiving well; the rectangular steel sleeve body (2) is formed by splicing a plurality of pipe joints and a rear cover; the base (1) is arranged corresponding to the pipe joints and the rear cover. According to the scheme, the safety in the construction process of the rectangular jacking pipe can be effectively guaranteed, it is guaranteed that a geological soil layer is stable and does not settle, it is guaranteed that the jacking pipe penetrates into the rectangular steel sleeve smoothly and safely when the jacking pipe is jacked, it is effectively guaranteed that the rectangular jacking pipe completes construction smoothly, and construction efficiency is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of protective devices for rectangular jacking pipe construction, in particular to a rectangular steel sleeve for rectangular jacking pipe construction. Background Art

[0002] Pipe jacking tunnel construction technology is a method of tunnel construction underground. It does not require excavation of the surface and can be constructed without affecting surface buildings and traffic. During the shallow buried large-section rectangular pipe jacking construction stage, due to the influence of geological conditions and construction parameters and other factors, there are often errors or failures due to settlement. This settlement will not only hinder the normal progress of the project, but also may cause damage to surrounding buildings and underground facilities, and may even cause more serious geological disasters.

[0003] Therefore, how to smoothly push the rectangular jacking pipe into the receiving well to complete the tunnel construction during the shallow buried large-section rectangular jacking pipe construction process is a technical problem that needs to be solved urgently. Utility Model Content

[0004] The utility model aims to solve at least one technical problem in the background technology and provides a rectangular steel sleeve for rectangular pipe jacking construction.

[0005] In order to achieve the above-mentioned purpose, the utility model provides a rectangular steel sleeve for rectangular pipe jacking construction, comprising:

[0006] Base;

[0007] A rectangular steel sleeve body supported on the base;

[0008] An axial support structure is arranged on the back of the rectangular steel sleeve body to support the rectangular steel sleeve body on the existing wall of the rectangular jacking pipe construction receiving well;

[0009] The rectangular steel sleeve body is composed of a plurality of pipe sections and a rear cover;

[0010] The base is arranged corresponding to each of the pipe sections and the rear cover.

[0011] According to one aspect of the utility model, the base includes a horizontal support portion and a limiting portion;

[0012] The horizontal support portion is supported in the concrete layer of the receiving well and is supported at the bottom of the rectangular steel sleeve body;

[0013] The limiting portion is supported at two ends of the horizontal supporting portion and extends in a vertical direction to be connected to the outer walls of both sides of the pipe section or the rear cover.

[0014] According to one aspect of the utility model, the rectangular steel sleeve body comprises a transition pipe section, a first intermediate pipe section, a second intermediate pipe section, a third intermediate pipe section and a rear cover;

[0015] The transition pipe section, the first intermediate pipe section, the second intermediate pipe section, the third intermediate pipe section and the rear cover are detachably connected end to end in sequence;

[0016] The transition pipe section, the first intermediate pipe section, the second intermediate pipe section, the third intermediate pipe section and the rear cover are all composed of two upper and lower parts that are detachably connected.

[0017] According to one aspect of the utility model, the axial support structure includes a support frame and a support body;

[0018] The support frame is fixedly arranged on the outer wall of the rear cover;

[0019] The support body array is arranged on the support frame.

[0020] According to one aspect of the utility model, the support frame includes a transverse support frame, a vertical support frame and a support seat;

[0021] The transverse support frames are evenly spaced and arranged on the rear cover along the vertical direction;

[0022] The vertical support frames are evenly spaced and arranged on the rear cover along the horizontal direction, and are connected to the horizontal support frames;

[0023] The support seat array is arranged at the connection between the transverse support frame and the vertical support frame, and the support body is installed on each of the support seats.

[0024] According to one aspect of the utility model, the support body is made of a steel pipe.

[0025] According to a scheme of the utility model, a rectangular steel sleeve for rectangular jacking construction includes: a base; a rectangular steel sleeve body supported on the base; an axial support structure arranged on the back of the rectangular steel sleeve body, supporting the rectangular steel sleeve body on the existing wall of the rectangular jacking construction receiving well; the rectangular steel sleeve body is composed of a plurality of pipe sections and a rear cover; and the base is arranged corresponding to each pipe section and the rear cover. With such an arrangement, the rectangular steel sleeve body can be stably and firmly supported in the jacking construction receiving well through the base, and the rectangular steel sleeve body can be stably and firmly supported on the existing wall of the receiving well in the axial direction through the axial support structure, so that the rectangular steel sleeve for rectangular jacking construction of the utility model can more reliably support the surrounding soil from settling during the rectangular jacking construction, protect the jacking pipe from being affected by any geological problems when penetrating into the rectangular steel sleeve, and ensure the safe and smooth completion of the jacking construction. In addition, the arrangement of each pipe section and the rear cover can make the installation and disassembly of the rectangular steel sleeve body smoother and more convenient, effectively improving the construction speed and efficiency.

