Suspension rod cable beam end back pressure tensioning construction structure

By designing the backpressure tensioning construction structure at the end of the bobbin cable, the single-end tensioning of the bobbin cable is used to solve the problems of safety risks and low efficiency in traditional construction, and the rapid, safe and efficient tensioning of the bobbin cable is achieved. , shortened the construction period and improved construction efficiency.

CN221956529UActive Publication Date: 2024-11-05CHINA HYDROPOWER ELEVENTH ENG BUREAU (ZHENGZHOU) CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202323470127.3
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-12-20
Publication Date
2024-11-05
Estimated Expiration
2033-12-20

AI Technical Summary

Technical Problem

Traditional boom cable tensioning construction has safety risks, large welding workload, bulky equipment, and long installation time, especially in steel pipe arch bridge deck tensioning construction, construction efficiency and safety are low.

Method used

A construction structure for the backpressure tensioning of the end of the hanging rod rope beam is designed, including the hanging rod rope pin, fixing frame, reaction frame, tensioning rod, jack and hydraulic system. The single-end tensioning of the hanging rod rope is avoided. The temporary action points of bridge deck welding simplify the equipment structure and improve construction efficiency and safety.

Benefits of technology

It realizes fast, safe and efficient tensioning of the boom cable, saves welding time and labor, shortens construction period, improves construction efficiency, and reduces the volume and installation complexity of the equipment.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221956529U_ABST
    Figure CN221956529U_ABST
Patent Text Reader

Abstract

The utility model provides a suspender cable beam end back pressure tensioning construction structure which comprises a first fixing frame and a second fixing frame which are of two-piece structures and are assembled and fixed through connecting bolts, the hinged end is installed on a suspender cable pin shaft through a hinged hole, and the first fixing frame and the second fixing frame are connected through a connecting bolt. The first fixing frame and the second fixing frame of the fixing end are each provided with a first tensioning rod penetrating hole. The counter-force frame comprises a first counter-force frame and a second counter-force frame which are of two-petal structures, the first counter-force frame and the second counter-force frame are assembled and fixed through splicing bolts, and the adjacent sides of the first counter-force frame and the second counter-force frame are each provided with a plurality of half holes so that a suspender cable penetrating hole and two second tension rod penetrating holes can be formed after splicing and assembling; jacks are respectively mounted at two second tension rod through holes in the upper end of the counter-force frame; the two tensioning rods sequentially penetrate through the first tensioning rod penetrating hole and the second tensioning rod penetrating hole in parallel. The suspender cable beam end back pressure tensioning construction structure has the advantages of being convenient to construct, safe and efficient.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the field of suspension bridge or steel tube arch bridge engineering, in particular to a hanger cable beam end back pressure tensioning construction structure. Background Art

[0002] Urban bridges adopt the structure of "arch + suspender cable" to enhance the landscape function of the bridge. The tensioning of steel tube arch suspender cable is the key technology for the construction of this type of bridge. The traditional suspender cable tensioning methods include arch tensioning, underbridge tensioning and beam end tensioning. The construction machinery, working environment and safety priorities under various tensioning methods vary greatly. Arch tensioning and underbridge tensioning are mostly used in China, while steel tube arch bridge deck tensioning construction is relatively rare.

[0003] The characteristics of existing technologies include: arch end tensioning poses a greater safety risk due to being at high altitude; beam end tensioning has a small safety risk and is the most novel, but traditional beam end tensioning generally sets a temporary fixed point on the bridge deck as a reaction force point, which requires a large amount of welding work and will also cause damage to the steel bridge deck.

[0004] Moreover, the current boom tensioning device is bulky and needs to be transferred and installed with the help of lifting equipment. The installation requires a large number of people and takes a long time, which results in serious waste of time and economy. Therefore, it is necessary to provide a boom tensioning structure to tension the boom accurately and efficiently. Utility Model Content

[0005] The utility model aims to address the deficiencies of the prior art and thus provide a boom cable beam end back pressure tensioning construction structure which is convenient in construction, safe and efficient.

