Post-cast strip pre-paving anti-sticking waterproof structure

By using a backstacked reverse sticking waterproof structure in underground projects, and using the combination of mesh cloth and plug-ins, the problem of destroying waterproof coils during the construction of the bottom plate steel bars is solved, achieving more stable waterproof performance and Structural connection strength.

CN222009001UActive Publication Date: 2024-11-15CNNC HUACHEN ENG MANAGEMENT CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202323524649.7
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-12-21
Publication Date
2024-11-15
Estimated Expiration
2033-12-21

AI Technical Summary

Technical Problem

In underground projects, when the prepaving reverse sticking method is used, the waterproof coil is easily damaged during the construction of the bottom plate steel bars, resulting in damage to the waterproof performance.

Method used

The back-painted waterproof structure is adopted for pre-painted back-adhesive waterproof structure, including a coil layer, a sand layer and a grid cloth layer. The grid cloth layer is laid on the surface of the sand layer facing away from the coil layer, used for steel bars to abut, and during the construction process The plug-in positioning and strengthening the connection strength is reduced to reduce the risk of steel bars destroying the coil layer.

Benefits of technology

It effectively reduces the risk of destroying waterproof coils during steel bar construction, enhances the connection strength between the coil layer and the main layer, and ensures the stability of waterproof performance and the strength of the overall structure.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222009001U_ABST
    Figure CN222009001U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of building waterproof engineering, and provides a post-cast strip pre-laying anti-sticking waterproof structure which comprises a coiled material layer, a sand layer and a gridding cloth layer, the sand layer is laid on the coiled material layer, the gridding cloth layer is laid on the surface, away from the coiled material layer, of the sand layer, and the gridding cloth layer is used for abutting against reinforcing steel bars. The method has the effect of reducing the risk that the waterproof roll is damaged in the construction process of the bottom plate reinforcing steel bars.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the field of building waterproof engineering technology, and in particular to a post-cast strip pre-laid anti-adhesive waterproof structure. Background Art

[0002] Underground projects, especially building basements, are usually required to set up post-cast strips when they are long or large in area to solve the problem of cracks caused by hydration shrinkage. The post-cast strips separate the basement floor at a certain distance.

[0003] In engineering practice, after pouring concrete in the post-casting strip, it is usually necessary to lay a layer of waterproof roll on the top for waterproofing. The existing methods of laying waterproof rolls include traditional laying and pre-laying reverse bonding. Among them, traditional laying is to bond the waterproof roll downward to the base layer; pre-laying reverse bonding is to bond the waterproof roll upward to the main body, forming a "skin-type" waterproof, without the risk of water leakage, and the waterproof performance is not affected by the settlement of the main structure, effectively preventing groundwater infiltration.

[0004] However, when using the pre-laid reverse-bonding method, the waterproof membrane is easily damaged during the construction of the bottom plate reinforcement. Utility Model Content

[0005] In order to reduce the risk of damaging the waterproof membrane during the construction of the bottom plate reinforcement, the present application provides a post-cast strip pre-laid anti-adhesive waterproof structure.

[0006] The present application provides a post-casting tape pre-paved reverse adhesive waterproof structure adopts the following technical solution:

[0007] A post-cast strip pre-laid reverse-adhesive waterproof structure comprises a coiled material layer, a sand layer and a mesh cloth layer, wherein the sand layer is laid on the coiled material layer, the mesh cloth layer is laid on the surface of the sand layer away from the coiled material layer, and the mesh cloth layer is used for reinforcement to abut.

[0008] By adopting the above technical solution, during construction, the coiled material layer is first laid on the post-casting strip, and then the isolation paper of the coiled material layer is torn off, and then sand is sprinkled on the coiled material layer to form a sand layer, and then a mesh cloth layer is laid on the sand layer; after laying the mesh cloth layer, steel bars are arranged on the mesh cloth layer, so that the mesh cloth layer is used to protect the coiled material layer, reducing the risk of the coiled material layer being damaged by the steel bars; after the steel bars are arranged, concrete is poured, and the concrete seeps from the pores of the mesh cloth layer into the sand layer, establishing a connection with the coiled material layer, thereby protecting the coiled material layer while ensuring the connection strength between the layers of the main body.

