Tailing discharging system
By designing a combined structure of ramps and drainage ditches in the tailings pond, the tailings conveying distance is extended, and the problem of poor liquidity of high-concentration tailings is solved, the capacity utilization and safety of the storage capacity is improved, and water and electricity consumption is reduced.
Patent Information
- Application Number
- CN202420667180.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-04-02
- Publication Date
- 2024-11-26
- Estimated Expiration
- 2034-04-02
AI Technical Summary
The liquidity of high-concentration fine-grained tailings is poor when discharged in tailings ponds, resulting in rapid deposition of the beach surface, low storage capacity utilization, and large waste of water resources during low-concentration transportation, high electricity consumption, and safety risks.
A tailings discharge system was designed, including accumulation dams, drainage wells, ramps, drainage ditches and discharge extension pipes. Through the combined structure of ramps and drainage ditches, the tailings conveying distance is extended and the concentration dilution demand is reduced. And set up floating bodies in the discharge ditch to improve emission efficiency.
It effectively solves the problem of poor liquidity of high-concentration tailings, improves the utilization rate of storage capacity, reduces water and electricity consumption, enhances the safety of mine discharge operations, and reduces the danger of dams.
Smart Images

Figure CN222057640U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of tailings discharge, in particular to a tailings discharge system suitable for high-concentration fine-grained tailings. Background Art
[0002] The statements in this section are merely intended to provide background information related to the technical solution of the present application to aid understanding, and they do not necessarily constitute prior art for the technical solution of the present application.
[0003] Wet tailings discharge in mineral processing is to transport the tailings slurry to the tailings pond for deposition and storage, and reuse the clarified return water. Tailings are generated when the mineral processing plant selects the concentrate. The tailings are pressurized by a centrifugal pump and transported to the top of the tailings pond through a pipeline. The discharge main pipe on the top of the dam is connected to the discharge branch pipe in the reservoir and discharged into the reservoir. An existing tailings pond is 8 kilometers away from the mineral processing plant. It is a third-class tailings pond on flat terrain upstream. It is divided into two compartments with an area of 2000m×2000m and 2000m×1800m respectively. A drainage well is set in the reservoir, and the bottom of the well is connected to the drainage culvert and drainage channel to discharge the sediment water.
[0004] Due to the quality of the raw ore and the beneficiation production process, some beneficiation plants produce fine tailings, with -200 mesh accounting for more than 85%, tailings specific gravity reaching 2.75t / m3, and high clay content in the tailings. The supporting tailings conveying equipment and facilities are generally suitable for discharge concentrations of 35%-38%. Therefore, when the concentration is close to or exceeds 40%, the tailings slurry discharged into the reservoir has a slow flow rate and poor fluidity. The tailings slurry deposits quickly at the discharge outlet near the inner slope of the dam, and the beach deposition height rises quickly, causing the discharged tailings to form a beach near the inner slope of the dam, and cannot reach the far end of the reservoir, resulting in low storage capacity utilization. Especially for the system using the peripheral discharge method, the dam body is far away from the drainage well in the reservoir, and there is no tailings deposition seepage discharge pipe in front of the dam at the bottom of the sub-dams of each stage of the surrounding dam body, resulting in a high beach infiltration line when the discharge concentration reaches 40%, and a high safety risk of the upstream heightened accumulation dam. If the tailings are transported and discharged at a low concentration, the return water produced by the tailings concentration will be significantly reduced, or it will be necessary to add return water, reclaimed water, or even clean water, resulting in a large waste of water resources and a high consumption of electrical energy for transporting the tailings.
[0005] In view of the above problems, the present application proposes a tailings discharge system suitable for high-concentration fine-grained tailings. Utility Model Content
[0006] One aspect of the utility model relates to a tailings discharge system, comprising:
[0007] accumulation dam;
[0008] Drainage wells;
[0009] A plurality of ramps extending radially from the top of the dam downwardly toward the drainage well;
[0010] A plurality of drainage ditches, each of which is located between two adjacent ramps and radially extends from the inner slope of the dam downwardly toward the drainage well;
[0011] A discharge main located on the stacking dam;
[0012] a plurality of discharge extension pipes located on the ramp, the discharge extension pipes being coupled to the discharge main pipe; and
[0013] A plurality of discharge extension pipes are located in the discharge ditch, and the discharge extension pipes are coupled to the discharge main pipe.
