Tower crane internal climbing device with center jacking function
By abolishing the lower inner climbing beam and frame, centralizing the hoisting equipment in the tower body, and adopting an automatic reset crawler structure, the problems of low construction efficiency and high cost of the inner climbing tower crane are solved, and efficient towers in small spaces are achieved The machine hoisting reduces construction costs and time.
Patent Information
- Application Number
- CN202420549399.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-21
- Publication Date
- 2024-11-15
- Estimated Expiration
- 2034-03-21
AI Technical Summary
In high-rise building lifting projects, the construction efficiency of the internal climbing tower crane is low and the labor cost is high. Especially due to the space limitations of the elevator shaft, the internal climbing device cannot be installed, and the lower equipment needs to be transported and installed after each lifting, which increases the cost and time.
设计了一种中心顶升的塔机内爬装置,取消下部内爬梁和框架,直接将内爬底节与建筑物连接,顶升油缸和横梁置于塔身内,采用自动复位爬爪结构,减少人工操作时间,并在塔身内集中顶升设备,适用于小空间电梯井。
All construction in the elevator shaft is achieved, avoiding hole openings, shortening the construction cycle, reducing labor costs and design change time, improving construction efficiency, and suitable for elevator shafts of various sizes.
Smart Images

Figure CN222007121U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of inner climbing of a tower crane, in particular to an inner climbing device of a tower crane with central lifting. Background Art
[0002] In the hoisting project of high-rise buildings, attached tower cranes and internal climbing tower cranes are common lifting equipment. They play a key role in the construction process of buildings. After the tower crane exceeds the independent use height, the attached tower crane is connected to the building through the attachment frame and attachment rod fixed on the tower crane body, and the horizontal force and bending moment of the tower crane are supported by the attachment rod. As the building increases in height, the tower height also needs to increase, and the cost of the tower crane increases greatly.
[0003] The internal climbing tower crane is installed in the elevator shaft of the building or a separate opening of the building through the internal climbing beam, internal climbing bottom section and internal climbing frame fixed on the building after the tower crane exceeds the independent use height. As the building increases in height, the tower crane is gradually raised to meet the lifting requirements by using internal climbing jacking mechanisms such as jacking cylinders. After each jacking of the internal climbing tower crane, the lower internal climbing beam, internal climbing frame, jacking cylinder and accessories must be moved and installed to the top of the building. Transportation and installation are time-consuming and labor-intensive. In addition, due to the limited size of the elevator shaft, the internal climbing device cannot be installed; opening a hole in the building requires modifying the design of the entire construction and adding hidden beams, resulting in low construction efficiency and high labor costs. Utility Model Content
[0004] In order to solve the above problems, that is, to solve the problems raised by the above background technology, the utility model proposes a center-lifting tower crane inner climbing device, which directly connects and fixes the inner climbing bottom section to the building by eliminating the lower inner climbing beam and inner climbing frame; the inner climbing oil cylinder and the lifting crossbeam originally installed on the outside of the tower body are installed in the tower body lifting section for use. The operating space for inner climbing lifting is reduced, and it is suitable for use in small space elevator shafts. In addition, an automatic reset structure for the lifting claw is designed to reduce the lifting time of manual operation and improve work efficiency. The tower body comprises an inner climbing bottom section, a standard section, an inner climbing lower section and an inner climbing upper section, wherein the inner climbing bottom section, the standard section, the inner climbing lower section and the inner climbing upper section are connected by pins, an inner climbing fixing frame and an inner climbing guide frame are sequentially installed on the outer wall of the top of the tower body from top to bottom, the four corners of the inner climbing fixing frame are respectively installed with fourth climbing claws through rotating pins and limiting pins, the inner sides of the front and rear end surfaces of the inner climbing fixing frame are connected with ladders through ladder connecting pieces, and the inner side of the ladder is installed A jacking mechanism is installed, which includes a jacking beam, a jacking cylinder, a second climbing claw, a third climbing claw and a cylinder pin shaft. The third climbing claw is installed on both sides of the jacking cylinder support through a rotating pin shaft and a limit pin shaft, the bottom of the jacking cylinder is connected to the jacking beam through the cylinder pin shaft, the second climbing claw is installed on both sides of the jacking beam through a rotating pin shaft and a limit pin shaft, and the first climbing claw is installed on the four corners of the bottom frame of the inner climbing bottom section through a rotating pin shaft and a limit pin shaft.