[0026] According to one solution of the utility model, the base includes a horizontal support part and a limiting part; the horizontal support part is supported in the concrete layer of the receiving well and supported at the bottom of the rectangular steel sleeve body; the limiting part is supported at both ends of the horizontal support part and extends in the vertical direction to connect with the outer walls of the pipe section or the rear cover on both sides. In this way, the base can support and limit the pipe section or the rear cover vertically and horizontally, ensuring that the support of each pipe section and the rear cover is more stable and reliable, ensuring the stability of the position, and improving the safety of the jacking construction.

[0027] According to one solution of the utility model, the rectangular steel sleeve body includes a transition pipe section, a first intermediate pipe section, a second intermediate pipe section, a third intermediate pipe section and a rear cover; the transition pipe section, the first intermediate pipe section, the second intermediate pipe section, the third intermediate pipe section and the rear cover are detachably connected end to end in sequence; the transition pipe section, the first intermediate pipe section, the second intermediate pipe section, the third intermediate pipe section and the rear cover are all composed of two detachably connected upper and lower parts. Such a setting can make the rectangular steel sleeve body more convenient and quick during the construction process in the well. Because the space in the well is small, the split setting between each pipe section and the rear cover can effectively overcome the difficulty of working in a small space, ensure smooth and fast construction, and effectively improve construction efficiency.

[0028] According to one solution of the utility model, the axial support structure includes a support frame and a support body; the support frame is fixedly arranged on the outer wall of the rear cover; and the support bodies are arranged in an array on the support frame. With such an arrangement, each support body can be stably and securely installed on the rear cover through the support frame, and the support bodies arranged in an array can effectively disperse the axial force of the rectangular steel sleeve body, and provide reverse support force for the rectangular steel sleeve body through the existing wall and the support body, and can make the force uniform, effectively preventing the displacement or deformation of the rectangular steel sleeve body due to uneven force during construction.

[0029] According to one solution of the utility model, the support frame includes a transverse support frame, a vertical support frame and a support seat; the transverse support frame is evenly arranged on the back cover along the vertical direction; the vertical support frame is evenly arranged on the back cover along the horizontal direction and connected to each transverse support frame; the support seat array is arranged at the connection between the transverse support frame and the vertical support frame, and the support body is installed on each support seat. Such an arrangement can make the support frame stably and firmly installed on the back cover, and can make the force transmission more uniform. The support body can be firmly installed on the back cover through the support seat to ensure stability.

[0030] According to the scheme of the utility model, the utility model can effectively ensure the safety during the construction of rectangular jacking pipes, ensure that the geological soil layer is stable and does not sink, ensure the smooth and safe penetration of the jacking pipe into the rectangular steel sleeve, effectively ensure the smooth completion of the construction of the rectangular jacking pipe, and improve the construction efficiency. BRIEF DESCRIPTION OF THE DRAWINGS

[0031] Figure 1 A side view schematically shows a rectangular steel sleeve for rectangular pipe jacking construction according to an embodiment of the utility model in use;

[0032] Figure 2 A schematic front view of a rectangular steel sleeve for rectangular pipe jacking construction according to an embodiment of the utility model is shown in use;

[0033] Figure 3 A rear view schematically showing a rectangular steel sleeve for rectangular pipe jacking construction according to an embodiment of the utility model in use;

[0034] Figure 4 The structural layout diagram of the base of a rectangular steel sleeve for rectangular jacking pipe construction according to one embodiment of the utility model is schematically shown. DETAILED DESCRIPTION

[0035] The present invention will now be discussed with reference to exemplary embodiments. It should be understood that the embodiments discussed are only intended to enable those skilled in the art to better understand and implement the present invention, rather than to imply any limitation on the scope of the present invention.

[0036] As used herein, the term “including” and variations thereof are to be interpreted as open-ended terms meaning “including, but not limited to.” The term “based on” is to be interpreted as “based, at least in part, on.” The terms “one embodiment” and “an embodiment” are to be interpreted as “at least one embodiment.”