[0014] In one embodiment, the drainage ditch ends closer to the drainage shaft than the ramp ends.
[0015] In one embodiment, a plurality of drainage ditches are formed between two adjacent inclined ramps.
[0016] In one embodiment, a plurality of discharge extension pipes are laid in each discharge ditch; and / or a plurality of discharge extension pipes are laid on each ramp.
[0017] In one embodiment, the tailings discharge system further comprises: a floating body fixed under the discharge extension pipe in the discharge ditch.
[0018] In one embodiment, the tailings discharge system further comprises: a floating body fixed under the discharge extension pipe located on the ramp.
[0019] In one embodiment, the buoy is a hollow box or a combination thereof.
[0020] In one embodiment, the ore discharge extension pipe is directly coupled to the ore discharge main pipe, or the ore discharge extension pipe is coupled to the ore discharge main pipe via a ore discharge branch pipe.
[0021] In one embodiment, the tailings discharge system further comprises drainage facilities located below the accumulation dam.
[0022] In one embodiment, the drainage facility comprises one or more layers of composite geotextile drainage nets.
[0023] The tailings discharge system based on this application provides a new solution for high-concentration tailings transportation and discharge operations in the reservoir, which can reduce the construction of equipment and facilities and the corresponding production links for diluting the tailings concentration before entering the reservoir area, as well as water and electricity consumption, and can also save water and electricity consumption compared with low-concentration transportation and discharge. This solution solves the problems of poor fluidity of high-concentration tailings discharged into the reservoir, rapid accumulation of the beach near the dam slope, and high beach infiltration line, which is beneficial to the safety of tailings transportation and discharge operations, and improves the effective volume of the existing tailings pond and reduces the danger of the dam body. BRIEF DESCRIPTION OF THE DRAWINGS
[0024] The following is a further description of the embodiments of the present invention with reference to the accompanying drawings, wherein:
[0025] Figure 1 A schematic plan view (partial) of a ramp and a drainage ditch of a tailings discharge system according to one embodiment is shown;
[0026] Figure 2 A schematic cross-sectional view of a tailings discharge system according to one embodiment is shown;
[0027] Figure 3 Shows about Figure 1 A-A' cross-sectional schematic diagram;
[0028] Figure 4 A schematic diagram of a drainage cushion layer at the base of a dam according to an embodiment is shown. DETAILED DESCRIPTION
[0029] In order to make the purpose, technical solution and advantages of the utility model more clear, the utility model is further described in detail through specific embodiments in conjunction with the accompanying drawings. It should be understood that the specific embodiments described here are only used to explain the utility model and are not used to limit the utility model.
[0030] In an existing tailings discharge system, the tailings conveying pipeline leads to the top of the accumulation dam, and its discharge main pipe is connected to the discharge branch pipe extending into the reservoir. When discharging tailings into the tailings pond, if the concentration is controlled at 35%-38%, the conveying pipeline on the dam will not sink, the discharge outlet will not be blocked, and it will be discharged into the reservoir normally. However, when the tailings slurry discharge concentration is close to 40%, the sedimentation speed near the discharge outlet is fast, and the beach surface sedimentation height rises quickly. Even when the tailings discharge concentration is 40% or above, the extension pipe discharge outlet is blocked, the pressure in the discharge main pipe increases suddenly, and a sinking pipe accident will occur at the end, and the beach surface infiltration line is high.
