Arch bridge suspender auxiliary tensioning device
By designing the auxiliary tensioning device of the arch bridge suspension rod, using components such as anchor pads, feet, anchor heads and support components, the problem of poor lifting stability of the arch bridge segments in the existing technology is solved, and more efficient and safe tensioning is achieved Effect.
Patent Information
- Application Number
- CN202420254053.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-02-01
- Publication Date
- 2024-11-12
- Estimated Expiration
- 2034-02-01
AI Technical Summary
In the prior art, the lifting of the split parts requires multiple lifting during the construction of the arch bridge, and the existing lifting tensioning rod devices are difficult to meet the support needs, resulting in poor stability and insufficient safety.
An auxiliary tensioning device for arch bridge suspension rod is designed, including anchor pad plate, support foot, anchor head, finished steel strand cable, support assembly, tension rod, jack and variable diameter sleeve. Through the design of support assembly and assembly cavity, Ensure the stability of the anchor head and tension rod when under stress, and protect the connection with friction pads to improve safety.
It improves the stability and safety of the tension rod, ensures support effect, is suitable for multiple tensioning usage scenarios, and has a beautiful structure, and is suitable for tension rods of different specifications.
Smart Images

Figure CN221989111U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field related to tensioning rods of arch bridge hangers, in particular to an auxiliary tensioning device for arch bridge hangers. Background Art
[0002] In the prior art, during the construction of arch bridges, when the components are relatively large, they are cut into sections, and these sections are hoisted gradually multiple times instead of all at once, which requires full consideration of support, etc. The hoisting tension rod device in the prior art is difficult to meet this requirement. Utility Model Content
[0003] The utility model aims to provide an auxiliary tensioning device for arch bridge hangers to solve the above technical problems.
[0004] In order to achieve the above-mentioned purpose, the utility model is implemented through the following technical solutions.
[0005] The auxiliary tensioning device of the arch bridge hanger comprises:
[0006] Anchor pad,
[0007] A plurality of support legs located below the anchor plate, wherein the plurality of support legs and the anchor plate form an assembly cavity;
[0008] An anchor head extending into the assembly cavity, the anchor head being connected to a finished steel strand cable, and a support assembly being provided on the assembly cavity;
[0009] A tension rod, the tension rod extends into the assembly cavity and is connected to the anchor head;
[0010] A jack is located at the bottom of the support leg, and the jack is used to push the assembly cavity to achieve tensioning of the tension rod.
[0011] Furthermore, the assembly cavity is centered on the anchor head, and the anchor plate, support leg, tension rod and jack are co-centrally arranged.
[0012] Furthermore, it also includes a reducing sleeve which is sleeved on the anchor head and located below the support assembly, the reducing sleeve forms a connecting cavity with a diameter gradually decreasing from top to bottom, and the pull rod is connected to the anchor head through the connecting cavity.
[0013] Furthermore, the projection of the support assembly is located on the reducer sleeve, the outer wall of the reducer sleeve is a constant diameter structure, and the inner wall of the reducer sleeve forms the connecting cavity whose diameter gradually decreases from top to bottom.
[0014] Furthermore, the connecting cavity is located in the assembly cavity, and an assembly gap is formed between the connecting cavity and the supporting assembly.
[0015] Furthermore, the support assembly is fitted with the top of the inner wall of the assembly cavity, and the support assembly is located outside the anchor head.
[0016] Furthermore, the supporting component is a spherical nut, which is threadedly connected to the anchor head and abuts against the inner wall of the top of the assembly cavity.
[0017] Furthermore, a nut is provided below the jack, and the nut is threadedly connected to the tension rod.
[0018] Furthermore, it also includes a friction pad located between the nut and the jack, and the friction pad covers the nut.
[0019] The beneficial effects of the utility model are as follows:
[0020] In the utility model, due to the support assembly, the anchor head and the tension rod are supported by the support assembly in the assembly cavity when the tension rod is subjected to force, so the stability is relatively good, the support in the tension rod is ensured, and the effect of the tension rod is improved.
[0021] In the utility model, since the assembly cavity is provided, the connection between the anchor head and the long pull rod is protected by the assembly cavity, thus avoiding external interference and the like, and being safer to use. BRIEF DESCRIPTION OF THE DRAWINGS
[0022] Figure 1 A schematic diagram of the structure of the arch bridge hanger auxiliary tensioning device provided by the utility model;
[0023] In the figure:
[0024] 1. Anchor plate; 2. Support foot; 3. Anchor head; 4. Finished steel strand rope; 5. Support assembly; 6. Tension rod; 7. Jack; 8. Reducer sleeve; 9. Nut; 10. Friction pad. DETAILED DESCRIPTION
[0025] The present invention is described in detail below in conjunction with the various embodiments shown in the accompanying drawings, but it should be noted that these embodiments are not limitations of the present invention, and any equivalent transformations or substitutions in functions, methods, or structures made by ordinary technicians in the field based on these embodiments are all within the scope of protection of the present invention.
