Slurry plugging plug suitable for precast concrete opening mold

By designing the plugging of multiple plug bodies and adjustment components, the problem of insufficient stability of plugging of slurry at the opening of precast concrete molds is solved, and higher stability and convenient installation are achieved, suitable for molds of different thicknesses and shapes.

CN222038957UActive Publication Date: 2024-11-22BBMG RESIDENTIAL INDUSTRIALIZATION (TANGSHAN) CO LTD +2
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202323581928.7
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-12-27
Publication Date
2024-11-22
Estimated Expiration
2033-12-27

AI Technical Summary

Technical Problem

The slurry plug at the opening of the existing precast concrete mold has poor stability and cannot effectively prevent concrete from flowing out. Especially due to insufficient friction, the slurry plug is prone to failure when the steel bars extend.

Method used

A plug plug consisting of a plurality of plug bodies is designed. The plug body is composed of a sealing strip, a pressing plate and a clamping strip. Through the elastic deformation and adjustment components of the plug body (such as threaded rods, knobs, grooves, pressing rings, nuts. ) to improve stability and fix the plug body through plug blocks and slots to ensure stable installation of the plug body under different thickness molds and opening shapes.

Benefits of technology

It improves the stability and installation convenience of the slurry plug, ensures that the plug body does not slide or loose during the concrete pouring process, is suitable for molds of different thicknesses, and the fixity of the plug body is enhanced by adjusting components to adapt to different shapes.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222038957U_ABST
    Figure CN222038957U_ABST
Patent Text Reader

Abstract

The utility model relates to the field of precast concrete, in particular to a slurry plugging plug suitable for a precast concrete opening mold, which comprises a plurality of plug bodies, the plug bodies are arranged along the length direction of an opening, each plug body comprises a plugging strip, a pressing plate and two clamping strips, the plugging strip is inserted into the opening, the pressing plate is arranged on one side of the plugging strip, and the clamping strips are arranged on the other side of the plugging strip. The pressing plate abuts against the outer wall of the mold, the clamping strips are also arranged on the side wall of the plugging strip, the two clamping strips are located on the two sides of the plugging strip, the clamping strips are located on the side, away from the pressing plate, of the mold, the clamping strips abut against the inner wall of the mold, and receding grooves allowing steel bars to penetrate through are formed in one end or two ends of the plug body in the length direction. The slurry plug has the effect of improving the stability of the slurry plug.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the field of precast concrete, and in particular to a slurry plug suitable for an open mold of precast concrete. Background Art

[0002] Precast concrete components are widely used in building design and construction. Precast concrete components require the use of molds to form specific shapes and sizes. Precast concrete components need to meet the requirements of the overlap of the steel bars in the post-cast concrete part. Therefore, most precast components have steel bars protruding from the edges. Therefore, the side of the mold is opened to meet the need for the steel bars to protrude. In order to ensure the density of the concrete during the concrete pouring process and the quality of the component after forming, it is often necessary to set a slurry plug at the mold opening. However, the existing slurry plugs generally use cylindrical foam rods, which use the elastic deformation of the foam rods themselves to clamp the foam rods at the opening of the mold to prevent the concrete from flowing out. However, the foam rods and the mold only rely on friction, so the stability of the foam rods is poor. Utility Model Content

[0003] In order to improve the stability of the slurry plug, the present application provides a slurry plug suitable for a precast concrete opening mold.

[0004] The present application provides a slurry plug for a precast concrete opening mold, which adopts the following technical solution:

[0005] A slurry plug suitable for a precast concrete open mold is arranged on the mold, a U-shaped opening is opened in the mold, the plug body includes a plurality of plug bodies, and the plurality of plug bodies are arranged along the length direction of the opening. The plug body includes a sealing strip, a pressure plate and two clamping strips, the sealing strip is inserted in the opening, the pressure plate is arranged on one side of the sealing strip, the pressure plate abuts against the outer wall of the mold, the clamping strip is also arranged on the side wall of the sealing strip, the two clamping strips are located on both sides of the sealing strip, the clamping strip is located on the side of the mold away from the pressure plate, the clamping strip abuts against the inner wall of the mold, and one end or both ends of the plug body in the length direction are provided with a makeshift groove for allowing steel bars to pass through.

