Surveying device for architectural design scheme design
By designing a height-adjustable survey platform and a folding mechanism, the difficulty of operating the electromagnetic survey instrument on uneven ground in the field is solved, the survey efficiency is improved and the carrying process is simplified.
Patent Information
- Application Number
- CN202420216161.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-01-30
- Publication Date
- 2024-10-29
- Estimated Expiration
- 2034-01-30
AI Technical Summary
The electromagnetic survey instrument is inconvenient to carry during field survey due to its large size, and the uneven ground in the field makes operation difficult, affecting survey efficiency.
A device including a survey platform, a pillar, an adjustment sleeve and a folding rod is designed. Through the combination of the adjustment sleeve and the pillar, the height of the survey platform is adjusted, and through the mechanism of the folding rod and compression spring, the survey platform can be positioned on uneven ground. Stay stable and easy to operate, and fold and store after the survey is completed to reduce space usage.
It achieves stable operation of the electromagnetic survey instrument on uneven ground, improves survey efficiency, and makes the device easier to carry through its folding design.
Smart Images

Figure CN221922653U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of surveying devices, and in particular to a surveying device for designing architectural design schemes. Background Art
[0002] Before construction of an engineering building, a survey of the construction geology will be conducted. Through geological survey, the geological conditions of the construction area will be evaluated, various engineering problems that may arise during the construction process will be predicted, and corresponding architectural design plans will be customized to ensure the safety of the construction and the stability of the building. When conducting geological surveys, electromagnetic survey instruments are often used to conduct geological surveys. The skin effect of electromagnetic induction is used, that is, high-frequency electromagnetic fields penetrate shallowly and low-frequency electromagnetic fields penetrate deeply. Under the condition that the distance between the source and the receiving point remains unchanged, the frequency of the electromagnetic field is changed to achieve the purpose of the survey.
[0003] At present, geological data is mainly collected through components such as magnetic sensors and fluxgate sensors, and then the data is processed by electromagnetic survey instruments to achieve the purpose of surveying. At present, when electromagnetic survey instruments are used for surveying in field environments, the survey platform is large and inconvenient to carry, and the uneven ground in the field easily causes the survey instrument to move. Generally, the electromagnetic survey instrument is placed on the ground in the field, which is inconvenient for operators to operate the electromagnetic survey instrument during the survey, which is not conducive to the survey. Therefore, a survey device for architectural design scheme design is needed to meet people's needs. Utility Model Content
[0004] The purpose of the utility model is to provide a surveying device for architectural design scheme design, so as to solve the problem raised in the above background technology that the surveying platform is large and inconvenient to carry, and the uneven ground in the field easily causes the surveying instrument to move. Generally, the electromagnetic surveying instrument is placed on the ground in the field, which makes it inconvenient for the operator to operate the electromagnetic surveying instrument during the survey, and is not conducive to the survey.
[0005] To achieve the above-mentioned purpose, the utility model provides the following technical solutions: a surveying device for architectural design scheme design, comprising an electromagnetic surveying instrument, a surveying platform is arranged below the electromagnetic surveying instrument, a storage box is installed on the surveying platform, a sleeve is installed on the storage box, an insert block is installed at the bottom of the electromagnetic surveying instrument, the insert block is inserted in the sleeve, a plurality of supporting seats are installed at the bottom of the surveying platform, pillars are rotatably installed in the plurality of supporting seats, an adjusting sleeve is sleeved on the outer wall of the pillar, a support rod is installed on the pillar, a first connecting seat is installed on the support rod, a first folding rod is rotatably installed on the first connecting seat, a bracket is installed at the bottom of the surveying platform, a second connecting seat is installed on the bracket, a second folding rod is rotatably installed on the second connecting seat, the second folding rod is rotatably installed on the first folding rod, a first support block is installed in the first folding rod, a second support block is installed in the second folding rod, one end of a compression spring is installed on the first support block, and the other end of the compression spring is installed on the second support block.
[0006] Preferably, a threaded groove is provided on the adjusting sleeve, and a fixing bolt is movably installed in the threaded groove.
[0007] Preferably, the storage box is provided with a cover plate, the cover plate is provided with a buckle, and the buckle is buckled on the storage box.
[0008] Preferably, a partition plate is installed in the storage box, and the thickness of the partition plate ranges from one centimeter to two centimeters.
[0009] Preferably, a sundries box is installed on the storage box, and a soft cushion is installed in the sundries box.
[0010] Preferably, an anti-skid pad is installed at the bottom of the adjustment sleeve, and the material of the anti-skid pad is rubber material.
[0011] Preferably, a first rotating shaft is installed on the first connecting seat, a second rotating shaft is installed on the second connecting seat, a rotating block is installed on the first folding rod, one end of the first folding rod is rotatably installed on the first rotating shaft, one end of the second folding rod is rotatably installed on the second rotating shaft, and the other end of the second folding rod is rotatably installed on the rotating block.