[0009] Optionally, a plurality of connectors are evenly arranged on the surface of the mesh cloth layer facing the sand layer, and the connectors are used to be inserted into the sand layer.

[0010] By adopting the above technical solution, the connector is inserted into the sand layer while laying the mesh cloth layer, so as to position the mesh cloth layer by using the connector, thereby preventing the mesh cloth layer from moving to a large extent during the arrangement of the steel bars.

[0011] Optionally, the plurality of connectors can be detachably connected to the mesh cloth layer.

[0012] By adopting the above technical solution, the storage and transportation of the mesh cloth layer are facilitated, and the installation density and quantity of the connectors can also be determined according to the actual construction situation.

[0013] Optionally, the connector includes an inserting portion and an abutting portion, the inserting portion has a pointed end, and the abutting portion is used to abut against a surface of the mesh cloth layer facing away from the sand layer.

[0014] By adopting the above technical solution, when installing the plug-in component, the plug-in part is inserted into the sand layer through the pointed end, and the abutting part is abutted against the mesh cloth layer. The structure is simple and easy to operate.

[0015] Optionally, the connector is provided with an inner cavity, the inner cavity is extended along the length direction of the connector, and an end of the inner cavity passes through the end surface of the connector away from the coil.

[0016] By adopting the above technical solution, when pouring concrete, the concrete seeps deep into the inner cavity, so that the connector is driven to move toward the coiled material layer under the action of the gravity of the concrete, further strengthening the connection strength between the mesh cloth layer and the sand layer.

[0017] Optionally, a side wall of the connector is provided with a plurality of through holes for concrete to pass through, and the through holes are connected to the inner cavity.

[0018] By adopting the above technical solution, the inner cavity and the through hole are used to provide a channel for concrete, which accelerates the penetration of concrete into the sand layer, and allows the concrete to flow out of the through hole and penetrate into the sand layer to form horizontal solid concrete after solidification, thereby improving the connection strength between the mesh cloth layer and the sand layer.

[0019] Optionally, the mesh cloth layer is provided with two layers, and the mesh cloth layer located at the lower layer is provided with a plurality of plug-in connectors, and the plug-in connectors are used to be inserted into the sand layer.

[0020] By adopting the above technical solution, after pouring concrete, the mesh cloth layer located at the lower layer moves downward at the connection of the connector under the gravity of the concrete in the cavity and the positioning effect of the sand layer, while the mesh cloth layer located at the upper layer forms a certain buoyancy under the buoyancy of the concrete. Finally, after the concrete solidifies, a gap is formed between the two mesh cloth layers and the gap is filled with concrete, thereby strengthening the integrity of the waterproof structure and utilizing the mesh cloth layer located at the upper layer to improve the structural strength of the concrete layer.

[0021] Optionally, it further comprises a steel bar, which is arranged above the mesh cloth layer; the surface of the steel bar facing the sand layer has a plurality of abutment ends, and the abutment ends are sleeved with a flexible sleeve.

[0022] By adopting the above technical solution, the risk of steel bars damaging the coil layer is further reduced.

[0023] In summary, the present application includes at least one of the following beneficial technical effects:

[0024] 1. By setting up a mesh cloth layer, the coil layer is protected to a certain extent, reducing the risk of damaging the coil layer during the laying of steel bars;

[0025] 2. By arranging a connector on the mesh cloth layer, the mesh cloth layer is positioned and the connection strength between the mesh cloth layer and the sand layer is strengthened;

[0026] 3. By opening an inner cavity and a through hole in the connector, the connection strength between the mesh cloth layer and the sand layer is further improved. BRIEF DESCRIPTION OF THE DRAWINGS

[0027] Figure 1 It is a schematic diagram of the structure of an embodiment of the present application.

[0028] Figure 2 It is a schematic diagram used to show the structure of the connector.

[0029] Figure 3 It is a schematic diagram used to show the structure of steel bars.

[0030] Explanation of the accompanying reference numerals: 1. coiled material layer; 2. sand layer; 3. mesh cloth layer; 4. steel bar; 41. abutment end; 42. flexible sleeve; 5. plug-in component; 51. plug-in portion; 52. abutment portion; 53. inner cavity; 54. through hole. DETAILED DESCRIPTION

[0031] The following is combined with Figure 1-3 This application is described in further detail.

