Quickly disassembled steel beam lifting lug
By designing quickly disassembled steel beam lifting lugs, using a combined structure of cover plate, boom, fixture and connecting plate, the surface damage and resources of steel beam lifting lugs caused by welding and drilling during installation of steel beam lifting lugs in the prior art are solved. The waste problem has achieved efficient lifting and disassembly of steel beams, reducing the risk of rust and corrosion.
Patent Information
- Application Number
- CN202420421737.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-05
- Publication Date
- 2024-11-26
- Estimated Expiration
- 2034-03-05
AI Technical Summary
The installation method of hanging lugs in existing steel structure buildings requires welding and drilling, which leads to damage to the anti-corrosion coating on the surface of steel beams, increases the risk of rust and corrosion, and wastes resources and long construction time.
A quick-disassembled steel beam hanging lug is designed, using a combined structure of cover plate, boom, fixture, connecting plate and elastic parts. Through sliding and rotating connection, the fixture clamps the steel beam to avoid welding and drilling, and realizes Quick disassembly.
The design does not damage the main structure of the steel beam, improves installation efficiency, reduces the risk of rust and corrosion, and saves resources and construction time.
Smart Images

Figure CN222063892U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of building construction hoisting, in particular to a fast-detachable steel beam lifting lug. Background Art
[0002] In recent years, more and more steel structures have appeared in people's lives. Steel structures have the characteristics of low comprehensive cost, environmental protection and cleanliness, fast construction speed, strong earthquake resistance, high space utilization, flexible design, energy saving and environmental protection, easy recycling, high compressive strength and high space utilization. At present, the installation method of steel beams of steel structures is usually to weld 2 to 4 steel lifting ears on the upper part of the steel beam, connect and fix the welded lifting ears with steel wire ropes through clamps, and then hoist them through lifting equipment. After the installation, the lifting ears are cut off.
[0003] First of all, this lifting method destroys the anti-corrosion coating on the surface of the steel beam during the welding of the lifting lugs, making the welds more susceptible to rust and corrosion during subsequent use. This will reduce the service life of the steel beam. Secondly, the lifting lugs in this process are all disposable, which is a waste of resources. Finally, welding the lifting lugs before lifting and cutting the lifting lugs after lifting both waste a lot of on-site construction time.
[0004] The Chinese patent with publication number CN204224098U discloses a steel beam lifting lug, which needs to be punched on the upper surface of the steel beam, and then the steel beam is clamped through the opening of the steel beam lifting lug, and the bolt is fixed to the steel beam through the hole. This design requires drilling holes in the steel beam, which will also damage the coating on the surface of the steel beam, further increasing the probability of rust and corrosion of the steel beam, and the procedure of drilling holes in the steel beam will increase the on-site operation time. Utility Model Content
[0005] The main purpose of the utility model is to provide a fast-detachable steel beam lifting eye to solve the problems existing in the prior art.
[0006] In order to solve the above-mentioned technical problems, the technical solution adopted by the utility model is to propose a quickly disassembled steel beam lifting ear, including: a cover plate, a hanger, a clamp, a first connecting plate, a second connecting plate and an elastic member; the hanger is slidably connected to the cover plate; the clamp is slidably connected to the cover plate, and the clamp includes a first clamp arm and a second clamp arm arranged opposite to each other; the first connecting plate is rotatably arranged on the cover plate, one end of the first connecting plate is movably connected to the hanger, and the other end of the first connecting plate is movably connected to the first clamp arm; the second connecting plate is rotatably arranged on the cover plate, one end of the second connecting plate is movably connected to the hanger, and the other end of the second connecting plate is movably connected to the second clamp arm; one end of the elastic member is sleeved on the hanger, and the other end of the elastic member abuts against the cover plate.
