Guardrail transition connecting piece at tunnel exit
By designing the guardrail transition connector at the tunnel exit, using existing guardrail components to transform them, it provides significant identification and protection, which solves the problem of insufficient protection of the early tunnel exit guardrail, reduces the cost of replacing the guardrail components, and improves the safety of the tunnel exit .
Patent Information
- Application Number
- CN202420575339.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-22
- Publication Date
- 2024-11-08
- Estimated Expiration
- 2034-03-22
AI Technical Summary
The corrugated beam guardrail at the exit of the highway tunnel built in early days failed to effectively protect the space extending outside the tunnel at the width of the maintenance road, resulting in sight deviations and risk of car accidents when the vehicle exits from the tunnel, and the cost of replacing the guardrail components is high.
Design a transition connection of guardrail at the tunnel exit, including the inner columns of the tunnel, the outer columns of the tunnel and corrugated beams and slabs. Use existing guardrail components to fix the L-shaped steel plate and column poles through expansion bolts, and set the corrugated beams and existing guardrails. Connect, provide significant identification and extend protection.
It has achieved significant identification and protection at the tunnel exit, reduced the upgrade and transformation costs of the expressway protection system, and effectively prevented the risk of car accidents.
Smart Images

Figure CN221972193U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of highway guardrails, in particular to a guardrail transition connector arranged at a tunnel exit. Background Art
[0002] Guizhou Province is located in the Yunnan-Guizhou Plateau, which has many mountains. Therefore, a large number of highway tunnels have been built during the more than 20 years of highway construction. Figure 1 This is a schematic diagram of some construction limits of highway tunnels; Figure 2 A schematic diagram of the location of a corrugated beam guardrail at an existing tunnel exit; Figure 2 The inner wall boundary of the tunnel is indicated by a dotted line, see Figure 1 and Figure 2 As shown, according to the current "Highway Engineering Technical Standards", the height of the inspection road should not exceed 25cm, but the height of the inspection roads in the early tunnels is often 40 to 60cm. In the one-way tunnels of the expressway, the width of the inspection road on the right is 25cm larger than that on the left, and the corresponding values for different design speeds on the left are 75 and 50cm. In the early tunnels of the expressways in Guizhou Province, the most common widths are 50cm on the left and 75cm on the right. At the exits of the early tunnels, the corrugated beam guardrails are usually installed as follows. Figure 2 As shown, it directly extends to the tunnel wall at the tunnel exit, and is either directly connected to the end or connected to the concrete guardrail, without considering the protection of the space extending outside the tunnel at the width of the inspection road.
[0003] Some sections of Guizhou Province's expressways have many tunnels and long downhill slopes, such as the Xifeng section of the Guizhou-Zunyi Expressway. That is to say, the tunnel and the road outside the tunnel are both downhill, and there will be a line of sight deviation when vehicles exit the tunnel. If a prominent sign can be set up at the tunnel exit and the space extending outside the tunnel at the width of the maintenance road can be protected, the risk of traffic accidents at the tunnel exit can be better prevented.
[0004] As the main body of highway maintenance in Guizhou Province, the applicant has generated a large number of replaced two-wave beam guardrail components with the implementation of the Guizhou Province highway upgrading and renovation project of using three-wave beam guardrails to replace the original two-wave beam guardrails. If these materials can be used to protect the tunnel exits of early highways, the upgrading and renovation costs of the highway protection system can be greatly reduced. Utility Model Content
[0005] The technical problem to be solved by the utility model is to provide a guardrail transition connector at a tunnel exit to reduce or avoid the above-mentioned problems.
[0006] In order to solve the above technical problems, the utility model proposes a guardrail transition connector at a tunnel exit, which includes an inner tunnel column arranged on an inspection road at the tunnel exit, an outer tunnel column arranged outside the tunnel, a corrugated beam plate for connecting an existing guardrail, and an end plate for covering the inner tunnel column.
[0007] Preferably, the tunnel interior column comprises an L-shaped steel plate which can be fixed on the inspection road at the tunnel exit by expansion bolts and two first column rods welded side by side on the L-shaped steel plate.
[0008] Preferably, the L-shaped steel plate is made of 2mm thick steel plate, with a length L1 of 300mm, a height H1 of 50mm, and a width W1 of 160mm.
[0009] Preferably, the tunnel outer column comprises a second column rod, and a mounting base plate is welded to the bottom of the second column rod.
