Working device for existing line tunnel construction
By designing a multi-degree of freedom swing telescopic structure and rope pulling warning system, the problem that existing wire tunnel construction equipment in the prior art is difficult to automatically surround the contact network, achieving efficient and safe construction coverage, and reducing construction strength and safety hazards.
Patent Information
- Application Number
- CN202420211675.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-01-29
- Publication Date
- 2024-11-12
- Estimated Expiration
- 2034-01-29
AI Technical Summary
It is difficult for existing existing line tunnel construction equipment to automatically circumvent the contact network, resulting in low construction efficiency and safety hazards, and there is a risk of safety accidents caused by operators' untimely response.
A working device including a sliding platform, a slewing platform, a main arm mechanism, a telescopic arm and an anti-collision detector was designed. Through a multi-degree of freedom swing and telescopic structure and a rope pulling warning system, the existing pipelines and contact lines in the tunnel are realized. Automatic circumvention and ensure construction safety through detection sensors and angle encoder.
The construction efficiency and safety are improved, the coverage of the full tunnel section is achieved, the subsequent construction intensity is reduced, and the construction safety is greatly improved through an automated early warning system, avoiding the situation of direct collision with the contact network.
Smart Images

Figure CN221990384U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of tunnel construction, in particular to a working device for existing line tunnel construction. Background Art
[0002] The construction of existing line tunnel lining usually includes the processes of concrete roughening, locking foot anchor construction, drill nail construction, arch frame installation, steel bar binding and welding, formwork installation, concrete pouring, etc. During the construction processes of concrete roughening, locking foot anchor construction, drill nail construction, arch frame installation, steel bar binding and welding, formwork installation, concrete pouring, etc., the existing pipelines and contact network in the tunnel must be protected and damage is strictly prohibited.
[0003] Traditional construction often uses manual scaffolding, and the construction process often requires manual intervention, and the contact network must be avoided at all times, which seriously affects construction efficiency. At the same time, due to long-term high-altitude operations, personnel are prone to fatigue, and safety accidents are prone to occur during the construction of crossing the contact line. In addition, most of the existing construction equipment is operated by the operator directly observing on site so that the actuator can avoid the contact network. There is a risk that the operator will not react in time and bump into the contact network, causing a safety accident. Therefore, it is difficult for existing construction equipment to effectively avoid existing structures in the tunnel, namely the contact line load-bearing cables, return lines, contact line columns, etc. During the construction process, these areas are often divided separately and then processed later. It is difficult to cover the entire tunnel section in one operation, which increases the work intensity and affects the construction efficiency. Utility Model Content
[0004] 1. Technical issues to be resolved
[0005] In view of the above-mentioned shortcomings and deficiencies of the prior art, the utility model provides a working device for existing line tunnel construction, which solves the technical problem that the existing existing line tunnel lining construction equipment is difficult to automatically avoid the contact network.
[0006] (II) Technical solution
[0007] In order to achieve the above-mentioned purpose, the working device for existing line tunnel construction of the utility model comprises:
[0008] Sliding platform;
[0009] A rotating platform, the rotating platform is installed on the sliding platform, and the sliding platform can drive the rotating platform to move between the inner walls on both sides of the tunnel;
[0010] A main arm mechanism, the main arm mechanism is hinged to the rotary platform and can perform a first pitch; the rotary platform can drive the main arm mechanism to rotate in a horizontal plane;
[0011] A first-stage telescopic arm, the head end of which is slidably connected to the tail end of the main arm mechanism; a first anti-collision detector is provided on the first-stage telescopic arm;
[0012] A secondary telescopic arm, the head end of the secondary telescopic arm is slidably connected to the tail end of the primary telescopic arm; both the primary telescopic arm and the secondary telescopic arm can be telescoped in the length direction of the main arm mechanism;
[0013] A jib mechanism, the head end of which is hinged to the tail end of the secondary telescopic arm and is capable of performing a second pitch;
[0014] An actuator, the head end of which is hinged to the tail end of the auxiliary arm mechanism and can swing around the hinge point; a second anti-collision detector is provided on the tail end of the actuator;
[0015] a first pull rope, one end of which is connected to the first anti-collision detector, and the other end of which is connected to the secondary telescopic arm;
[0016] A second pull rope, one end of which is connected to the auxiliary arm mechanism, and the other end of which is connected to the second anti-collision detector; the first pull rope and the second pull rope are arranged away from the sliding platform.