[0007] In a preferred embodiment, the surface of the cover plate has a first guide groove, and the first clamping arm is slidably connected to the cover plate via the first guide groove; the surface of the cover plate has a second guide groove, and the second clamping arm is slidably connected to the cover plate via the second guide groove; the surface of the cover plate has a third guide groove, and the suspension rod is slidably connected to the cover plate via the third guide groove; the surface of the cover plate has a first through hole, and the first connecting plate is rotatably connected to the cover plate via the first through hole; the surface of the cover plate has a second through hole, and the second connecting plate is rotatably connected to the cover plate via the second through hole; the surface of the cover plate has a protruding block, and the protruding block is suitable for abutting against the elastic member.
[0008] In a preferred embodiment, the first connecting plate is in a "V" shape, and a vertically arranged first connecting column is provided at the top corner of the first connecting plate, the first connecting column matches the first through hole, and the first connecting plate is rotatably connected to the cover plate through the first connecting column; the two ends of the first connecting plate are respectively provided with a vertically arranged second connecting column and a third connecting column;
[0009] In a preferred embodiment, the second connecting plate is in a "V" shape, and a fourth connecting column is vertically arranged at the top corner of the second connecting plate, the fourth connecting column matches the second through hole, and the second connecting plate is rotatably connected to the cover plate through the fourth connecting column; the two ends of the second connecting plate respectively have a fifth connecting column and a sixth connecting column vertically arranged.
[0010] In a preferred solution, a first sliding groove is provided at one end of the first clamp arm, and the first sliding groove is suitable for the second connecting column to slide inside;
[0011] In a preferred solution, a second sliding groove is formed at one end of the second clamping arm, and the second sliding groove is suitable for the fifth connecting column to slide inside.
[0012] In a preferred solution, a third sliding groove is provided at the lower part of the suspension rod, and the third sliding groove is suitable for slidingly connecting the third connecting column and the fourth connecting column; a fourth sliding groove is provided on the suspension rod, and the fourth sliding groove is suitable for accommodating the fixed elastic member. A hanging hole is provided at the top of the suspension rod, and is suitable for installing a wire rope.
[0013] In a preferred solution, the elastic member is a spring.
[0014] The beneficial effects of the utility model are as follows: the first clamp arm and the second clamp arm are used to clamp the steel beam, and when the suspension rod is subjected to an upward force, the force is converted into a force for the first clamp arm and the second clamp arm to clamp the steel beam toward the middle through the first connecting plate and the second connecting plate. The heavier the weight of the steel beam, the greater the clamping force of the first clamp arm and the second clamp arm toward the middle. When the longitudinal force on the suspension rod decreases after the steel beam is hoisted into place, the supporting force of the first clamp arm and the second clamp arm toward the middle will also decrease. This allows the steel beam to be placed directly on the steel column. This hoisting process does not require the destruction of the main structure of the steel beam. Since drilling and welding of lifting ears are not required, quick disassembly is achieved, further improving the efficiency of installation. BRIEF DESCRIPTION OF THE DRAWINGS
[0015] The utility model is further described below in conjunction with the accompanying drawings and embodiments:
[0016] Figure 1 It is a schematic diagram of the main structure of the quick-disassembly steel beam lifting lug of the utility model;
[0017] Figure 2 It is the front view of the cover plate of the utility model;
[0018] Figure 3 It is a schematic diagram of the main structure of the first connecting plate of the utility model;
[0019] Figure 4 It is a schematic diagram of the main structure of the second connecting plate of the utility model;
[0020] Figure 5 It is a schematic diagram of the main structure of the first clamping arm of the utility model;
[0021] Figure 6 It is a schematic diagram of the main structure of the second clamping arm of the utility model;
[0022] Figure 7 It is a schematic diagram of the main structure of the utility model suspension rod;
[0023] Figure 8 It is a schematic diagram of the hoisting of the utility model.