[0006] By adopting the above technical solution, when installing the slurry plug, the sealing strip is inserted from the open port, the clamping strip abuts against the inner wall of the mold, the pressure plate abuts against the outer wall of the mold, and the clamping strip and the pressure plate are clamped on both sides of the mold, thereby improving the stability of the slurry plug.

[0007] Optionally, the plug body is made of rubber material.

[0008] By adopting the above technical solution, the plug body has a certain elasticity, and the plug body can be directly inserted into the opening from the outside of the mold, which makes the installation of the plug body more convenient.

[0009] Optionally, an adjustment assembly is provided on the plug body, and the adjustment assembly includes a threaded rod, which is vertically arranged on the side wall of the sealing strip close to the pressure plate, and the threaded rod passes through the pressure plate. A knob is threadedly connected to the threaded rod, and the knob is located on the side of the pressure plate away from the sealing strip, and the knob abuts against the pressure plate.

[0010] By adopting the above technical solution, the knob is turned to move in a direction away from the blocking strip, and the pressing plate can slide on the threaded rod, thereby adjusting the distance between the pressing plate and the card strip, so as to be suitable for molds of different thicknesses.

[0011] Optionally, a plurality of grooves are provided on the side wall of the knob, and the plurality of grooves are arranged around the knob.

[0012] By adopting the above technical solution, the groove can increase the friction between the human hand and the knob, making it easier for the staff to turn the knob.

[0013] Optionally, a pressure ring is provided on the side wall of the knob, and the pressure ring abuts against the pressure plate.

[0014] By adopting the above technical solution, the pressure ring can increase the contact area between the knob and the pressure plate, thereby reducing the squeezing force of the knob on the pressure plate.

[0015] Optionally, a nut is threadedly connected to the threaded rod, and the nut is located on a side of the knob facing away from the pressure plate, and the nut abuts against the knob.

[0016] By adopting the above technical solution, the nut can prevent the knob from loosening and improve the stability of the knob.

[0017] Optionally, a blocking block is inserted into the port of the opening, and clamping blocks are provided on two opposite side walls of the blocking block. A clamping groove is provided on two opposite side walls of the opening, and the clamping block is clamped in the clamping groove. The blocking block abuts against the sealing strip, and the blocking block and the clamping block are both made of rubber material.

[0018] By adopting the above technical solution, a blocking block is inserted from the port of the opening, and the blocking block is inserted into the card slot to fix the blocking block. The blocking block abuts against the sealing strip to prevent the plug body from sliding along the length direction of the opening, thereby improving the stability of the plug body.

[0019] Optionally, two taking slots are provided in the blocking block, and the two taking slots are located on both sides of the blocking block.

[0020] By adopting the above technical solution, the staff inserts two fingers into the two taking grooves respectively, clamps the block and then pulls out the block. The taking grooves make it easy for the staff to take out the block.

[0021] In summary, the present application includes at least one of the following beneficial technical effects:

[0022] 1. When installing the plugging plug, insert the plugging strip from the open port, the clip strip abuts against the inner wall of the mold, the pressing plate abuts against the outer wall of the mold, and the clip strip and the pressing plate are clamped on both sides of the mold to improve the stability of the plugging plug;

[0023] 2. Turn the knob to move away from the blocking strip, and the pressure plate can slide on the threaded rod to adjust the distance between the pressure plate and the card strip, so as to be suitable for molds of different thicknesses;

[0024] 3. Insert the blocking block from the port of the opening, and insert the blocking block into the card slot to fix the blocking block. The blocking block abuts against the sealing strip to prevent the plug body from sliding along the length direction of the opening, thereby improving the stability of the plug body. BRIEF DESCRIPTION OF THE DRAWINGS

[0025] Figure 1 It is a structural schematic diagram of a slurry plug suitable for a precast concrete opening mold in an embodiment of the present application.

[0026] Figure 2 This is a cross-sectional view showing the plug body and adjustment assembly.

[0027] Figure 3 This is a cross-sectional view made to show the blockage.

