Leakage-proof device for thermal production pipeline
By designing a leak-proof device for thermal production pipelines, using welded connections and sealing ring structures, combined with humidity sensors, the problem of leakage and detection of thermal pipeline interfaces has been solved, and efficient sealing and automatic detection have been achieved.
Patent Information
- Application Number
- CN202420575810.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-25
- Publication Date
- 2024-10-29
- Estimated Expiration
- 2034-03-25
AI Technical Summary
Existing thermal pipelines are prone to leaks at their interfaces, and it is difficult to complete leakage inspections through manual inspections.
A leak-proof device for thermal production pipelines is designed, including the main body of the thermal pipeline, a nozzle, an outer sealing ring, an inner sealing ring and a leak-proof detection mechanism. It is connected through welding and uses fastening bolts and sealing rings to achieve multi-layer sealing, combined with humidity Sensors detect leaks.
It effectively prevents leakage at the thermal pipeline interface and realizes automatic leakage detection at the joint, improving the sealing performance and detection efficiency of the pipeline.
Smart Images

Figure CN221923141U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of pipeline leakage prevention devices, in particular to a thermal production pipeline leakage prevention device. Background Art
[0002] The heat supply network is also called heat supply pipeline, which starts from the boiler room, direct-fired machine room, heating center, etc. and leads from the heat source to the heat supply entrance of the building. Multiple heat supply pipelines form a network.
[0003] The shortcomings of the existing technology: The joints of thermal pipes in the existing technology are usually welded or installed with flanges. After long-term use, the joints of the thermal pipes are very likely to leak. At present, the joints of thermal pipes can be inspected for leaks through manual inspections, but it is difficult to complete leak inspections for longer thermal pipes themselves through manual inspections.
[0004] In view of this, the present technical solution proposes a thermal production pipeline leakage prevention device to better solve the above-mentioned problems. Utility Model Content
[0005] The purpose of the utility model is to provide a thermal production pipeline leakage prevention device in order to solve the above-mentioned problems.
[0006] The technical solution adopted by the utility model is as follows: a thermal production pipeline leakage prevention device, comprising a thermal pipeline main body 1 and a thermal pipeline main body 2, the thermal pipeline main body 1 and the thermal pipeline main body 2 are both provided with a thermal insulation layer on the outside, and the thermal pipeline main body 1 and the thermal pipeline main body 2 are both fixedly installed with a drainage nozzle on the right side, and the drainage nozzle fixedly installed at the right end of the thermal pipeline main body 2 is plugged into the left end of the thermal pipeline main body 1;
[0007] The thermal pipeline body 1 and the thermal pipeline body 2 are clamped with an upper mounting outer ring and a lower mounting outer ring, and the upper mounting outer ring and the lower mounting outer ring are hinged at the rear, and the upper mounting outer ring and the lower mounting outer ring are fixed at the front by fastening bolts;
[0008] The inner edges of the upper mounting outer ring and the lower mounting outer ring are both fixedly connected to outer sealing rings, and the middle parts of the inner walls of the upper mounting outer ring and the lower mounting outer ring are both fixedly connected to inner sealing rings;
[0009] A leak-proof detection mechanism is installed below the lower mounting outer ring, and the leak-proof detection mechanism includes a water receiving ring threadedly connected below the lower mounting outer ring, a mounting seat threadedly connected below the water receiving ring, and a humidity sensor is arranged inside the mounting seat.
[0010] In a preferred embodiment, the connection between the drainage nozzle and the thermal pipe body 1 and the thermal pipe body 2 is welded, and the left opening of the drainage nozzle is larger than the right opening of the drainage nozzle.
[0011] In a preferred embodiment, fixing ears are integrally formed at the front of the upper mounting outer ring and the lower mounting outer ring, and the fastening bolts are installed in the fixing ears by cooperating with nuts.
[0012] In a preferred embodiment, the outer sealing ring is in contact with the thermal pipe body 1 and the thermal pipe body 2, and the inner sealing ring is in contact with the joint installation position of the thermal pipe body 1 and the thermal pipe body 2.
[0013] In a preferred embodiment, an upper external threaded ring is fixedly installed above the water receiving ring, and the upper external threaded ring is threadedly connected to the lower inner part of the lower mounting outer ring.