[0032] The present application embodiment discloses a post-cast belt pre-paved reverse adhesive waterproof structure. Figure 1A post-cast strip pre-laid reverse-adhesive waterproof structure comprises a roll material layer 1, a sand layer 2, a mesh cloth layer 3 and a steel bar 4. The sand layer 2 is laid on the roll material layer 1, the mesh cloth layer 3 is laid on the surface of the sand layer 2 away from the roll material layer 1, the mesh cloth layer 3 is used for the steel bar to abut, and the steel bar 4 is arranged above the mesh cloth layer 3. During construction, the roll material layer 1 is first laid on the post-cast strip, and then the isolation paper of the roll material layer 1 is torn off, and then sand is sprinkled on the roll material layer 1 to form a sand layer 2, and then the mesh cloth layer 3 is laid on the sand layer 2; after laying the mesh cloth layer 3, the steel bar 4 is arranged on the mesh cloth layer 3, so that the mesh cloth layer 3 is used to protect the roll material layer 1, and the risk of the roll material layer 1 being damaged by the steel bar 4 is reduced; after the steel bar 4 is arranged, concrete is poured, and the concrete penetrates from the pores of the mesh cloth layer 3 into the sand layer 2, and establishes a connection with the roll material layer 1, so as to protect the roll material layer 1 while ensuring the connection strength between the layers of the main body.

[0033] Furthermore, a plurality of connectors 5 are evenly arranged on the surface of the mesh cloth layer 3 facing the sand layer 2, and the connectors 5 are used to be inserted into the sand layer. The connectors 5 are inserted into the sand layer 2 while the mesh cloth layer 3 is being laid, so that the mesh cloth layer 3 can be positioned by using the connectors 5 to avoid a large degree of movement of the mesh cloth layer 3 during the arrangement of the steel bars 4.

[0034] In order to reduce the risk of the connector 5 damaging the coiled material layer 1 , the connector 5 is made of rubber.

[0035] Furthermore, the connector 5 can be detachably connected to the mesh cloth layer 3 to facilitate storage and transportation of the mesh cloth layer 3, and the installation density and number of the connector 5 can also be determined according to actual construction conditions. In other embodiments, the connector 5 can also be fixedly connected to the mesh cloth layer 3, and the fixing method can be adhesive fixing.

[0036] Specifically, the structure of the detachable connection between the plug-in connector 5 and the mesh cloth layer 3 is that the plug-in connector 5 includes a plug-in portion 51 and a contact portion 52, the plug-in portion 51 has a pointed end, and the contact portion 52 is used to contact the surface of the mesh cloth layer 3 away from the sand layer 2. When installing the plug-in connector 5, the plug-in portion 51 is inserted into the sand layer 2 through the pointed end, and the contact portion 52 is contacted with the mesh cloth layer 3. The structure is simple and easy to operate.

[0037] Furthermore, the connector 5 is provided with an inner cavity 53, which extends along the length direction of the connector 5. The end of the inner cavity 53 passes through the end face of the connector 5 away from the coil, so that when pouring concrete, the concrete seeps into the inner cavity 53, thereby driving the connector 5 to move towards the coil layer 1 under the action of the gravity of the concrete, further strengthening the connection strength between the mesh cloth layer 3 and the sand layer 2.

[0038] Furthermore, the side wall of the connector 5 is provided with a plurality of through holes 54 for concrete to pass through, and the through holes 54 are connected with the inner cavity 53, so that the inner cavity 53 and the through holes 54 provide a channel for the concrete, accelerate the penetration of the concrete into the sand layer 2, and make the concrete flow out of the through holes 54 and penetrate into the sand layer 2 to form horizontal solid concrete after solidification, thereby improving the connection strength between the mesh cloth layer 3 and the sand layer 2.

[0039] The surface of the reinforcement member 4 facing the sand layer 2 has a plurality of abutment ends 41 , and the abutment ends 41 are sleeved with flexible sleeves 42 . The flexible sleeves 42 are made of rubber, which further reduces the risk of the reinforcement member 4 damaging the coiled material layer 1 during the laying process.