[0028] Explanation of the reference numerals: 1. mold; 10. opening; 2. plug body; 20. sealing strip; 21. pressure plate; 22. clamping strip; 23. clearance groove; 3. adjustment assembly; 30. threaded rod; 31. knob; 310. groove; 32. pressure ring; 33. nut; 4. block; 40. clamping block; 41. clamping slot; 42. taking slot. DETAILED DESCRIPTION

[0029] The following is combined with Figure 1 -Attached Figure 3 This application is described in further detail.

[0030] The present application embodiment discloses a slurry plug suitable for a precast concrete opening mold. Figure 1 and Figure 2 A slurry plug suitable for a precast concrete open mold is arranged on a mold 1. A U-shaped opening 10 is opened in the mold 1. The slurry plug includes a plurality of plug bodies 2. The plurality of plug bodies 2 are arranged along the length direction of the opening 10. The plug bodies 2 are inserted into the opening 10. In this embodiment, two plug bodies 2 are provided. The plug bodies 2 include a sealing strip 20, a pressure plate 21 and two clamping strips 22. The sealing strip 20 is inserted into the opening 10. The pressure plate 21 is located on one side of the sealing strip 20. The pressure plate 21 abuts against the outer wall of the mold 1.

[0031] Reference Figure 1 and Figure 2The clamping strip 22 is fixed to the side wall of the blocking strip 20, and the clamping strip 22 is arranged along the length direction of the blocking strip 20. The two clamping strips 22 are located on both sides of the blocking strip 20. The clamping strip 22 is located on the side of the mold 1 away from the pressing plate 21, and the clamping strip 22 abuts against the inner wall of the mold 1; a semicircular arc-shaped clearance groove 23 is opened at one or both ends of the length direction of the plug body 2. In the two plug bodies 2 of this embodiment, one plug body 2 is provided with a clearance groove 23 at both ends, and the other plug body 2 is provided with a clearance groove 23 at one end. A make way groove 23, a plug body 2 with a make way groove 23 at one end is arranged near the port of the opening 10, a circular through hole is formed between the make way groove 23 of the plug body 2 and the arc-shaped side wall of the opening 10, a circular through hole is also formed between the two make way grooves 23 located on the two plug bodies 2, and the circular through hole is used to allow the steel bars to extend out; the plug body 2 is made of rubber material, so the plug body 2 has a certain elasticity, and the plug body 2 can be directly inserted into the opening 10 from the outside of the mold 1, and the installation of the plug body 2 is more convenient.

[0032] Reference Figure 1 and Figure 2 An adjusting component 3 is provided on the plug body 2, and the adjusting component 3 is used to adjust the distance between the pressure plate 21 and the card strip 22, so as to be suitable for molds 1 of different thicknesses. The adjusting component 3 includes a threaded rod 30, and the threaded rod 30 is vertically fixed to the side wall of the sealing strip 20 close to the pressure plate 21. The threaded rod 30 vertically penetrates the pressure plate 21, and a knob 31 is threadedly connected to the threaded rod 30. The knob 31 is located on the side of the pressure plate 21 away from the sealing strip 20, and the knob 31 abuts against the pressure plate 21. A plurality of grooves 310 are opened on the side wall of the knob 31, and the plurality of grooves 310 are arranged around the knob 31, and the grooves 310 are used to increase the friction between the human hand and the knob 31.

[0033] Reference Figure 1 and Figure 2 An annular pressure ring 32 is fixedly connected to the side wall of the knob 31, and the pressure ring 32 abuts against the pressure plate 21. The pressure ring 32 is used to increase the contact area between the knob 31 and the pressure plate 21, thereby reducing the squeezing force of the knob 31 on the pressure plate 21; a nut 33 is threadedly connected to the threaded rod 30, and the nut 33 is located on the side of the knob 31 away from the pressure plate 21. The nut 33 abuts against the knob 31, and the nut 33 is used to prevent the knob 31 from loosening.

[0034] Reference Figure 1 and Figure 3A blocking block 4 is inserted into the port of the opening 10, and a clamping block 40 is fixedly connected to the two opposite side walls of the blocking block 4. A clamping groove 41 is provided on the two opposite side walls of the opening 10. The clamping block 40 is clamped in the clamping groove 41, and the blocking block 4 abuts against the blocking strip 20, thereby preventing the plug body 2 from sliding along the length direction of the opening 10 and improving the stability of the plug body 2; two taking grooves 42 are provided in the blocking block 4, and the two taking grooves 42 are located on both sides of the blocking block 4. The taking grooves 42 are convenient for the staff to take out the blocking block 4, and the blocking block 4 and the clamping block 40 are both made of rubber material.