[0037] Figure 1 A side view schematically shows a rectangular steel sleeve for rectangular pipe jacking construction according to an embodiment of the utility model in use; Figure 2 A schematic front view of a rectangular steel sleeve for rectangular pipe jacking construction according to an embodiment of the utility model is shown in use; Figure 3 A rear view schematically showing a rectangular steel sleeve for rectangular pipe jacking construction according to an embodiment of the utility model in use; Figure 4 The following is a schematic diagram showing the structural arrangement of the base of a rectangular steel sleeve for rectangular pipe jacking construction according to an embodiment of the present invention. Figure 1-Figure 4 As shown, in this embodiment, a rectangular steel sleeve for rectangular pipe jacking construction includes:

[0038] Base 1;

[0039] A rectangular steel sleeve body 2 is supported on a base 1;

[0040] The axial support structure 3 is arranged on the back of the rectangular steel sleeve body 2 to support the rectangular steel sleeve body 2 on the existing wall of the rectangular jacking construction receiving well;

[0041] The rectangular steel sleeve body 2 is composed of a plurality of pipe sections and a rear cover;

[0042] The base 1 is arranged corresponding to each pipe section and the back cover. With such arrangement, the rectangular steel sleeve body 2 can be stably and securely supported in the receiving well of the jacking pipe construction through the base 1, and the rectangular steel sleeve body 2 can be stably and securely supported on the existing wall of the receiving well in the axial direction through the axial support structure 3. In this way, the rectangular steel sleeve for rectangular jacking pipe construction of the utility model can more reliably support the surrounding soil from settling during the rectangular jacking pipe jacking construction, protect the jacking pipe from being affected by any geological problems when penetrating into the rectangular steel sleeve, and ensure the safe and smooth completion of the jacking construction. In addition, the arrangement of each pipe section and the back cover can make the installation and disassembly of the rectangular steel sleeve body 2 smoother and more convenient, effectively improving the construction speed and efficiency.

[0043] Furthermore, if Figure 4 As shown, in this embodiment, the base 1 includes a horizontal support portion 4 and a limiting portion 5;

[0044] The horizontal support part 4 is supported in the concrete layer of the receiving well and supported on the bottom of the rectangular steel sleeve body 2;

[0045] The limiting part 5 is supported at both ends of the horizontal supporting part 4, and extends in the vertical direction to be connected to the outer walls of the pipe section or the rear cover on both sides. In this way, the base 1 can support and limit the pipe section or the rear cover in the vertical and horizontal directions, ensuring that the support of each pipe section and the rear cover is more stable and reliable, ensuring the stability of the position, and improving the safety of the jacking construction.

[0046] Furthermore, if Figure 1 As shown, in this embodiment, the rectangular steel sleeve body 2 includes a transition pipe section 6, a first intermediate pipe section 7, a second intermediate pipe section 8, a third intermediate pipe section 9 and a rear cover 10;

[0047] The transition pipe section 6, the first intermediate pipe section 7, the second intermediate pipe section 8, the third intermediate pipe section 9 and the rear cover 10 are detachably connected end to end in sequence;

[0048] The transition pipe section 6, the first intermediate pipe section 7, the second intermediate pipe section 8, the third intermediate pipe section 9 and the rear cover 10 are all composed of two detachably connected upper and lower parts. Such a configuration can make the rectangular steel sleeve body 2 more convenient and quick during the construction process in the well. Because the space in the well is narrow, the separate configuration between each pipe section and the rear cover can effectively overcome the difficulty of working in a narrow space, ensure smooth and rapid construction, and effectively improve construction efficiency.

[0049] Furthermore, if Figure 3 As shown, in this embodiment, the axial support structure 3 includes a support frame 11 and a support body 12;

[0050] The support frame 11 is fixedly arranged on the outer wall of the rear cover 10;

[0051] The support bodies 12 are arranged in an array on the support frame 11. With such an arrangement, each support body 12 can be stably and securely mounted on the rear cover 10 through the support frame 11, and the support bodies 12 arranged in an array can effectively disperse the axial force of the rectangular steel sleeve body 2, and the existing wall and support bodies 12 provide reverse support force for the rectangular steel sleeve body 2, and can make the force uniform, effectively preventing the displacement or deformation of the rectangular steel sleeve body 2 due to uneven force during construction.