[0024] In the figure: cover plate 1, first guide groove 11, second guide groove 12, third guide groove 13, first through hole 14, second through hole 15, protruding block 16, hanging rod 2, third slide groove 21, fourth slide groove 22, hanging hole 23, clamp 3, first clamp arm 31, first slide groove 311, second clamp arm 32, second slide groove 321, first connecting plate 4, first connecting column 41, second connecting column 42, third connecting column 43, second connecting plate 5, fourth connecting column 51, fifth connecting column 52, sixth connecting column 53, elastic member 6, steel beam 7. DETAILED DESCRIPTION
[0025] like Figures 1 to 7As shown, the quick-detachable steel beam lifting ear comprises: a cover plate 1, a suspension rod 2, a clamp 3, a first connecting plate 4, a second connecting plate 5 and an elastic member 6; the suspension rod 2 is slidably connected to the cover plate 1; the clamp 3 is slidably connected to the cover plate 1, and the clamp 3 comprises a first clamp arm 31 and a second clamp arm 32 which are arranged opposite to each other; the first connecting plate 4 is rotatably arranged on the cover plate 1, one end of the first connecting plate 4 is movably connected to the suspension rod 2, and the other end of the first connecting plate 4 is movably connected to the first clamp arm 31; the second connecting plate 5 is rotatably arranged on the cover plate 1, one end of the second connecting plate 5 is movably connected to the suspension rod 2, and the other end of the second connecting plate 5 is movably connected to the second clamp arm 32; one end of the elastic member 6 is sleeved on the suspension rod 2, and the other end of the elastic member 6 is abutted against the cover plate 1.
[0026] In this embodiment, the steel beam 7 is clamped by the first clamp arm 31 and the second clamp arm 32, and when the suspension rod 2 is subjected to an upward force, the force is converted into a force for the first clamp arm 31 and the second clamp arm 32 to clamp the steel beam 7 in the middle through the first connecting plate 4 and the second connecting plate 5. The heavier the weight of the steel beam 7, the greater the clamping force of the first clamp arm 31 and the second clamp arm 32 in the middle. When the longitudinal force on the suspension rod 2 decreases after the steel beam 7 is hoisted into place, the supporting force of the first clamp arm 31 and the second clamp arm 32 in the middle will also decrease accordingly. This allows the steel beam 7 to be placed directly on the steel column. This hoisting process does not require the destruction of the main structure of the steel beam 7. Since drilling and welding of lifting ears are not required, quick disassembly is achieved, further improving the efficiency of installation.
[0027] In one of the specific embodiments, the surface of the cover plate 1 has a first guide groove 11, and the first clamp arm 31 is slidably connected to the cover plate 1 through the first guide groove 11; the surface of the cover plate 1 has a second guide groove 12, and the second clamp arm 32 is slidably connected to the cover plate 1 through the second guide groove 12; the surface of the cover plate 1 has a third guide groove 13, and the suspension rod 2 is slidably connected to the cover plate 1 through the third guide groove 13; the surface of the cover plate 1 has a first through hole 14, and the first connecting plate 4 is rotatably connected to the cover plate 1 through the first through hole 14; the surface of the cover plate 1 has a second through hole 15, and the second connecting plate 5 is rotatably connected to the cover plate 1 through the second through hole 15; the surface of the cover plate 1 has a protrusion 16, and the protrusion 16 is suitable for abutting against the elastic member 6. In this design, the cover plate 1 is narrow at the top and wide at the bottom, and the first guide groove 11 is longitudinally arranged in the middle position of the upper part of the cover plate 1, and the first guide groove 11 is composed of two protrusions. The second guide groove 12 is transversely arranged at the lower left position of the cover plate 1, and the second guide groove 12 is composed of two protrusions with a short upper part and a long lower part, and the short protrusion is suitable for avoiding the first connecting plate 4. The third guide groove 13 is composed of two protrusions with a short upper part and a long lower part, and the short protrusion is suitable for avoiding the second connecting plate 5. The protrusion block 16 is located in the first guide groove 11.
[0028] In one specific embodiment, the first connecting plate 4 is in a "V" shape, and a vertically arranged first connecting column 41 is provided at the top corner of the first connecting plate 4, the first connecting column 41 matches the first through hole 14, and the first connecting plate 4 is rotatably connected to the cover plate 1 through the first connecting column 41; the two ends of the first connecting plate 4 are respectively provided with a vertically arranged second connecting column 42 and a third connecting column 43; in this design, the first connecting plate 4 is in an inverted V shape. The first connecting column 41 is located at the top.