[0005] The utility model is further configured as follows: a plurality of screw tighteners are installed on the top ends of the inner climbing bottom section, the inner climbing guide frame and the inner climbing fixed frame.
[0006] The utility model is further configured as follows: a plurality of guide rollers are installed on the inner sides of the four corners of the inner climbing guide frame.
[0007] The utility model is further configured as follows: a plurality of clamping wedge plates are installed on the inner sides of the four corners of the inner climbing fixing frame.
[0008] The utility model is further configured as follows: the first climbing claw and the fourth climbing claw extend into a reserved hole in the elevator shaft.
[0009] The utility model is further configured as follows: the second climbing claw and the third climbing claw can be automatically reset.
[0010] The beneficial technical effects of the utility model are as follows: the utility model concentrates the lifting beam, oil cylinder, ladder and the like in the middle of the upper and lower lifting sections, and can be used in the entire construction process after one assembly, and utilizes the lifting inside the tower body to reduce the working area and the transportation of the lifting equipment; the peripheral equipment is eliminated to minimize the working area, and all of them can be used in the elevator shaft, avoiding opening a hole in the middle of the building, saving the time for design changes and later filling of the hole, and saving labor costs; the climbing claws can be automatically reset, reducing the labor intensity of the workers, shortening the working cycle, and improving work efficiency; the application range is wide, and it is applicable to elevator shafts of large and small sizes. BRIEF DESCRIPTION OF THE DRAWINGS
[0011] Figure 1 Shown is a schematic diagram of the structure of the utility model.
[0012] Figure 2 Shown is a front view of the utility model.
[0013] Figure 3 Shown is a side view of the utility model.
[0014] Figure 4 A schematic diagram of the jacking mechanism structure is shown.
[0015] Figure 5 A schematic diagram of the inner climbing fixed frame structure is shown.
[0016] Figure 6 A schematic diagram of the inner climbing guide frame structure is shown.
[0017] Figure 7 A schematic diagram of the structure of the initial position of the climbing claw is shown.
[0018] Figure 8 A schematic diagram of the rotation structure of the climbing claw is shown.
[0019] Fig. 9 A schematic diagram of the climbing claw resetting structure is shown.
[0020] Figure numerals: 1. inner climbing bottom section, 2. standard section, 3. inner climbing lower section, 4. lifting beam, 5. inner climbing upper section, 6. lifting cylinder, 7. inner climbing guide frame, 8. inner climbing fixed frame, 9. first climbing claw, 10. ladder, 11. second climbing claw, 12. third climbing claw, 13. cylinder pin, 14. fourth climbing claw, 15. screw tensioner, 16. clamping wedge, 17. guide roller, 18. ladder connecting piece, 19. rotating pin, 20. limit pin. DETAILED DESCRIPTION
[0021] Please refer to the attached Figure 1-9Those skilled in the art should understand that these embodiments are only used to explain the technical principles of the present invention and are not intended to limit the protection scope of the present invention.
[0022] The utility model proposes a center-lifting inner climbing device for a tower crane, comprising a tower body, wherein the tower body comprises an inner climbing bottom section 1, a standard section 2, an inner climbing lower section 3 and an inner climbing upper section 5, wherein the inner climbing bottom section 1, the standard section 2, the inner climbing lower section 3 and the inner climbing upper section 5 are connected by pins, and the number of standard sections 2 is determined according to construction needs. The outer wall at the top of the tower body is sequentially installed with an inner climbing fixed frame 8 and an inner climbing guide frame 7 from top to bottom, and the four corners of the inner climbing fixed frame 8 are respectively installed with a fourth climbing claw 14 through a rotating pin 19 and a limit pin 20. When the fourth climbing claw 14 is extended, it rests in a reserved hole in the elevator shaft to withstand the lifting force when the tower crane is lifted. The inner sides of the front and rear end surfaces of the inner climbing fixed frame 8 are connected with a ladder 10 through a ladder connector 18, and the ladder 10 is segmented, and a custom combination is provided according to the climbing height. A lifting mechanism is installed on the inner side of the ladder 10, and the lifting mechanism includes a lifting beam 4, a lifting cylinder 6, a second climbing claw 11, a third climbing claw 12 and a cylinder pin 13. The third climbing claw 12 is installed on both sides of the support of the lifting cylinder 6 through a rotating pin 19 and a limit pin 20, and the bottom of the lifting cylinder 6 is connected to the lifting beam 4 through the cylinder pin 13. The second climbing claw 11 is installed on both sides of the lifting beam 4 through a rotating pin 19 and a limit pin 20, and the first climbing claw 9 is installed at the four corners of the bottom frame of the inner climbing bottom section 1 through a rotating pin 19 and a limit pin 20. When the first climbing claw 9 is extended, it is placed in the reserved hole in the elevator shaft to withstand the vertical force of the tower crane.