[0031] In order to improve the current situation of tailings in the reservoir area with fine particle size and low bearing capacity, tailings slurry deposits quickly near the inner slope of the dam when the discharge concentration reaches 40%, poor fluidity, high beach infiltration line, and high dam body danger, the tailings sand in the reservoir can be taken or the tailings can be filled into film bags along with the tailings pond. The film bags are arranged and stacked, and the ramps sloping downward from the top of the tailings pond dam body to the drainage well in the reservoir are distributed at large intervals. On the beach between adjacent ramps, a bulldozer can be used to push out the drainage ditch. Along the ramp and the drainage ditch, a drainage extension pipe connected to the dam top drainage main pipe can be laid to its end, and the tailings flow from the outlet of the drainage extension pipe to the drainage well in the reservoir.
[0032] Figure 1 A schematic plan view (partial) of a ramp and a drainage ditch of a tailings discharge system according to an embodiment is shown. The accumulation dam 1 of the tailings discharge system is about 5 meters high, and inside the accumulation dam 1 is a reservoir beach 4, and a drainage well 5. The accumulation dam 1 can be formed by the accumulation of gravel soil.
[0033] A plurality of ramps 2 are built in the reservoir, which extend radially from the top of the dam 1 obliquely downward toward the drainage well 5. In one embodiment, the ramps 2 can be built with tailings sand in the reservoir, compacted in layers, and covered with soil and rolled; or the tailings slurry is filled into geomembrane bags, arranged and stacked in order according to the above distribution positions to form the ramps 2, and then covered with soil.
[0034] There are one or more drainage ditches 3 at the beach 4 in the reservoir between two adjacent ramps 2, which extend radially from the inner slope of the dam 1 downward in the direction of the drainage well 5. The drainage ditches 3 can be evenly spaced. In one embodiment, a bulldozer can be used to push out the drainage ditches. In one embodiment, the end of the drainage ditch 3 can be longer than the end of the ramp 2, that is, closer to the drainage well 5. In one embodiment, the end of the drainage ditch 3 can be 1-5 meters longer than the end of the ramp 2, and preferably 2-3 meters longer. The end of the drainage ditch 3 can be horizontal with the beach 4 in the reservoir.
[0035] Figure 2 A schematic cross-sectional view of a tailings discharge system according to an embodiment is shown. The figure shows a discharge main pipe 6 located on the heap dam 1 and a discharge extension pipe 8 laid on the surface of the ramp 2. Tailings can be discharged into the reservoir through the discharge main pipe 6 and the discharge extension pipe 8. In one embodiment, multiple discharge extension pipes 8 can be laid side by side on the surface of the ramp 2. The discharge extension pipe 8 on the ramp 2 can be pressed and fixed with tailings bags at different positions.
[0036] A discharge extension pipe 8 is also laid along the discharge ditch 3, and the tailings can be discharged into the reservoir through the discharge main pipe 6 and the discharge extension pipe 8. In one embodiment, several discharge extension pipes 8 can be laid along the discharge ditch 3 in parallel.
[0037] exist Figure 2 Also shown is a discharge branch pipe 7, wherein the discharge extension pipe 8 is coupled to the discharge main pipe 6 via the discharge branch pipe 7. In one embodiment, the discharge extension pipe 8 can also be directly coupled to the discharge main pipe 6, and the discharge branch pipe 7 can be omitted.
[0038] By laying a discharge extension pipe 8 on the ramp 2 and the discharge ditch 3 to discharge tailings, the tailings slurry can be discharged to a far distance in the reservoir as needed, which changes the defects of the original tailings discharge and deposition in the area in front of the dam, low reservoir capacity utilization, and high beach surface infiltration line. In addition, the discharge extension pipe 8 only needs to be connected once, and does not need to be deposited on the beach surface with the discharge of ore within the elevation (for example, 5 meters) of the accumulation dam 1. The discharge extension pipe is repeatedly connected after being buried each time and the beach surface is consolidated.
[0039] Figure 3 Shows about Figure 1 In one embodiment, a float 9 is fixed under the discharge extension pipe 8 laid in the discharge ditch 3. The float 9 can be, for example, a high-strength polyethylene hollow float, or a hollow box or a combination thereof.