[0029] In one specific embodiment, the second connecting plate 5 is in a "V" shape, and a fourth connecting column 51 is vertically arranged at the top corner of the second connecting plate 5, and the fourth connecting column 51 matches the second through hole 15. The second connecting plate 5 is rotatably connected to the cover plate 1 through the fourth connecting column 51; the two ends of the second connecting plate 5 are respectively provided with a fifth connecting column 52 and a sixth connecting column 53 vertically arranged. In this design, the second connecting plate 5 is in an inverted V shape. The fourth connecting column 51 is located at the top.
[0030] In one specific embodiment, a first sliding groove 311 is provided at one end of the first clamp arm 31, and the first sliding groove 311 is suitable for the second connecting column 42 to slide inside; in this design, the first clamp arm 31 is a semi-enclosed structure, and the other end of the first clamp arm 31 has a clamping block suitable for clamping the steel beam 7.
[0031] In one specific embodiment, a second slide groove 321 is formed at one end of the second clamp arm 32, and the second slide groove 321 is suitable for the fifth connecting column 52 to slide inside. In this design, the second clamp arm 32 is a semi-enclosed structure, and the other end of the second clamp arm 32 has a clamp block suitable for clamping the steel beam 7.
[0032] In one specific embodiment, a third sliding groove 21 is disposed transversely at the lower portion of the suspension rod 2, and the third sliding groove 21 is suitable for slidingly connecting the third connecting column 43 and the fourth connecting column 51 therein; a fourth sliding groove 22 is disposed on the suspension rod 2, and the fourth sliding groove 22 is suitable for accommodating the fixing elastic member 6. A hanging hole 23 is provided at the top of the suspension rod 2, and is suitable for installing a wire rope.
[0033] In one specific embodiment, the elastic member 6 is a spring.
[0034] like Figure 8 As shown, when the steel beam 7 is not hoisted, the elastic member 6 makes the suspension rod 2 and the cover plate 1 overlap with each other in a large area. In this state, the third connection column 43 of the first connection plate 4 is located at the end of the third slide groove 21, and the sixth connection column 53 of the second connection plate 5 is located at the other end of the third slide groove 21. The second connection column 42 of the first connection plate 4 is located at the upper end of the first slide groove 311, and the fifth connection column 52 of the second connection plate 5 is located at the upper end of the second slide groove 321. At this time, the clamp 3 is in a far away state.
[0035] When it is necessary to hoist the steel beam 7, the clamping end of the first clamping arm 31 or the second clamping arm 32 needs to be placed on the lower end surface of the upper flange of the I-beam 7, so that when the hoisting equipment hoists the steel beam 7 upward, the first clamping arm 31 or the second clamping arm 32 can maintain the same height during the rising process of the suspension rod 2. At this time, the protruding block 16 compresses the elastic member 6, and the suspension rod 2 moves upward relative to the cover plate 1 in the third guide groove 13. The suspension rod 2 drives the third connecting column 43 to rotate counterclockwise, and the third connecting column 43 slides to the middle position in the third slide groove 21. Further drive the second connecting column 42 to rotate counterclockwise, pull the first clamping arm 31 along the first guide groove 11 to approach the middle, and the second connecting column 42 moves downward inside the first slide groove 311. The suspension rod 2 drives the sixth connecting column 53 to rotate clockwise, and the sixth connecting column 53 slides to the middle position in the third slide groove 21. The fifth connecting column 52 is further driven to rotate clockwise, pulling the second clamping arm 32 toward the middle position along the second guide groove 12, and the fifth connecting column 52 moves downward inside the second sliding groove 321. Thus, the operation of clamping the steel beam 7 is completed.
[0036] After the first clamping arm 31 and the second clamping arm 32 clamp the steel beam 7 , the lifting device can continue to lift the steel beam 7 .
[0037] The above embodiments are only preferred technical solutions of the present invention and should not be regarded as limitations of the present invention. The protection scope of the present invention shall be the technical solutions recorded in the claims, including equivalent replacement solutions of the technical features in the technical solutions recorded in the claims. That is, equivalent replacement improvements within this scope are also within the protection scope of the present invention.
