Fabricated aluminum alloy pipe and concrete combined member joint
By designing the nodes of prefabricated aluminum alloy pipe concrete assembly components, using welding and concrete pouring technology, the node connection problem in the aluminum alloy pipe concrete structure is solved, the strength and reliability of the structure are improved, and the installation quality and safety of the construction site are ensured. .
Patent Information
- Application Number
- CN202420715133.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-04-09
- Publication Date
- 2024-11-22
- Estimated Expiration
- 2034-04-09
AI Technical Summary
In the aluminum alloy pipe concrete composite structure, it is difficult to solve the problem of how to effectively install the aluminum alloy pipe concrete column and the aluminum alloy pipe concrete beam, avoid mutual collision, and ensure the rationality of the structure and the connection quality.
A prefabricated aluminum alloy pipe concrete assembly node is designed, including upper and lower prefabricated columns, middle connecting sleeves, open-hole inner partitions, embedded parts, left and right steel hinges and prefabricated beams, through welding and concrete Pouring realizes the strength and reliability of the nodes, and uses internal stiffened double steel plate connectors and pin connectors to decompose bending moment force, transmit axial force and shear force, and adapt to temperature changes.
The strength and overall reliability of node connections are improved, and the shock absorption effect of the internally stiffened double steel plate connectors ensures the stability and safety of the structure and adapts to the assembly needs of the construction site.
Smart Images

Figure CN222044509U_ABST
Abstract
Description
Technical Field
[0001] The utility model belongs to the technical field of aluminum alloy tube concrete composite components and relates to an assembled aluminum alloy tube concrete composite component node. Background Art
[0002] With the development of engineering technology, aluminum alloy tube concrete composite structure as an innovative structural form has gradually attracted attention and has been widely used in bridges, offshore drilling platforms, high-rise buildings and other fields. In these structures, the aluminum alloy tube concrete frame structure node is a key link to ensure the quality of the project. The node is not only the intersection of the upper and lower frame columns and the frame beams, but also the core area of the seismic design of the structure. Given that the prefabricated frame columns and prefabricated frame beams are made of aluminum alloy materials, how to achieve the effective installation of aluminum alloy tube concrete columns and aluminum alloy tube concrete beams, avoid mutual collision, and ensure the rationality of the structure has become an important issue to be solved in current research. At the same time, this is also a technical problem that needs to be overcome urgently during the assembly process on the construction site. Utility Model Content
[0003] In order to solve the above technical problems, the purpose of the utility model is to provide a prefabricated aluminum alloy tube concrete composite component node, which node structure not only ensures the connection quality, but also effectively solves the node connection problem caused by the inability to perform traditional welding operations on aluminum alloy materials.
[0004] The utility model provides an assembled aluminum alloy tube concrete composite component node, comprising: an upper prefabricated column, a lower prefabricated column, a middle connecting sleeve, an open hole inner partition, an embedded part, a left steel hinge, a right steel hinge, a left prefabricated beam, a right prefabricated beam, a left connecting sleeve and a right connecting sleeve;
[0005] An open hole inner partition is arranged in the middle position of the middle connecting sleeve, an upper prefabricated column is arranged on the top surface of the open hole inner partition, and a lower prefabricated column is arranged on the bottom surface of the open hole inner partition; the left prefabricated beam is fixedly installed at the bottom of the left connecting sleeve, and the right prefabricated beam is fixedly installed at the bottom of the right connecting sleeve; the left connecting sleeve is connected to the middle connecting sleeve through a left steel hinge, and the right connecting sleeve is connected to the middle connecting sleeve through a right steel hinge;
[0006] The upper prefabricated column adopts an aluminum alloy tube concrete composite structure, and the bottom of its aluminum alloy outer tube is positioned on the top surface of the hole inner partition; the lower prefabricated column adopts an aluminum alloy tube concrete composite structure, and the bottom of its aluminum alloy outer tube is positioned on the bottom surface of the hole inner partition; the embedded parts are welded to the top and bottom surfaces of the hole inner partition respectively, and the upper prefabricated column and the lower prefabricated column are poured with concrete together through the reserved holes on the hole inner partition.
[0007] Furthermore, the middle connecting sleeve includes a first sleeve and two arc-shaped steel plates, and a plurality of first connecting holes are respectively provided on the left and right sides of the surface of the first sleeve; the two arc-shaped steel plates are respectively fixedly connected to the first sleeve by nuts and bolts;
[0008] The left connecting sleeve comprises a second sleeve and a second connecting steel plate, the second connecting steel plate and the second sleeve are fixed by welding, and the second connecting steel plate is provided with a second connecting hole for facilitating the connection of the left steel hinge;
[0009] The right connecting sleeve includes a third sleeve and a third connecting steel plate. The third connecting steel plate and the third sleeve are fixed by welding. The third connecting steel plate reserves a third connecting hole to facilitate the connection of the right steel hinge.