[0026] Refer to the attached Figure 1As shown, in this embodiment, the auxiliary tensioning device of the arch bridge suspender includes an anchor plate 1, a plurality of legs 2 located below the anchor plate 1, and the plurality of legs 2 and the anchor plate 1 form an assembly cavity for later enclosure. It also includes an anchor head 3 extending into the assembly cavity, a finished steel strand cable 4 is connected to the anchor head 3, and a support assembly 5 is provided on the assembly cavity; a tensioning rod 6, the tensioning rod 6 extends into the assembly cavity and is connected to the anchor head 3; and a jack 7 located at the bottom of the legs 2, the jack 7 is used to push the assembly cavity to achieve tensioning of the tensioning rod 6.
[0027] In the utility model, the support legs and the anchor pads form an assembly cavity, so that the connected anchor heads and the connection points of the tension rods are well protected. Furthermore, during stress, the tension rods with large stress are in the assembly cavity, and a support component is provided in the assembly cavity, so that the tension rods are stable after being stressed, thereby improving the use efficiency.
[0028] The utility model is more suitable for multiple tensioning usage scenarios and has better stability.
[0029] In order to ensure stability, the assembly cavity forms a symmetrical structure with the anchor head 3 as the center, and then the anchor plate 1, the support leg 2, the tension rod 6 and the jack 7 are arranged cocentrically, so that the force in the tension rod is evenly dispersed and the stability is good.
[0030] Furthermore, it also includes a reducing sleeve 8 which is sleeved on the anchor head 3 and located below the support assembly 5, the reducing sleeve 8 forms a connecting cavity with a diameter gradually decreasing from top to bottom, and the tension rod 6 is connected to the anchor head 3 through the connecting cavity. In this embodiment, the reducing sleeve and the like are used to enable the anchor head 3 to match tension rods 6 of different diameters and sizes, thereby improving adaptability.
[0031] In order to provide better support and to be more beautiful, the projection of the support assembly 5 is located on the reducer sleeve 8, the outer wall of the reducer sleeve 8 is an equal diameter structure, and the inner wall of the reducer sleeve forms the connecting cavity with a diameter gradually decreasing from top to bottom. In this embodiment, the outer diameter of the support assembly 5 is the same as the outer diameter of the reducer sleeve 8, and then the inner wall is assembled, the structure is beautiful, and the reducer sleeve 8 is below the support assembly 5 to protect and support it.
[0032] In order to ensure that the support assembly and other internal structures in the finished steel strand tension rod are not deformed in case of force, a certain space is needed for force release and buffering, so the connecting cavity is located in the assembly cavity, and an assembly gap is formed between the connecting cavity and the support assembly 5. At this time, a release space is formed between the support assembly 5 and the connecting cavity, and the connecting cavity is located in the assembly cavity, and the assembly cavity simultaneously protects the connecting cavity.
[0033] In order to achieve a better supporting effect, the support assembly 5 is fitted with the top of the inner wall of the assembly cavity, and the support assembly 5 is located outside the anchor head 3. At this time, the support assembly 5 is well supported on the anchor head 3.
[0034] Specifically, the support assembly 5 is a spherical nut, which is threadedly connected to the anchor head 3 and abuts against the inner wall of the top of the assembly cavity. The spherical nut is selected, and its surface is arc-shaped, etc., so that the concentrated load force can be dissipated and decomposed faster.
[0035] In order to protect the tension rod 6, a nut 9 is provided below the jack 7, and the nut 9 is threadedly connected to the tension rod 6. The nut realizes support and the like.
[0036] In order to protect the jack and the long pull rod 6, a friction pad 10 is added. The friction pad 10 has a large cross-sectional area and completely covers the nut 9 to ensure safety. The friction pad 10 can be a rubber pad.
[0037] Refer to the attached Figure 1 As shown, the arch bridge hanger auxiliary tensioning device in the utility model is used for arch bridge hoisting, and its use process is as follows:
[0038] First, the installation of the tension rod equipment
[0039] Before installation, the combination of the jack and the oil pump should be checked first to ensure that it is consistent with the combination during calibration, and then tested to check for oil leakage, etc. The jack and other tension rod equipment are transported to the tension rod position under the bridge deck by a hydraulic vehicle and installed one by one. During installation, the center lines of the anchor plate, support leg, jack, and tension rod should be aligned.
[0040] Secondly, the order of the suspender rod tensioning:
[0041] The tension rods are suspended from the middle of the arch bridge to the supports on both sides. Each batch of tension rods is symmetrically tensioned on both sides, with a total of 2 hangers. The cable force of the hanger bridge is 572kN-2118kN, and a 250t (200t) jack tension rod tooling is used.
[0042] In actual arch bridge construction, it is necessary to complete the assembly of the arch foot, longitudinal and transverse beams, and main arch ribs in a predetermined order, and then hang the hangers and tension the rods. After finite element calculation, the tensioning sequence of the hangers is symmetrical from the middle to both sides.
[0043] (3) Tension rod classification
[0044] The tension rod grading is carried out according to the grading of 0→10% (holding load for 15 minutes) → 20% (holding load for 5 minutes) → 50% (holding load for 5 minutes) → 80% (holding load for 5 minutes) → 100% of the initial tension rod force value (holding load for 2 minutes and anchoring), and corresponding adjustments should be made according to the requirements of the monitoring unit, the tension rods should be tensioned symmetrically at the two tops simultaneously, and a dedicated person should be appointed to command.