[0014] In a preferred embodiment, a lower external thread ring is fixedly installed below the water receiving ring, and the lower external thread ring is threadedly connected in the mounting seat.
[0015] In a preferred embodiment, the water receiving ring is an integrated structure with the upper external threaded ring and the lower external threaded ring.
[0016] To sum up, due to the adoption of the above-mentioned technical scheme, the beneficial effects of the utility model are: it is convenient to better perform multi-layer sealing treatment on the joint between the thermal pipeline main body one and the thermal pipeline main body two, prevent leakage at the joint between the thermal pipeline main body one and the thermal pipeline main body two, and can perform leak-proof detection on the joint between the thermal pipeline main body one and the thermal pipeline main body two.
[0017] 1. In the present invention, the drainage nozzle fixedly connected on the right side of the thermal pipeline main body 2 is inserted into the left side of the thermal pipeline main body 1, and the interface completes the docking of the thermal pipeline main body 1 and the thermal pipeline main body 2. Then the thermal pipeline main body 1 and the thermal pipeline main body 2 can be welded or connected together in other ways to complete the docking of the thermal pipeline main body 1 and the thermal pipeline main body 2.
[0018] 2. In the present invention, the upper mounting outer ring and the lower mounting outer ring can be locked and clamped at the joint of the thermal pipeline main body 1 and the thermal pipeline main body 2 by cooperating with the fixing ears and the fastening bolts. At this time, the outer sealing ring is attached to the thermal pipeline main body 1 and the thermal pipeline main body 2, and the inner sealing ring is attached to the joint of the thermal pipeline main body 1 and the thermal pipeline main body 2, so that the joint of the thermal pipeline main body 1 and the thermal pipeline main body 2 can be leak-proof and sealed.
[0019] 2. In the present invention, when leakage occurs at the joint between the thermal pipe body 1 and the thermal pipe body 2, the leaked liquid enters the water receiving ring and the mounting seat under the protection of the outer sealing ring and contacts the humidity sensor. At this time, the humidity sensor transmits a signal to the external control console, and the joint between the thermal pipe body 1 and the thermal pipe body 2 can be maintained. BRIEF DESCRIPTION OF THE DRAWINGS
[0020] Figure 1 It is a structural schematic diagram of the utility model;
[0021] Figure 2 For this utility model Figure 1 A schematic diagram of the enlarged structure of the middle A area;
[0022] Figure 3 It is a schematic diagram of the structure of the leak-proof detection mechanism of the utility model.
[0023] Markings in the figure: 1-thermal pipe body one; 2-thermal pipe body two; 3-insulation layer; 4-drainage nozzle; 5-upper mounting outer ring; 6-lower mounting outer ring; 7-fixing ear; 8-fastening bolt; 9-outer sealing ring; 10-inner sealing ring; 11-leakage detection mechanism; 12-water receiving ring; 13-upper external threaded ring; 14-lower external threaded ring; 15-mounting seat; 16-humidity sensor. DETAILED DESCRIPTION
[0024] In order to make the purpose, technical solution and advantages of the embodiments of the utility model clearer, the technical solution in the embodiments of the utility model will be clearly and completely described below in combination with the embodiments of the utility model. Obviously, the described embodiments are part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments of the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0025] The following will be combined Figure 1-Figure 3 A thermal production pipeline leakage prevention device according to an embodiment of the utility model is described in detail.
[0026] refer to Figure 1-2 As shown, a thermal production pipeline leakage prevention device includes a thermal pipeline main body 1 and a thermal pipeline main body 2, the outside of the thermal pipeline main body 1 and the thermal pipeline main body 2 are both provided with an insulation layer 3, and the right sides of the thermal pipeline main body 1 and the thermal pipeline main body 2 are both fixedly installed with a drainage nozzle 4, and the drainage nozzle 4 fixedly installed at the right end of the thermal pipeline main body 2 is inserted into the left end of the thermal pipeline main body 1, the connection between the drainage nozzle 4 and the thermal pipeline main body 1 and the thermal pipeline main body 2 is welded, and the left opening of the drainage nozzle 4 is larger than the right opening of the drainage nozzle 4.