[0040] In this embodiment, the mesh cloth is provided with two layers, and the plurality of connectors 5 are all provided on the mesh cloth layer 3 located at the lower layer. With this design, after pouring concrete, the mesh cloth layer 3 located at the lower layer moves downward at the connection of the connector 5 under the gravity of the concrete in the cavity and the positioning effect of the sand layer 2, while the mesh cloth layer 3 located at the upper layer forms a certain buoyancy under the buoyancy of the concrete. Finally, after the concrete solidifies, a gap is formed between the two mesh cloth layers 3 and the gap is filled with concrete, thereby strengthening the integrity of the waterproof structure, and using the mesh cloth layer 3 located at the upper layer to improve the structural strength of the concrete layer.

[0041] The implementation principle of pre-laying the anti-adhesive waterproof layer in the post-cast strip according to the embodiment of the present application is as follows: during construction, a coiled material layer 1 is laid in the post-cast strip, and after the laying is completed, the isolation paper of the coiled material layer 1 is torn off; then sand is sprinkled on the coiled material layer 1 to complete the laying of the sand layer 2; then a first mesh cloth layer 3 is laid on the sand layer 2, and the first mesh cloth layer 3 is fixed by the connector 5 during the laying; then a second mesh cloth layer 3 is laid, and after the second mesh cloth layer 3 is laid, a steel bar 4 is laid on top of the mesh cloth layer 3, and it is noted that a flexible sleeve 42 is sleeved on the abutting end 41 of the steel bar 4; after the laying of the steel bar 4 is completed, concrete is poured in the post-cast strip.

[0042] The above are all preferred embodiments of the present application, and the protection scope of the present application is not limited thereto. Therefore, any equivalent changes made according to the structure, shape, and principle of the present application should be included in the protection scope of the present application.

Claims

1. A post-cast belt pre-paved reverse adhesive waterproof structure, characterized in that: The invention comprises a coiled material layer (1), a sand layer (2) and a mesh cloth layer (3), wherein the sand layer (2) is laid on the coiled material layer (1), the mesh cloth layer (3) is laid on a surface of the sand layer (2) facing away from the coiled material layer (1), and the mesh cloth layer (3) is used for abutment of steel bars.

2. The post-cast strip pre-laid reverse-adhesive waterproof structure according to claim 1 is characterized in that: A plurality of plug-in connectors (5) are evenly arranged on the surface of the mesh cloth layer (3) facing the sand layer (2), and the plug-in connectors (5) are used to be inserted into the sand layer (2).

3. The post-cast strip pre-paved reverse-adhesive waterproof structure according to claim 2 is characterized in that: The plurality of connectors (5) can be detachably connected to the mesh fabric layer (3).

4. The post-cast strip pre-paved reverse-adhesive waterproof structure according to claim 3 is characterized in that: The plug-in connector (5) comprises an inserting portion (51) and an abutting portion (52); the inserting portion (51) has a pointed end; and the abutting portion (52) is used to abut against a surface of the mesh cloth layer (3) facing away from the sand layer (2).

5. The post-cast strip pre-laid reverse-adhesive waterproof structure according to claim 2 is characterized in that: The plug connector (5) is provided with an inner cavity (53), the inner cavity (53) extending along the length direction of the plug connector (5), and the end of the inner cavity (53) passes through the end surface of the plug connector (5) away from the coil.

6. The post-cast strip pre-laid reverse-adhesive waterproof structure according to claim 5, characterized in that: The side wall of the connector (5) is provided with a plurality of through holes (54) for concrete to pass through, and the through holes (54) are in communication with the inner cavity (53).

7. The post-cast strip pre-laid reverse-adhesive waterproof structure according to claim 1 is characterized in that: The mesh cloth layer (3) is provided with two layers, and the mesh cloth layer (3) located at the lower layer is provided with a plurality of plug-in connectors (5), and the plug-in connectors (5) are used to be inserted into the sand layer (2).

8. The post-cast strip pre-laid reverse-adhesive waterproof structure according to claim 1 is characterized in that: It also comprises a steel bar (4), the steel bar (4) being arranged above the mesh cloth layer (3); the surface of the steel bar (4) facing the sand layer (2) has a plurality of abutment ends (41), the abutment ends (41) being sleeved with a flexible sleeve (42).