[0006] In order to achieve the above-mentioned purpose, the technical solution adopted by the utility model is: a suspension rod cable beam end counter-pressure tensioning construction structure, including a suspension rod cable pin shaft, a fixing frame, a reaction frame, a tensioning rod, a jack and a hydraulic system;

[0007] The fixing frame includes a first fixing frame and a second fixing frame of a two-petal structure, the first fixing frame and the second fixing frame are assembled and fixed by connecting bolts, the fixing frame includes a hinged end and a fixed end, the hinged end is installed on the pin shaft of the boom cable through a hinge hole, the first fixing frame and the second fixing frame of the fixed end are both provided with a first tension rod through hole, the first tension rod through hole is perpendicular to the pin shaft of the boom cable, and a through hole for passing the boom cable is provided at the center of the fixing frame;

[0008] The reaction frame comprises a first reaction frame and a second reaction frame of a two-petal structure, the first reaction frame and the second reaction frame are assembled and fixed by splicing bolts, and a plurality of half holes are respectively arranged on adjacent sides of the first reaction frame and the second reaction frame so that after splicing and assembly, a suspension cable through hole and two second tension rod through holes are formed, and the second tension rod through hole, the first tension rod through hole and the suspension cable through hole are parallel;

[0009] The jacks are respectively installed at the through holes of the two second pull rods at the upper end of the reaction frame, and the fluid circuit of the jacks is connected to the hydraulic system;

[0010] The tension rods are configured with two tension rods, which pass through the first tension rod through-hole and the second tension rod through-hole in parallel in sequence. The lower end of the tension rod is locked to the lower end of the first tension rod through-hole by a first locking nut, and the upper end of the tension rod is locked in the jack by a second locking nut. The two tension rods constitute a guide structure for the jack and the reaction frame to travel.

[0011] Preferably, the first fixing frame and the second fixing frame are hinged to the suspension rod cable pin shaft at the hinge holes at the hinge ends through M20 high-strength bolts.

[0012] Preferably, the first fixing frame and the second fixing frame are fastened together at the fixing ends by at least two transverse high-strength bolts and a connecting sleeve.

[0013] Preferably, the first reaction frame and the second reaction frame are locked together in the thickness direction by at least four symmetrical connecting bolts.

[0014] Preferably, a suspension rod cable through-hole pad is installed in the through-hole of the suspension rod, and a jack through-hole pad is installed in the through-hole of the second tension rod.

[0015] Preferably, both the upper and lower halves of the tension rod are provided with steel threads with a diameter ≥ 7 cm.

[0016] Preferably, a reinforcing rib is provided at the fixed end of the fixing frame corresponding to the through hole of the first pull rod.

[0017] Preferably, a reinforcing rib is provided on the outer side of the reaction frame.

[0018] The utility model has substantial characteristics and progress compared with the prior art. Specifically, the utility model has the following advantages:

[0019] 1. The entire tensioning structure uses the single-end tensioning hanger cable pin as a temporary action point, avoiding welding of temporary action points on the bridge surface, saving time, labor and materials required for temporary welding of temporary action points.

[0020] 2. The entire tensioning structure is simple in structure, and the tensioning adjustment of each hanger cable can be achieved by quickly replacing the installation position. The construction speed is fast and the construction period is guaranteed.

[0021] 3. The entire tensioning structure is simple in structure, and the adjustment device is adjusted directly based on the installation position of the boom cable, avoiding the transfer and installation process of the boom cable after the adjustment, thereby improving construction efficiency.

[0022] 4. The design of the reaction frame and the fixed frame is extremely simplified, and the equipment volume is more compact than the traditional solution. BRIEF DESCRIPTION OF THE DRAWINGS

[0023] Figure 1 It is one of the structural schematic diagrams of a suspension rod cable beam end back pressure tensioning construction structure in the utility model.

[0024] Figure 2 This is the second structural schematic diagram of a suspension rod cable beam end back pressure tensioning construction structure in the utility model.

