Steel pipe butt joint fixing device for sewage construction
By designing a steel pipe docking fixture combining telescopic rods and electric winchs, the problem of steel pipe docking deviation in sewage plant construction is solved, accurate docking and efficient lifting of steel pipes are achieved, and construction efficiency is improved.
Patent Information
- Application Number
- CN202420824631.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-04-19
- Publication Date
- 2024-11-15
- Estimated Expiration
- 2034-04-19
AI Technical Summary
There is a deviation in the docking and fixing of steel pipes during sewage plant construction, which affects the accuracy of welding or flange connections, and requires multiple people to assist, which is inefficient.
A steel pipe docking fixing device including a base plate, a docking mechanism and a lifting assembly is designed. The angle of the support plate is adjusted by a telescopic rod, combined with electric winch, wire rope and motor drive to achieve accurate docking and lifting of the steel pipe.
It improves the accuracy and efficiency of steel pipe docking, reduces labor demand, and improves construction efficiency.
Smart Images

Figure CN222007123U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of pipe construction, in particular to a steel pipe butt fixing device for sewage construction. Background Art
[0002] Sewage refers to the discharged water from life and production that is polluted to a certain extent. Water that has lost its original function is referred to as sewage. It is mainly water used in life. It contains more organic matter and is easier to treat.
[0003] The steel pipes used in sewage treatment plant construction are usually large-diameter steel pipes. The steel pipes are usually fixed by butt welding or flange connection. During the installation process, they are mainly positioned and fixed by manpower. Since some sewage pipes need to have a height difference, that is, they are installed at an angle, deviations are prone to occur during installation, resulting in the inability to connect the steel pipes or inaccurate connection, affecting the accuracy of subsequent welding or flange connection, reducing efficiency, and requiring the assistance of multiple people during the connection process, which is extremely inconvenient. Utility Model Content
[0004] The technical problem to be solved by the utility model is to overcome the above technical defects and provide a steel pipe butt fixing device for sewage construction.
[0005] In order to solve the above problems, the technical solution of the utility model is: a steel pipe docking and fixing device for sewage construction, comprising a bottom plate, a plurality of casters are installed at the bottom of the bottom plate, a docking mechanism is provided at the top, a plurality of columns are fixedly connected to the rear end of the top of the bottom plate, a top plate is fixedly connected to the top of the column, and a hoisting assembly is provided at one side of the bottom of the top plate;
[0006] The docking mechanism comprises two support plates symmetrically arranged above the bottom plate, a plurality of U-shaped frames are installed on the top of the support plates, an angle adjustment assembly is provided at the bottom, a fixed block is fixedly connected in the middle of the U-shaped frame, rollers are installed between the fixed block and the two side walls of the U-shaped frame, a plurality of telescopic rods II are installed on the top of the support plate on one side of the U-shaped frame, a fixed column is fixedly connected to the top of the telescopic rod II, and a movable column for pressing the pipeline is detachably installed on the fixed column;
[0007] The lifting assembly includes two slide rails, the bottom of the slide rails is slidably connected to a mounting plate through a slider, electric winches are installed at the bottom of both ends of the mounting plate, and a steel wire rope is wound on the electric winch, one end of the steel wire rope is connected to a hook, and a lifting rope is installed on the hook, and a driving assembly for driving the mounting plate to move is provided between the two slide rails.
[0008] Furthermore, the angle adjustment assembly includes three groups of telescopic rods, among which the top of a group of telescopic rods close to the end of the base plate is hinged to the support plate, and the bottom is fixedly mounted on the base plate through a positioning seat, and the two ends of the other two groups of telescopic rods are respectively hinged to the support plate and the base plate.
[0009] Furthermore, a mounting tube is fixedly connected to one side of the fixed column, an insertion rod inserted in the mounting tube is fixedly connected to one end of the movable column, and through holes are opened on the mounting tube and the insertion rod, and a positioning pin is inserted in the through hole.
