Full-mechanized mining supporting structure

By designing anchor rods, anchor nets and concrete spray layers in mining support structures, the problems of high cost of use of traditional mining support structures and inconvenient grouting of anchor rods are solved, and the stability and reliability of anchor rods are achieved, satisfying the satisfaction of the support structures. Improved mining process requirements.

CN222045793UActive Publication Date: 2024-11-22GUIZHOU XIANGXIN MINING MACHINERY CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420865020.4
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-04-24
Publication Date
2024-11-22
Estimated Expiration
2034-04-24

AI Technical Summary

Technical Problem

The traditional mining support structure is costly and the anchor rod is inconvenient to grout when used longitudinally downward of the head, resulting in poor stability of the anchor rod and unable to meet the improved process needs.

Method used

Design a fully mechanized mining support structure, including setting up anchor rods, anchor nets and concrete spray layer on the top of the mine cave. The rock mass is penetrated into the upper end of the anchor rod, and the anchor net extends out of the lower end. The concrete spray layer covers the anchor net. The anchor rod includes a hollow rod body, an anchor part and a closure plate. Grouting is carried out through the grouting hole to ensure that the grouting in the anchor rod hole is full.

Benefits of technology

The stability and reliability of the anchor rod are achieved, the improved mining process needs for the top support of the mine cave, and the labor and material costs are reduced.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222045793U_ABST
    Figure CN222045793U_ABST
Patent Text Reader

Abstract

A full-mechanized mining supporting structure comprises anchor rods arranged at the top of a mine hole, anchor nets and a concrete guniting layer, the upper ends of the anchor rods are driven into rock mass at the top, the lower ends of the anchor rods extend out of the mine hole by a certain distance, the anchor nets are installed at the lower ends of the anchor rods, and the concrete guniting layer wraps the anchor nets. The anchor net and the concrete guniting layer are constructed on the top of the mine through the anchor rods, so that the concrete guniting layer can stably support the top of the mine, and the improved process requirements are met.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of mine support structures, in particular to a fully mechanized mining support structure. Background Art

[0002] During mining operations, the mine cave needs to be supported. In traditional support structures, such as the new mining support device disclosed in CN216841736U, and the mining equipment disclosed in CN116446927A, both the top wall and the side wall of the mine cave are supported. The installation of the above-mentioned support devices and equipment requires more manpower and material resources, and the cost of use is relatively high. Therefore, our company has improved the mining process of the mine cave and designed a mining support structure for fully mechanized mining.

[0003] In addition, the current anchor rods cannot be conveniently grouted when in use, especially when the head is used vertically downward. The anchor rod hole is not fully grouted, resulting in poor stability of the anchor rod. Combined with our company's improvement of the mine mining process, the structure of the anchor rod is also improved to meet the support structure requirements of the improved process. Utility Model Content

[0004] The technical problem to be solved by the utility model is: to solve the problems existing in the above-mentioned background technology, and to provide a fully mechanized mining support structure, in which an anchor net and a concrete shotcrete layer are constructed on the top of the mine cave through designed anchor rods, so that the concrete shotcrete layer can stably support the top of the mine cave to meet the improved process requirements.

[0005] In order to solve the above technical problems, the technical solution adopted by the utility model is: a fully mechanized mining support structure, including an anchor rod, an anchor net and a concrete shotcrete layer arranged at the top of the mine cave, the upper end of the anchor rod is driven into the rock mass at the top, the lower end of the anchor rod extends out of the mine cave for a distance, the lower end of the anchor rod is installed with an anchor net, and the concrete shotcrete layer covers the anchor net;

[0006] The anchor rod includes a hollow rod body, an anchoring portion and a closing plate. The outer wall of the hollow rod body is axially provided with multiple anchoring portions. A closing plate is provided near one end of the hollow rod body. The closing plate is provided with grouting holes. An end of the hollow rod body located at one end of the closing plate is provided with an external thread, a nut is screwed on the external thread, and a pad is installed on the hollow rod body between the closing plate and the nut.

[0007] The anchoring part is composed of a plurality of anchoring rods surrounding a hollow rod body, one end of the anchoring rod is welded to the outer wall of the hollow rod body, and the other end extends outward.

[0008] One end of the anchor rod is welded to the outer wall of the hollow rod body, and the other end faces the closing plate and extends outwardly in an inclined manner.

[0009] An elastic grout-stopping pad is installed on one side of the closing plate facing the anchoring portion, and an escape opening is arranged on the grout-stopping pad at the position of the grouting hole.

[0010] The grouting hole is provided with an internal thread.

[0011] The mine hole is also filled with a concrete support body, which seals the mine hole.

