Foundation pile structure suitable for pile cutting construction in narrow space

By designing the bridge pile foundation structure and using drilling and pile cutting technology, the problems of high noise and high cost in construction in narrow spaces are solved, and the foundation pile construction effect with high stability, low noise and low cost is achieved.

CN221972466UActive Publication Date: 2024-11-08QINHUANGDAO DUNTONG CONSTR ENG CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202323480029.8
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-12-20
Publication Date
2024-11-08
Estimated Expiration
2033-12-20

AI Technical Summary

Technical Problem

As urban underground space development is becoming increasingly saturated, the construction space is getting smaller and smaller, surrounded by residential areas, with more surrounding pipelines, high construction noise requirements, strict settlement control requirements, traditional pile cutting technology has high noise and high cost, and requires a A stable foundation pile structure suitable for narrow spaces.

Method used

A foundation pile structure including bridge pile foundation, bridge pile original bearing platform, external reinforcement space, external pressure ring, external extension strong rod and hydraulic equipment was designed. The rear guide hole and water drilling holes were used to cut the piles to increase the soil layer. Contact area to reduce noise and construction space requirements.

Benefits of technology

It realizes stable pile cutting in a narrow space, reduces noise and construction costs, improves construction efficiency and safety, and is suitable for green and environmentally friendly construction in small spaces.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221972466U_ABST
    Figure CN221972466U_ABST
Patent Text Reader

Abstract

The utility model relates to a foundation pile structure suitable for narrow space pile cutting construction in the field of foundation pile structures, which comprises a bridge pile foundation, the upper end of the bridge pile foundation is fixedly connected with a bridge pile original bearing platform, the lower side of the outer end of the bridge pile original bearing platform is provided with an external reinforcing space, and the outer end of the external reinforcing space is slidably connected with two external pressing rings. The ends, close to each other, of the two outer pressing rings are fixedly connected with a plurality of outer extending strong rods, rotating shafts are installed in the middles of the outer extending strong rods, the upper side of the outer pressing ring located at the upper end is fixedly connected with a plurality of connecting blocks, and the upper ends of the connecting blocks are fixedly connected with lower pressing rods. According to the scheme, the portion between the two outwards-extending strong rods arranged outside the bridge pile foundation is extruded and extends outwards, the stability of the contact face of the bridge pile foundation and the soil layer is higher, meanwhile, construction is conducted in a narrow space, the characteristic that a water drill is used for punching and pile cutting in a rear pilot tunnel is adopted, and reasonable construction of workers in a small-space foundation pit is facilitated.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to a pile foundation structure suitable for pile cutting construction in a narrow space, in particular to a pile foundation structure suitable for pile cutting construction in a narrow space, which is applied to the field of pile foundation structures. Background Art

[0002] During subway construction, in order to ensure the quality of the pile head during pile foundation construction, the pile top elevation is generally required to be higher than the design elevation, or the tunnel excavation needs to pass under existing buildings, etc. During construction, the elevated pile foundation or the lower piles of the existing building need to be cut off.

[0003] The current construction technology is to use a rope saw to cut the piles or a pneumatic pick to break the pile foundation concrete and then use an air cutter to cut the pile foundation steel bars. The traditional pile cutting technology is already very mature, but it is noisy, requires a large working space, is costly, and requires a large (vertical shaft / foundation pit) construction space to be excavated before cutting the pile foundation. It has a certain market share.

[0004] However, as the development of urban underground space becomes increasingly saturated, the available construction space is getting smaller and smaller. It is surrounded by residential areas and there are many surrounding pipelines. The construction noise requirements are high and the settlement control requirements are strict. Therefore, it is necessary to design a more stable pile foundation structure suitable for pile construction in narrow spaces to solve the above problems. Utility Model Content

[0005] In view of the above-mentioned prior art, the technical problem to be solved by the utility model is that as the development of urban underground space becomes increasingly saturated, the available construction space is getting smaller and smaller. It is surrounded by residential areas and there are many surrounding pipelines. The requirements for construction noise are high and the requirements for settlement control are strict. Therefore, it is necessary to design a more stable pile foundation structure suitable for pile construction in a narrow space to solve the above problems.