[0040] The siltation of tailings sediment water at the end of the discharge extension pipe 8 in the discharge ditch 3 may affect the discharge efficiency of the discharge extension pipe 8. When the floating body 9 is provided, when the discharged tailings sediment water slowly gathers at the floating body 9, the discharge extension pipe 8 can be floated by the floating body 9 and can drift and change its position naturally, which is conducive to the continuous discharge of tailings.
[0041] In one embodiment, a floating body 9 may also be fixed under the discharge extension pipe 8 laid on the ramp 2 .
[0042] In one embodiment, the number, width and length of the ramp 2 and the discharge ditch 3 can be determined according to the actual situation of the tailings discharged during production (e.g., production conditions and factors of the beach surface in the reservoir), and the length, number and diameter of the corresponding discharge extension pipe 8 can be determined. The length can be determined by considering the total length from the inner edge of the dam to the nearest drainage well minus the shortest distance that the tailings can be clarified around the drainage well and the shortest distance for the slurry to flow by itself, and a certain margin can be left.
[0043] In one embodiment, the discharge extension pipe 8 can be made of thin-walled PE composite pipe (e.g., DN200 and DN150), hot-melt connection, and end opening. As the discharge beach surface rises, the discharge extension pipe 8 on the ramp 2 will be gradually buried, so artificial cutting can be arranged to reopen. When opening, the first mouth can be opened just above the 500mm position from the outlet, the DN200 PE pipe opens a mouth of about 30mm wide and about 1000mm long, and the DN150 PE pipe opens a mouth of about 25mm wide and about 1000mm long. The second mouth and the first mouth can be spaced about 500mm apart, and the size is the same. The flooding of the discharge port can be observed in time, the discharge valve of the discharge extension pipe 8 can be adjusted to close, and the interval of 3-5 meters is determined according to the slope of the ramp 2, and then the next group of openings is cut.
[0044] In one embodiment, tailings may be loaded into geomembrane bags to build the ramp 2 , for example, conventional 50m*10m geomembrane bags may be used, and specific specification parameters may be sufficient to build the ramp 2 .
[0045] In one embodiment, the float 9 can be a hollow pontoon made of high-strength UV-resistant polyethylene, or a pontoon assembly, the size of which can float the weight of the discharge extension pipe 8 when the pipe is full of slurry. In actual operation, multiple groups of floats 9 can be fixedly connected to the discharge extension pipe 8 at a certain distance.
[0046] In one embodiment, at the starting end of the tailings pressurized transportation, before the tailings are concentrated, collected and transported in each workshop, a stirring device can be installed to fully mix the tailings slurry before entering the pressurized delivery pump. After the tailings slurry concentration is uniform, the pressure fluctuation of the discharge pipeline is small, which avoids the pipeline pressure fluctuating and the tailings discharge being poor. In one embodiment, the tailings transported from the production workshop are concentrated by different high-efficiency thickeners, and the concentrated tailings slurry is collected into the slurry pool before the pressurized transportation. A stirring device is installed on the slurry pool to continuously stir the concentrated tailings slurry.
[0047] In one embodiment, the conditions of tailings discharge and beach surface in the reservoir can be fed back to the front-end tailings transportation operation in a timely manner, so as to dispatch and adjust the tailings discharge mainly with high concentration and interspersed with low concentration, timely reduce the concentration of the transported slurry, and use low-concentration and high-flow slurry to flush the slurry close to the inner slope of the dam, thereby promoting the flow of tailings slurry to the center of the reservoir area.
[0048] In one embodiment, when building the dam 1, drainage facilities can be added underneath it. Figure 4The schematic diagram of the drainage cushion layer of the base of the accumulation dam according to an embodiment is shown. When building the accumulation dam, a certain distance B is extended parallel to the horseway on the dam surface of the previous accumulation dam, and the value can be about 40 meters. The tailings cushion layer in this area has relatively coarse particles and relatively good mechanical properties. The beach surface is compacted, and a gravel cushion layer and a composite geotextile drainage net are laid to form a drainage system under the accumulation dam. In one embodiment, a second layer of composite geotextile drainage net can be laid at a certain elevation to improve and promote the drainage of sediment water in the reservoir by the dam body.