[0012] The utility model has the following beneficial effects:

[0013] 1. The utility model inserts a hollow rod body provided with an anchoring part into the anchor hole, and the anchoring part abuts against the inner wall of the anchor hole, thereby fixing the hollow rod body. When the hollow rod body is installed, the closing plate abuts against the anchor hole to close the anchor hole, and then the grouting pipe of the grouting equipment is inserted into the grouting hole to grout the anchor hole. The air in the anchor hole is discharged from the central hole of the hollow rod body, so that the grouting in the anchor hole is full, thereby ensuring the stability and reliability of the anchor installation. At the same time, the utility model constructs an anchor net and a concrete shotcrete layer on the top of the mine cave through the anchor rod, so that the concrete shotcrete layer can stably support the top of the mine cave to meet the improved process requirements. BRIEF DESCRIPTION OF THE DRAWINGS

[0014] The utility model is further described below in conjunction with the accompanying drawings and embodiments.

[0015] Figure 1 This is a cross-sectional diagram of mine excavation support.

[0016] Figure 2 This is a schematic diagram of the cross-section of the mine layered construction.

[0017] Figure 3 This is a cross-sectional diagram of the mine tunnel being sealed with concrete supports after excavation.

[0018] Figure 4 It is a schematic cross-sectional diagram of the mineral layers on both sides of the excavated concrete support body.

[0019] Figure 5 Schematic diagram of the three-dimensional structure of the anchor rod.

[0020] Figure 6 This is a schematic diagram of the three-dimensional structure of the anchor rod from another perspective.

[0021] Figure 7 This is a cross-sectional diagram of the anchor rod in use.

[0022] In the figure:

[0023] Anchor rod 10, hollow rod body 11, anchoring part 12, closing plate 13, grouting hole 14, grouting pad 15, avoidance opening 16, backing plate 17, nut 18;

[0024] Grouting pipe 20, ore layer 30, rock mass 40, mine cave 50, anchor net 60, concrete shotcrete layer 70, concrete support body 80. DETAILED DESCRIPTION

[0025] See also Figure 1-4 A fully mechanized mining support structure includes an anchor rod 10, an anchor net 60 and a concrete shotcrete layer 70 arranged at the top of a mine cave 50. The upper end of the anchor rod 10 is driven into the top rock mass 40, and the lower end of the anchor rod 10 extends a distance out of the mine cave 50. The anchor net 60 is installed at the lower end of the anchor rod 10, and the concrete shotcrete layer 70 covers the anchor net 60. The anchor net 60 and the concrete shotcrete layer 70 are constructed on the top of the mine cave by the anchor rod 10, so that the concrete shotcrete layer can stably support the top of the mine cave to meet the improved process requirements.

[0026] During construction, according to the new process requirements, the width of the mine hole is controlled to ensure the stability of the support structure. Multiple mine holes 50 can be set at intervals. The ore layer 30 between adjacent mine holes supports the top rock mass 40, and the ore layers in the mine hole are mined downward in layers.

[0027] Since the existing anchor rods cannot be conveniently grouted when the head is used vertically downward, the anchor rod hole is not fully grouted, resulting in poor stability of the anchor rod. Figure 5-7 The anchor rod 10 includes a hollow rod body 11, an anchoring portion 12 and a closing plate 13. The outer wall of the hollow rod body 11 is axially provided with multiple anchoring portions 12. The closing plate 13 is provided near one end of the hollow rod body 11. The closing plate 13 is provided with a grouting hole 14. The end of the hollow rod body 11 at one end of the closing plate 13 is provided with an external thread, and a nut 18 is screwed on the external thread. A pad 17 is also installed on the hollow rod body 11 between the closing plate 13 and the nut 18. Through the above structure, the stability and reliability of the installation of the anchor rod 10 are guaranteed.

[0028] When using, see Figure 7 First, an anchor hole is constructed at the top of the mine cave 50 by using an anchor trolley, and a hollow rod body 11 provided with an anchoring part 12 is inserted into the anchor hole. The anchoring part 12 abuts against the inner wall of the anchor hole, thereby fixing the hollow rod body 11. When the hollow rod body 11 is installed, the closing plate 13 abuts against the anchor hole to close the anchor hole. Then, the grouting pipe 20 of the grouting equipment is inserted into the grouting hole 14, so as to grout the anchor hole. The air in the anchor hole is discharged from the center hole of the hollow rod body 11, thereby ensuring that the grouting in the anchor hole is full.

[0029] Specifically, the anchoring portion 12 is composed of a plurality of anchoring rods surrounding the hollow rod body 11, one end of the anchoring rod is welded to the outer wall of the hollow rod body 11, and the other end extends outward. In this embodiment, one end of the anchoring rod is welded to the outer wall of the hollow rod body 11, and the other end extends radially or obliquely outward toward the closing plate 13.

[0030] Further, in Figure 5-7 In the embodiment, one end of the anchor rod is welded to the outer wall of the hollow rod body 11, and the other end faces the closing plate 13 and extends outwardly at an angle. In the preferred embodiment, the anchor rod adopts 6-10 mm steel bars, and the anchor rod has a straight section and an inclined section at one end, the straight section is welded to the anchor rod, and the inclined section faces the closing plate 13 and extends outwardly at an angle. The anchor rod forms a barb structure, and when the hollow rod body 11 is installed and inserted into the anchor hole, due to the elasticity of the steel bar, the anchor rod deforms outward, which is convenient for installation. After the hollow rod body 11 is loosened, the anchor rod with a barb structure abuts against the inner wall of the anchor hole, and the hollow rod body 11 will not fall out.

