Coal gangue powder bin for goaf surface subsidence treatment

By burying heaters and designing cross-shaped structural beams on the surface of the reinforced concrete structural beams of the gangue powder silo, combining the steel filter mesh and pointed slope top, the structural stability and construction efficiency problems caused by gangue powder slab are solved, and gangue is realized Easy removal of powder and improved stability of the silo.

CN222041470UActive Publication Date: 2024-11-22SHAANXI TIANDI GEOLOGICAL
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202420087737.0
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-01-15
Publication Date
2024-11-22
Estimated Expiration
2034-01-15

AI Technical Summary

Technical Problem

During the treatment of surface subsidence in the goaf area, the gangue powder silo silo has a structural beam slab due to the moisture and adhesion of the gangue powder, which affects the structural stability and construction efficiency, and the slab silo is difficult to remove, increasing the risk of self-weight and blockage.

Method used

The heater is buried on the upper surface of the reinforced concrete structural beam to reduce the moisture content of gangue powder, design cross-shaped structural beams and set up steel filters, adopt a pointed slope top structure, and use an electric heater to remove gangue powder from plates and improve structural strength and stability.

Benefits of technology

Effectively prevent gangue powder board from forming, improve the structural stability and construction efficiency of the silo, reduce the impact of construction, and extend the service life of the equipment.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222041470U_ABST
    Figure CN222041470U_ABST
Patent Text Reader

Abstract

The utility model discloses a coal gangue powder bin for goaf surface subsidence treatment, which comprises a reinforced concrete bin body, a reinforced concrete structural beam is arranged in the middle of the reinforced concrete bin body, and a heater is embedded in the upper surface layer of the reinforced concrete structural beam. The utility model has the characteristics that hardened gangue powder is easy to remove, the structural stability of the stock bin is high, and the influence on construction is small; in addition, the method also has the characteristics of difficult hardening of the gangue powder, flexible use and reasonable design.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to a silo, in particular to a gangue powder silo used for treating ground subsidence in goaf areas. Background Art

[0002] During the mining process, underground rock containing minerals is continuously excavated, and a large number of goafs are formed under the mine. Due to the loss of support, the rock at the top of the goaf sinks under its own gravity, causing cracks on the ground and buildings on the ground, resulting in great economic losses and safety hazards.

[0003] After the ore is extracted, the rock mass without minerals is separated and called gangue. At present, the treatment of gangue is mainly based on stockpiling, and the area where gangue is piled is called tailings mountain. However, under the action of rainwater, tailings mountain will pollute the surrounding surface land and groundwater, and may also bring certain harmful volatile gases into the air. In addition, the tailings mountain formed by the accumulation of gangue is prone to collapse, causing natural disasters such as landslides and mudslides. Therefore, the treatment of gangue has become a difficult problem that needs to be solved urgently in this field.

[0004] Goaf backfill technology is an effective method for goaf management that has emerged in recent years. Its main means is to inject some filling materials into the mine to support the rock mass at the top of the goaf, thereby preventing the ground in the goaf from collapsing. Gangue, as a natural filling material, is also a waste after ore processing. Using local gangue for goaf backfill is an effective way to solve both goaf subsidence and gangue storage problems.

[0005] When the gangue is used to backfill the mined-out area, it needs to undergo a series of processing, the most basic of which is crushing and demuding. The gangue powder after demuding is then put into the silo for buffering. When needed, it is transported from the bottom of the silo to the mixer for mixing and slurrying by a conveyor belt, and then pumped into the mine cave in the mined-out area for filling.

[0006] The problem is that the amount of gangue powder is very large, so the volume of the silo used as a buffer is also very large. In order to ensure its structural strength, a steel-concrete structure is usually adopted, and a structural beam with improved tensile strength needs to be set inside the silo. However, since the gangue powder itself contains a certain amount of moisture and adhesion, when a large amount of gangue powder is accumulated, part of the gangue powder will be compacted on the upper surface of the structural beam, which is difficult to remove. Over time, the compaction thickness will continue to increase, which will increase the deadweight of the structural beam and reduce the stability of the silo structure. On the other hand, the expansion of the compaction area will hinder the gangue powder from falling, affecting construction. Utility Model Content

[0007] In order to solve the above technical problems, the utility model provides a coal gangue powder silo for the treatment of surface subsidence in goaf areas. The utility model has the characteristics of easy removal of compacted gangue powder, high stability of the silo structure, and small impact on construction; in addition, the gangue powder is not easy to compact, flexible to use, and reasonably designed.

[0008] The technical solution of this utility model:

[0009] A coal gangue powder bin for treating ground subsidence in goaf areas comprises a reinforced concrete bin body, a reinforced concrete structural beam is arranged in the middle of the reinforced concrete bin body, and a heater is buried in the upper surface of the reinforced concrete structural beam.