[0012] The beneficial effects of the utility model are:
[0013] In the utility model, the survey platform is placed at a suitable surveying position through the design of the survey platform, pillars, adjustment sleeves, fixing bolts and other mechanisms. At this time, the height of the survey platform is adjusted according to the height of the surveyor and the flatness of the terrain. The adjustment sleeve can be slid on the pillar. The height of the survey platform can be adjusted by adjusting the depth of the adjustment sleeve on the pillar, so that the height of the survey platform reaches a suitable operating height for the surveyor, which is convenient for the surveyor to operate the electromagnetic survey instrument, and the survey platform can be horizontally stood on an uneven survey ground to avoid the electromagnetic survey instrument from moving during the survey.
[0014] In the utility model, through the design of the first folding rod, the second folding rod, the compression spring, the support rod and other mechanisms, the rotation of the adjusting sleeve will drive the rotation of the pillar, the rotation of the pillar will drive the rotation of the support rod, the rotation of the support rod will drive the first connecting seat to rotate, the rotation of the first connecting seat will squeeze and drive the first folding rod to rotate, the rotation of the first folding rod will squeeze and drive the second folding rod to rotate, the first folding rod can be folded onto the second folding rod, so that the support rod and the adjusting sleeve can be folded and stored, reducing the space occupied by the surveying platform and making it convenient to carry. BRIEF DESCRIPTION OF THE DRAWINGS
[0015] Figure 1 This is a schematic diagram of the structure of a survey device for architectural design proposed by the utility model;
[0016] Figure 2 A schematic diagram of the side structure of a survey device for architectural design proposed by the utility model;
[0017] Figure 3 This is a schematic diagram of the bottom structure of a survey device for architectural design proposed by the utility model;
[0018] Figure 4 This is a schematic diagram of the structure of part A of a survey device for architectural design proposed in the utility model;
[0019] Figure 5 The utility model provides a schematic cross-sectional structure diagram of a storage box and a partition plate of a survey device for architectural design scheme design.
[0020] In the figure: 1. Electromagnetic survey instrument; 2. Survey table; 3. Storage box; 4. Sleeve; 5. Insert block; 6. Support seat; 7. Pillar; 8. Adjustment sleeve; 9. Fixing bolt; 10. Threaded groove; 11. First connecting seat; 12. First folding rod; 13. Bracket; 14. Second connecting seat; 15. Second folding rod; 16. First support block; 17. Second support block; 18. Compression spring; 19. Cover plate; 20. Buckle; 21. Partition plate; 22. Miscellaneous box; 23. Support rod. DETAILED DESCRIPTION
[0021] The technical solutions in the embodiments of the present invention will be described clearly and completely below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all of the embodiments.
[0022] Example 1: Reference Figure 1-5A surveying device for architectural design scheme design includes an electromagnetic surveying instrument 1, a surveying platform 2 is arranged below the electromagnetic surveying instrument 1, a storage box 3 is installed on the surveying platform 2, a sleeve 4 is installed on the storage box 3, an insert block 5 is installed at the bottom of the electromagnetic surveying instrument 1, the insert block 5 is inserted in the sleeve 4, a plurality of support seats 6 are installed at the bottom of the surveying platform 2, a plurality of support seats 6 are rotatably installed with pillars 7, an outer wall of the pillar 7 is sleeved with an adjustment sleeve 8, a support rod 23 is installed on the pillar 7, a first connecting seat 11 is installed on the support rod 23, a first folding rod 12 is rotatably installed on the first connecting seat 11, a bracket 13 is installed at the bottom of the surveying platform 2, a second connecting seat 14 is installed on the bracket 13, and a second folding rod 15 is rotatably installed on the second connecting seat 14 The second folding rod 15 is rotatably mounted on the first folding rod 12, a first support block 16 is mounted in the first folding rod 12, a second support block 17 is mounted in the second folding rod 15, one end of a compression spring 18 is mounted on the first support block 16, and the other end of the compression spring 18 is mounted on the second support block 17. When geological survey is required, the magnetic sensor and the fluxgate sensor are first placed on the survey ground, and the survey platform 2 is placed in a suitable survey position. At this time, the height of the survey platform 2 is adjusted according to the height of the surveyor and the flatness of the terrain. The