Concrete guardrail drilling pedestal

By designing a concrete guardrail drilling base, using the combination of positioning plates and sliding components, the problems of drilling bit offset and hole inclination are solved, the accuracy and safety of drilling are achieved, and the repeated operations and operations of construction workers are reduced. Face damage risk.

CN222021921UActive Publication Date: 2024-11-19GUANGDONG PROVINCIAL ARCHITECTURAL ENG MACHINERY CONSTR
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202323261200.6
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-11-30
Publication Date
2024-11-19
Estimated Expiration
2033-11-30

AI Technical Summary

Technical Problem

During the drilling process of concrete guardrails, the drill bit is prone to offset, resulting in the inclination of the hole, which is difficult to meet the needs of later installation, and is accompanied by high safety risks.

Method used

A concrete guardrail drilling pedestal is designed, including two main beams and a table plate. Through the spacing adjustment of the first positioning plate and the second positioning plate and the use of sliding components, the drill bit is ensured to be stable and accurate, and combined with the suction cup. and buffer blocks reduce vibration impacts, ensuring accuracy and safety of drilling.

Benefits of technology

It effectively avoids drill bit offset and hole inclination problems, improves drilling accuracy and safety, reduces repeated operations by construction personnel, and reduces the risk of damage on the work surface.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222021921U_ABST
    Figure CN222021921U_ABST
Patent Text Reader

Abstract

The utility model relates to a concrete guardrail drilling pedestal which comprises two main beams and a bedplate, and in the first direction, the two main beams are arranged in a spaced mode; the two ends of the platen are arranged on the two main beams in a sleeving mode respectively, and the platen can move on the two main beams in the second direction; a first positioning plate and a second positioning plate, wherein through holes are formed in the first positioning plate and the second positioning plate; the first positioning plate and the second positioning plate are arranged in a spaced mode in the second direction. The first positioning plate is fixedly connected between the two main beams, the second positioning plate is fixedly connected to the bedplate, the first connecting piece is fixed on the main beams, the second connecting piece is fixed on the bedplate, and the connecting rod is connected with the first connecting piece and the second connecting piece. And the first connecting piece and the second connecting piece are connected through the connecting rod, so that the problem that a hole is inclined due to the fact that the drill bit is easy to deviate during punching is solved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of drilling rigs, in particular to a concrete guardrail drilling pedestal. Background Art

[0002] In industry and daily life, drilling tools are often used for drilling, such as construction drilling, exploration drilling, and wall drilling when installing air conditioners and other equipment in life. The drilling methods include water drill drilling and ordinary drilling. Ordinary drilling needs to be carried out on a soft substrate, with slow drilling speed and low drilling efficiency; water drill drilling can be used on a hard substrate, and the drilling speed is faster than ordinary drilling; water drill drilling uses water as a coolant, which can effectively reduce dust and protect the working environment, and is widely used. When drilling holes in concrete guardrails, water drills are used. First, the drill bit is placed at the location where the hole needs to be drilled, and then the water drill rig is started. Since the drill bit is a hollow structure and the working surface of the building / construction beam (such as concrete guardrail) is smooth, it is difficult to grasp the positioning and stability of the drill bit at the beginning of drilling. Therefore, it is easy for the drilling position to be inaccurate or the drill bit to be loosely fixed, resulting in deviations in the drilling position. The holes drilled by the drill bit are easy to deviate, and inclined holes are easy to be produced, which cannot meet the needs of later device installation. Subsequently, construction personnel are required to repeatedly start the drill several times, resulting in damage to the working surface, and accompanied by higher safety risks. Utility Model Content

[0003] One of the purposes of the utility model is to provide a concrete guardrail drilling pedestal to solve the problem that the drill bit of the existing drilling rig is easily offset when drilling, resulting in the hole being tilted.

[0004] In order to achieve the above purpose, the technical solution adopted by the utility model is as follows:

[0005] A concrete guardrail drilling pedestal comprises two main beams and a platform, wherein the two main beams are spaced apart in a first direction; two ends of the platform are respectively sleeved on the two main beams, and the platform can move on the two main beams along a second direction;

[0006] A first positioning plate and a second positioning plate, wherein the first positioning plate and the second positioning plate are both provided with through holes; the first positioning plate and the second positioning plate are parallel to each other, and the first positioning plate and the second positioning plate are spaced apart along a second direction; the first positioning plate is fixedly connected between the two main beams, the second positioning plate is fixedly connected to the table top, and the plane where the second positioning plate is located is perpendicular to the plane where the table top is located;

[0007] It also includes a first connecting member, a second connecting member and a connecting rod, wherein the first connecting member is fixed on the main beam, the second connecting member is fixed on the table plate, and the first connecting member and the second connecting member are connected by the connecting rod;

[0008] The first direction and the second direction are perpendicular to each other.

