Auxiliary device for testing speed of low-speed isolation and grounding switch

By designing an isolation and ground switch speed test auxiliary device including mounting plate, rotating shaft and gear mechanism, the problem of slow running speed test of isolation and ground switches in ultra-high voltage power grid is solved, and the speed measurement function with simple structure and low cost is realized. Suitable for a variety of working conditions.

CN221993597UActive Publication Date: 2024-11-12SHANDONG TAIKAI HIGH VOLTAGE SWITCH
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420286137.7
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-02-06
Publication Date
2024-11-12
Estimated Expiration
2034-02-06

AI Technical Summary

Technical Problem

The prior art cannot effectively test the slow running speed of isolation and grounding switches in ultra-high voltage power grids, especially because the isolation and grounding switch body cannot be equipped with linear sensors, and there are two complex operating conditions: single-phase operation and three-phase linkage, which leads to Speed ​​tests are difficult to implement.

Method used

A slow-speed isolation and grounding switch speed test auxiliary device is designed, including a mounting plate, rotating shaft and gear mechanism arranged in parallel. The large output rotation angle is converted into a small output rotation angle by meshing gear, and an angular displacement sensor is installed to achieve speed measurement. Simple, low cost, easy to install, suitable for single-phase and three-phase linked operations.

Benefits of technology

The speed test of isolation and grounding switches is realized, which meets the requirements of various working conditions, avoids the mechanism's external output shaft, reduces the burden on isolation and grounding switches, is low in cost and is convenient to install.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221993597U_ABST
    Figure CN221993597U_ABST
Patent Text Reader

Abstract

The utility model discloses a low speed isolation and grounding switch speed test auxiliary device, and relates to the isolation and grounding switch speed test auxiliary technology field, a left rotating shaft and a right rotating shaft are arranged in parallel between a first installation plate and a second installation plate, the left rotating shaft is provided with a left large gear and a left small gear, the right rotating shaft is provided with a right large gear, and the left small gear is provided with a right small gear. The left small gear is meshed with the right large gear, an internal gear of the isolation and grounding switch is utilized, the large output rotation angle of the isolation and grounding switch is converted into the small output rotation angle by meshing the internal gear of the isolation and grounding switch and utilizing matching of different reference circle gears on the device, and an output shaft is arranged at the end of the right rotation shaft. The speed measurement of the isolation and grounding switch is realized, the design structure is simple, the cost is low, and the processing and the installation are convenient. The installation position of the speed test auxiliary device avoids the mechanism external output shaft, and the speed test auxiliary device is suitable for single-phase operation, three-phase linkage operation isolation and grounding switch speed test.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of isolation and grounding switch speed test auxiliary, in particular to a slow isolation and grounding switch speed test auxiliary device. Background Art

[0002] With the continuous advancement of my country's power system technology, the research and development capabilities of major high-voltage electrical appliance manufacturing companies have been continuously enhanced, the high-voltage switch structure has become more reasonable, and the performance has become more reliable, making my country's ultra-high voltage and high-voltage electrical appliances widely used. The use of ultra-high voltage transmission lines, such as 550kV transmission lines, can not only promote the upgrading of my country's power grid technology, improve the efficiency and economy of long-distance large-capacity transmission, and save transmission corridor resources, but also help to enhance my country's independent innovation capabilities in the power transmission and transformation manufacturing industry. The transmission capacity of ultra-high voltage transmission lines is largely determined by the stability of the power system. The stability of the operation of closed combination electrical isolation and grounding switches plays a key role in the entire ultra-high voltage power supply system.

[0003] The current power grid has put forward higher requirements on the stability of the operation of isolation and earthing switches. The slow isolation and earthing switches equipped with isolation and earthing switches need to have speed test conditions. Since the isolation and earthing switch body cannot be equipped with a linear sensor, the output angle of the isolation and earthing switch exceeds the maximum test angle of the angular displacement sensor installation axis, and the isolation and grounding mechanism has both single-phase operation and three-phase linkage operating conditions, the speed test problem of the isolation and earthing switch has not been solved. Utility Model Content

[0004] In order to overcome the defect that the speed test problem of isolation and grounding switches in the prior art has not been solved, the utility model provides a slow isolation and grounding switch speed test auxiliary device to realize the speed measurement of the isolation and grounding switches. The design structure is simple, the cost is low, and the processing and installation are convenient.