[0017] Optionally, the first anti-collision detector and the second anti-collision detector each include a detection sensor, a clockwork spring and a housing;
[0018] The housing is mounted on the primary telescopic arm or the actuator;
[0019] The spring is built into the housing; the spring is connected to the first pull rope, or the spring is connected to the second pull rope;
[0020] The detection sensor is installed on the shell.
[0021] Optionally, a support wheel is provided at the top end of the auxiliary arm mechanism and / or the secondary telescopic arm; the support wheel is slidably connected to the first pull rope, or the support wheel is slidably connected to the second pull rope.
[0022] Optionally, the support wheel includes a base, a connecting rod, an upper roller and a lower roller;
[0023] The base is arranged at the top of the auxiliary arm mechanism and / or the secondary telescopic arm;
[0024] The lower roller is rotatably connected to the base; the upper roller is arranged above the lower roller, and the two are connected by the connecting rod;
[0025] The first pull rope or the second pull rope slides in a gap between the upper roller and the lower roller.
[0026] Optionally, the detection sensor is a laser sensor, a tension sensor or a pressure sensor.
[0027] Optionally, a first grating is provided at the top of the primary telescopic arm, and a second grating is provided at the top of the secondary telescopic arm.
[0028] Optionally, a first angle encoder is arranged on the rotary platform; a second angle encoder is arranged on the main arm mechanism; a third angle encoder is arranged on the auxiliary arm mechanism; and a fourth angle encoder is arranged on the actuator.
[0029] Optionally, the second anti-collision detector is detachably connected to the actuator.
[0030] (III) Beneficial effects
[0031] The beneficial effects of the utility model are:
[0032] The multi-degree-of-freedom swinging and telescopic structure of the working device can bypass existing pipelines and contact lines in the tunnel during construction, and single-point parking can cover a larger working range or completely cover the construction working surface of the entire tunnel section.
[0033] One end of the second pull rope is connected to the auxiliary arm mechanism, and the other end is connected to the second anti-collision detector. The second pull rope can be synchronously extended and retracted with the second pitch and the swing of the actuator, and the second pull rope is always in a taut state during the construction process. Similarly, one end of the first pull rope is connected to the first anti-collision detector, and the other end is connected to the secondary telescopic arm. The first pull rope can be synchronously extended and retracted with the extension and retraction of the secondary telescopic arm, and the first pull rope is always in a taut state during the construction process. On this basis, the first pull rope and the second pull rope are set away from the sliding platform, that is, close to the top of the tunnel, so that when the working device is operating, the first pull rope or the second pull rope contacts the contact network before other mechanisms of the working device. After the contact, the force of the first pull rope or the second pull rope suddenly changes, which is monitored and warned by the first anti-collision detector or the second anti-collision detector, and the pitch or rotation action of the working device is stopped in time, and only the actuator is controlled to continue the operation. Therefore, the construction safety of the working device on the entire tunnel section can be improved, and the operation coverage can be improved, which effectively improves the construction efficiency and reduces the subsequent construction intensity.
[0034] The second pull rope covers the warning area at the top of the auxiliary arm mechanism and the actuator, and the first pull rope covers the warning area at the top of the first-level telescopic arm and the second-level telescopic arm, which effectively avoids the working device from directly colliding with the contact network, realizes the automated warning operation of the working device, and greatly improves the construction safety. BRIEF DESCRIPTION OF THE DRAWINGS
[0035] Figure 1 It is a structural schematic diagram of the working device for existing line tunnel construction of the utility model;
[0036] Figure 2 It is a schematic diagram of the first limit state of the working device for existing line tunnel construction of the utility model in a double-line tunnel;
[0037] Figure 3 It is a schematic diagram of the second limit state of the working device for existing line tunnel construction of the utility model in a double-line tunnel.