[0010] Furthermore, an arc-shaped groove is provided on the bottom surface of the movable column, and an anti-slip pad is installed in the arc-shaped groove.
[0011] Furthermore, two ends of the sling are fixedly connected with connecting rings, and the connecting rings are sleeved on the hooks.
[0012] Furthermore, the driving assembly includes a rectangular frame, a driving block connected to the mounting plate is provided inside the rectangular frame, and a screw rod penetrating the driving block is rotatably installed inside the rectangular frame, the screw rod is threadedly connected to the driving block, and a motor for driving the screw rod to rotate is installed at one end of the rectangular frame.
[0013] The advantages of the utility model compared with the existing technology are: the utility model can adjust the inclination angle of the support plate through the extension and retraction of the telescopic rod, further realize the adjustment of the angle of the steel pipe, and facilitate the precise docking of two pipelines. The steel pipe can be hoisted by the cooperation of the electric winch, wire rope, hook and lifting rope. The motor drives the installation plate to move, which can realize the precise placement of the steel pipe. It has a high degree of mechanization, saves labor, and improves the docking and fixing efficiency of the pipeline, and is highly practical. BRIEF DESCRIPTION OF THE DRAWINGS
[0014] Figure 1 It is a stereogram of the utility model.
[0015] Figure 2 It is a connection structure diagram of the support plate of the utility model.
[0016] Figure 3 This utility model Figure 2 sectional view of .
[0017] Figure 4 It is a structural diagram of the lifting assembly of the utility model.
[0018] As shown in the figure: 1. Base plate; 2. Casters; 3. Column; 4. Top plate; 5. Support plate; 6. U-shaped frame; 7. Fixed block; 8. Roller; 9. Telescopic rod one; 10. Telescopic rod two; 11. Fixed column; 12. Mounting tube; 13. Movable column; 14. Insert rod; 15. Anti-slip pad 16. Slide rail; 17. Mounting plate; 18. Electric winch; 19. Wire rope; 20. Hook; 21. Lifting rope; 22. Rectangular frame; 23. Drive block; 24. Screw; 25. Motor. DETAILED DESCRIPTION
[0019] The technical solutions in the embodiments of the utility model will be clearly and completely described below in conjunction with the drawings in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, rather than all of the embodiments; based on the embodiments of the utility model, all other embodiments obtained by ordinary technicians in this field without making creative work are within the scope of protection of the utility model.
[0020] like Figures 1 to 3 As shown, a steel pipe docking and fixing device for sewage construction includes a base plate 1, a plurality of casters 2 are installed at the bottom of the base plate 1, a docking mechanism is provided on the top, a plurality of columns 3 are fixedly connected to the rear end of the top of the base plate 1, a top plate 4 is fixedly connected to the top of the columns 3, and a lifting assembly is provided on one side of the bottom of the top plate 4.
[0021] The docking mechanism includes two support plates 5 symmetrically arranged above the base plate 1, a plurality of U-shaped frames 6 are installed on the top of the support plate 5, and an angle adjustment component is provided at the bottom. A fixed block 7 is fixedly connected in the middle of the U-shaped frame 6, and rollers 8 are installed between the fixed block 7 and the two side walls of the U-shaped frame 6. The two rollers 8 are in a V-shaped structure. A plurality of telescopic rods 10 are installed on the top of the support plate 5 on one side of the U-shaped frame 6, and a fixed column 11 is fixedly connected to the top of the telescopic rod 10. A movable column 13 for tightening the pipeline is detachably installed on the fixed column 11, a mounting cylinder 12 is fixedly connected to one side of the fixed column 11, and an insertion rod 14 inserted in the mounting cylinder 12 is fixedly connected to one end of the movable column 13, and through holes are opened on the mounting cylinder 12 and the insertion rod 14, and a positioning pin is inserted in the through hole.