[0025] In the figure: 1. boom cable pin; 2. fixed frame; 3. reaction frame; 4. tension rod; 5. jack; 6. hydraulic system; 7. boom cable; 8. adjustment end;

[0026] 11. First fixing bracket; 12. Second fixing bracket; 13. Articulated end; 14. Fixed end; 15. M20 high-strength bolt; 16. High-strength bolt;

[0027] 21. First reaction frame; 22. Second reaction frame; 23. Connecting bolts; 24. Through hole for suspension rod; 25. Through hole for second tie rod; 26. Through hole pad for jack; 27. Through hole pad for suspension rod; 41. First locking nut. DETAILED DESCRIPTION

[0028] The technical solution of the utility model is further described in detail below through specific implementation methods.

[0029] like Figure 1 As shown, a suspension rod cable beam end counter-pressure tensioning construction structure includes a suspension rod cable pin shaft 1, a fixing frame 2, a reaction frame 3, a tensioning rod 4, a jack 5 and a hydraulic system 6.

[0030] The fixing frame 2 includes a first fixing frame 21 and a second fixing frame 22 of a two-petal structure, and the first fixing frame 21 and the second fixing frame 22 are assembled and fixed by connecting bolts. The fixing frame includes a hinged end 13 and a fixed end 14. Specifically, the first fixing frame 21 and the second fixing frame 22 are hinged to the suspension rod cable pin shaft 1 at the hinge hole of the hinged end 13 by an M20 high-strength bolt 15; the first fixing frame 21 and the second fixing frame 22 are fastened together at the fixed end 14 by at least two transverse high-strength bolts 16 and a connecting sleeve, and a reinforcing rib is provided at the fixed end of the fixing frame 24 for the through-hole of the first tensioning rod. Pay attention to making the upper and lower parts of the fixing frame evenly stressed to prevent the upper part from being too tight and causing the lower part to detach during the tensioning process.

[0031] The hinged end 13 is installed on the boom cable pin shaft 1 through a hinge hole, and the first fixing frame 21 and the second fixing frame 22 of the fixed end 14 are both provided with a first tension rod through hole 16, and the first tension rod through hole 16 is perpendicular to the boom cable pin shaft 1, and a through hole for passing the boom cable 7 is provided at the center of the fixing frame 24.

[0032] The reaction frame 3 includes a first reaction frame 31 and a second reaction frame 32 of a two-petal structure, the first reaction frame 31 and the second reaction frame 32 are locked together in the thickness direction by at least four symmetrical connecting bolts 23, a plurality of half holes are respectively arranged on adjacent sides of the first reaction frame 31 and the second reaction frame 32 so as to form a suspension rod cable through hole 24 and two second tension rod through holes 25 after splicing and assembly, a reinforcing rib is arranged on the outer side of the reaction frame, the second tension rod through hole 25, the first tension rod through hole 16 and the suspension rod cable through hole 24 are parallel, a suspension rod cable through hole pad 27 is installed in the suspension rod cable through hole 24, and a jack through hole pad 26 is installed in the second tension rod through hole 25.

[0033] Specifically, the reaction frame 3 is hoisted and assembled with two 5-ton fall chains, and then respectively installed at the rear ends of the anchor cups at the ends of the beams, connected with a splicing plate, and the connecting bolts are tightened. The through-hole pads at the jack and the through-hole pads of the boom cable are fastened in place with high-strength bolts (the pads are prefabricated in advance according to the size of the boom cable), and the bolts of various parts of the reaction frame are fastened in place.

[0034] There is no necessary order for the installation of the reaction frame and the fixed frame. For the convenience of construction organization, the reaction frame can be installed first and then the fixed frame, or the fixed frame can be installed first and then the reaction frame. Regardless of the installation order, it should be ensured that no damage is caused to the components of the previous step.

[0035] The jacks 5 are respectively installed at the two second tension rod through holes 25 at the upper end of the reaction frame 3 , and the fluid path of the jacks 5 is connected to the hydraulic system 6 .

[0036] The tension rods 4 are configured with two, and the upper and lower halves of the tension rods are both provided with steel threads with a diameter ≥7 cm. The two tension rods 4 are parallelly passed through the first tension rod through hole 16 and the second tension rod through hole 25 in sequence. The lower end of the tension rod 4 is locked to the lower end of the first tension rod through hole 16 by a first locking nut 41, and the upper end of the tension rod 4 is locked in the jack 5 by a second locking nut (not shown in the figure). The two tension rods 4 constitute a guiding structure for the jack 5 and the reaction frame 3 to move.