[0045] After the first tensioning of the suspender cable is completed, the cable force and main arch deformation should be comprehensively observed. The test results show that the cable force deviation of the side suspender or the middle suspender is large and the cable force is uneven. In the subsequent construction, the cable force needs to be appropriately adjusted to make it as uniform as possible.
[0046] The control parameters of the suspender tension rod are the deformation of the main arch, the tension of the suspender rod and the elongation. During the construction, the left and right symmetry and the synchronous pressure of the jacks must be maintained, and each suspender tension rod record must be carefully made. When the suspender cable tension rod meets the design and monitoring requirements, the monitoring of the main arch shall be strengthened.
[0047] (4) Specific operation steps of tension rod
[0048] Connect the oil pipes of the oil pump and the jack, check whether the precision pressure gauge matches the jack. Before tensioning the tension rod, you can move two strokes under no-load conditions to ensure that there are no problems with the jack when tensioning the tension rod.
[0049] The tension rod jack and oil pressure gauge must be calibrated before tensioning the rod, and the tension rod should be tensioned in sequence according to the tension rod force of the suspender.
[0050] Start the oil pump. During the tensioning process, the boom cable moves down slowly. At the same time, the boom cable anchor ring should be rotated upward so that it does not move too high from the anchor pad.
[0051] When the design, monitoring and supervision requirements are met, the oil pressure should be stabilized and then the anchor ring should be tightened to fully combine the anchor ring with the anchor pad.
[0052] Finally, release the oil pressure, return the oil, shut down the machine, and cut off the power to complete the tensioning rod work.
[0053] The series of detailed descriptions listed above are only specific descriptions of feasible implementation methods of the utility model. They are not intended to limit the protection scope of the utility model. Any equivalent implementation methods or changes that do not deviate from the technical spirit of the utility model should be included in the protection scope of the utility model.
[0054] It is obvious to those skilled in the art that the present invention is not limited to the details of the exemplary embodiments described above, and that the present invention can be implemented in other specific forms without departing from the spirit or essential features of the present invention. Therefore, the embodiments should be regarded as exemplary and non-restrictive from any point of view, and the scope of the present invention is defined by the appended claims rather than the above description, and it is intended that all changes falling within the meaning and scope of the equivalent elements of the claims be included in the present invention. Any reference numeral in a claim should not be regarded as limiting the claim to which it relates.
[0055] In addition, it should be understood that although the present specification is described according to implementation modes, not every implementation mode contains only one independent technical solution. This description of the specification is only for the sake of clarity. Those skilled in the art should regard the specification as a whole. The technical solutions in each embodiment may also be appropriately combined to form other implementation modes that can be understood by those skilled in the art.
Claims
1. The arch bridge hanger auxiliary tensioning device is characterized by: include, Anchor pad, A plurality of support legs located below the anchor plate, wherein the plurality of support legs and the anchor plate form an assembly cavity; An anchor head extending into the assembly cavity, the anchor head being connected to a finished steel strand cable, and a support assembly being provided on the assembly cavity; A tension rod, the tension rod extends into the assembly cavity and is connected to the anchor head; A jack is located at the bottom of the support leg, and the jack is used to push the assembly cavity to achieve tensioning of the tension rod.
2. The arch bridge hanger auxiliary tensioning device according to claim 1, characterized in that: The assembly cavity is centered on the anchor head, and the anchor pad, support foot, tension rod and jack are co-centrally arranged.
3. The arch bridge hanger auxiliary tensioning device according to claim 1, characterized in that: It also includes a reducing sleeve which is sleeved on the anchor head and located below the support assembly. The reducing sleeve forms a connecting cavity with a gradually decreasing diameter from top to bottom. The pull rod is connected to the anchor head through the connecting cavity.
4. The arch bridge hanger auxiliary tensioning device according to claim 3, characterized in that: The projection of the support assembly is located on the reducer sleeve, the outer wall of the reducer sleeve is a constant diameter structure, and the inner wall of the reducer sleeve forms the connecting cavity with a diameter gradually decreasing from top to bottom.
5. The arch bridge hanger auxiliary tensioning device according to claim 3, characterized in that: The connecting cavity is located in the assembly cavity, and an assembly gap is formed between the connecting cavity and the supporting assembly.
6. The arch bridge hanger auxiliary tensioning device according to claim 1, characterized in that: The support component is fitted with the top of the inner wall of the assembly cavity, and the support component is located outside the anchor head.
7. The arch bridge hanger auxiliary tensioning device according to claim 6, characterized in that: The supporting component is a spherical nut, which is threadedly connected to the anchor head and abuts against the inner wall of the top of the assembly cavity.
8. The arch bridge hanger auxiliary tensioning device according to claim 1, characterized in that: A nut is arranged below the jack, and the nut is threadedly connected to the tension rod.
9. The arch bridge hanger auxiliary tensioning device according to claim 8, characterized in that: It also includes a friction pad located between the nut and the jack, wherein the friction pad covers the nut.