[0052] Furthermore, if Figure 3 As shown, in this embodiment, the support frame 11 includes a horizontal support frame 13, a vertical support frame 14 and a support seat 15;

[0053] The transverse support frames 13 are evenly spaced and arranged on the rear cover 10 along the vertical direction;

[0054] The vertical support frames 14 are evenly spaced and arranged on the rear cover 10 along the horizontal direction, and are connected to each of the horizontal support frames 13;

[0055] The support seats 15 are arranged in an array at the connection between the horizontal support frame 13 and the vertical support frame 14, and the support body 12 is installed on each support seat 15. In this way, the support frame 11 can be stably and firmly installed on the back cover 10, and the force transmission can be more uniform. The support body 12 can be firmly installed on the back cover 10 through the support seat 15 to ensure stability.

[0056] In this embodiment, the support body 12 is made of a steel pipe. This arrangement can make the support strength higher and ensure the support stability and rigidity of the rectangular steel sleeve body 2.

[0057] Moreover, Figure 1-Figure 4 As shown, in this embodiment, transverse and vertical reinforcing ribs 16 are evenly arranged on the outer wall of the rectangular steel sleeve body 2, so that the structural strength of the rectangular steel sleeve body 2 is higher and the ability to resist external forces is stronger.

[0058] According to the above scheme of the utility model, the utility model can effectively ensure the safety during the construction of rectangular jacking pipes, ensure that the geological soil layer is stable and does not sink, ensure the smooth and safe penetration of the jacking pipe into the rectangular steel sleeve, effectively ensure the smooth completion of the construction of the rectangular jacking pipe, and improve the construction efficiency.

[0059] Finally, it should be noted that the above preferred embodiments are only used to illustrate the technical solution of the utility model rather than to limit it. Although the utility model has been described in detail through the above preferred embodiments, those skilled in the art should understand that various changes can be made in form and details without departing from the scope defined by the claims of the utility model.

Claims

1. Rectangular steel sleeve for rectangular pipe jacking construction, It is characterized in that include: Base (1); A rectangular steel sleeve body (2) supported on the base (1); An axial support structure (3) is arranged on the back of the rectangular steel sleeve body (2) to support the rectangular steel sleeve body (2) on the existing wall of the rectangular jacking pipe construction receiving well; The rectangular steel sleeve body (2) is composed of a plurality of pipe sections and a rear cover; The base (1) is arranged corresponding to each of the pipe sections and the rear cover.

2. The rectangular steel sleeve for rectangular pipe jacking construction according to claim 1, It is characterized in that The base (1) comprises a horizontal supporting portion (4) and a limiting portion (5); The horizontal support part (4) is supported in the concrete layer of the receiving well and is supported at the bottom of the rectangular steel sleeve body (2); The limiting portion (5) is supported at both ends of the horizontal supporting portion (4), and extends in a vertical direction, and is connected to the outer walls on both sides of the pipe section or the rear cover.

3. The rectangular steel sleeve for rectangular pipe jacking construction according to claim 1, It is characterized in that The rectangular steel sleeve body (2) comprises a transition pipe section (6), a first intermediate pipe section (7), a second intermediate pipe section (8), a third intermediate pipe section (9) and a rear cover (10); The transition pipe section (6), the first intermediate pipe section (7), the second intermediate pipe section (8), the third intermediate pipe section (9) and the rear cover (10) are detachably connected end to end in sequence; The transition pipe section (6), the first intermediate pipe section (7), the second intermediate pipe section (8), the third intermediate pipe section (9) and the rear cover (10) are all composed of two upper and lower parts that are detachably connected.

4. A rectangular steel sleeve for rectangular pipe jacking construction according to any one of claims 1 to 3, It is characterized in that The axial support structure (3) comprises a support frame (11) and a support body (12); The support frame (11) is fixedly arranged on the outer wall of the rear cover (10); The support bodies (12) are arranged in an array on the support frame (11).

5. The rectangular steel sleeve for rectangular pipe jacking construction according to claim 4, It is characterized in that The support frame (11) comprises a transverse support frame (13), a vertical support frame (14) and a support seat (15); The transverse support frames (13) are arranged on the rear cover (10) at even intervals along the vertical direction; The vertical support frames (14) are evenly spaced and arranged on the rear cover (10) along the horizontal direction, and are connected to each of the transverse support frames (13); The support seats (15) are arranged in an array at the connection between the transverse support frame (13) and the vertical support frame (14), and the support body (12) is mounted on each of the support seats (15).

6. The rectangular steel sleeve for rectangular pipe jacking construction according to claim 4, It is characterized in that The support body (12) is made of a steel pipe.