[0038] [Description of Reference Numerals]
[0039] 1: sliding platform; 2: drag chain mechanism; 3: sliding frame; 4: first angle encoder; 5: second angle encoder; 6: rotating platform; 7: first pitch cylinder; 8: main arm mechanism; 9: first telescopic cylinder; 10: first anti-collision detector; 11: first grating; 12: second grating; 13: third angle encoder; 14: support wheel; 15: second pull rope; 16: second anti-collision detector; 17: actuator; 18: mounting seat; 19: fourth angle encoder; 20: swing cylinder; 21: auxiliary arm mechanism; 22: second pitch cylinder; 23: second telescopic arm; 24: first telescopic arm; 25: flatbed transport vehicle; 26: existing pipeline; 27: first pull rope. DETAILED DESCRIPTION
[0040] In order to better explain the present invention and facilitate understanding, the present invention is described in detail below through specific implementation modes in conjunction with the accompanying drawings.
[0041] It should be noted that all directional indications in the embodiments of the present invention (such as up, down, left, right, front, back...) are only used to explain the relative position relationship, movement status, etc. between the components under a certain specific posture (as shown in the accompanying drawings). If the specific posture changes, the directional indication will also change accordingly.
[0042] In addition, in the present invention, the descriptions of "first", "second", etc. are only used for descriptive purposes and cannot be understood as indicating or implying their relative importance or implicitly indicating the number of the indicated technical features. Therefore, the features defined as "first" or "second" may explicitly or implicitly include at least one of the features. In the description of the present invention, the meaning of "plurality" is at least two, such as two, three, etc., unless otherwise clearly and specifically defined.
[0043] In the present invention, unless otherwise clearly specified and limited, the terms "connection", "fixation", etc. should be understood in a broad sense. For example, "fixation" can be a fixed connection, a detachable connection, or an integral connection; "connection" can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, and it can be the internal connection of two elements or the interaction relationship between two elements, unless otherwise clearly defined. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0044] See also Figures 1 to 3 The utility model provides a working device for existing line tunnel construction, the working device includes a sliding platform 1, a rotating platform 6, a main arm mechanism 8, a primary telescopic arm 24, a secondary telescopic arm 23, a secondary arm mechanism 21, an actuator 17, a first pull rope 27 and a second pull rope 15. The rotating platform 6 is installed on the sliding platform 1, and the sliding platform 1 can drive the rotating platform 6 to move between the inner walls on both sides of the tunnel, that is, to move in a direction perpendicular to the tunnel construction; the main arm mechanism 8 is hinged with the rotating platform 6 and can perform a first pitch to adjust the height of the actuator 17 in the vertical direction; the rotating platform 6 can drive the main arm mechanism 8 to rotate in the horizontal plane to adjust the angle of the actuator 17 relative to the inner wall of the tunnel; the head end of the first-level telescopic arm 24 is slidably connected to the tail end of the main arm mechanism 8, and the head end of the utility model is the end close to the rotating platform 6, and the tail end is the end away from the rotating platform 6; the first-level telescopic arm 24 is provided with a first anti-collision detector 10; the head end of the second-level telescopic arm 23 is slidably connected to the tail end of the first-level telescopic arm 24; the first-level telescopic arm 24 and the second-level telescopic arm 24 are connected to each other. The retractable arms 23 can be extended and retracted in the length direction of the main arm mechanism 8 to extend the telescopic length of the main arm mechanism 8, and cooperate with the sliding platform 1 to extend the actuator 17 to the inner wall of the tunnel; the head end of the auxiliary arm mechanism 21 is hinged to the tail end of the secondary telescopic arm 23, and can perform a second pitch; the head end of the actuator 17 is hinged to the tail end of the auxiliary arm mechanism 21, and can swing around the hinge point to make the actuator 17 fit and fit the inner wall; a second anti-collision detector 16 is arranged on the tail end of the actuator 17; one end of the first pull rope 27 is connected to the first anti-collision detector 10, and the other end is connected to the secondary telescopic arm 23; one end of the second pull rope 15 is connected to the auxiliary arm mechanism 21, and the other end is connected to the second anti-collision detector 16; the first pull rope 27 and the second pull rope 15 are arranged away from the sliding platform 1.