[0023] Several screw tighteners 15 are installed on the top of the inner climbing bottom section 1, the inner climbing guide frame 7 and the inner climbing fixed frame 8, and their function is to tighten with the inner side of the elevator shaft to transmit horizontal force and bending moment to the building.
[0024] A plurality of guide rollers 17 are installed on the inner sides of the four corners of the inner climbing guide frame 7 to guide the tower body and keep the tower crane vertical when the tower crane climbs.
[0025] A plurality of clamping wedge plates 16 are installed on the inner sides of the four corners of the inner climbing fixing frame 8. When the tower crane is working, the tower body and the inner climbing fixing frame 8 are tightly combined together to withstand the horizontal force and bending moment when the tower crane is working.
[0026] The first climbing claw 9 and the fourth climbing claw 14 extend into the reserved hole of the elevator shaft. When the first climbing claw 9 and the fourth climbing claw 14 are extended, they are placed in the reserved hole of the elevator shaft to withstand the lifting force when the tower crane is lifted.
[0027] The second climbing claw 11 and the third climbing claw 12 can be automatically reset. For details on the automatic reset process of the second climbing claw 11, see Figure 7 , Figure 8 and Fig. 9 , the initial position of the second climbing claw 11, see Figure 7 : The second climbing claw 11, the rotating pin 19, and the limit pin 20 are all installed on the lifting beam 4. The center of gravity of the second climbing claw 11 is in front of the rotating pin 19. It relies on its own weight and the rear arc to contact with the limit pin 20 to limit the rotation of the second climbing claw 11, so the second climbing claw 11 can withstand the vertical force;
[0028] When the lifting beam 4 rises, Figure 8 , the second climbing claw 11 is separated from the square opening of the ladder 10. When the ladder 10 contacts the ladder surface, the second climbing claw 11 rotates according to the rotating pin 19 under the thrust of the ladder surface, without affecting the rising action of the lifting beam 4;
[0029] The second climbing claw 11 is reset, Fig. 9 , the lifting beam 4 continues to rise, and when the second climbing claw 11 leaves the ladder surface, the second climbing claw 11 relies on its own weight to rotate according to the rotating pin 19, and the rear arc of the second climbing claw 11 contacts the limit pin 20, completing an automatic reset process.
[0030] Internal climbing process:
[0031] S1. Adjust the balance of the tower crane, lift it vertically, and check the hydraulic system and cylinder;
[0032] S2, loosen the clamping wedge 16 of the inner climbing fixing frame 8, and loosen the screw tightener 15 on the inner climbing bottom section 1;
[0033] S3, start the hydraulic system lifting handle, the lifting cylinder 6 extends, and the second climbing claw 11 on the lifting beam 4 is stuck in the square opening of the ladder 10;
[0034] S4. After checking and confirming, continue to extend the lifting cylinder 6, slowly lift the tower crane, and the third climbing claw 12 on the inner climbing section 5 automatically enters the square opening of the ladder 10;
[0035] S5, start the hydraulic system to retract the handle, the lifting cylinder 6 retracts, and the third climbing claw 12 on the inner climbing section 5 contacts and gets stuck with the square opening of the ladder 10;
[0036] S6, continue to retract the jacking cylinder 6, drive the jacking beam 4 to rise, the second climbing claw 11 is separated from the square opening of the ladder 10, and rises to the upper square opening of the ladder 10, completing a jacking cycle;
[0037] S7. After multiple lifting cycles, the tower crane reaches a predetermined height, and the lifting cylinder 6 is slightly retracted to make the first climbing claw 9 effectively contact with the reserved opening of the elevator shaft. The weight of the entire tower crane is borne by the building. The screw tightener 15 on the inner climbing bottom 1 is adjusted to make the inner climbing bottom section 1 contact and tighten with the four walls of the elevator shaft;
[0038] S8. Clamp the clamping wedge 16 on the inner climbing fixed frame 8 to ensure the rigid contact between the tower crane and the inner climbing fixed frame 8. Adjust the screw tightener 15 on the inner climbing fixed frame 8 to make the inner climbing fixed frame 8 contact and tighten with the four walls of the elevator shaft. At this point, the inner climbing process of the tower crane is completed.