[0010] This solution embeds a heater inside the upper surface of the reinforced concrete structural beam to heat the material during storage, thereby reducing the moisture content of the gangue powder on the surface of the reinforced concrete structural beam, making it difficult for the gangue powder to compact on the surface of the reinforced concrete structural beam. The silo structure has higher stability and is less likely to be blocked, with less impact on construction. At the same time, when compaction occurs on the surface of the reinforced concrete structural beam, heating can be used to cause the compacted gangue powder on the surface to collapse, making the compacted gangue powder easier to remove.

[0011] Preferably, in the aforementioned coal gangue powder silo for treating surface subsidence in goaf areas, the reinforced concrete structural beam is in a cross shape.

[0012] This solution can further improve the structural strength of the silo and provide better stability by designing the reinforced concrete structural beam into a cross shape.

[0013] Preferably, in the aforementioned coal gangue powder silo for treating surface subsidence in goaf areas, a steel filter is provided between the reinforced concrete structural beam and the inner wall of the reinforced concrete silo body.

[0014] This solution can further improve the structural strength of the silo by setting up a steel filter, while ensuring material discharge, making the silo more stable.

[0015] Preferably, in the aforementioned coal gangue powder silo for treating surface subsidence in goaf areas, a pointed slope top is provided on the upper side of the reinforced concrete structural beam.

[0016] This solution can reduce the adhesion of gangue powder to the upper surface of the reinforced concrete structural beam by setting the upper side of the reinforced concrete structural beam as a pointed slope top, thereby further reducing the possibility of gangue powder compaction.

[0017] Preferably, in the aforementioned coal gangue powder silo for goaf area surface subsidence treatment, the heater is an electric heater.

[0018] This solution limits the heater to an electric heater, which is more flexible and practical than water heating.

[0019] Preferably, in the aforementioned coal gangue powder silo for goaf area surface subsidence treatment, the heater comprises an insulating sleeve and an electric heating wire arranged in the insulating sleeve.

[0020] The present solution further defines that the heater includes an insulating sleeve and a heating wire, so that the heater is more reasonably designed, safer to use, and has a longer service life.

[0021] Preferably, in the aforementioned gangue powder silo for goaf area surface subsidence treatment, the insulating sleeve has a diameter of 1-2 cm, a buried depth of 3-5 cm, and is evenly distributed along the width direction of the reinforced concrete structural beam, with a spacing of 5-8 cm.

[0022] This solution further limits the layout of the heater and has a reasonable design.

[0023] Beneficial effects of the utility model:

[0024] The utility model embeds a heater inside the upper surface layer of the reinforced concrete structural beam to heat the material during storage, thereby reducing the moisture content of the gangue powder on the surface of the reinforced concrete structural beam, making it difficult for the gangue powder to be compacted on the surface of the reinforced concrete structural beam, and the silo structure has higher stability and is not easy to be blocked, with less impact on construction; at the same time, when compaction occurs on the surface of the reinforced concrete structural beam, heating can be used to cause the compacted gangue powder on the surface to collapse, thereby making the compacted gangue powder easier to remove.

[0025] The utility model can further improve the structural strength of the silo by designing the reinforced concrete structural beam into a cross shape, and the stability is better. The utility model can further improve the structural strength of the silo by setting a steel filter screen while ensuring material discharge, so that the stability of the silo is better.

[0026] The utility model can reduce the adhesion of gangue powder on the upper surface of the reinforced concrete structure beam by setting the upper side of the reinforced concrete structure beam as a pointed slope top, thereby further reducing the possibility of gangue powder compaction.

[0027] The utility model defines the heater as an electric heater, which is more flexible to use and more practical than water heating. The utility model further defines the heater as including an insulating sleeve and a heating wire, so that the heater is more reasonably designed, safer to use and has a longer service life.

[0028] The utility model further limits the layout of the heater and has a reasonable design. BRIEF DESCRIPTION OF THE DRAWINGS

[0029] Attached Figure 1 It is a structural schematic diagram of the utility model;

[0030] Attached Figure 2 It is a top view of the utility model;

[0031] Attached Figure 3 It is the cross-section diagram of reinforced concrete structural beam;

[0032] Attached Figure 4 This is a cross-section view of a reinforced concrete structural beam.

[0033] Explanation of the reference numerals: 1-reinforced concrete silo, 2-reinforced concrete structural beam, 3-heater, 4-reinforced filter screen, 5-slope top, 31-insulating sleeve, 32-electric heating wire. DETAILED DESCRIPTION

[0034] The present invention is further described below in conjunction with the embodiments, but is not intended to be a basis for limiting the present invention.

[0035] Embodiments of the present utility model

[0036] A coal gangue powder silo for treating surface subsidence in goaf areas, as shown in the attached Figure 1-4 As shown, it comprises a reinforced concrete warehouse body 1, a reinforced concrete structural beam 2 is arranged in the middle of the reinforced concrete warehouse body 1, and a heater 3 is buried inside the upper surface layer of the reinforced concrete structural beam 2.