[0022] The angle adjustment assembly includes three groups of telescopic rods 9, among which the top of a group of telescopic rods 9 close to the end of the base plate 1 is hinged to the support plate 5, and the bottom is fixedly installed on the base plate 1 through a positioning seat, and the two ends of the other two groups of telescopic rods 9 are respectively hinged to the support plate 5 and the base plate 1, and the bottom surface of the movable column 13 is provided with an arc groove, and an anti-slip pad 15 is installed in the arc groove.
[0023] The inclination angle of the support plate 5 can be adjusted by the cooperation of the three sets of telescopic rods 9. When the steel pipe is placed above the roller 8, the insertion rod 14 is inserted into the installation tube 12 and fixed by the positioning pin, so that the connection between the movable column 13 and the telescopic rod 10 is realized. The contraction of the telescopic rod 10 makes the movable column 13 press and fix the steel pipe. The anti-skid pad 15 can prevent the steel pipe from rolling on the roller 8. The inclination angle of the support plate 5 is the inclination angle of the steel pipe.
[0024] like Figure 1 and Figure 4As shown, the lifting assembly includes two slide rails 16, and the bottom of the slide rails 16 is slidably connected to a mounting plate 17 through a slider, and electric winches 18 are installed at the bottom of both ends of the mounting plate 17, and a steel wire rope 19 is wound on the electric winch 18, and one end of the steel wire rope 19 is connected to a hook 20, and a lifting rope 21 is installed on the hook 20, and both ends of the lifting rope 21 are fixedly connected with connecting rings, and the connecting ring is sleeved on the hook 20, and a driving assembly for driving the mounting plate 17 to move is provided between the two slide rails 16.
[0025] The driving assembly includes a rectangular frame 22, a driving block 23 connected to the mounting plate 17 is provided inside the rectangular frame 22, and a screw rod 24 penetrating the driving block 23 is rotatably installed inside the rectangular frame 22, the screw rod 24 is threadedly connected to the driving block 23, and a motor 25 for driving the screw rod 24 to rotate is installed at one end of the rectangular frame 22.
[0026] The motor 25 drives the lead screw 24 to rotate, prompting the driving block 23 to drive the mounting plate 17 to move, so as to adjust the position of the electric winch 18. When the electric winch 18 is unwound, the lifting rope 21 can be removed from the hook 20, and the lifting rope 21 is tied to the steel pipe. Then, the connecting ring is set on the hook 20 to connect the wire rope 19 to the steel pipe. When the electric winch 18 is reeled in, the steel pipe can be lifted. The motor 25 drives the mounting plate 17 to move to the top of the U-shaped frame 6. Then, when the electric winch 18 is unwound, the steel pipe on the ground can be lifted onto the roller 8.
[0027] In specific use, when welding the steel pipe to the inclined steel pipe, the bottom plate 1 is moved to the position where the fixed steel pipe and the movable steel pipe need to be connected, and the support plate 5 on the side without the lifting component is located directly below the fixed steel pipe, and then the three sets of telescopic rods 9 are extended to make the rollers 8 abut against the steel pipe, and the angle of one support plate 5 is fixed at this time; the angle of the other support plate 5 can be adjusted according to the inclination angle of the fixed support plate 5 by extending the other three sets of telescopic rods 9, and the two support plates 5 are in the same plane, the motor 25 drives the mounting plate 17 to move outward, and the electric winch 18 is unwound, and the lifting rope 21 is used to realize The movable steel pipe is connected to the steel wire rope 19, and then the electric winch 18 is wound up, and the motor 25 drives the mounting plate 17 to move to the top of the support plate 5, and then the movable steel pipe is placed on the roller 8 on the top of another support plate 5 by unwinding the electric winch 18, and the insertion rod 14 is inserted into the mounting tube 12 and fixed by the positioning pin, and the movable steel pipe is moved along the roller 8, and the movable steel pipe is abutted against the fixed steel pipe, and the three groups of telescopic rods 9 under the movable steel pipe are fine-tuned to align the ends of the movable steel pipe with the fixed steel pipe, and the contraction of the telescopic rod 2 10 causes the movable column 13 to press and fix the movable steel pipe, and the two steel pipes can be welded and fixed at this time.