[0039] Although the present invention has been described with reference to preferred embodiments, various modifications may be made thereto and parts thereof may be replaced with equivalents without departing from the scope of the present invention. In particular, the various technical features mentioned in the various embodiments may be combined in any manner as long as there is no structural conflict. The present invention is not limited to the specific embodiments disclosed herein, but includes all technical solutions falling within the scope of the claims.
[0040] In the description of the present invention, the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer" and the like indicating directions or positional relationships are based on the directions or positional relationships shown in the drawings, which are only for the convenience of description, and do not indicate or imply that the device or element must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as limiting the present invention. In addition, the terms "first", "second", and "third" are used for descriptive purposes only, and cannot be understood as indicating or implying relative importance.
[0041] In addition, it should be noted that in the description of the present invention, unless otherwise clearly specified and limited, the terms "installation", "connection" and "connection" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For those skilled in the art, the specific meanings of the above terms in the present invention can be understood according to the specific circumstances.
[0042] The term "comprise" or any other similar term is intended to cover a non-exclusive inclusion, such that a process, article, or apparatus / device that includes a list of elements includes not only those elements but also other elements not expressly listed, or elements inherent to such process, article, or apparatus / device.
[0043] So far, the technical solution of the present invention has been described in conjunction with the preferred embodiments shown in the accompanying drawings. However, it is easy for those skilled in the art to understand that the protection scope of the present invention is obviously not limited to these specific embodiments. Without departing from the principle of the present invention, those skilled in the art can make equivalent changes or substitutions to the relevant technical features, and the technical solutions after these changes or substitutions will fall within the protection scope of the present invention.
Claims
1. A central jacking tower crane inner climbing device, comprising a tower body, Features: The tower body comprises an inner climbing bottom section (1), a standard section (2), an inner climbing lower section (3) and an inner climbing upper section (5), wherein the inner climbing bottom section (1), the standard section (2), the inner climbing lower section (3) and the inner climbing upper section (5) are connected via a pin shaft; The outer wall of the top of the tower body is sequentially installed with an inner climbing fixed frame (8) and an inner climbing guide frame (7) from top to bottom, the four corners of the inner climbing fixed frame (8) are respectively installed with fourth climbing claws (14) through rotating pins (19) and limiting pins (20), and the inner sides of the front and rear end surfaces of the inner climbing fixed frame (8) are connected to a ladder (10) through a ladder connecting piece (18); A lifting mechanism is installed inside the ladder (10), and the lifting mechanism comprises a lifting crossbeam (4), a lifting oil cylinder (6), a second climbing claw (11), a third climbing claw (12) and an oil cylinder pin shaft (13); the third climbing claw (12) is installed on both sides of the support of the lifting oil cylinder (6) through a rotating pin shaft (19) and a limit pin shaft (20); the bottom of the lifting oil cylinder (6) is connected to the lifting crossbeam (4) through the oil cylinder pin shaft (13); the second climbing claw (11) is installed on both sides of the lifting crossbeam (4) through a rotating pin shaft (19) and a limit pin shaft (20); The four corners of the bottom frame of the inner climbing bottom section (1) are respectively provided with first climbing claws (9) via rotating pins (19) and limiting pins (20).
2. A center-lift tower crane inner climbing device according to claim 1, Features: A plurality of screw tighteners (15) are installed at the top ends of the inner climbing bottom section (1), the inner climbing guide frame (7) and the inner climbing fixing frame (8).
3. A center-lift tower crane inner climbing device according to claim 1, Features: A plurality of guide rollers (17) are installed on the inner sides of the four corners of the inner climbing guide frame (7).
4. A center-lift tower crane inner climbing device according to claim 1, Features: A plurality of clamping wedge plates (16) are installed on the inner sides of the four corners of the inner climbing fixing frame (8).
5. The inner climbing device of a tower crane with center lifting according to claim 1, Features: The first climbing claw (9) and the fourth climbing claw (14) extend into a reserved hole in the elevator shaft.
6. The inner climbing device of a tower crane with center lifting according to claim 1, Features: The second climbing claw (11) and the third climbing claw (12) can be automatically reset.
Citation Information
Cited By
Integral formwork system and internal climbing tower crane collaborative lifting equipment and lifting method
CN119191126A