adjustment sleeve 8 can be slid on the pillar 7. The height of the survey platform 2 can be adjusted by adjusting the depth of the adjustment sleeve 8 on the pillar 7, so that the height of the survey platform 2 reaches the appropriate operating height for the surveyor. The degree is convenient for the surveyor to operate the electromagnetic survey instrument 1, and the survey platform 2 is horizontally placed on the uneven survey ground to avoid the electromagnetic survey instrument 1 from moving during the survey. Then the electromagnetic survey instrument 1 is opened, and the plug block 5 is inserted into the sleeve 4 to carry out geological survey. After the survey is completed, the cover plate 19 can be opened, and the electromagnetic survey instrument 1 is placed in the space on one side of the partition plate 21, and the magnetic sensor and fluxgate sensor and other objects are placed in the space on the other side of the partition plate 21. The cover plate 19 is covered, and the buckle 20 is clamped, and then the fixing bolt 9 is unscrewed from the thread groove 10, and then the adjusting sleeve 8 is rotated into the electromagnetic survey instrument 1. The rotation of the adjusting sleeve 8 will drive the support 7 to rotate, and the rotation of the support 7 will drive the support rod 23 to rotate, and the rotation of the support rod 23 will The first connecting seat 11 is driven to rotate. The rotation of the first connecting seat 11 will squeeze and drive the first folding rod 12 to rotate. The rotation of the first folding rod 12 will squeeze and drive the second folding rod 15 to rotate. The first folding rod 12 can be folded on the second folding rod 15, so that the support column 7 and the adjusting sleeve 8 can be folded and stored, reducing the occupied space of the surveying platform 2 and making it convenient to carry. On the other hand, when the support column 7 and the adjusting sleeve 8 are unfolded, the compression spring 18 can play a supporting role for the support column 7 and the adjusting sleeve 8. When the support column 7 and the adjusting sleeve 8 are folded, the compression spring 18 will also be bent at a certain angle. At this time, the compression spring 18 will have the force to push the first folding rod 12 obliquely upward to prevent the support column 7 and the adjusting sleeve 8 from being unfolded after being folded.
[0023] Example 2: Reference Figure 2, Figure 3 A threaded groove 10 is provided on the adjusting sleeve 8, and a fixing bolt 9 is movably installed in the threaded groove 10. A cover plate 19 is provided on the storage box 3, and a buckle 20 is installed on the cover plate 19. The buckle 20 is clamped on the storage box 3. A partition plate 21 is installed in the storage box 3, and the thickness of the partition plate 21 ranges from one centimeter to two centimeters. After adjusting the height of the survey platform 2 and keeping the survey platform 2 horizontal, the fixing bolt 9 can be screwed into the adjusting sleeve 8 and pressed against the outer wall of the pillar 7, so that the position of the survey platform 2 can be locked. The cover plate 19 can be disassembled and assembled by unfastening the buckle 20, so that the storage box 3 can be convenient for storing objects. The space in the storage box 3 can be divided into two parts by the partition plate 21, and the storage box 3 is convenient for the survey platform 2 to classify and store objects.
[0024] Reference Figure 5 In order to facilitate the placement of sundries, a sundries box 22 is installed on the storage box 3, and a soft cushion is installed in the sundries box 22. Some sundries used by the surveyor can be placed in the sundries box 22, and the soft cushion can reduce the impact of vibration on the sundries.
[0025] Reference Figure 2 In order to prevent the survey platform 2 from moving, an anti-skid pad is installed at the bottom of the adjustment sleeve 8. The anti-skid pad is made of rubber material. The rubber material has a large friction resistance and good anti-skid property, which can prevent the survey platform 2 from moving.
[0026] Reference Figure 2 , Figure 4 In order to facilitate folding the support column 7 and the adjusting sleeve 8, a first rotating shaft is installed on the first connecting seat 11, a second rotating shaft is installed on the second connecting seat 14, and a rotating block is installed on the first folding rod 12. One end of the first folding rod 12 is rotatably installed on the first rotating shaft, one end of the second folding rod 15 is rotatably installed on the second rotating shaft, and the other end of the second folding rod 15 is rotatably installed on the rotating block. Through the arrangement of the first rotating shaft, the second rotating shaft and the rotating block, the first folding rod 12 and the second folding rod 15 can rotate freely at both ends, which is convenient for folding the support column 7 and the adjusting sleeve 8.