[0009] According to the above technical solution, the two main beams are used to support the table plate, and the table plate can move in the first direction along the main beams. The first positioning plate is fixed between the two main beams, and the second positioning plate is fixed on the table plate. The distance between the first positioning plate and the second positioning plate can be adjusted and can be adaptively changed according to the width of the concrete guardrail to adapt to concrete guardrails of different widths.

[0010] At the same time, the utility model is provided with a first connecting member, a second connecting member and a connecting rod. The first connecting member is fixed on the main beam, the second connecting member is fixed on the table plate, and the first connecting member and the second connecting member are connected by a connecting rod, which is used to fix the first positioning plate and the second positioning plate to facilitate drilling work.

[0011] Furthermore, it also includes a sliding component, which is arranged in the table and can move along a third direction; wherein the third direction is perpendicular to the first direction and the second direction.

[0012] Furthermore, the sliding assembly includes a frame, a roller and an adjustment assembly, the roller is rollingly connected to the frame, and the roller can extend out of the table to drive the table to move; the adjustment assembly is connected to the side of the frame away from the roller, and is used to drive the frame to move along the third direction.

[0013] According to the above technical solution, by installing the roller at the bottom of the frame, when the sliding assembly moves upward, the roller is stored in the table and no longer contacts the top of the concrete guardrail, which is convenient for the subsequent first positioning plate and the second positioning plate to clamp the concrete guardrail; when the sliding assembly moves downward, the roller extends out of the table and contacts the top of the concrete guardrail, which is convenient for movement. At the same time, the movement of the roller can be counted by the circle counter, which is convenient for drilling according to the preset movement distance.

[0014] Furthermore, the sliding assembly also includes a circle counter, a support and a transmission rod, the circle counter is connected to the frame via the support, one end of the transmission rod is connected to the circle counter, and the other end of the transmission rod is eccentrically connected to one of the rollers.

[0015] According to the above technical solution, by connecting the circle counter with the roller, when the roller rotates, it can drive the circle counter to count. During construction, the staff can determine the distance moved by the sliding component by observing the value on the circle counter, so as to achieve the purpose of drilling according to the preset distance.

[0016] Furthermore, the adjustment assembly includes a support rod, a clamping piece and a clamping block, one end of the support rod is rotatably connected to the frame, the other end of the support rod is fixedly connected to the clamping piece, the clamping block is fixedly mounted on the table, and the clamping piece can be clamped with the clamping block.

[0017] According to the above technical solution, the support rod is installed on the frame, and the support rod can rotate on the frame. At the same time, the top of the support rod is fixedly connected to the clamping piece, and the clamping piece can be clamped into the clamping hole or the clamping block. When the clamping piece is clamped into the clamping hole, the roller extends out from the bottom of the table; when the clamping piece is clamped into the clamping block, the roller retracts to the inside of the table.

[0018] Furthermore, a clamping hole is provided on the table plate at a position corresponding to the clamping piece, and the clamping piece extends out of or retracts into the table plate through the clamping hole; and the clamping piece can be clamped with the clamping hole.

[0019] Furthermore, it also includes three or more adjustment rods, each of which is distributed around the table top, and the adjustment rods are used to adjust the horizontal state of the table top.

[0020] According to the above technical solution, an adjusting rod is provided to adjust the table top, so as to adjust the table top to a horizontal state.

[0021] Furthermore, a suction cup is provided at the bottom of each adjusting rod.

[0022] By setting the suction cup, which is a rubber suction cup, it will be adsorbed on the top of the concrete guardrail, increasing the stability of the entire device and reducing the vibration impact generated when the drilling rig is working.

[0023] Furthermore, a level ruler is provided on the table top, and the level ruler is used to judge the horizontal state of the table top.