[0037] When installing the tension rod, unscrew the nut at one end, pass the bolt through the fixing frame, and then screw on the high-strength connecting nut for temporary fixation. After the reaction frame and jack are installed, pass the remaining tension rod through the reaction frame and the center of the jack, and connect and tighten it with the lower tension rod through the high-strength connecting nut. The main function of the tension rod is to guide the movement of the jack when starting the jack, and it is also connected to the reaction frame and the fixing frame. It should be noted that before installing the tension rod, the appearance quality of the tension rod and the integrity of the thread of the screw rod should be checked. It is strictly forbidden to use the tension rod if there are cracks or thread damage.

[0038] The hydraulic system 6 needs to be debugged before use. The hydraulic system includes hydraulic pipes and oil pumps, etc. After the fixed frame, tension rods, and reaction frames are installed and checked, the hydraulic system is connected. Before formal tensioning, a trial tensioning should be carried out first, and the trial tensioning should be carried out according to the prescribed tensioning force (0.3δcon). If it passes, tensioning can be carried out according to the established construction plan. Note that the jack and the hydraulic system must be installed and used in conjunction, and they must be calibrated as required before being put into use. If the hydraulic pipe or oil gauge is found to be damaged, it is strictly prohibited to use it.

[0039] Working principle description:

[0040] First, based on the original installation structure of the boom cable, that is, the boom cable pin shaft 1, the entire device is installed in place. At this time, the boom cable 7 passes through the fixed frame 2 and the reaction frame 3 in sequence, and the adjustment end 8 of the boom cable 7 is located between the fixed frame 2 and the reaction frame 3, and is pulled by the reaction frame 3.

[0041] Among them, the adjusting end is a structure provided by the boom cable 7, which includes an adjusting end connecting anchor, an adjusting rod and an adjusting nut that cooperate with the reaction frame 3. The lower end of the adjusting nut cooperates with the root thread of the boom cable 7, and the upper end of the adjusting nut cooperates with the adjusting rod thread. The upper end of the adjusting rod is axially locked with the adjusting end connecting anchor and circumferentially movable. The connecting end anchor is fixed to the main body of the boom cable 7 and cannot pass through the through hole of the boom cable due to the reaction frame. When the reaction frame moves downward, the adjusting end connecting anchor moves downward synchronously, so that the entire adjusting end is loosened, and then the adjusting nut is screwed to shorten the distance between the adjusting rod and the boom cable 7, so as to adjust the tightness of the entire boom cable.

[0042] After the tensioning test confirms that the tensioning system and equipment are correct, the first order tensioning is carried out according to the principles of synchronization, symmetry and grading. During the tensioning process, the adjusting nut of the suspender cable is adjusted in time to keep the suspender cable in a tensioned state. The initial tensioning control stress is achieved by tensioning-tightening the nut. If the hydraulic system is found to be defective or the tensioning operation is abnormal during the operation, the operation should be stopped immediately, and the subsequent operation can be carried out after the abnormality is checked and eliminated.

[0043] The tensioning of the boom cable is carried out in stages. After the first stage of tensioning is completed, the load is applied according to the design requirements. The cable force of the boom cable is monitored during the load loading process. After the loading is completed, the cable force is adjusted through the second stage of tensioning according to the monitoring results. The process of cable force adjustment is to adjust the adjustment end 8 of the boom cable 7. After the cable force adjustment is completed, the auxiliary structure is constructed according to the design and the cable force is monitored. After the construction of the auxiliary structure is completed, the cable force is adjusted through the third stage of tensioning according to the monitoring results. After this stage is completed, the tensioning stage is over.

[0044] Cable force monitoring runs through the entire tensioning process, and cable force monitoring should still be carried out according to design requirements after the tensioning stage. If any abnormality is found during the monitoring process, timely analysis and adjustment should be carried out.