[0045] The first telescopic arm 24 and the second telescopic arm 23 can extend the telescopic length of the main arm mechanism 8, and cooperate with the sliding platform 1 to extend the actuator 17 to the inner wall of the tunnel. The first pitch and the second pitch can assist the main arm mechanism 8 to further pitch, and flexibly adjust the lifting height of the actuator 17. The actuator 17 can swing around the hinge point with the auxiliary arm mechanism 21, and can assist the rotating platform 6 to flexibly adjust the relative angle between the actuator 17 and the inner wall, so as to fit the actuator 17 to the inner wall. The multi-degree-of-freedom swinging and telescopic structure of the working device can bypass existing pipelines and contact lines in the tunnel during construction, and single-point parking can cover a larger working range, or completely cover the construction working surface of the entire tunnel section.
[0046] One end of the second pull rope 15 is connected to the auxiliary arm mechanism 21, and the other end is connected to the second anti-collision detector 16. The second pull rope 15 can be synchronously extended and retracted with the second pitch and the swing of the actuator 17. The second pull rope 15 is always in a taut state during the construction process. Similarly, one end of the first pull rope 27 is connected to the first anti-collision detector 10, and the other end is connected to the secondary telescopic arm 23. The first pull rope 27 can be synchronously extended and retracted with the extension and retraction of the secondary telescopic arm 23. The first pull rope 27 is always in a taut state during the construction process. On this basis, the first pull rope 27 and the second pull rope 15 are set away from the sliding platform 1, that is, close to the top of the tunnel, so that when the working device is operating, the first pull rope 27 or the second pull rope 15 contacts the contact network before other mechanisms of the working device. After the contact, the force of the first pull rope 27 or the second pull rope 15 suddenly changes, which is monitored and warned by the first anti-collision detector 10 or the second anti-collision detector 16, and the pitch or rotation action of the working device is stopped in time, and only the actuator 17 is controlled to continue the operation. Therefore, the construction safety of the working device on the entire tunnel section can be improved, and the operation coverage can be increased, which effectively improves the construction efficiency and reduces the subsequent construction intensity.
[0047] It should be noted that if Figure 2 and Figure 3 As shown, when the first pull rope 27 touches the contact network warning, and the second pull rope 15 does not touch the contact network, it is in Figure 2 When the working device is in the first limit state shown in FIG. 1 , the auxiliary arm mechanism 21 and the actuator 17 can continue to operate, that is, the connection structure with the second pull rope 15 can continue to operate; until the second pull rope 15 touches the contact network warning, that is, in the Figure 3In the second limit state of the working device shown, the action of the auxiliary arm mechanism 21 is stopped, and only the actuator 17 is operated. The warning area at the top of the auxiliary arm mechanism 21 and the actuator 17 is covered by the second pull rope 15, and the warning area at the top of the first telescopic arm 24 and the second telescopic arm 23 is covered by the first pull rope 27, which effectively avoids the situation where the working device directly hits the contact network, realizes the automatic warning operation of the working device, and greatly improves the construction safety. Of course, according to the actual construction conditions and needs, pull ropes and detectors can also be set at the top of the main arm mechanism 8 for early warning.