[0037] The reinforced concrete silo 1 of this embodiment is about 10m high and is provided with a layer of reinforced concrete structural beams 2. The number of layers of reinforced concrete structural beams 2 can be selected according to actual needs during actual construction. It is built on-site near the mining area, and a discharge port is provided at the bottom according to conventional requirements to facilitate the transportation of gangue powder.

[0038] During storage, the gangue powder after the mud and water are removed is transported to the reinforced concrete silo 1, a large amount of gangue powder is accumulated and squeezes the upper surface of the reinforced concrete structural beam 2. At this time, the heater 3 is started. Under the action of the heater 3, a high-temperature zone is formed near the surface of the reinforced concrete structural beam 2, and the moisture in the gangue powder on its surface is evaporated, thereby greatly reducing the viscosity of the gangue powder and reducing the possibility of compaction.

[0039] When compaction occurs, the surface temperature of the reinforced concrete structural beam 2 can be increased by the heater 3, so that the compacted gangue powder can be broken and fallen off at high temperature.

[0040] Further implementation examples include Figure 1-4 As shown, the reinforced concrete structural beam 2 is in a cross shape, and its ends are fixedly connected to the inner wall of the reinforced concrete warehouse body 1 to play a pulling role.

[0041] Further implementation examples include Figure 1-4As shown, a steel filter 4 is provided between the reinforced concrete structural beam 2 and the inner wall of the reinforced concrete silo 1. The steel filter 4 is made of welded steel bars, and the ends are respectively inserted into the reinforced concrete structural beam 2 and the reinforced concrete silo 1, and the mesh size thereof needs to be large enough to avoid obstruction to the falling of the gangue powder.

[0042] Further implementation examples include Figure 1-4 As shown, the upper side of the reinforced concrete structural beam 2 is provided with a pointed slope top 5. The pointed slope top 5 of this embodiment is similar to a pointed slope roof. When the gangue powder is pressed down, the adhesion of the surface of the reinforced concrete structural beam 2 will be greatly reduced, thereby reducing the possibility of compaction. At the same time, the gangue powder will fall more smoothly. When the compacted gangue powder is disintegrated by heat, it can also slide down under the action of its own gravity, which is convenient for removal.

[0043] Further implementation examples include Figure 1-4 As shown, the heater 3 is an electric heater. When in use, the heater 3 can be used by connecting it to an external power source, and the heating time is arranged according to actual needs.

[0044] Further implementation examples include Figure 1-4 As shown, the heater 3 includes an insulating sleeve 31 and a heating wire 32 arranged in the insulating sleeve 31 .

[0045] Further implementation examples include Figure 1-4 As shown, the diameter of the insulating sleeve 31 is 1-2 cm, the buried depth is 3-5 cm, and the insulating sleeve 31 is evenly distributed along the width direction of the reinforced concrete structural beam 2, with a spacing of 5-8 cm.

[0046] The above description is only a preferred specific implementation manner of the present invention, but the protection scope of the present invention is not limited thereto. Any technician familiar with the technical field can make equivalent replacements or changes based on the technical solution and the utility model of the present invention within the technical scope disclosed by the present invention, which should be covered by the protection scope of the present invention.

Claims

1. A coal gangue powder silo for treating surface subsidence in goaf areas, characterized by: It comprises a reinforced concrete warehouse body (1), a reinforced concrete structural beam (2) is provided in the middle of the reinforced concrete warehouse body (1), and a heater (3) is buried inside the upper surface layer of the reinforced concrete structural beam (2); A steel filter (4) is provided between the reinforced concrete structural beam (2) and the inner wall of the reinforced concrete warehouse body (1); The upper side of the reinforced concrete structural beam (2) is provided with a pointed slope top (5).

2. The coal gangue powder silo for treating surface subsidence in goaf according to claim 1 is characterized by: The reinforced concrete structural beam (2) is in a cross shape.

3. The coal gangue powder silo for treating surface subsidence in goaf according to claim 1 is characterized by: The heater (3) is an electric heater.

4. The coal gangue powder silo for treating surface subsidence in goaf according to claim 3 is characterized by: The heater (3) comprises an insulating sleeve (31) and an electric heating wire (32) arranged in the insulating sleeve (31).

5. The coal gangue powder silo for treating surface subsidence in goaf according to claim 4 is characterized by: The diameter of the insulating sleeve (31) is 1-2 cm, the buried depth is 3-5 cm, and the insulating sleeves (31) are evenly distributed along the width direction of the reinforced concrete structural beam (2), with a spacing of 5-8 cm.

Citation Information

Cited By

  • Coal gangue powder bin for goaf surface subsidence treatment

    CN223891648U