Prefabricated box girder prestressed pipeline positioning device

Through the combination of guide pipe and symmetrical pipe, the clamping and sliding mechanisms are used to achieve alignment of steel bars and end mold holes, solving the problem of difficulty in alignment of steel bars in box beam installation and improving installation efficiency.

CN222021881UActive Publication Date: 2024-11-19CCCC THIRD HARBOR ENGINEERING CO LTD +2
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202421116392.3
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-05-21
Publication Date
2024-11-19
Estimated Expiration
2034-05-21

AI Technical Summary

Technical Problem

During the installation of box beams, the number of steel bars is large and the winding structure is complex, which makes it difficult to install the end molds, and requires a lot of time and manual operations to align the steel bars through the end mold holes.

Method used

Using a device including a guide tube, a symmetrical tube and aligning head, the steel bar and end mold hole are inserted through a symmetrical tube, and the clamping mechanism of the bottom block and the insertion is used to cooperate with the elastic clamping pin and threaded connection to achieve pre-guided alignment of the steel bar and the hole. , simplify the operation process.

Benefits of technology

It greatly improves the efficiency of steel bar perforation, simplifies the end mold installation process, reduces manual operation time, and is suitable for the installation of multiple steel bars.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222021881U_ABST
    Figure CN222021881U_ABST
Patent Text Reader

Abstract

The utility model discloses a precast box girder prestressed pipeline positioning device, which belongs to the field of box girder installation equipment, symmetrical pipes are respectively inserted into holes of end moulds and correspondingly installed reinforcing steel bars, embedding heads slowly slide into embedding grooves by moving aligning heads, preferably, two embedding grooves and two embedding heads are respectively arranged, at the moment, the two symmetrical pipes are coaxial, and the two symmetrical pipes are coaxial. Then the guide pipe penetrates into the hole in the outer side of the end mold, so that when the end part of the guide pipe is located on the outer side of the end mold, the hole of the end mold is communicated with the reinforcing steel bar, and at the moment, the aligning head is loosened, so that one-time pre-guiding connection of the reinforcing steel bar and the hole can be completed, and after all the reinforcing steel bars are aligned with the hole of the end mold through multiple operations, the end mold can be mounted in place; the steel bar perforating device is easy to operate, replaces manual steel bar perforating, improves the perforating efficiency and facilitates installation of the end die.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model belongs to the field of box beam installation equipment, and in particular relates to a prefabricated box beam prestressed pipeline positioning device. Background Art

[0002] Before pouring the box girder, a shell-shaped box girder mold needs to be built. Figure 1 , wherein it is necessary to install the end formwork at the end of the box girder formwork to form a sealed structure. A number of holes are opened on the end formwork for the steel bars to pass through, and on the box girder body, there are a number of transversely extending steel bars that need to pass through the end formwork. Due to the large number of steel bars and the complex winding structure, when installing the end formwork, all the steel bars need to be passed through the holes of the end formwork one by one. Due to the influence of gravity and winding action on the steel bars, the holes and the steel bars cannot be aligned, and the operator needs to manually align them, and then pass all the steel bars through the holes of the end formwork as a whole. This will take a lot of alignment time, and the installation difficulty increases with the increase in the number of steel bars.

[0003] Chinese patent (CN210104573U) discloses a continuous beam end steel bar and prestressed pipe positioning and fixing template device, including a template and a supporting rib mechanism, the template includes an end template, a left web, a right web, a top plate and a bottom plate, a casting chamber surrounded by the left web, the right web and the bottom plate, and the supporting rib mechanism includes a transverse supporting steel bar and a longitudinal supporting steel bar, and the supporting rib mechanism is located in the casting chamber; the edge of the end template is evenly distributed with a number of U-shaped slots, one end of the longitudinal supporting steel bar is connected to the beam end of the continuous beam, and the other end extends out and rests on the U-shaped slot, the transverse supporting steel bars are staggered and connected to the longitudinal supporting steel bars, and the top plate is pressed on the top of the casting chamber. It avoids the problem of low positioning accuracy and difficult fixing of the longitudinal supporting steel bars of the beam body, ensures the overall rigidity and safety of the template, although it assists the alignment of the steel bars, but the alignment method is difficult, which is not conducive to the installation of the end template. Utility Model Content

[0004] In view of this, the purpose of the utility model is to provide a prefabricated box girder prestressed pipeline positioning device, which can align the steel bars with the end mold holes in sequence to facilitate the installation of the end mold.

[0005] In order to achieve the above object, the utility model provides the following technical solutions:

[0006] The utility model comprises a guide tube, two symmetrical tubes and two alignment heads, wherein the outer diameter of the guide tube is smaller than the inner diameter of the symmetrical tube, and the inner diameter is larger than the outer diameter of the steel bar at the end of the box beam, the outer diameter of the symmetrical tube is smaller than the steel bar hole at the end of the box beam template, and the alignment head comprises a bottom block, a U-groove for embedding the end of the symmetrical tube is provided on the bottom block, a pressing block for clamping the symmetrical tube at the bottom of the U-groove is slidably provided on the bottom block, wherein an embedding groove is provided on the bottom block, and an embedding head is fixedly provided on the other bottom block, and when the embedding head is inserted into the embedding groove, the symmetrical tubes clamped by the two bottom blocks are coaxial.