[0048] In this embodiment, the sliding platform 1 includes a bracket, a drag chain mechanism 2 and a sliding frame 3. The drag chain mechanism 2 is installed inside the bracket; the sliding frame 3 is installed on the drag chain mechanism 2, and the sliding frame 3 is slidably connected to the top surface of the bracket. The sliding frame 3 is driven by the drag chain mechanism 2 to move between the inner walls on both sides of the tunnel. The main arm mechanism 8 includes a main arm and a first pitch cylinder 7. One end of the first pitch cylinder 7 is hinged to the rotating platform 6, and the other end is hinged to the main arm. The pitch of the main arm mechanism 8 relative to the rotating platform 6 can be achieved by the extension and contraction of the first pitch cylinder 7. A first telescopic cylinder 9 is arranged inside the first telescopic arm 24. One end of the first telescopic cylinder 9 is connected to the main arm mechanism 8, and the other end is connected to the first telescopic arm 24. The extension and contraction of the first telescopic cylinder 9 can achieve the extension and contraction of the first telescopic arm 24. Similarly, a second telescopic cylinder is arranged inside the second telescopic arm 23; the auxiliary arm mechanism 21 includes an auxiliary arm and a second pitch cylinder 22; the actuator 17 includes an actuator unit, a mounting seat 18 and a swing cylinder 20. Among them, the secondary telescopic arm 23 can be set up in an analogous manner to the primary telescopic arm 24, and the auxiliary arm mechanism 21 and the actuator 17 can be set up in an analogous manner to the main arm mechanism 8, which will not be repeated here.
[0049] Furthermore, the first anti-collision detector 10 and the second anti-collision detector 16 each include a detection sensor, a clockwork spring and a housing; the housing is mounted on the first telescopic arm 24 or the actuator 17; the clockwork spring is built into the housing; the clockwork spring is connected to the first pull rope 27, or the clockwork spring is connected to the second pull rope 15; the detection sensor is mounted on the housing. Specifically, the clockwork spring and the housing are equivalent to a tape measure structure. When the pull rope is pulled, the clockwork spring can be compressed or pulled up synchronously, so that the pull rope is always in a taut state during the pitch or extension process of the working device, forming an early warning line. The detection sensor is used to detect whether the pull rope collides with the contact network. If a collision occurs, the collision signal is fed back to the operating interface of the working device, and the operating system immediately and automatically stops the arm-related actions to ensure the safety of the existing contact network line in the tunnel.
[0050] Secondly, a support wheel 14 is provided at the top of the auxiliary arm mechanism 21 and / or the secondary telescopic arm 23; the top of the support wheel 14 is slidably connected to the first pull rope 27, or the top of the support wheel 14 is slidably connected to the second pull rope 15. As the working device pitches or telescopes, the pull rope is synchronously lengthened or shortened. When the length of the pull rope is stretched longer, the center of gravity of the pull rope is far away from its two fixed ends, so the center of gravity position of the pull rope is easy to fall, affecting the accuracy of the pull rope warning. By providing the support wheel 14, the pull rope can be effectively supported, so that the pull rope is always at a preset height, and a safe response distance is formed between the pull rope and the auxiliary arm mechanism 21 (and the secondary telescopic arm 23), and it is monitored by the detection sensor, which can effectively prevent the boom from directly colliding with the contact network, thereby improving construction safety. The setting position and number of the support wheel 14 can be set according to actual needs.
[0051] Furthermore, the support wheel 14 includes a base, a connecting rod, an upper roller and a lower roller; the base is arranged at the top of the auxiliary arm mechanism 21 and / or the secondary telescopic arm 23; the lower roller is rotatably connected to the base; the upper roller is arranged above the lower roller, and the two are connected by a connecting rod; the first pull rope 27 or the second pull rope 15 slides in the gap between the upper roller and the lower roller. That is, the first pull rope 27 or the second pull rope 15 is placed between a pair of rollers, and the pair of rollers limit the movement of the pull rope relative to the radial direction of the rollers, which is suitable for the situation where the auxiliary arm mechanism 21 has a large pitch range, that is, when the center of gravity of the pull rope moves away from the lower roller, the pull rope can be limited by the upper roller, which further ensures that the pull rope is always in a taut state during the construction process.
[0052] In addition, the detection sensor is a laser sensor, a tension sensor or a pressure sensor. The laser sensor is used to scan whether there is a pull rope within the safety response distance. If there is a pull rope, it means that the pull rope has collided with the contact network, and the laser sensor transmits a signal warning. The tension sensor and the pressure sensor monitor the force on the pull rope. When the pull rope collides with the contact network, the force on the pull rope will suddenly change. By monitoring the tension or pressure of the pull rope, when the tension or pressure of the pull rope suddenly changes, it means that the pull rope has collided with the contact network, and the tension sensor or the pressure sensor transmits a signal warning. Of course, the detection sensor can also be other types of sensors, as long as it can monitor the position change or force change of the pull rope.