[0010] Preferably, the mounting base plate is made of a rectangular steel plate with a thickness of 2 mm.
[0011] Preferably, the tunnel outer column is arranged close to the inspection road, at a position on the road surface side of the tunnel outer drainage ditch, and does not exceed the position of the inner extension line of the inspection road in the direction toward the road surface. The mounting base plate is fixed to the ground by bolts.
[0012] Preferably, the length of the corrugated beam plate is not less than three meters, and after assembly, the angle α between the corrugated beam plate and the existing guardrail is between 20 degrees and 40 degrees.
[0013] The utility model provides a guardrail transition connector at a tunnel exit, which can be manufactured by simply modifying existing components, has low cost, can provide a significant mark at the tunnel exit, and can protect the space extending outside the tunnel at the width of the inspection road. BRIEF DESCRIPTION OF THE DRAWINGS
[0014] The following drawings are only intended to illustrate and explain the present invention, and do not limit the scope of the present invention.
[0015] Figure 1 This is a schematic diagram of some construction limits of highway tunnels;
[0016] Figure 2 This is a schematic diagram of the location of the corrugated beam guardrail at an existing tunnel exit;
[0017] Figure 3 It is a schematic diagram of the structural principle of a guardrail transition connector at a tunnel exit according to a specific embodiment of the utility model;
[0018] Figure 4 for Figure 3 A schematic diagram of the structural principle of a part of the structure of the guardrail transition connector at the tunnel exit from another perspective;
[0019] Figure 5 for Figure 4 Schematic diagram of the partial three-dimensional decomposition structure principle of the tunnel inner and outer columns. DETAILED DESCRIPTION
[0020] In order to have a clearer understanding of the technical features, purpose and effect of the utility model, the specific implementation of the utility model is now described with reference to the accompanying drawings. Among them, the same components are marked with the same numbers.
[0021] Figure 3 It is a schematic diagram of the structural principle of a guardrail transition connector at a tunnel exit according to a specific embodiment of the utility model; Figure 4 for Figure 3 A schematic diagram of the structural principle of a part of the structure of the guardrail transition connector at the tunnel exit from another perspective; Figure 5 for Figure 4 Schematic diagram of the partial three-dimensional decomposition structure principle of the tunnel inner column and tunnel outer column. Figures 3 to 5 As shown, the utility model provides a guardrail transition connector at a tunnel exit, which includes an inner tunnel column 1 arranged on an inspection road at the tunnel exit, an outer tunnel column 2 arranged outside the tunnel, a corrugated beam plate 3 for connecting an existing guardrail, and an end plate 4 for covering the inner tunnel column 1.
[0022] The column 1 in the tunnel includes an L-shaped steel plate 11 that can be fixed on the inspection road at the tunnel exit by expansion bolts and two first column rods 12 welded side by side on the L-shaped steel plate 11. The L-shaped steel plate 11 can be made of a 2mm thick steel plate, the length L1 can be 300mm, the height H1 can be 50mm, and the width W1 can be 160mm. It can be fixed on the inspection road at the tunnel exit by expansion bolts. The first column rod 12 can be made of a column with a diameter of 114mm or 140mm in a two-wave beam assembly replaced from other highways, and the length can be about 1 meter. The two first column rods 12 can be fixed together by spot welding first, and then fixed to the L-shaped steel plate 11 by welding, and the arrangement direction is consistent with the length direction of the L-shaped steel plate 11.
[0023] The tunnel outer column 2 arranged outside the tunnel is mainly used to provide a support position for the corrugated beam plate 3. The tunnel outer column 2 includes a second column rod 21, and a mounting base plate 22 is welded at the bottom of the second column rod 21. The second column rod 21 can also be made of a column with a diameter of 114mm or 140mm in a second wave beam assembly replaced from other highways. The mounting base plate 22 can be made of a rectangular steel plate with a thickness of 2mm. The tunnel outer column 2 is arranged close to the inspection road, usually at the position of the drainage ditch outside the tunnel close to the road surface, but in the direction toward the road surface, it does not exceed the position of the inner extension line of the inspection road. The mounting base plate 22 can be fixed to the ground by bolts.