[0024] According to the above technical solution, the problem of imbalance on the top of the concrete guardrail is effectively solved by setting a level ruler, thereby ensuring the balance of the entire drilling platform.

[0025] Furthermore, buffer blocks are provided on the first positioning plate and the second positioning plate on the sides close to each other.

[0026] According to the above technical solution, a buffer block is provided to reduce the vibration effect generated during the drilling process.

[0027] Beneficial effects of the utility model:

[0028] The utility model uses two main beams to support a table plate, and the table plate can move in a first direction along the main beams. The first positioning plate is fixed between the two main beams, and the second positioning plate is fixed on the table plate. When drilling holes in the concrete guardrail, the first positioning plate and the second positioning plate are respectively located on both sides of the concrete guardrail, and the distance between the first positioning plate and the second positioning plate can be adjusted. The first connecting member, the second connecting member and the connecting rod are used to clamp and fix the first positioning plate and the second positioning plate according to the width of the concrete guardrail.

[0029] By opening through holes on the first positioning plate and the second positioning plate, when the drill bit passes through the through holes during use, the through holes on the first positioning plate / the second positioning plate can guide the drill bit, thereby preventing the drill bit from being misaligned during the drilling operation and facilitating drilling. BRIEF DESCRIPTION OF THE DRAWINGS

[0030] Figure 1 This is a schematic diagram of the structure of the concrete guardrail drilling pedestal of the utility model in the use state when it spans the concrete guardrail;

[0031] Figure 2 It is a schematic diagram of the overall structure of the concrete guardrail drilling pedestal of the utility model in one direction;

[0032] Figure 3 This is a cross-sectional view of the overall structure of the concrete guardrail drilling pedestal of the utility model from another direction;

[0033] Figure 4 The utility model is a concrete guardrail drilling pedestal Figure 3 Schematic diagram of the structure of part A;

[0034] Figure 5 The utility model is a concrete guardrail drilling pedestal Figure 3 Schematic diagram of the structure of part B;

[0035] Figure 6 It is a partial schematic diagram of the drilling pedestal of the concrete guardrail of the utility model;

[0036] Figure 7 The utility model is a concrete guardrail drilling pedestal Figure 6 Schematic diagram of the structure of part C;

[0037] Figure 8 It is a schematic diagram of the local structure of the drilling pedestal of the concrete guardrail of the utility model;

[0038] Fig. 9 The utility model is a concrete guardrail drilling pedestal Figure 8 Schematic diagram of the structure of part D.

[0039] Among them, the main beam 1, the table plate 2, the clamping hole 201, the first positioning plate 3, the second positioning plate 4, the through hole 5, the first connecting member 6, the second connecting member 7, the connecting rod 8, the frame 901, the roller 902, the adjustment component 903, the support rod 9031, the clamping member 9032, the clamping block 9033, the level 10, the buffer block 11, the adjustment rod 12, the suction cup 121, the circle counter 13, the pillar 14, and the transmission rod 15. DETAILED DESCRIPTION

[0040] The following will describe the implementation of the present invention with reference to the accompanying drawings and preferred embodiments. Those skilled in the art can easily understand other advantages and effects of the present invention from the contents disclosed in this specification. The present invention can also be implemented or applied through other different specific implementations, and the details in this specification can also be modified or changed in various ways based on different viewpoints and applications without departing from the spirit of the present invention. It should be understood that the preferred embodiments are only for illustrating the present invention, not for limiting the scope of protection of the present invention.

[0041] It should be noted that the illustrations provided in the following embodiments are only schematic illustrations of the basic concept of the present invention, and thus the drawings only show components related to the present invention rather than being drawn according to the number, shape and size of components in actual implementation. In actual implementation, the type, quantity and proportion of each component may be changed at will, and the component layout may also be more complicated.

[0042] This embodiment provides a concrete guardrail drilling pedestal, such as Figure 1 , Figure 2 and Figure 4 As shown, it includes two main beams 1 and a platform 2. Figure 2 As shown, in the first direction, two main beams 1 are arranged at intervals; both ends of the platform 2 are respectively mounted on the two main beams 1, and the platform 2 can move on the two main beams 1 along the second direction.