[0010] Furthermore, the left precast beam adopts an aluminum alloy tube concrete composite structure, wherein the bottom of its aluminum alloy outer tube is pre-placed at the bottom of the second sleeve and connected to the second connecting steel plate; embedded parts are welded on the top surface of the second connecting steel plate; the right precast beam adopts an aluminum alloy tube concrete composite structure, wherein the bottom of its aluminum alloy outer tube is pre-placed at the bottom of the third sleeve and connected to the third connecting steel plate; embedded parts are welded on the top surface of the third connecting steel plate; concrete is cast in the aluminum alloy outer tubes of the left precast beam and the right precast beam.
[0011] Further, the left steel hinge includes two left inner stiffening double steel plate connectors and a left pin connector, and the two sides of the left inner stiffening double steel plate connector are respectively connected to the second connecting steel plate and the arc-shaped steel plate on the left side by welding; the left pin connector is fixed to the second connecting hole reserved on the second connecting steel plate and the first connecting hole reserved on the arc-shaped steel plate by bolts;
[0012] The right steel hinge includes two right inner stiffened double steel plate connectors and a right pin connector. The two sides of the right inner stiffened double steel plate connector are connected to the third connecting steel plate and the arc-shaped steel plate on the right side by welding; the right pin connector is fixed to the third connecting hole reserved on the third connecting steel plate and the first connecting hole reserved on the arc-shaped steel plate by bolts.
[0013] Furthermore, the left pin shaft connecting piece is composed of a left pin shaft, a left main ear plate and a left secondary ear plate. After the through holes on the left main ear plate and the left secondary ear plate are aligned, the left pin shaft is inserted into the hole and locked; the right pin shaft connecting piece is composed of a right pin shaft, a right main ear plate and a right secondary ear plate. After the through holes on the main ear plate and the right secondary ear plate are aligned, the right pin shaft is inserted into the through hole and locked.
[0014] Furthermore, the first sleeve, the second sleeve and the third sleeve are all cylindrical structures made of steel.
[0015] The utility model provides an assembled aluminum alloy tube concrete composite component node, which has at least the following beneficial effects:
[0016] During the manufacturing process of the middle connecting sleeve of the node of the utility model, a perforated inner partition is welded and installed at the center of the sleeve. Concrete is poured into the upper and lower aluminum alloy tube concrete columns through the perforated inner partition, so as to ensure the strength of the node connection and improve the overall connection reliability at the node. The internally reinforced double steel plate connector in the steel hinge serves as a shock-absorbing and energy-consuming component, and bears the tensile (compressive) axial force generated by the decomposition of the bending moment. Its mechanical properties are the key to the force transmission and plastic energy consumption of the energy-absorbing and shock-absorbing node. After the internally reinforced double steel plate connector yields, the steel hinge can rotate around the pin shaft. The pin shaft connection in the node is responsible for transmitting axial force, shear force, bending moment, torque and additional stress caused by vibration and impact loads. At the same time, it must also adapt to the force caused by temperature changes to ensure the stability and safety of the structure. Embedded parts are a kind of component used in building construction. When the structure is poured, it is placed inside the concrete to play a role of connection and fixation. BRIEF DESCRIPTION OF THE DRAWINGS
[0017] Figure 1 It is a structural schematic diagram of a node of an assembled aluminum alloy tube concrete composite component of the utility model;
[0018] Figure 2 It is a cross-sectional view of a node of an assembled aluminum alloy tube concrete composite member of the utility model;
[0019] Figure 3 This is a top view schematic diagram of the sleeve structure of the utility model;
[0020] Figure 4 It is a structural schematic diagram of the middle connecting sleeve of the utility model;
[0021] Figure 5 It is a structural schematic diagram of the left connecting sleeve of the utility model;
[0022] Figure 6 It is a structural schematic diagram of the right connecting sleeve of the utility model;
[0023] Figure 7 This is a structural schematic diagram of the left steel hinge of the utility model;
[0024] Figure 8 This is a structural schematic diagram of the right steel hinge of the utility model;
[0025] In the figure: 1, middle connecting sleeve; 2, left connecting sleeve; 3, right connecting sleeve; 4, upper precast column; 5, lower precast column; 6, left precast beam; 7, right precast beam; 8, open hole inner partition; 9, right steel hinge; 10, arc steel plate; 11, first sleeve; 12, embedded parts; 13, left steel hinge; 20, second connecting steel plate; 21, second sleeve; 30, third connecting steel plate; 31, third sleeve; 90, right pin connector; 91, right inner stiffening double steel plate connector; 92, right main ear plate; 93, right secondary ear plate; 94, right pin shaft; 130, left pin connector; 131, left inner stiffening double steel plate connector; 132, left main ear plate; 133, left secondary ear plate; 134, left pin shaft. DETAILED DESCRIPTION
[0026] like Figure 1-3 As shown, an assembled aluminum alloy tube concrete composite component node of the utility model includes: an upper precast column 4, a lower precast column 5, a middle connecting sleeve 1, an open inner partition 8, an embedded part 12, a left steel hinge 13, a right steel hinge 9, a left precast beam 6, a right precast beam 7, a left connecting sleeve 2 and a right connecting sleeve 3.