[0053] Furthermore, a first grating 11 is provided at the top of the first telescopic arm 24, and a second grating 12 is provided at the top of the second telescopic arm 23. The first grating 11 and the second grating 12 form a grating net. When the contact network falls into the grating net, it means that the contact network is about to collide with the second telescopic arm 23. At this time, the first grating 11 and / or the second grating 12 gives an early warning. In this embodiment, two groups of early warning nets are provided at the first telescopic arm 24 and the second telescopic arm 23. The first pull rope 27 and the second telescopic arm 23 form a safe response distance as the first group of early warning nets, and the first grating 11 and the second grating 12 form a grating net as the second group of early warning nets. The two groups of early warning nets work together to monitor and give early warnings to the contact network.
[0054] It should be noted that the upper limit of the telescopic length of the first pull rope 27 is generally greater than the upper limit of the telescopic length of the second pull rope. This is because the action of the first telescopic arm 24 and the second telescopic arm 23 is telescopic, while the action of the auxiliary arm mechanism 21 and the actuator 17 is pitching. Compared with pitching, telescopic requires a longer distance in the length direction of the main arm mechanism 8. When the extension length of the first telescopic arm 24 and the second telescopic arm 23 is short, the first pull rope 27 is short in length, and it is difficult to deform, which is easy to affect the detection accuracy, thereby causing a safety accident. Under this condition, it can be monitored by the grating network to ensure the detection accuracy of the contact network; when the extension length of the first telescopic arm 24 and the second telescopic arm 23 is long, resulting in a poor grating detection effect, or when the starting light source of the grating is blocked by the existing pipeline 26 cable in the tunnel and cannot form a grating network, under this condition, it can be monitored by the pull rope to ensure the detection accuracy of the contact network. Of course, the pull rope and the grating can also be enabled at the same time, and the pull rope and / or the grating can be installed at each position of the arm of the working device.
[0055] Secondly, a first angle encoder 4 is provided on the rotary platform 6; a second angle encoder 5 is provided on the main arm mechanism 8; a third angle encoder 13 is provided on the auxiliary arm mechanism 21; and a fourth angle encoder 19 is provided on the actuator 17. An angle encoder is a device used to measure and record the angle of an object. Its main function is to convert the angle of the machine movement into an electrical signal for controlling and measuring the system. In this embodiment, the angle encoder is used to calibrate the rotation angle of the corresponding mechanism. The accuracy and reliability of the angle encoder are very high, which can effectively improve the operating stability and accuracy of the corresponding mechanism, realize high-quality bypassing construction of existing line tunnels, including the alarm stop of the boom and the high-precision bypassing operation after the stop, and can also enhance the safety of construction.
[0056] In addition, the second anti-collision detector 16 is detachably connected to the actuator 17, and can be detachably connected by pins or bolts. The actuator 17 is installed according to the actual construction needs, and the actuator 17 includes actuators involved in operations such as concrete roughening, locking foot anchor construction, dowel construction, arch installation, steel bar binding and welding, formwork installation or concrete pouring. After replacing different actuators on the auxiliary arm mechanism 21, the second anti-collision detector 16 can be removed from the original actuator and then installed on the newly replaced actuator for reuse, saving construction costs.
[0057] In this embodiment, the working device is installed on a special flatbed transport vehicle 25 for railway standard transportation during construction. The working device mounted on the flatbed transport vehicle 25 is transported to the lining treatment section by a tractor. The working device's movement posture is calibrated by the working device's detection sensors, gratings and angle encoders. The actuator 17 avoids the construction of existing facilities along the tunnel ring. At the same time, the system automatically identifies the collision risk source and automatically stops the action after the alarm, thereby solving the risk of collision accidents caused by complete reliance on manual observation and the operator's untimely response.
[0058] It should be understood that the above description of the specific embodiments of the utility model is only for illustrating the technical route and features of the utility model, and its purpose is to enable those skilled in the art to understand the content of the utility model and implement it accordingly, but the utility model is not limited to the above specific implementation methods. All changes or modifications made within the scope of the claims of the utility model should be included in the protection scope of the utility model.