[0043] The first positioning plate 3 and the second positioning plate 4 are both provided with a through hole 5. When the drill bit passes through the through hole 5, the through hole 5 can guide the drill bit to avoid the drill bit from deflecting during the drilling work, which is convenient for drilling. The first positioning plate 3 and the second positioning plate 4 are parallel to each other, and the first positioning plate 3 and the second positioning plate 4 are spaced apart along the second direction; the first positioning plate 3 is fixedly connected between the two main beams 1, and the second positioning plate 4 is fixedly connected to the table 2, and the plane where the second positioning plate 4 is located is perpendicular to the plane where the table 2 is located; it also includes a first connecting member 6, a second connecting member 7 and a connecting rod 8, the first connecting member 6 is fixed on the main beam 1, the second connecting member 7 is fixed on the table 2, and the first connecting member 6 and the second connecting member 7 are connected by the connecting rod 8; as a preferred embodiment, the first connecting member 6 and the second connecting member 7 of the utility model are bolts, and the second connecting member 7 is a screw; wherein the first direction and the second direction are perpendicular to each other.

[0044] In the present invention, two main beams 1 are used to support the platform 2. Figure 2 As shown, the platform 2 can move on the main beam 1, the first positioning plate 3 is fixed between the two main beams 1, and the second positioning plate 4 is fixed on the platform 2. When the platform 2 moves and adjusts, the spacing between the first positioning plate 3 and the second positioning plate 4 is also adjusted accordingly. By changing the position of the platform 2, the platform 2 can be adaptively changed according to the width of the concrete guardrail to adapt to concrete guardrails of different widths. At the same time, the first connecting member 6 is fixed on the main beam 1, and the second connecting member 7 is fixed on the platform 2. The first connecting member 6 and the second connecting member 7 are connected by a connecting rod 8, which is used to fix the first positioning plate 3 and the second positioning plate 4 to facilitate subsequent drilling work.

[0045] Furthermore, the utility model also includes a sliding assembly, which is arranged in the table 2, such as Figure 2 , Figure 6 , Figure 7 and Figure 8 As shown, the sliding assembly can move along the third direction (that is, the sliding assembly can be adjusted up and down in the platform 2); wherein the third direction is perpendicular to the first direction and the second direction. The utility model installs the sliding assembly in the platform 2, and the sliding assembly moves to drive the platform to move, so that the main beam 1 and the platform 2 can move along the length direction of the concrete guardrail, and multiple holes can be drilled quickly.

[0046] Furthermore, if Figure 6As shown, the sliding assembly includes a frame 901, a roller 902 and an adjusting assembly 903. The roller 902 is installed at the bottom of the frame 901, and the roller 902 can extend out of the platform 2. When the roller 902 extends out of the platform 2, it contacts the top surface of the concrete guardrail, which is convenient for movement and distance measurement. When in use, the roller 902 can extend out of the platform 2 and contact the upper surface of the concrete guardrail to drive the platform 2 to move. The adjusting assembly 903 is connected to the side of the frame 901 away from the roller 902 (that is, the adjusting assembly 903 is connected to the top of the frame 901), and is used to drive the frame 901 to rise or fall. When the adjusting assembly 903 is lifted, the frame 901 and the roller 902 can be driven to move upward.

[0047] Furthermore, if Figure 5 and Figure 7 As shown, the adjustment component 903 includes a support rod 9031, a clamping piece 9032 and a clamping block 9033. One end of the support rod 9031 is rotatably connected to the frame 901 (i.e., the bottom end of the support rod 9031 is rotatably connected to the upper surface of the frame 901), and the support rod 9031 can rotate on the frame 901; the other end of the support rod 9031 is fixedly connected to the clamping piece 9032 (i.e., the top of the support rod 9031 is fixedly connected to the clamping piece 9032). Of course, it can be understood that the support rod 9031 can also be an integrally formed structure with the clamping piece 9032; the clamping block 9033 is fixedly installed on the table 2, and the clamping piece 9032 can be clamped with the clamping block 9033. The support rod 9031 is installed on the frame 901, and the support rod 9031 can rotate on the frame 901. At the same time, the top of the support rod 9031 is fixedly connected to the clamping member 9032. The top of the platform 2 is provided with a clamping hole 201. The clamping member 9032 extends out or retracts into the platform 2 through the clamping hole 201, and the clamping member 9032 can be clamped with the clamping hole 201. The clamping member 9032 can be clamped into the clamping hole 201 or the clamping block 9033. When the clamping member 9032 is clamped into the clamping hole 201, the roller 902 extends out from the bottom of the platform 2, and the roller 902 contacts the top of the concrete guardrail; when the clamping member 9032 is clamped into the clamping block 9033, the roller 902 retracts into the inside of the platform 2, and the roller 902 no longer contacts the top of the concrete guardrail.