Claims
1. A quick-detachable steel beam lifting eye, characterized in that: include: A cover plate (1), a suspension rod (2), a clamp (3), a first connecting plate (4), a second connecting plate (5), and an elastic member (6); The suspension rod (2) is slidably connected to the cover plate (1); The clamp (3) is slidably connected to the cover plate (1), and the clamp (3) comprises a first clamp arm (31) and a second clamp arm (32) which are arranged opposite to each other; The first connecting plate (4) is rotatably arranged on the cover plate (1), one end of the first connecting plate (4) is movably connected to the suspension rod (2), and the other end of the first connecting plate (4) is movably connected to the first clamping arm (31); The second connecting plate (5) is rotatably arranged on the cover plate (1), one end of the second connecting plate (5) is movably connected to the suspension rod (2), and the other end of the second connecting plate (5) is movably connected to the second clamping arm (32); One end of the elastic member (6) is sleeved on the suspension rod (2), and the other end of the elastic member (6) is in contact with the cover plate (1).
2. The quick-detachable steel beam lifting eye according to claim 1, characterized in that: The surface of the cover plate (1) has a first guide groove (11), and the first clamping arm (31) is slidably connected to the cover plate (1) via the first guide groove (11); The surface of the cover plate (1) has a second guide groove (12), and the second clamping arm (32) is slidably connected to the cover plate (1) via the second guide groove (12); The surface of the cover plate (1) is provided with a third guide groove (13), and the suspension rod (2) is slidably connected to the cover plate (1) via the third guide groove (13); The surface of the cover plate (1) has a first through hole (14), and the first connecting plate (4) is rotatably connected to the cover plate (1) via the first through hole (14); The surface of the cover plate (1) has a second through hole (15), and the second connecting plate (5) is rotatably connected to the cover plate (1) via the second through hole (15); The surface of the cover plate (1) is provided with a protruding block (16), and the protruding block (16) is suitable for abutting against the elastic member (6).
3. The quick-detachable steel beam lifting eye according to claim 2, characterized in that: The first connecting plate (4) is in a "V" shape, and has a vertically arranged first connecting column (41) at a top corner of the first connecting plate (4), the first connecting column (41) matches the first through hole (14), and the first connecting plate (4) is rotatably connected to the cover plate (1) via the first connecting column (41); and the two ends of the first connecting plate (4) respectively have a vertically arranged second connecting column (42) and a third connecting column (43).
4. The quick-detachable steel beam lifting eye according to claim 3, characterized in that: The second connecting plate (5) is in a "V" shape, and a fourth connecting column (51) is vertically arranged at a top corner of the second connecting plate (5), the fourth connecting column (51) matches the second through hole (15), and the second connecting plate (5) is rotatably connected to the cover plate (1) via the fourth connecting column (51); The two ends of the second connecting plate (5) are respectively provided with a fifth connecting column (52) and a sixth connecting column (53) which are arranged vertically.
5. The quick-detachable steel beam lifting eye according to claim 4, characterized in that: A first sliding groove (311) is formed at one end of the first clamping arm (31), and the first sliding groove (311) is suitable for the second connecting column (42) to slide inside.
6. The quick-detachable steel beam lifting eye according to claim 5, characterized in that: A second sliding groove (321) is formed at one end of the second clamping arm (32), and the second sliding groove (321) is suitable for the fifth connecting column (52) to slide inside.
7. The quick-detachable steel beam lifting eye according to claim 6, characterized in that: A third sliding groove (21) is disposed transversely at the lower portion of the suspension rod (2), and the third sliding groove (21) is suitable for slidingly connecting the third connecting column (43) and the sixth connecting column (53) therein; A fourth slide groove (22) is provided on the suspension rod (2), and the fourth slide groove (22) is suitable for accommodating a fixed elastic member (6); The top of the suspension rod (2) is provided with a suspension hole (23) suitable for installing a steel wire rope.
8. The quick-detachable steel beam lifting eye according to claim 1, characterized in that: The elastic member (6) is a spring.