[0027] By inserting the drainage nozzle 4 fixedly connected on the right side of the thermal pipe main body 2 into the left side of the thermal pipe main body 1, the interface completes the docking of the thermal pipe main body 1 and the thermal pipe main body 2. Then the thermal pipe main body 1 and the thermal pipe main body 2 can be welded or connected together in other ways to complete the docking of the thermal pipe main body 1 and the thermal pipe main body 2.
[0028] refer to Figure 1-2 As shown, an upper mounting outer ring 5 and a lower mounting outer ring 6 are clamped on the thermal pipeline main body 1 and the thermal pipeline main body 2, and the upper mounting outer ring 5 and the lower mounting outer ring 6 are hinged at the rear, and the upper mounting outer ring 5 and the lower mounting outer ring 6 are fixed in front by fastening bolts 8, and the front of the upper mounting outer ring 5 and the lower mounting outer ring 6 are integrally formed with fixing ears 7, and the fastening bolts 8 are installed in the fixing ears 7 by cooperating with nuts, and the inner edges of the upper mounting outer ring 5 and the lower mounting outer ring 6 are fixedly connected with outer sealing rings 9, and the outer sealing rings 9 are fitted with the thermal pipeline main body 1 and the thermal pipeline main body 2, and the middle parts of the inner walls of the upper mounting outer ring 5 and the lower mounting outer ring 6 are fixedly connected with inner sealing rings 10, and the inner sealing ring 10 is fitted with the thermal pipeline main body 1 and the thermal pipeline main body 2 at the joint installation position.
[0029] By cooperating with the fixing ear 7 and the fastening bolt 8, the upper mounting outer ring 5 and the lower mounting outer ring 6 can be locked and clamped at the joint of the thermal pipeline main body 1 and the thermal pipeline main body 2. At this time, the outer sealing ring 9 is attached to the thermal pipeline main body 1 and the thermal pipeline main body 2, and the inner sealing ring 10 is attached to the joint of the thermal pipeline main body 1 and the thermal pipeline main body 2, so that the joint of the thermal pipeline main body 1 and the thermal pipeline main body 2 can be leak-proof and sealed.
[0030] refer to Figure 1-3 As shown, a leak-proof detection mechanism 11 is installed at the lower part of the lower mounting outer ring 6, and the leak-proof detection mechanism 11 includes a water receiving ring 12 threadedly connected to the lower part of the lower mounting outer ring 6, an upper external threaded ring 13 is fixedly installed above the water receiving ring 12, and the upper external threaded ring 13 is threadedly connected to the lower part of the lower mounting outer ring 6, the upper external threaded ring 13 is located between the outer sealing ring 9 and the inner sealing ring 10, a mounting seat 15 is threadedly connected below the water receiving ring 12, a lower external threaded ring 14 is fixedly installed below the water receiving ring 12, and the lower external threaded ring 14 is threadedly connected to the mounting seat 15, the water receiving ring 12, the upper external threaded ring 13 and the lower external threaded ring 14 are an integrated structure, and a humidity sensor 16 is arranged inside the mounting seat 15.
[0031] When leakage occurs at the joint between the thermal pipe body 1 and the thermal pipe body 2, the leaked liquid enters the water receiving ring 12 and the mounting seat 15 under the protection of the outer sealing ring 9 and contacts the humidity sensor 16. At this time, the humidity sensor 16 transmits a signal to the external control console, and the joint between the thermal pipe body 1 and the thermal pipe body 2 can be maintained.
[0032] The advantages of this application are: it is convenient to better perform multi-layer sealing treatment on the joint between the thermal pipeline main body 1 and the thermal pipeline main body 2, prevent leakage at the joint between the thermal pipeline main body 1 and the thermal pipeline main body 2, and can perform leak-proof detection on the joint between the thermal pipeline main body 1 and the thermal pipeline main body 2.
[0033] Working principle: When docking and installing the thermal pipeline main body 1 and the thermal pipeline main body 2 2, first insert the drainage nozzle 4 fixedly connected on the right side of the thermal pipeline main body 2 2 into the left side of the thermal pipeline main body 1, and the interface completes the docking of the thermal pipeline main body 1 and the thermal pipeline main body 2 2. Then the thermal pipeline main body 1 and the thermal pipeline main body 2 2 can be welded or connected together in other ways to complete the docking of the thermal pipeline main body 1 and the thermal pipeline main body 2 2.