[0049] In one embodiment, a roller can be used to compact the beach surface, and a 600mm thick gravel layer can be laid to form a cushion layer with a slope of 1%-2% outward, on which a composite geotextile drainage net can be laid. The length can be 42m×width 5m, the thickness can be 6.3mm, and the water conductivity can be ≥4.8x10-3m 2 / s, two ribs, two sides of composite geotextile. The composite geotextile drainage net is arranged vertically to the dam body, sewed and overlapped with nylon thread, and the surface is covered with 600mm of soil and compacted. If a second layer of composite geotextile drainage net is needed, it can be spaced about 600mm in elevation.
[0050] References herein to "various embodiments", "some embodiments", "one embodiment", or "an embodiment" refer to specific features, structures, or properties described in conjunction with the embodiments being included in at least one embodiment. Therefore, the phrases "in various embodiments", "in some embodiments", "in one embodiment", or "in an embodiment" appearing throughout the present invention do not necessarily refer to the same embodiment. In addition, specific features, structures, or properties may be combined in any suitable manner in one or more embodiments. Therefore, specific features, structures, or properties shown or described in conjunction with one embodiment may be combined in whole or in part with features, structures, or properties of one or more other embodiments without restriction, as long as the combination is not illogical or inoperable. Expressions similar to "according to A", "based on A", "through A", or "using A" appearing herein are intended to be non-exclusive, that is, "according to A" may include "according to A only" or "according to A and B", unless it is specifically stated that its meaning is "according to A only". In this application, for the sake of clarity, some exemplary operating steps are described in a certain order, but those skilled in the art will understand that each of these operating steps is not essential, and some of the steps may be omitted or replaced by other steps. These operation steps do not have to be executed sequentially in the manner shown; on the contrary, some of these operation steps can be executed in different orders or in parallel according to actual needs, as long as the new execution manner is not illogical or inoperable.
[0051] Having thus described several aspects of at least one embodiment of the present invention, it will be appreciated that various changes, modifications and improvements will readily occur to those skilled in the art. Such changes, modifications and improvements are intended to be within the spirit and scope of the present invention. Although the present invention has been described by way of some embodiments, the present invention is not limited to the embodiments described herein, and includes various changes and variations made without departing from the scope of the present invention.
Claims
1. A tailings discharge system, comprising: accumulation dam; Drainage wells; A plurality of ramps extending radially from the top of the dam downwardly toward the drainage well; A plurality of drainage ditches, each of which is located between two adjacent ramps and radially extends from the inner slope of the dam downwardly toward the drainage well; A discharge main located on the stacking dam; a plurality of discharge extension pipes located on the ramp, the discharge extension pipes being coupled to the discharge main pipe; and A plurality of discharge extension pipes are located in the discharge ditch, and the discharge extension pipes are coupled to the discharge main pipe.
2. The tailings discharge system according to claim 1, wherein: The end of the drainage ditch is closer to the drainage well than the end of the ramp.
3. The tailings discharge system according to claim 1, wherein: A plurality of drainage ditches are formed between two adjacent ramps.
4. The tailings discharge system according to claim 1, wherein: Multiple discharge extension pipes are laid in each discharge trench; and / or Multiple discharge extension pipes are laid on each ramp.
5. The tailings discharge system according to claim 1, further comprising: A floating body is fixed under the ore discharge extension pipe in the ore discharge ditch.
6. The tailings discharge system according to claim 4, further comprising: A floating body is fixed under the ore discharge extension pipe on the ramp.
7. The tailings discharge system according to claim 5 or 6, wherein: The floating body is a hollow box or a combination thereof.
8. The tailings discharge system according to claim 1, wherein: The ore discharge extension pipe is directly coupled to the ore discharge main pipe, or the ore discharge extension pipe is coupled to the ore discharge main pipe via a ore discharge branch pipe.
9. The tailings discharge system according to claim 1, further comprising drainage facilities located below the accumulation dam.
10. The tailings discharge system according to claim 9, wherein: The drainage facility comprises one or more layers of composite geotextile drainage net.