[0006] In order to solve the above problems, the utility model provides a pile structure suitable for pile cutting construction in a narrow space, including a bridge pile foundation, the upper end of the bridge pile foundation is fixedly connected to the original bridge pile cap, the lower side of the outer end of the bridge pile cap is provided with an external reinforcement space, the outer end of the external reinforcement space is slidably connected to two external pressure rings, the ends of the two external pressure rings close to each other are fixedly connected to a plurality of externally extended strong rods, a rotating shaft is installed in the middle of the externally extended strong rods, a plurality of connecting blocks are fixedly connected to the upper side of the external pressure ring at the upper end, the upper end of the connecting block is fixedly connected to a lower pressure rod, and the lower pressure rod is externally connected to a hydraulic device.

[0007] In the above-mentioned pile foundation structure suitable for pile cutting construction in a narrow space, this solution arranges two externally extended strong rods outside the bridge pile foundation and is squeezed and extended outward, so that the contact area between the bridge pile foundation and the soil layer is wider and the stability is higher. At the same time, the present invention is constructed in a narrow space and adopts the characteristics of using a water drill to drill holes and cut piles in the rear guide hole, which is beneficial for workers to reasonably construct in a small space foundation pit.

[0008] As a further improvement of the present application, the original cap of the bridge pile is located between two underpinning beams, and drainage ditches are respectively provided on the left and right sides of the upper end of the underpinning beam.

[0009] As a further improvement of the present application, a pile cutting hole located between two replacement beams is provided below the original cap of the bridge pile.

[0010] As a further improvement of the present application, a foundation pit is provided at the side end of the original cap of the bridge pile, and a reinforced concrete support is fixedly connected to the inner wall of the foundation pit.

[0011] As another improvement of the present application, a rear guide hole is provided at one end of the foundation pit close to the original cap of the bridge pile.

[0012] As another improved supplement of the present application, a water drill is built into the rear guide hole and a fan is built into the foundation pit.

[0013] In summary, in this scheme, two sliding external pressure rings are arranged outside the pile foundation of the bridge pile. After the hydraulic equipment connected to the lower pressure rod presses down the upper external pressure ring, the two external extension strong rods can be squeezed and extended outward and inserted into the soil layer, so that the contact area between the pile foundation of the bridge pile and the soil layer is wider and more stable. At the same time, the present invention is constructed in a narrow space and adopts the characteristics of using a water drill to drill holes and cut piles in the rear guide hole. There will be no vibration in the process of cutting piles, and the noise is relatively small. Compared with gas cutting equipment, the water drilling equipment is smaller in size, which is conducive to workers to reasonably construct in a small space foundation pit. BRIEF DESCRIPTION OF THE DRAWINGS

[0014] Figure 1 This is a front view of a bridge pile foundation according to the first embodiment of the present application;

[0015] Figure 2 This is a diagram of the truncated state of the bridge pile foundation according to the first embodiment of the present application;

[0016] Figure 3 This is a front view of the foundation pit excavation of the first embodiment of the present application;

[0017] Figure 4 This is a side view of the foundation pit excavation of the first embodiment of the present application.

[0018] Description of the numbers in the figure:

[0019] 1. Original cap of bridge piles; 2. Replacement beam; 3. Drainage ditch; 4. Pile cut hole; 5. Bridge pile foundation; 6. Reinforced concrete support; 7. Foundation pit; 8. Rear guide hole; 9. External pressure ring; 10. External extension strong rod; 11. Rotating shaft; 12. Connecting block; 13. Down pressure rod; 14. External reinforcement space. DETAILED DESCRIPTION

[0020] Two implementation modes of the present application are described in detail below with reference to the accompanying drawings.

[0021] The first implementation method:

[0022] Figure 1 It is shown that it includes a bridge pile foundation 5, the upper end of the bridge pile foundation 5 is fixedly connected to the original bridge pile cap 1, the lower side of the outer end of the bridge pile cap 1 is provided with an external reinforcement space 14, the outer end of the external reinforcement space 14 is slidably connected to two external pressure rings 9, the ends of the two external pressure rings 9 close to each other are fixedly connected to a plurality of external extension strong rods 10, a rotating shaft 11 is installed in the middle of the external extension strong rod 10, a plurality of connection blocks 12 are fixedly connected to the upper side of the external pressure ring 9 at the upper end, the upper end of the connection block 12 is fixedly connected to a lower pressure rod 13, and the lower pressure rod 13 is externally connected to a hydraulic device.