[0007] Furthermore, a vertical rod is provided on a side of the bottom block away from the U groove, a handle is transversely provided at the end of the vertical rod, and a beam handle is vertically slidably provided on the vertical rod, and the beam handle is fixedly connected to the pressing block.

[0008] Furthermore, the notch of the embedding groove tends to converge from the outside to the inside.

[0009] Furthermore, a tapered tube is threadedly connected to the middle section of the guide tube.

[0010] Furthermore, the side wall of the bottom block is provided with a through hole toward the embedding groove, an elastic bayonet is arranged in the through hole, the embedding head is provided with a pin hole at a corresponding position behind the embedding groove, and the outer end of the through hole is threadedly connected with a threaded column that resists the elastic bayonet.

[0011] The beneficial effects of the utility model are:

[0012] The utility model inserts the symmetrical tubes into the holes of the end mold and the corresponding installed steel bars respectively, and the U grooves of the two bottom blocks are respectively moved in from the sides of the two symmetrical tubes. The operator pinches the handle and the beam handle at the same time, and under the traction of the beam handle, the bottom block is pressed by the pressing block to clamp the symmetrical tube, and then the insertion head is slowly slid into the embedding groove by moving the alignment head. Preferably, two embedding grooves and two embedding heads are respectively provided. At this time, the two symmetrical tubes are coaxial, and then the guide tube is deepened from the hole on the outside of the end mold, so that the end of the guide tube can be outside the end mold, and the end mold hole and the steel bar are connected in series. At this time, the alignment head is released to complete a pre-guided connection between the steel bar and the hole. After several operations, all the steel bars are aligned with the end mold holes, and the end mold can be installed in place. Under the guidance of the guide tube, the steel bar can be smoothly sent out of the end mold hole. This device is simple to operate, replaces manual steel bar punching, improves punching efficiency, and is convenient for the installation of the end mold.

[0013] Other advantages, objectives and features of the utility model will be described in the following description and will be apparent to those skilled in the art to some extent, or those skilled in the art can be taught from the practice of the utility model. The objectives and other advantages of the utility model can be realized and obtained through the following description. BRIEF DESCRIPTION OF THE DRAWINGS

[0014] In order to make the purpose, technical solution and beneficial effects of the utility model clearer, the utility model is described with the following drawings:

[0015] Figure 1 This is a schematic diagram of the installation of the box girder end template in the embodiment of the utility model;

[0016] Figure 2 This is a schematic diagram of the installation device docking of the embodiment of the utility model;

[0017] Figure 3 This is a schematic diagram of the installation device of the utility model embodiment;

[0018] Figure 4 This is a cross-sectional view of an alignment head according to an embodiment of the utility model;

[0019] The markings in the attached drawings are as follows: 1. Guide tube; 2. Symmetrical tube; 3. Alignment head; 31. Bottom block; 311. U-groove; 312. Embedded groove; 313. Through hole; 32. Press block; 33. Embedded head; 331. Pin hole; 34. Vertical rod; 35. Handle; 36. Beam handle; 37. Elastic bayonet; 38. Threaded column; 4. Tapered cylinder; 5. Rebar; 6. End mold. DETAILED DESCRIPTION

[0020] like Figures 2 to 4 As shown, the utility model discloses a prefabricated box girder prestressed pipeline positioning device, including a guide pipe 1, two symmetrical pipes 2 and two alignment heads 3, the outer diameter of the guide pipe 1 is smaller than the inner diameter of the symmetrical pipe 2, and the inner diameter is larger than the outer diameter of the box girder end steel bar 5, the outer diameter of the symmetrical pipe 2 is smaller than the steel bar 5 hole of the box girder end mold 6, the alignment head 3 includes a bottom block 31, a U groove 311 for the end of the symmetrical pipe 2 to be embedded is provided on the bottom block 31, a pressing block 32 for clamping the symmetrical pipe 2 at the bottom of the U groove 311 is slidably provided on the bottom block 31, and the bottom A vertical rod 34 is provided on one side of the block 31 away from the U groove 311, and a handle 35 is transversely provided at the end of the vertical rod 34. A beam handle 36 is also vertically slidably provided on the vertical rod 34, and the beam handle 36 is fixedly connected to the pressing block 32. A embedding groove 312 is provided on the bottom block 31, and the notch of the embedding groove 312 tends to converge from the outside to the inside. In this embodiment, the embedding groove 312 is in an acute angle shape. An embedding head 33 is fixedly provided on the other bottom block 31. When the embedding head 33 is inserted into the embedding groove 312, the symmetrical tubes 2 clamped by the two bottom blocks 31 are coaxial.