[0031] Furthermore, due to the unevenness of the mine top, when the closing plate 13 abuts against the anchor hole, a gap will appear between the closing plate 13 and the anchor hole, causing slurry to leak out. Therefore, an elastic grout-stopping pad 15 is installed on the side of the closing plate 13 facing the anchoring portion 12, and the grout-stopping pad 15 is provided with an escape opening 16 at the position of the grouting hole 14. The gap between the closing plate 13 and the anchor hole is closed by the elastic structure of the grout-stopping pad 15.

[0032] Preferably, the stop pad 15 is made of EPDM foam material or sponge pad.

[0033] To facilitate grouting, see Figure 6 The grouting hole 14 is provided with an internal thread. When in use, an external thread joint is provided at the end of the grouting pipe 20, and the external thread joint is screwed to the grouting hole 14, so that there is no need to manually hold the grouting pipe 20 all the time.

[0034] See also Figure 3 After the ore layer in the mine hole 50 is mined, a concrete support body 80 is filled in the mine hole 50, and the concrete support body 80 seals the mine hole 50. After the concrete support body 80 supports the mine hole, Figure 4 , it is possible to exploit the ore layers on both sides of the concrete support body 80. In a preferred embodiment, the concrete support body 80 is cast in concrete.

[0035] The working principle or action process of the utility model is as follows:

[0036] See also Figure 1 First, dig along the top rock layer 40 to excavate a mine cave 50, and multiple mine caves 50 are set at intervals.

[0037] An anchor hole is drilled at the top of the mine cave 50 by an anchor trolley, and an anchor is installed in the anchor hole. When the hollow rod body 11 is installed, the closing plate 13 abuts against the anchor hole to close the anchor hole, and then the grouting pipe 20 of the grouting equipment is inserted into the grouting hole 14, so as to grout the anchor hole, and the air in the anchor hole is discharged from the center hole of the hollow rod body 11 until the slurry flows out of the center hole of the hollow rod body 11, and the slurry in the anchor hole is filled.

[0038] Then, the anchor net 60 is hung by the anchor rod trolley, and the anchor net 60 passes through the lower end of the anchor rod. The lower end of the anchor net 60 is installed with a pad 17 and a nut 18 to fix the anchor net 60 on the pad 17. Then, the top wall of the mine cave 50 is sprayed by a spraying device to form a concrete spraying layer 70.

[0039] See also Figure 2 , the mine is mined in layers.

[0040] See also Figure 3 When the ore layer in the mine hole 50 is mined, a concrete support body 80 is filled in the mine hole 50 , and the concrete support body 80 seals the mine hole 50 , and the mine hole is supported by the concrete support body 80 .

[0041] See also Figure 4 , and then exploit the ore layers on both sides of the concrete support body 80.

Claims

1. A fully mechanized mining support structure, characterized in that: It comprises an anchor rod (10), an anchor net (60) and a concrete shotcrete layer (70) arranged at the top of a mine cave (50), wherein the upper end of the anchor rod (10) is driven into the rock mass (40) at the top, the lower end of the anchor rod (10) extends a certain distance out of the mine cave (50), the lower end of the anchor rod (10) is installed with an anchor net (60), and the concrete shotcrete layer (70) covers the anchor net (60); The anchor rod (10) comprises a hollow rod body (11), an anchoring portion (12) and a closing plate (13); a plurality of anchoring portions (12) are axially arranged on the outer wall of the hollow rod body (11); a closing plate (13) is arranged near one end of the hollow rod body (11); a grouting hole (14) is arranged on the closing plate (13); an end of the hollow rod body (11) located at one end of the closing plate (13) is provided with an external thread, a nut (18) is screwed onto the external thread, and a pad (17) is also installed on the hollow rod body (11) between the closing plate (13) and the nut (18).

2. A fully mechanized mining support structure according to claim 1, characterized in that: The anchoring portion (12) is composed of a plurality of anchoring rods surrounding a hollow rod body (11); one end of the anchoring rod is welded to the outer wall of the hollow rod body (11), and the other end extends outward.

3. A fully mechanized mining support structure according to claim 2, characterized in that: One end of the anchor rod is welded to the outer wall of the hollow rod body (11), and the other end faces the closing plate (13) and extends outwardly at an angle.

4. A fully mechanized mining support structure according to claim 1, characterized in that: An elastic grout-stopping pad (15) is installed on one side of the closing plate (13) facing the anchoring portion (12), and the grout-stopping pad (15) is provided with an escape opening (16) at a position located at the grouting hole (14).

5. A fully mechanized mining support structure according to claim 1, characterized in that: The grouting hole (14) is provided with an internal thread.

6. A fully mechanized mining support structure according to claim 1, characterized in that: The mine hole (50) is also filled with a concrete support body (80), and the concrete support body (80) seals the mine hole (50).