[0023] Figure 2-4 It is shown that the original cap 1 of the bridge pile is located between two underpinning beams 2, drainage ditches 3 are respectively arranged on the left and right sides of the upper end of the underpinning beam 2, a pile cutting hole 4 located between the two underpinning beams 2 is arranged below the original cap 1 of the bridge pile, a foundation pit 7 is arranged at the side end of the original cap 1 of the bridge pile, a reinforced concrete support 6 is fixedly connected to the inner wall of the foundation pit 7, a rear guide hole 8 is arranged at one end of the foundation pit 7 close to the original cap 1 of the bridge pile, a water drill is built in the rear guide hole 8, and a fan is built in the foundation pit 7.

[0024] Figure 1 It is shown that in this solution, two slidable external pressure rings 9 are arranged outside the bridge pile foundation 5. After the hydraulic equipment connected to the lower pressure rod 13 presses down the upper external pressure ring 9, the two external extension strong rods 10 can be squeezed and extended outward and inserted into the soil layer, so that the contact area between the bridge pile foundation 5 and the soil layer is wider and the stability is higher.

[0025] Figure 2-4It is shown that the invention is constructed in a narrow space and adopts the characteristics of using a water drill to drill holes and cut piles in the rear guide hole 8. There will be no vibration in the process of cutting piles, and the noise is relatively small. Compared with gas cutting equipment, the water drilling equipment is smaller in size, which is conducive to workers to reasonably construct in a small space foundation pit 7. It has the characteristics of low construction cost, high efficiency, convenient operation, environmental protection, etc., reduces dust dispersion, and is green and environmentally friendly. Specifically, the foundation pit 7 is first constructed near the underpinning pile by a reverse method, and the side wall of the foundation pit 7 is set with a rear guide hole 8. The existing bridge pile foundation 5 is dug at the position of the underpinning beam 2 by the method of the rear guide hole 8, and then the pile is manually cut with a water drill. At the same time, a drainage ditch 3 is constructed on the ground, and excavation is carried out in layers from the bottom to the top, with the underpinning beam 2 as support. Through measurement and strict control, manual excavation is carried out with a pneumatic pick until the working surface is completely exposed, and the cutting work is carried out. The concrete is broken and the steel bars are cut. In the process of breaking the piles, the blower is mainly used to take over the ventilation. Finally, part of the bridge pile foundation 5 is successfully cut off, and there is no need to increase the construction space conditions of the deep foundation pit, which saves costs for the project.

[0026] In view of current practical needs, the protection scope of the above-mentioned implementation mode adopted in this application is not limited to this. Various changes made within the knowledge scope of technical personnel in this field without departing from the concept of this application still fall within the protection scope of this utility model.

Claims

1. A pile foundation structure suitable for pile cutting construction in a narrow space, characterized by: The invention comprises a bridge pile foundation (5), wherein the upper end of the bridge pile foundation (5) is fixedly connected to the original bridge pile foundation (1), an external reinforcement space (14) is provided on the lower side of the outer end of the original bridge pile foundation (1), the outer end of the external reinforcement space (14) is slidably connected to two external pressure rings (9), and the ends of the two external pressure rings (9) close to each other are fixedly connected to multiple external extension rods (10), a rotating shaft (11) is installed in the middle of the external extension rod (10), and the upper side of the external pressure ring (9) at the upper end is fixedly connected to multiple connection blocks (12), the upper end of the connection block (12) is fixedly connected to a lower pressure rod (13), and the lower pressure rod (13) is externally connected to a hydraulic device.

2. A pile foundation structure suitable for pile cutting construction in a narrow space according to claim 1, characterized in that: The original bridge pile cap (1) is located between two underpinning beams (2), and drainage ditches (3) are respectively provided on the left and right sides of the upper end of the underpinning beam (2).

3. The pile foundation structure suitable for pile cutting construction in a narrow space according to claim 1, characterized in that: A pile cut hole (4) located between two underpinning beams (2) is provided below the original bridge pile cap (1).

4. The pile foundation structure suitable for pile cutting construction in a narrow space according to claim 1, characterized in that: A foundation pit (7) is provided at the side end of the original bridge pile cap (1), and a reinforced concrete support (6) is fixedly connected to the inner side wall of the foundation pit (7).