[0027] An open hole inner partition 8 is set in the middle position of the middle connecting sleeve 1, the upper prefabricated column 4 is set on the top surface of the open hole inner partition 8, and the lower prefabricated column 5 is set on the bottom surface of the open hole inner partition 8; the left prefabricated beam 6 is fixedly installed at the bottom of the left connecting sleeve 2, and the right prefabricated beam 7 is fixedly installed at the bottom of the right connecting sleeve 3; the left connecting sleeve 2 is connected to the middle connecting sleeve 1 through the left steel hinge 13, and the right connecting sleeve 3 is connected to the middle connecting sleeve 1 through the right steel hinge 9.
[0028] The upper precast column 4 adopts an aluminum alloy tube concrete composite structure, and the bottom of its aluminum alloy outer tube is positioned on the top surface of the perforated inner partition 8; the lower precast column 5 adopts an aluminum alloy tube concrete composite structure, and the bottom of its aluminum alloy outer tube is positioned on the bottom surface of the perforated inner partition 8; the embedded parts 12 are welded to the top and bottom surfaces of the perforated inner partition 8 respectively, and the upper precast column 4 and the lower precast column 5 are poured with concrete together through the reserved holes on the perforated inner partition 8.
[0029] like Figure 4 As shown, the middle connecting sleeve 1 includes a first sleeve 11 and two arc-shaped steel plates 10, and a plurality of first connecting holes are respectively provided on the left and right sides of the surface of the first sleeve 11; the two arc-shaped steel plates 10 are respectively fixedly connected to the first sleeve 11 by nuts and bolts.
[0030] like Figure 5 As shown, the left connecting sleeve 2 includes a second sleeve 21 and a second connecting steel plate 20 . The second connecting steel plate 20 is fixed to the second sleeve 21 by welding. The second connecting steel plate 20 reserves a second connecting hole to facilitate the connection of the left steel hinge 13 .
[0031] like Figure 6 As shown, the right connecting sleeve 3 includes a third sleeve 31 and a third connecting steel plate 30 . The third connecting steel plate 30 and the third sleeve 31 are fixed by welding. The third connecting steel plate 30 reserves a third connecting hole to facilitate the connection of the right steel hinge 9 .
[0032] The left precast beam 6 adopts an aluminum alloy tube concrete composite structure, wherein the bottom of its aluminum alloy outer tube is pre-placed at the bottom of the second sleeve 21 and connected to the second connecting steel plate 20; the embedded part 12 is welded on the top surface of the second connecting steel plate 20; the right precast beam 7 adopts an aluminum alloy tube concrete composite structure, wherein the bottom of its aluminum alloy outer tube is pre-placed at the bottom of the third sleeve 31 and connected to the third connecting steel plate 30; the embedded part 12 is welded on the top surface of the third connecting steel plate 30; concrete is cast in the aluminum alloy outer tubes of the left precast beam and the right precast beam.
[0033] like Figure 7 and Figure 8 As shown, the left steel hinge 13 includes two left inner stiffening double steel plate connectors 131 and a left pin connector 130. The two sides of the left inner stiffening double steel plate connector 131 are respectively connected to the second connecting steel plate 20 and the arc-shaped steel plate 10 on the left side by welding; the left pin connector 130 is fixed to the second connecting hole reserved on the second connecting steel plate 20 and the first connecting hole reserved on the arc-shaped steel plate 10 by bolts.
[0034] The right steel hinge 9 includes two right inner stiffening double steel plate connectors 91 and a right pin connector 90. The two sides of the right inner stiffening double steel plate connector 91 are connected to the third connecting steel plate 30 and the arc-shaped steel plate 10 on the right side by welding; the right pin connector 90 is fixed to the third connecting hole reserved on the third connecting steel plate 30 and the first connecting hole reserved on the arc-shaped steel plate 10 by bolts.