[0005] The technical solution adopted by the utility model to solve its technical problems is: a slow isolation and earthing switch speed test auxiliary device, comprising a first mounting plate and a second mounting plate arranged in parallel, the right sides of the first mounting plate and the second mounting plate are connected by a fixing plate, a left rotating shaft and a right rotating shaft are arranged in parallel between the first mounting plate and the second mounting plate, a left large gear and a left small gear are installed on the left rotating shaft, a right large gear is installed on the right rotating shaft, the left small gear meshes with the right large gear, an output shaft is provided at the end of the right rotating shaft, an angular displacement sensor mounting shaft is installed on the output shaft, and a mounting frame that can be installed on the isolation and earthing switch is fixed on the outer side surface of the first mounting plate.

[0006] As a further improvement of the present invention, the left ends of the first mounting plate and the second mounting plate are provided with fastening bolts capable of fixing the mounting frame.

[0007] As a further improvement of the utility model, the mounting frame is provided with threaded holes for fixing to the isolating and earthing switch.

[0008] As a further improvement of the present invention, the left rotating shaft and the right rotating shaft are respectively mounted on the first mounting plate and the second mounting plate through corresponding bearing seats.

[0009] As a further improvement of the utility model, the fixing plate is fixed to the side surfaces of the first mounting plate and the second mounting plate by tightening bolts.

[0010] As a further improvement of the utility model, the left large gear and the right large gear are hollow gears.

[0011] Compared with the prior art, the utility model has the following beneficial effects: in this scheme, a left rotating shaft and a right rotating shaft are arranged in parallel between the first mounting plate and the second mounting plate, a left large gear and a left small gear are installed on the left rotating shaft, and a right large gear is installed on the right rotating shaft, the left small gear meshes with the right large gear, and the internal gears of the isolating and earthing switch are utilized to mesh with the internal gears of the isolating and earthing switch and utilize the cooperation of gears with different pitch circles on the device to convert the large output angle of the isolating and earthing switch into a small output angle, an output shaft is provided at the end of the right rotating shaft, an angular displacement sensor mounting shaft is installed on the output shaft, and an angular displacement sensor is installed on the angular displacement sensor mounting shaft to realize the speed measurement of the isolating and earthing switch, with a simple design structure, low cost, and convenient processing and installation; the installation position of the speed test auxiliary device avoids the external output shaft of the mechanism, and can be suitable for single-phase operation, three-phase linkage operation isolation and earthing switch speed measurement tests, meeting the requirements of various working conditions. BRIEF DESCRIPTION OF THE DRAWINGS

[0012] The utility model is further described below in conjunction with the accompanying drawings and specific implementation methods.

[0013] Figure 1 The utility model is a structural schematic diagram of a slow isolation and grounding switch speed test auxiliary device.

[0014] Figure 2 It is a schematic diagram of the assembly structure of the speed test auxiliary device and the isolation and earthing switch.

[0015] Figure 3 for Figure 2 Cross-section view of AA.

[0016] In the figure: 1. First mounting plate; 2. Second mounting plate; 3. Fixed plate; 4. Left rotating shaft; 5. Right rotating shaft; 6. Left large gear; 7. Left small gear; 8. Right large gear; 9. Mounting frame; 10. Isolating and grounding switch; 11. Output shaft; 12. Angular displacement sensor mounting shaft; 13. Fastening bolts; 14. Threaded hole; 15. Bearing seat; 16. Tightening bolts. DETAILED DESCRIPTION

[0017] In order to make the technical solution and beneficial effects of the present invention more clearly understood, the present invention is further described in detail below in conjunction with specific embodiments.

[0018] Reference Figures 1 to 3 The embodiment of the utility model discloses a slow isolation and earthing switch speed test auxiliary device, comprising a first mounting plate 1 and a second mounting plate 2 arranged in parallel, the right sides of the first mounting plate 1 and the second mounting plate 2 are connected by a fixing plate 3, a left rotating shaft 4 and a right rotating shaft 5 are arranged in parallel between the first mounting plate 1 and the second mounting plate 2, a left large gear 6 and a left small gear 7 are installed on the left rotating shaft 4, a right large gear 8 is installed on the right rotating shaft 5, the left small gear 7 meshes with the right large gear 8, an output shaft 11 is provided at the end of the right rotating shaft 5, an angular displacement sensor mounting shaft 12 is installed on the output shaft 11, and a mounting bracket 9 that can be mounted on the isolation and earthing switch 10 is fixed on the outer side surface of the first mounting plate 1.