[0035] The implementation principle of a slurry plug suitable for a precast concrete opening mold in an embodiment of the present application is as follows: when installing the slurry plug, press the plug body 2 from the outside of the mold 1 into the opening 10, the clamping strip 22 and the sealing strip 20 are deformed and inserted into the opening 10, and when the clamping strip 22 passes through the opening 10, the clamping strip 22 is restored and clamped on the inner wall of the mold 1, and the clamping strip 22 and the pressure plate 21 are clamped on both sides of the mold 1, thereby improving the stability of the slurry plug; then insert the blocking block 4 into the port of the opening 10, the blocking block 40 is clamped into the clamping groove 41, and the blocking block 4 abuts against the sealing strip 20, thereby preventing the slurry plug from moving along the length direction of the opening 10, further improving the stability of the slurry plug.

[0036] The above are all preferred embodiments of the present application, and the protection scope of the present application is not limited thereto. Therefore, any equivalent changes made according to the structure, shape, and principle of the present application should be included in the protection scope of the present application.

Claims

1. A slurry plug for a precast concrete open mold, arranged on a mold (1), wherein a U-shaped opening (10) is provided in the mold (1), characterized in that: The invention comprises a plurality of plug bodies (2), wherein the plurality of plug bodies (2) are arranged along the length direction of the opening (10), the plug body (2) comprises a blocking strip (20), a pressure plate (21) and two clamping strips (22), the blocking strip (20) is inserted into the opening (10), the pressure plate (21) is arranged on one side of the blocking strip (20), the pressure plate (21) abuts against the outer wall of the mould (1), the clamping strip (22) is also arranged on the side wall of the blocking strip (20), the two clamping strips (22) are located on both sides of the blocking strip (20), the clamping strip (22) is located on the side of the mould (1) away from the pressure plate (21), the clamping strip (22) abuts against the inner wall of the mould (1), and one end or both ends of the plug body (2) in the length direction are provided with a clearance groove (23) for allowing a steel bar to pass through.

2. The slurry plug for precast concrete open mold according to claim 1, characterized in that: The plug body (2) is made of rubber material.

3. The slurry plug for precast concrete open mold according to claim 1 or 2, characterized in that: The plug body (2) is provided with an adjustment component (3), and the adjustment component (3) includes a threaded rod (30). The threaded rod (30) is vertically arranged on the side wall of the sealing strip (20) close to the pressure plate (21), and the threaded rod (30) passes through the pressure plate (21). A knob (31) is threadedly connected to the threaded rod (30), and the knob (31) is located on the side of the pressure plate (21) away from the sealing strip (20), and the knob (31) abuts against the pressure plate (21).

4. The slurry plug for precast concrete open mold according to claim 3, characterized in that: A plurality of grooves (310) are provided on the side wall of the knob (31), and the plurality of grooves (310) are arranged around the knob (31).

5. The slurry plug for precast concrete open mold according to claim 3, characterized in that: A pressure ring (32) is provided on the side wall of the knob (31), and the pressure ring (32) abuts against the pressure plate (21).

6. The slurry plug for precast concrete open mold according to claim 3, characterized in that: A nut (33) is threadedly connected to the threaded rod (30). The nut (33) is located on a side of the knob (31) away from the pressure plate (21), and the nut (33) abuts against the knob (31).

7. The slurry plug for precast concrete open mold according to claim 1 or 2, characterized in that: A blocking block (4) is inserted into the port of the opening (10), and a clamping block (40) is provided on two opposite side walls of the blocking block (4). A clamping groove (41) is provided on two opposite side walls of the opening (10), and the clamping block (40) is clamped in the clamping groove (41). The blocking block (4) abuts against the sealing strip (20), and the blocking block (4) and the clamping block (40) are both made of rubber material.

8. The slurry plug for precast concrete open mold according to claim 7, characterized in that: Two taking grooves (42) are provided in the blocking block (4), and the two taking grooves (42) are located on two sides of the blocking block (4).