[0035] The left pin shaft connecting member 130 is composed of a left pin shaft 134, a left main ear plate 132 and a left secondary ear plate 133. After the through holes on the left main ear plate 132 and the left secondary ear plate 133 are aligned, the left pin shaft 134 is inserted into the hole and locked; the right pin shaft connecting member 90 is composed of a right pin shaft 94, a right main ear plate 92 and a right secondary ear plate 93. After the through holes on the main ear plate 92 and the right secondary ear plate are aligned, the right pin shaft 94 is inserted into the through hole and locked.
[0036] The first sleeve 11, the second sleeve 21 and the third sleeve 31 are all cylindrical structures made of steel.
[0037] The construction method of the assembled aluminum alloy tube concrete composite component node of the utility model comprises the following steps:
[0038] Step 1: Connect the sleeve 1 during prefabrication, weld the perforated inner partition 8 to the position in the first sleeve during the steel plate rolling process, weld the embedded parts 12 above and below the perforated inner partition 8, and fix the two arc-shaped steel plates to the left and right sides of the first sleeve;
[0039] Step 2: prefabricate the lower prefabricated column 5, vertically lift the aluminum alloy outer tube of the lower prefabricated column 5 to the designed position of the first sleeve 11, and install the aluminum alloy outer tube of the lower prefabricated column 5 in place;
[0040] Step 3: prefabricate the upper prefabricated column 4, vertically hoist the aluminum alloy outer tube of the upper prefabricated column 4 to the designed position of the first sleeve 11, and install the aluminum alloy outer tube of the upper prefabricated column 4 in place;
[0041] Step 4: pouring concrete, pouring concrete together with the upper precast column 4 and the lower precast column 5 through the reserved holes on the perforated inner partition 8;
[0042] Step 5: prefabricate the left prefabricated beam 6, install the aluminum alloy outer tube of the left prefabricated beam into the left connecting sleeve and fix it to the top surface of the second connecting steel plate 20 with angle steel and self-tapping screws, weld the embedded part 12 on the top surface of the second connecting steel plate 20, and cast the left prefabricated beam 6 with the top surface of the second connecting steel plate 20 as the casting surface;
[0043] Step 6: prefabricate the right prefabricated beam 7, install the aluminum alloy outer tube of the right prefabricated beam into the right connecting sleeve and fix it to the top surface of the third connecting steel plate 30 with angle steel and self-tapping screws, weld the embedded part 12 on the top surface of the third connecting steel plate 30, and cast the right prefabricated beam 7 with the top surface of the third connecting steel plate 30 as the casting surface;
[0044] Step 7: hoist the left steel hinge 13, lift the left steel hinge 13 horizontally and align it with the first sleeve 11, use bolts to connect the left pin connector 130 with the first connecting hole, and weld the left inner stiffening double steel plate connector 131 to the arc-shaped steel plate 10 to complete the connection between the left steel hinge 13 and the first sleeve 11;
[0045] Step eight: hoist the right steel hinge 9, lift the right steel hinge 9 horizontally and align it with the first sleeve 11, use bolts to connect the right pin shaft connector 90 to the first connecting hole, and weld the right inner stiffening double steel plate connector 91 to the arc-shaped steel plate 10 to complete the connection between the right steel hinge 9 and the first sleeve 11.
[0046] Step 9: hoist the left precast beam 6, lift the left precast beam 6 horizontally so that the second connecting steel plate 20 is aligned with the left steel hinge 13, use bolts to connect the left pin connector 130 with the reserved second connecting hole, and weld the left inner stiffening double steel plate connector 131 to the second connecting steel plate 20 to complete the connection between the left steel hinge 13 and the second sleeve 21;
[0047] Step 10: hoist the right prefabricated beam 7, lift the right prefabricated beam 7 horizontally so that the third connecting steel plate 30 is aligned with the right steel hinge 9, use bolts to connect the right pin shaft connector 90 with the reserved third connecting hole, weld the right inner stiffening double steel plate connector 91 to the third connecting steel plate 30, and complete the connection between the right steel hinge 9 and the third sleeve 31;
[0048] Step 11: Install formwork in the areas of the left steel hinge, right steel hinge, left connecting sleeve, right connecting sleeve and middle connecting sleeve, and pour concrete as a protective layer so that the middle connecting sleeve is subjected to forces equivalent to a column at the node, and the left steel hinge, right steel hinge, left connecting sleeve and right connecting sleeve are subjected to forces equivalent to a beam at the node, rather than just connecting components. Complete the construction after removing the formwork.