[0019] The left ends of the first mounting plate 1 and the second mounting plate 2 are provided with fastening bolts 13 capable of fixing the mounting frame 9. The mounting frame 9 is provided with threaded holes 14 for fixing to the isolating and earthing switch 10. The fixing plate 3 is fixed to the side surfaces of the first mounting plate 1 and the second mounting plate 2 by tightening bolts 16. The first mounting plate 1 and the mounting frame 9 can also be designed as an L-shaped aluminum plate as a whole.

[0020] A left rotating shaft 4 and a right rotating shaft 5 are arranged in parallel between the first mounting plate 1 and the second mounting plate 2. A left large gear 6 and a left small gear 7 are installed on the left rotating shaft 4, and a right large gear 8 is installed on the right rotating shaft 5. The left small gear 7 meshes with the right large gear 8. By using the internal gear of the isolation and earthing switch 10, the large output angle of the isolation and earthing switch 10 is converted into a small output angle by meshing the internal gear of the isolation and earthing switch 10 and using the cooperation of gears with different pitch circles on the device. The transmission ratio is about 3.26:1. An output shaft 11 is arranged at the end of the right rotating shaft 5. An angular displacement sensor installation shaft 12 is installed on the output shaft 11. An angular displacement sensor is installed on the angular displacement sensor installation shaft 12 to realize the speed measurement of the isolation and earthing switch. The design structure is simple, the cost is low, and the processing and installation are convenient. The installation position of the speed test auxiliary device avoids the external output shaft of the mechanism, which can be applied to the speed measurement test of the isolation and earthing switch of single-phase operation and three-phase linkage operation, and meets the requirements of various working conditions.

[0021] The left rotating shaft 4 and the right rotating shaft 5 are respectively mounted on the first mounting plate 1 and the second mounting plate 2 through corresponding bearing seats 15. The left large gear 6 and the right large gear 8 are hollow gears, which reduces the burden of the device on the isolation and grounding switch 10.

[0022] It should be understood that the specific embodiments described herein are only used to understand the present invention and are not used to limit the present invention. All other embodiments obtained by those skilled in the art without making any creative work are within the scope of protection of the present invention.

Claims

1. A slow isolation and grounding switch speed test auxiliary device, characterized in that: The invention comprises a first mounting plate (1) and a second mounting plate (2) which are arranged in parallel, the right sides of the first mounting plate (1) and the second mounting plate (2) being connected via a fixing plate (3), a left rotating shaft (4) and a right rotating shaft (5) being arranged in parallel between the first mounting plate (1) and the second mounting plate (2), a left large gear (6) and a left small gear (7) being installed on the left rotating shaft (4), a right large gear (8) being installed on the right rotating shaft (5), the left small gear (7) being meshed with the right large gear (8), an output shaft (11) being provided at the end of the right rotating shaft (5), an angular displacement sensor mounting shaft (12) being installed on the output shaft (11), and a mounting frame (9) capable of being mounted on an isolating and earthing switch (10) being fixed on the outer side surface of the first mounting plate (1).

2. A slow isolation and grounding switch speed test auxiliary device according to claim 1, characterized in that: The left ends of the first mounting plate (1) and the second mounting plate (2) are provided with fastening bolts (13) capable of fixing the mounting frame (9).

3. A slow isolation and grounding switch speed test auxiliary device according to claim 2, characterized in that: The mounting frame (9) is provided with a threaded hole (14) for fixing the mounting frame (9) on the isolating and earthing switch (10).

4. A slow isolation and grounding switch speed test auxiliary device according to claim 3, characterized in that: The left rotating shaft (4) and the right rotating shaft (5) are respectively mounted on the first mounting plate (1) and the second mounting plate (2) via corresponding bearing seats (15).

5. A slow isolation and grounding switch speed test auxiliary device according to claim 4, characterized in that: The fixing plate (3) is fixed to the side surfaces of the first mounting plate (1) and the second mounting plate (2) by tightening bolts (16).

6. A slow isolation and grounding switch speed test auxiliary device according to claim 5, characterized in that: The left large gear (6) and the right large gear (8) are hollow gears.