[0027] Working principle of the utility model: when it is necessary to conduct geological survey, firstly place the magnetic sensor and the fluxgate sensor on the survey ground, and place the survey platform 2 at a suitable survey position. At this time, the height of the survey platform 2 can be adjusted according to the height of the surveyor and the flatness of the terrain. The adjustment sleeve 8 can be slid on the pillar 7. The height of the survey platform 2 can be adjusted by adjusting the depth of the adjustment sleeve 8 sleeved on the pillar 7, so that the height of the survey platform 2 reaches a suitable operating height for the surveyor, which is convenient for the surveyor to operate the electromagnetic survey instrument 1, and the survey platform 2 can be horizontally placed on the uneven survey ground to avoid the electromagnetic survey instrument 1 from moving during the survey. Then, the electromagnetic survey instrument 1 is opened, and the plug 5 is inserted into the sleeve 4, so that geological survey can be carried out. After the survey is completed, the cover plate 19 can be opened, the electromagnetic survey instrument 1 can be placed in the space on one side of the partition plate 21, and the magnetic sensor, fluxgate sensor and other objects can be placed in the space on the other side of the partition plate 21, and the cover plate 19 is covered and snapped on. The buckle 20 is then screwed out of the fixing bolt 9 from the thread groove 10, and then the adjusting sleeve 8 is rotated into the electromagnetic survey instrument 1. The rotation of the adjusting sleeve 8 will drive the pillar 7 to rotate, and the rotation of the pillar 7 will drive the support rod 23 to rotate. The rotation of the support rod 23 will drive the first connecting seat 11 to rotate. The rotation of the first connecting seat 11 will squeeze and drive the first folding rod 12 to rotate. The rotation of the first folding rod 12 will squeeze and drive the second folding rod 15 to rotate, and the first folding rod 12 can be folded on the second folding rod 15, so that the pillar 7 and the adjusting sleeve 8 can be folded and stored, reducing the occupied space of the surveying platform 2 and making it convenient to carry. On the other hand, when the pillar 7 and the adjusting sleeve 8 are unfolded, the compression spring 18 can play a supporting role for the pillar 7 and the adjusting sleeve 8. When the pillar 7 and the adjusting sleeve 8 are folded, the compression spring 18 will also be bent at a certain angle. At this time, the compression spring 18 will have a force to push the first folding rod 12 obliquely upward to prevent the pillar 7 and the adjusting sleeve 8 from unfolding after folding.
[0028] The above description is only a preferred specific implementation manner of the present invention, but the protection scope of the present invention is not limited thereto. Any technician familiar with the technical field can make equivalent replacements or changes within the technical scope disclosed by the present invention according to the technical scheme and the utility model concept of the present invention, which should be covered by the protection scope of the present invention.
Claims
1. A surveying device for designing architectural design schemes, comprising an electromagnetic surveying instrument (1), characterized in that: A survey platform (2) is arranged below the electromagnetic survey instrument (1), a storage box (3) is installed on the survey platform (2), a sleeve (4) is installed on the storage box (3), an insert block (5) is installed at the bottom of the electromagnetic survey instrument (1), the insert block (5) is inserted into the sleeve (4), a plurality of support seats (6) are installed at the bottom of the survey platform (2), pillars (7) are rotatably installed in the plurality of support seats (6), an adjustment sleeve (8) is sleeved on the outer wall of the pillar (7), a support rod (23) is installed on the support rod (23), a first connecting seat (11) is installed on the first connecting seat (11), and a plurality of support seats (6) are rotatably installed in the plurality of support seats (6). A first folding rod (12) is rotatably mounted on the survey platform (2); a bracket (13) is mounted on the bottom of the survey platform (2); a second connecting seat (14) is mounted on the bracket (13); a second folding rod (15) is rotatably mounted on the second connecting seat (14); the second folding rod (15) is rotatably mounted on the first folding rod (12); a first support block (16) is mounted in the first folding rod (12); a second support block (17) is mounted in the second folding rod (15); one end of a compression spring (18) is mounted on the first support block (16); and the other end of the compression spring (18) is mounted on the second support block (17).
2. A surveying device for architectural design scheme design according to claim 1, characterized in that: The adjusting sleeve (8) is provided with a thread groove (10), and a fixing bolt (9) is movably installed in the thread groove (10).
3. The surveying device for architectural design scheme design according to claim 1, characterized in that: The storage box (3) is provided with a cover plate (19), a buckle (20) is installed on the cover plate (19), and the buckle (20) is buckled on the storage box (3).
4. The surveying device for architectural design scheme design according to claim 3 is characterized in that: A partition plate (21) is installed in the storage box (3), and the thickness of the partition plate (21) ranges from one centimeter to two centimeters.
5. The surveying device for architectural design scheme design according to claim 4 is characterized in that: A sundries box (22) is installed on the storage box (3), and a soft cushion is installed in the sundries box (22).
6. The surveying device for architectural design scheme design according to claim 2, characterized in that: An anti-skid pad is installed at the bottom of the adjustment sleeve (8), and the material of the anti-skid pad is rubber material.
7. The surveying device for architectural design scheme design according to claim 1, characterized in that: A first rotating shaft is mounted on the first connecting seat (11), a second rotating shaft is mounted on the second connecting seat (14), a rotating block is mounted on the first folding rod (12), one end of the first folding rod (12) is rotatably mounted on the first rotating shaft, one end of the second folding rod (15) is rotatably mounted on the second rotating shaft, and the other end of the second folding rod (15) is rotatably mounted on the rotating block.