[0028] The undisclosed parts in the present invention are all prior art, and their specific structures and working principles are not described in detail.
[0029] It should be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device.
[0030] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.
[0031] The above description of the utility model and its implementation methods is not restrictive. The drawings show only one implementation method of the utility model, and the actual structure is not limited thereto. In short, if ordinary technicians in this field are inspired by it and design structural methods and embodiments similar to the technical solution without creativity without departing from the purpose of the invention of the utility model, they should all fall within the protection scope of the utility model.
Claims
1. A steel pipe docking and fixing device for sewage construction, comprising a base plate (1), a plurality of casters (2) are installed at the bottom of the base plate (1), and a docking mechanism is provided at the top, characterized in that: A plurality of columns (3) are fixedly connected to the rear end of the top of the bottom plate (1), a top plate (4) is fixedly connected to the top of the columns (3), and a lifting assembly is provided on one side of the bottom of the top plate (4); The docking mechanism comprises two support plates (5) symmetrically arranged above the bottom plate (1), a plurality of U-shaped frames (6) are installed on the top of the support plates (5), an angle adjustment assembly is provided on the bottom, a fixed block (7) is fixedly connected in the middle of the U-shaped frame (6), rollers (8) are installed between the fixed block (7) and the two side walls of the U-shaped frame (6), a plurality of telescopic rods (10) are installed on the top of the support plate (5) on one side of the U-shaped frame (6), a fixed column (11) is fixedly connected to the top of the telescopic rod (10), and a movable column (13) for pressing the pipeline is detachably installed on the fixed column (11); The hoisting assembly comprises two slide rails (16), the bottom of the slide rails (16) is slidably connected to a mounting plate (17) via a slider, electric winches (18) are installed at the bottom of both ends of the mounting plate (17), and a steel wire rope (19) is wound around the electric winch (18), one end of the steel wire rope (19) is connected to a hook (20), and a hoisting rope (21) is installed on the hook (20), and a driving assembly for driving the mounting plate (17) to move is provided between the two slide rails (16).
2. A steel pipe docking and fixing device for sewage construction according to claim 1, characterized in that: The angle adjustment assembly comprises three groups of telescopic rods (9), wherein the top of a group of telescopic rods (9) close to the end of the base plate (1) is hinged to the support plate (5), and the bottom is fixedly mounted on the base plate (1) through a positioning seat, and the two ends of the other two groups of telescopic rods (9) are respectively hinged to the support plate (5) and the base plate (1).
3. A steel pipe docking and fixing device for sewage construction according to claim 1, characterized in that: One side of the fixed column (11) is fixedly connected to a mounting tube (12), one end of the movable column (13) is fixedly connected to an insertion rod (14) inserted into the mounting tube (12), and through holes are formed on the mounting tube (12) and the insertion rod (14), and a positioning pin is inserted into the through hole.
4. A steel pipe docking and fixing device for sewage construction according to claim 3, characterized in that: The bottom surface of the movable column (13) is provided with an arc-shaped groove, and an anti-slip pad (15) is installed in the arc-shaped groove.
5. The steel pipe docking and fixing device for sewage construction according to claim 1 is characterized by: Both ends of the suspension rope (21) are fixedly connected with connecting rings, and the connecting rings are sleeved on the hook (20).
6. The steel pipe docking and fixing device for sewage construction according to claim 1 is characterized by: The driving assembly comprises a rectangular frame (22), a driving block (23) connected to the mounting plate (17) is arranged inside the rectangular frame (22), a screw rod (24) penetrating the driving block (23) is rotatably mounted inside the rectangular frame (22), the screw rod (24) is threadedly connected to the driving block (23), and a motor (25) for driving the screw rod (24) to rotate is mounted at one end of the rectangular frame (22).