[0024] The corrugated beam plate 3 and the end plate 4 can also be made of two corrugated beam corrugated plates and ends (for example, R160 type ends) in two-wave beam assemblies replaced from other expressways. The length of the corrugated beam plate 3 is not less than three meters. The side close to the existing guardrail can be bent and directly fixed to the existing guardrail by bolts, and the side close to the tunnel is installed on the second column rod 21. The end plate 4 is also installed on the second column rod 21, and after bending, the arc-shaped head of the end plate 4 covers the first column rod 12.
[0025] As described in the background technology section, the height of the early tunnel inspection roads is often 40 to 60 cm. When installing the corrugated beam plate 3, the height of the inspection road can be set with reference to it. That is to say, after the corrugated beam plate 3 is installed in place, its bottom edge can be only slightly higher than the top surface of the inspection road. Therefore, after the column 1 in the tunnel is installed and the arc-shaped head of the end plate 4 covers the first column rod 12, the first column rod 12 can still have a large part (about 50 cm) exposed in the vertical direction of the end plate 4. Therefore, reflective markings can also be pasted or sprayed on the exposed parts of the end plate 4 and the first column rod 12, so that a large area of prominent markings close to the road surface can be provided, thereby reminding the driver in the tunnel that he is about to exit the tunnel. In addition, the exposed part of the first column rod 12 can also be pasted with warning signs and other markings as needed.
[0026] The length of the corrugated beam plate 3 is not less than three meters, so that after assembly, the angle α between the corrugated beam plate 3 and the existing guardrail can be about 20 to 40 degrees. The most important function of the corrugated beam plate 3 is to serve as a visual warning. Secondly, when a vehicle deviates from the road surface after exiting the tunnel due to various reasons such as fatigue driving, the corrugated beam plate 3 can play a certain guiding and protective role, protecting the space extending outside the tunnel at the width of the inspection road, and transferring the main force to the existing guardrail. Because it is a forward collision and the angle is very small, the second column rod 21 does not need to be installed according to the standard burial depth. When a special situation occurs and the second column rod 21 has a large displacement, part of the force can also be transferred to the first column rod 12 through the end plate 4 for sharing.
[0027] The utility model provides a guardrail transition connector at a tunnel exit, which can be manufactured by simply modifying existing components, has low cost, can provide a significant mark at the tunnel exit, and can protect the space extending outside the tunnel at the width of the inspection road.
[0028] Those skilled in the art should understand that although the present invention is described in the form of multiple embodiments, not every embodiment contains only one independent technical solution. Such description in the specification is only for the sake of clarity. Those skilled in the art should understand the specification as a whole and regard the technical solutions involved in each embodiment as being able to be combined into different embodiments to understand the scope of protection of the present invention.
[0029] The above description is only an illustrative embodiment of the present invention and is not intended to limit the scope of the present invention. Any equivalent changes, modifications and combinations made by any technician in the field without departing from the concept and principle of the present invention shall fall within the scope of protection of the present invention.
Claims
1. A guardrail transition connector at a tunnel exit, characterized in that: It comprises a tunnel inner column arranged on the inspection road at the tunnel exit, a tunnel outer column arranged outside the tunnel, a corrugated beam plate used for connecting the existing guardrail and an end plate used for covering the tunnel inner column.
2. The guardrail transition connector at the tunnel exit according to claim 1, characterized in that: The tunnel interior column comprises an L-shaped steel plate fixed on the inspection road at the tunnel exit by expansion bolts and two first column rods welded side by side on the L-shaped steel plate.
3. The guardrail transition connector at the tunnel exit according to claim 2, characterized in that: The L-shaped steel plate is made of 2mm thick steel plate, with a length L1 of 300mm, a height H1 of 50mm, and a width W1 of 160mm.
4. The guardrail transition connector at the tunnel exit according to claim 1, characterized in that: The tunnel outer column comprises a second column rod, and a mounting base plate is welded to the bottom of the second column rod.
5. The guardrail transition connector at the tunnel exit according to claim 4, characterized in that: The installation base plate is made of a rectangular steel plate with a thickness of 2 mm.
6. The guardrail transition connector at the tunnel exit according to claim 5, characterized in that: The tunnel outer column is arranged close to the inspection road, at a position on the road side of the tunnel outer drainage ditch, and does not exceed the position of the inner extension line of the inspection road in the direction toward the road surface. The mounting base plate is fixed to the ground by bolts.
7. The guardrail transition connector at the tunnel exit according to claim 1, characterized in that: The length of the corrugated beam plate is not less than three meters. After assembly, the angle α between the corrugated beam plate and the existing guardrail is between 20 degrees and 40 degrees.