[0034] By cooperating with the fixing ear 7 and the fastening bolt 8, the upper mounting outer ring 5 and the lower mounting outer ring 6 can be locked and clamped at the joint of the thermal pipeline main body 1 and the thermal pipeline main body 2. At this time, the outer sealing ring 9 is attached to the thermal pipeline main body 1 and the thermal pipeline main body 2, and the inner sealing ring 10 is attached to the joint of the thermal pipeline main body 1 and the thermal pipeline main body 2, so that the joint of the thermal pipeline main body 1 and the thermal pipeline main body 2 can be leak-proof and sealed.
[0035] When leakage occurs at the joint between the thermal pipeline main body 1 and the thermal pipeline main body 2, the leaked liquid enters the water receiving ring 12 and the mounting seat 15 under the protection of the outer sealing ring 9 and contacts the humidity sensor 16. At this time, the humidity sensor 16 transmits a signal to the external control console, and the joint between the thermal pipeline main body 1 and the thermal pipeline main body 2 can be maintained. When transporting gas, the humidity sensor 16 can be replaced with a gas sensor.
[0036] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.
Claims
1. A thermal production pipeline leakage prevention device, comprising a thermal pipeline body 1 (1) and a thermal pipeline body 2 (2), characterized in that: The exterior of the thermal pipeline main body 1 (1) and the thermal pipeline main body 2 (2) are both provided with a heat insulation layer (3), and the right sides of the thermal pipeline main body 1 (1) and the thermal pipeline main body 2 (2) are both fixedly installed with a drainage nozzle (4), and the drainage nozzle (4) fixedly installed at the right end of the thermal pipeline main body 2 (2) is plugged into the interior of the left end of the thermal pipeline main body 1 (1); The thermal pipeline main body 1 (1) and the thermal pipeline main body 2 (2) are clamped with an upper mounting outer ring (5) and a lower mounting outer ring (6), and the upper mounting outer ring (5) and the lower mounting outer ring (6) are hinged at the rear, and the upper mounting outer ring (5) and the lower mounting outer ring (6) are fixed at the front by fastening bolts (8); An outer sealing ring (9) is fixedly connected to the inner edges of the upper mounting outer ring (5) and the lower mounting outer ring (6), and an inner sealing ring (10) is fixedly connected to the middle of the inner wall of the upper mounting outer ring (5) and the lower mounting outer ring (6); A leak-proof detection mechanism (11) is installed below the lower mounting outer ring (6), and the leak-proof detection mechanism (11) comprises a water receiving ring (12) threadedly connected below the lower mounting outer ring (6), a mounting seat (15) threadedly connected below the water receiving ring (12), and a humidity sensor (16) is arranged inside the mounting seat (15).
2. A thermal production pipeline leakage prevention device according to claim 1, characterized in that: The connection between the drainage nozzle (4) and the first thermal pipe body (1) and the second thermal pipe body (2) is welded, and the left opening of the drainage nozzle (4) is larger than the right opening of the drainage nozzle (4).
3. A thermal production pipeline leakage prevention device according to claim 1, characterized in that: The upper mounting outer ring (5) and the lower mounting outer ring (6) are both integrally formed with fixing ears (7) at the front, and the fastening bolts (8) are mounted in the fixing ears (7) by means of nuts.
4. A thermal production pipeline leakage prevention device according to claim 1, characterized in that: The outer sealing ring (9) is fitted with the first thermal pipeline body (1) and the second thermal pipeline body (2), and the inner sealing ring (10) is fitted with the joint installation position of the first thermal pipeline body (1) and the second thermal pipeline body (2).
5. A thermal production pipeline leakage prevention device as claimed in claim 1, characterized in that: An upper external threaded ring (13) is fixedly mounted above the water receiving ring (12), and the upper external threaded ring (13) is threadedly connected to the lower interior of the lower mounting outer ring (6).
6. A thermal production pipeline leakage prevention device as claimed in claim 5, characterized in that: A lower external thread ring (14) is fixedly mounted below the water receiving ring (12), and the lower external thread ring (14) is threadedly connected to the mounting seat (15).
7. A thermal production pipeline leakage prevention device as claimed in claim 5, characterized in that: The water receiving ring (12), the upper external thread ring (13) and the lower external thread ring (14) are an integrated structure.