[0045] The structure was tested in the reconstruction project of Yuyang Bridge in Nanyang City. The main bridge of Yuyang Bridge is a mid-span seven-span five-arch unequal-span continuous arch-beam cooperative system. The main bridge is 578m long. The main beam is a steel structure box-type double main beam, and the arch rib is an irregular polygonal steel box section. The cross bridge of the arch rib of the main bridge is inclined outward by 10°, and a cable is set every 7m. There are 86 cables in the whole bridge, and the main beam and arch rib are jointly stressed through the hangers.

[0046] The non-welded hanger cable counter-pressure tensioning construction method was successfully applied in the reconstruction project of Yuyang Bridge in Nanyang City. The installation and tensioning of the bridge hanger cables took a total of 20 days, which saved 7 days of construction time compared with the traditional process.

[0047] Finally, it should be noted that: The above describes in detail the preferred implementation of this patent, but this patent is not limited to the above implementation. Various changes can be made within the knowledge scope of ordinary technicians in this field without departing from the purpose of this patent.

Claims

1. A suspension rod cable beam end back pressure tensioning construction structure, characterized in that: It includes a boom cable pin shaft, a fixing frame, a reaction frame, a tension rod, a jack and a hydraulic system; The fixing frame includes a first fixing frame and a second fixing frame of a two-petal structure, the first fixing frame and the second fixing frame are assembled and fixed by connecting bolts, the fixing frame includes a hinged end and a fixed end, the hinged end is installed on the pin shaft of the boom cable through a hinge hole, the first fixing frame and the second fixing frame of the fixed end are both provided with a first tension rod through hole, the first tension rod through hole is perpendicular to the pin shaft of the boom cable, and a through hole for passing the boom cable is provided at the center of the fixing frame; The reaction frame comprises a first reaction frame and a second reaction frame of a two-petal structure, the first reaction frame and the second reaction frame are assembled and fixed by splicing bolts, and a plurality of half holes are respectively arranged on adjacent sides of the first reaction frame and the second reaction frame so that after splicing and assembly, a suspension cable through hole and two second tension rod through holes are formed, and the second tension rod through hole, the first tension rod through hole and the suspension cable through hole are parallel; The jacks are respectively installed at the through holes of the two second pull rods at the upper end of the reaction frame, and the fluid circuit of the jacks is connected to the hydraulic system; The tension rods are configured with two tension rods, which pass through the first tension rod through-hole and the second tension rod through-hole in parallel in sequence. The lower end of the tension rod is locked to the lower end of the first tension rod through-hole by a first locking nut, and the upper end of the tension rod is locked in the jack by a second locking nut. The two tension rods constitute a guide structure for the jack and the reaction frame to travel.

2. The back-pressure tensioning construction structure of the suspender cable beam end according to claim 1 is characterized in that: The first fixing frame and the second fixing frame are hinged to the suspension rod cable pin shaft at the hinge holes at the hinge ends through M20 high-strength bolts.

3. The back-pressure tensioning construction structure of the suspender cable beam end according to claim 2 is characterized in that: The first fixing frame and the second fixing frame are fastened together at the fixing ends by at least two transverse high-strength bolts and a connecting sleeve.

4. The back-pressure tensioning construction structure of the suspender cable beam end according to claim 3 is characterized in that: The first reaction frame and the second reaction frame are locked together in the thickness direction by at least four symmetrical connecting bolts.

5. The back-pressure tensioning construction structure of the suspender cable beam end according to claim 4 is characterized in that: A suspension rod cable through-hole pad is installed in the through-hole of the suspension rod cable, and a jack through-hole pad is installed in the through-hole of the second tension rod.

6. The back-pressure tensioning construction structure of the suspender cable beam end according to claim 5 is characterized in that: The upper and lower halves of the tension rod are both provided with steel threads with a diameter of ≥7 cm.

7. The back-pressure tensioning construction structure of the suspender cable beam end according to claim 6 is characterized in that: A reinforcing rib is arranged at the fixed end of the fixing frame corresponding to the through hole of the first pull rod.

8. The back-pressure tensioning construction structure of the suspender cable beam end according to claim 7 is characterized in that: A reinforcing rib is arranged on the outer side of the reaction frame.