[0048] As a preferred embodiment, Fig. 9As shown, the sliding assembly also includes a circle counter 13, a support 14 and a transmission rod 15. The circle counter 13 is connected to the frame 901 through the support 14. Specifically, the circle counter 13 is located above the table 2, one end of the transmission rod 15 is connected to the circle counter 13, and the other end of the transmission rod 15 is eccentrically connected to one of the rollers 902. It should be noted that the utility model adopts four rollers 902 installed at the bottom of the frame 901. The roller 902 connected to the other end of the transmission rod 15 is a directional wheel, and the other three rollers 902 are not limited. The other three rollers 902 can be directional wheels or universal wheels. By eccentrically connecting the circle counter 13 to the roller 902, when the roller 902 rotates, the circle counter 13 can be driven to count through the transmission rod 15. During construction, the staff can determine the distance moved by the roller 902 by observing the value on the circle counter 13. (In the early stage of debugging the circle counter 13, it is necessary to calculate the value of the circle counter jumping every meter forward based on the circumference of the roller 902) to achieve the purpose of drilling at a preset distance. By pushing the table 2 to move and observing the changes in the value on the circle counter 13, fast fixed-distance drilling can be achieved.

[0049] As a preferred embodiment, Figure 2 and Figure 3 As shown, a level ruler 10 is also provided on the platform 2, and the level ruler 10 is used to determine the horizontal state of the platform 2. Figure 6 As shown, it also includes more than three adjustment rods 12, each of which is distributed around the table 2, and the adjustment rods 12 are used to adjust the horizontal state of the table 2. As an exemplary embodiment, the utility model has four adjustment rods 12, which are respectively located around the table 2. The adjustment rods 12 can adjust the horizontal height of the table 2 and are used to adjust the table 2 to a horizontal state. As an exemplary embodiment, the adjustment rod 12 is a screw rod, and the adjustment rod 12 is threadedly connected to the table 2. When the adjustment rod 12 is rotated, the screw rod can move upward or downward, thereby adjusting the horizontal state of the table 2; of course, it can be understood that the adjustment rod 12 can also be other structures that can achieve horizontal adjustment of the table 2.

[0050] Furthermore, if Fig. 9 As shown, a suction cup 121 is also provided at the bottom of each adjusting rod 12. The suction cup 121 is a rubber suction cup 121, which is adsorbed on the top of the concrete guardrail to increase the stability of the entire device and reduce the vibration effect generated when the drilling rig is working.

[0051] As a preferred embodiment, a buffer block 11 is provided on the first positioning plate 3 and the second positioning plate 4 on the side close to each other. The suction cup 121 and the buffer block 11 can reduce the vibration effect generated during the drilling process and avoid the deviation of the hole.

[0052] During the implementation of the utility model, the device is placed across the concrete guardrail, the first positioning plate 3 and the second positioning plate 4 are respectively located on both sides of the concrete guardrail, and the clamping piece 9032 is adjusted to be clamped into the clamping hole 201. At this time, the roller 902 extends out from the bottom of the platform 2, and the roller 902 is used to contact the top of the concrete guardrail, which is convenient for moving the device. At the same time, when the directional wheel is moving, each rotation of the directional wheel drives the counter to count. The staff and workers only need to watch the value of the circle counter turn to the indicated value to stop the platform 2, and can drill holes equidistantly along the length of the concrete guardrail. It is particularly suitable for long-distance drilling, such as drilling concrete guardrails on highways; when the device moves to the specified position, the clamping piece 9032 is clamped into the clamping block 9033, and the roller 902 is retracted to the inside of the table 2, and the roller 902 no longer contacts the top of the concrete guardrail; the adjusting rod 12 is turned to make the suction cup 121 at the bottom of the adjusting rod 12 contact the upper surface of the concrete guardrail, and observe whether the level ruler 10 is in a horizontal state. At the same time, the adjusting rod 12 is adjusted, and the bubble of the level ruler 10 is centered according to the bubble of the level ruler 10 set on the table 2 to prevent the device from tilting. Next, the connecting rod 8 is manually adjusted to adjust the distance between the first positioning plate 3 and the second positioning plate 4, so that the first positioning plate 3 and the second positioning plate 4 are tightly attached to the two sides of the concrete guardrail and fixed; by passing the drill bit through the through hole 5, the through hole 5 can limit the drill bit, so as to prevent the drill bit from deviating during the drilling process and causing the hole to tilt.