[0049] The above description is only a preferred embodiment of the present invention and is not intended to limit the concept of the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the protection scope of the present invention.
Claims
1. A prefabricated aluminum alloy tube concrete composite component node, It is characterized in that include: Upper precast column, lower precast column, middle connecting sleeve, perforated inner partition, embedded parts, left steel hinge, right steel hinge, left precast beam, right precast beam, left connecting sleeve and right connecting sleeve; An open hole inner partition is arranged in the middle position of the middle connecting sleeve, an upper prefabricated column is arranged on the top surface of the open hole inner partition, and a lower prefabricated column is arranged on the bottom surface of the open hole inner partition; the left prefabricated beam is fixedly installed at the bottom of the left connecting sleeve, and the right prefabricated beam is fixedly installed at the bottom of the right connecting sleeve; the left connecting sleeve is connected to the middle connecting sleeve through a left steel hinge, and the right connecting sleeve is connected to the middle connecting sleeve through a right steel hinge; The upper prefabricated column adopts an aluminum alloy tube concrete composite structure, and the bottom of its aluminum alloy outer tube is positioned on the top surface of the hole inner partition; the lower prefabricated column adopts an aluminum alloy tube concrete composite structure, and the bottom of its aluminum alloy outer tube is positioned on the bottom surface of the hole inner partition; the embedded parts are welded to the top and bottom surfaces of the hole inner partition respectively, and the upper prefabricated column and the lower prefabricated column are poured with concrete together through the reserved holes on the hole inner partition.
2. The assembled aluminum alloy tube concrete composite component node according to claim 1, It is characterized in that The middle connecting sleeve comprises a first sleeve and two arc-shaped steel plates, and a plurality of first connecting holes are respectively provided on the left and right sides of the surface of the first sleeve; the two arc-shaped steel plates are respectively fixedly connected to the first sleeve by nuts and bolts; The left connecting sleeve comprises a second sleeve and a second connecting steel plate, the second connecting steel plate and the second sleeve are fixed by welding, and the second connecting steel plate is provided with a second connecting hole for facilitating the connection of the left steel hinge; The right connecting sleeve includes a third sleeve and a third connecting steel plate. The third connecting steel plate and the third sleeve are fixed by welding. The third connecting steel plate reserves a third connecting hole to facilitate the connection of the right steel hinge.
3. The assembled aluminum alloy tube concrete composite component node according to claim 2, It is characterized in that The left precast beam adopts an aluminum alloy tube concrete composite structure, wherein the bottom of its aluminum alloy outer tube is pre-placed at the bottom of the second sleeve and connected to the second connecting steel plate; embedded parts are welded on the top surface of the second connecting steel plate; the right precast beam adopts an aluminum alloy tube concrete composite structure, wherein the bottom of its aluminum alloy outer tube is pre-placed at the bottom of the third sleeve and connected to the third connecting steel plate; embedded parts are welded on the top surface of the third connecting steel plate; concrete is cast in the aluminum alloy outer tubes of the left precast beam and the right precast beam.
4. The assembled aluminum alloy tube concrete composite component node according to claim 2, It is characterized in that The left steel hinge comprises two left inner stiffening double steel plate connectors and a left pin connector. The two sides of the left inner stiffening double steel plate connector are respectively connected to the second connecting steel plate and the arc-shaped steel plate on the left side by welding; the left pin connector is fixed to the second connecting hole reserved on the second connecting steel plate and the first connecting hole reserved on the arc-shaped steel plate by bolts; The right steel hinge includes two right inner stiffened double steel plate connectors and a right pin connector. The two sides of the right inner stiffened double steel plate connector are connected to the third connecting steel plate and the arc-shaped steel plate on the right side by welding; the right pin connector is fixed to the third connecting hole reserved on the third connecting steel plate and the first connecting hole reserved on the arc-shaped steel plate by bolts.
5. The assembled aluminum alloy tube concrete composite component node according to claim 4, It is characterized in that The left pin shaft connecting piece is composed of a left pin shaft, a left main ear plate and a left secondary ear plate. After the through holes on the left main ear plate and the left secondary ear plate are aligned, the left pin shaft is inserted into the hole and locked; the right pin shaft connecting piece is composed of a right pin shaft, a right main ear plate and a right secondary ear plate. After the through holes on the main ear plate and the right secondary ear plate are aligned, the right pin shaft is inserted into the through hole and locked.
6. The assembled aluminum alloy tube concrete composite component node according to claim 1, It is characterized in that The first sleeve, the second sleeve and the third sleeve are all cylindrical structures made of steel.