[0021] The operation method of this scheme is as follows: the symmetrical tubes 2 are respectively inserted into the holes of the end mold 6 and the corresponding installed steel bars 5, and the U grooves 311 of the two bottom blocks 31 are respectively moved in from the sides of the two symmetrical tubes 2. The operator pinches the handle 35 and the beam handle 36 at the same time, and under the traction of the beam handle 36, the bottom block 31 is pressed by the pressing block 32 to clamp the symmetrical tube 2, and then the alignment head 3 is moved to slowly slide the embedding head 33 into the embedding groove 312. Preferably, two embedding grooves 312 and two embedding heads 33 are respectively provided. At this time, the two symmetrical tubes 2 coaxially, and then the guide tube 1 is inserted deeply from the hole outside the end mold 6, so that when the end of the guide tube 1 is outside the end mold 6, the hole of the end mold 6 is connected with the steel bar 5. At this time, the alignment head 3 is loosened to complete the pre-guided connection between the steel bar 5 and the hole. After several operations, all the steel bars 5 are aligned with the holes of the end mold 6, and the end mold 6 can be installed in place. Under the guidance of the guide tube 1, the steel bar 5 can be smoothly sent to the hole of the end mold 6. This device is simple to operate, replaces manual steel bar 5 punching, improves punching efficiency, and facilitates the installation of the end mold 6.

[0022] For further solutions, refer to Figure 3 The middle section of the guide tube 1 is threadedly connected to a tapered tube 4. By setting the tapered tube 4, the middle section of the guide tube 1 can be fixed in the hole position of the end mold 6 to prevent the guide tube 1 from being pushed out during the punching process of the steel bar 5.

[0023] In a further solution, Figure 4 As shown, the side wall of the bottom block 31 is provided with a through hole 313 in the direction of the embedding groove 312, and an elastic bayonet 37 is arranged in the through hole 313. The embedding head 33 is provided with a pin hole 331 at a corresponding position behind the embedding groove 312, and a threaded column 38 is threadedly connected at the outer end of the through hole 313 to resist the elastic bayonet 37. Through the clamping of the elastic bayonet 37, when aligning the symmetrical tubes 2 and inserting the guide tube 1, the two coaxial symmetrical tubes 2 can be temporarily fixed to assist the smooth insertion of the guide tube 1, and finally, by rotating the threaded column 38, the elastic bayonet 37 can be loosened and the alignment head 3 can be removed.

[0024] Finally, it should be noted that the above preferred embodiments are only used to illustrate the technical solution of the utility model rather than to limit it. Although the utility model has been described in detail through the above preferred embodiments, those skilled in the art should understand that various changes can be made in form and details without departing from the scope defined by the claims of the utility model.

Claims

1. A prefabricated box girder prestressed pipeline positioning device, characterized in that: The invention comprises a guide tube (1), two symmetrical tubes (2) and two alignment heads (3); the outer diameter of the guide tube (1) is smaller than the inner diameter of the symmetrical tube (2), and the inner diameter is larger than the outer diameter of the steel bar (5) at the end of the box beam; the outer diameter of the symmetrical tube (2) is smaller than the steel bar (5) hole of the plate of the box beam end mold (6); the alignment head (3) comprises a bottom block (31); a U groove (311) is provided on the bottom block (31) for the end of the symmetrical tube (2) to be embedded; a pressing block (32) is slidably provided on the bottom block (31) for clamping the symmetrical tube (2) at the bottom of the U groove (311); an embedding groove (312) is provided on the bottom block (31); an embedding head (33) is fixedly provided on the other bottom block (31); when the embedding head (33) is inserted into the embedding groove (312), the symmetrical tubes (2) clamped by the two bottom blocks (31) are coaxial.

2. The prefabricated box girder prestressed pipe positioning device according to claim 1 is characterized in that: A vertical rod (34) is provided on a side of the bottom block (31) away from the U groove (311), a handle (35) is transversely provided at the end of the vertical rod (34), and a beam handle (36) is vertically slidably provided on the vertical rod (34), and the beam handle (36) is fixedly connected to the pressing block (32).

3. The prefabricated box girder prestressed pipe positioning device according to claim 1 is characterized in that: The notch of the embedding groove (312) tends to converge from the outside to the inside.

4. The prefabricated box beam prestressed pipe positioning device according to claim 1 is characterized in that: The middle section of the guide tube (1) is threadedly connected to a tapered cylinder (4).

5. The prefabricated box girder prestressed pipe positioning device according to claim 1 is characterized in that: A through hole (313) is formed on the side wall of the bottom block (31) in the direction of the embedding groove (312), an elastic bayonet (37) is arranged in the through hole (313), a pin hole (331) is formed at a corresponding position behind the embedding groove (312), and a threaded column (38) is threadedly connected to the outer end of the through hole (313) for resisting the elastic bayonet (37).