[0053] The above embodiments are only preferred embodiments for fully illustrating the present invention, and the protection scope of the present invention is not limited thereto. Any equivalent substitution or modification made by a person skilled in the art based on the present invention is within the protection scope of the present invention.

Claims

1. A concrete guardrail drilling pedestal, characterized in that: include: Two main beams (1) and a platform (2), wherein the two main beams (1) are spaced apart in a first direction; two ends of the platform (2) are respectively sleeved on the two main beams (1), and the platform (2) can move on the two main beams (1) along a second direction; A first positioning plate (3) and a second positioning plate (4), wherein the first positioning plate (3) and the second positioning plate (4) are both provided with a through hole (5); the first positioning plate (3) and the second positioning plate (4) are parallel to each other, and the first positioning plate (3) and the second positioning plate (4) are spaced apart along a second direction; the first positioning plate (3) is fixedly connected between the two main beams (1), the second positioning plate (4) is fixedly connected to the platform (2), and the plane where the second positioning plate (4) is located is perpendicular to the plane where the platform (2) is located; It also comprises a first connecting member (6), a second connecting member (7) and a connecting rod (8), wherein the first connecting member (6) is fixed on the main beam (1), the second connecting member (7) is fixed on the platform (2), and the first connecting member (6) and the second connecting member (7) are connected via the connecting rod (8); The first direction and the second direction are perpendicular to each other.

2. The concrete guardrail drilling pedestal according to claim 1, characterized in that: It also includes a sliding component, which is arranged in the table (2) and can move along a third direction; wherein the third direction is perpendicular to the first direction and the second direction.

3. The concrete guardrail drilling pedestal according to claim 2, characterized in that: The sliding assembly comprises a frame (901), a roller (902) and an adjusting assembly (903); the roller (902) is rollingly connected to the frame (901), and the roller (902) can extend out of the table (2) to drive the table (2) to move; the adjusting assembly (903) is connected to a side of the frame (901) away from the roller (902) to drive the frame (901) to move along the third direction.

4. The concrete guardrail drilling pedestal according to claim 3, characterized in that: The sliding assembly also includes a circle counter (13), a support (14) and a transmission rod (15); the circle counter (13) is connected to the frame (901) via the support (14); one end of the transmission rod (15) is connected to the circle counter (13); and the other end of the transmission rod is eccentrically connected to one of the rollers (902).

5. The concrete guardrail drilling pedestal according to claim 4, characterized in that: The adjustment assembly (903) comprises a support rod (9031), a clamping piece (9032) and a clamping block (9033); one end of the support rod (9031) is rotatably connected to the frame (901); the other end of the support rod (9031) is fixedly connected to the clamping piece (9032); the clamping block (9033) is fixedly mounted on the platform (2); and the clamping piece (9032) can be clamped with the clamping block (9033).

6. The concrete guardrail drilling pedestal according to claim 5, characterized in that: A clamping hole (201) is provided on the table top (2) at a position corresponding to the clamping piece (9032); the clamping piece (9032) extends out of or retracts into the table top (2) through the clamping hole (201); and the clamping piece (9032) can be clamped with the clamping hole (201).

7. The concrete guardrail drilling pedestal according to claim 1, characterized in that: It also comprises three or more adjusting rods (12), each of the adjusting rods (12) being distributed around the platform (2), and the adjusting rods (12) being used to adjust the horizontal state of the platform (2).

8. The concrete guardrail drilling pedestal according to claim 7, characterized in that: A suction cup (121) is provided at the bottom of each adjusting rod (12).

9. The concrete guardrail drilling pedestal according to claim 7, characterized in that: The platform (2) is also provided with a level ruler (10), and the level ruler (10) is used to judge the horizontal state of the platform (2).

10. The concrete guardrail drilling pedestal according to claim 1, characterized in that: A buffer block (11) is provided on the first positioning plate (3) and the second positioning plate (4) on one side close to each other.