Claims
1. A working device for existing tunnel construction, characterized in that: The working device comprises: Sliding platform (1); A rotating platform (6), wherein the rotating platform (6) is mounted on the sliding platform (1), and the sliding platform (1) is capable of driving the rotating platform (6) to move between the inner walls on both sides of the tunnel; A main arm mechanism (8), the main arm mechanism (8) is hinged to the rotating platform (6) and is capable of performing a first pitch; the rotating platform (6) is capable of driving the main arm mechanism (8) to rotate in a horizontal plane; A first-stage telescopic arm (24), the head end of the first-stage telescopic arm (24) being slidably connected to the tail end of the main arm mechanism (8); a first anti-collision detector (10) is provided on the first-stage telescopic arm (24); A secondary telescopic arm (23), the head end of the secondary telescopic arm (23) being slidably connected to the tail end of the primary telescopic arm (24); both the primary telescopic arm (24) and the secondary telescopic arm (23) are capable of telescoping in the length direction of the main arm mechanism (8); A jib mechanism (21), the head end of which is hinged to the tail end of the secondary telescopic arm (23) and is capable of performing a second pitch; An actuator (17), the head end of the actuator (17) being hinged to the tail end of the auxiliary arm mechanism (21) and being capable of swinging around the hinge point; a second anti-collision detector (16) is provided on the tail end of the actuator (17); a first pull rope (27), one end of the first pull rope (27) being connected to the first anti-collision detector (10), and the other end of the first pull rope (27) being connected to the secondary telescopic arm (23); A second pull rope (15), one end of the second pull rope (15) is connected to the auxiliary arm mechanism (21), and the other end is connected to the second anti-collision detector (16); the first pull rope (27) and the second pull rope (15) are arranged away from the sliding platform (1).
2. The working device for existing tunnel construction according to claim 1, characterized in that: The first anti-collision detector (10) and the second anti-collision detector (16) both comprise a detection sensor, a spring and a housing; The housing is mounted on the primary telescopic arm (24) or the actuator (17); The spring is built into the housing; the spring is connected to the first pull rope (27), or the spring is connected to the second pull rope (15); The detection sensor is installed on the shell.
3. The working device for existing tunnel construction according to claim 2, characterized in that: A support wheel (14) is provided at the top end of the auxiliary arm mechanism (21) and / or the secondary telescopic arm (23); the support wheel (14) is slidably connected to the first pull rope (27), or the support wheel (14) is slidably connected to the second pull rope (15).
4. The working device for existing tunnel construction according to claim 3, characterized in that: The supporting wheel (14) comprises a base, a connecting rod, an upper roller and a lower roller; The base is arranged at the top end of the auxiliary arm mechanism (21) and / or the secondary telescopic arm (23); The lower roller is rotatably connected to the base; the upper roller is arranged above the lower roller, and the two are connected by the connecting rod; The first pull rope (27) or the second pull rope (15) slides in the gap between the upper roller and the lower roller.
5. The working device for existing tunnel construction according to claim 2, characterized in that: The detection sensor is a laser sensor, a tension sensor or a pressure sensor.
6. The working device for existing tunnel construction according to any one of claims 1 to 5, characterized in that: The top end of the primary telescopic arm (24) is provided with a first grating (11), and the top end of the secondary telescopic arm (23) is provided with a second grating (12).
7. The working device for existing tunnel construction according to any one of claims 1 to 5, characterized in that: The rotary platform (6) is provided with a first angle encoder (4); the main arm mechanism (8) is provided with a second angle encoder (5); the auxiliary arm mechanism (21) is provided with a third angle encoder (13); and the actuator (17) is provided with a fourth angle encoder (19).
8. The working device for existing tunnel construction according to any one of claims 1 to 5, characterized in that: The second anti-collision detector (16) is detachably connected to the actuator (17).
Citation Information
Cited By
Dabbling device for repairing diseases of operated tunnel
CN115596478A
A chiseling device for repairing a disease of an already operated tunnel
CN115596478B