Built-in shear hinge steel spring floating slab ballast bed with newly-added overhead shear hinge

By designing an upper shear hinge structure of an inverted conical shear hinge anchoring screw and a transparent silicone sleeve in a steel spring floating plate bed, the problem of limited installation space after the mid-type shear hinge fails, and shearing is achieved The improvement of transmission and maintenance efficiency is suitable for the repair of existing roadbeds.

CN222065043UActive Publication Date: 2024-11-26CHINA RAILWAY SHANGHAI DESIGN INST GRP CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420168848.4
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-01-24
Publication Date
2024-11-26
Estimated Expiration
2034-01-24

AI Technical Summary

Technical Problem

In steel spring floating plate beds, after the middle shear hinge fails, the upper shear hinge often faces space limitations when installing the upper shear hinge, and it is difficult to effectively replace the failure of the middle shear hinge.

Method used

Design an upper shear hinge structure including an inverted conical shear hinge anchoring screw and a transparent silicone sleeve. It is installed on the floating plate by anchoring screw and anchoring agent to ensure shear transmission and provide observation convenience, combined with leveling Steel plate and adhesive for stable installation.

Benefits of technology

Effectively reduce installation space, improve installation efficiency and maintenance convenience, ensure the stability and reliability of shear hinges, and are suitable for repairing existing roadbeds.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222065043U_ABST
    Figure CN222065043U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of floating slab ballast beds, in particular to a built-in shear hinge steel spring floating slab ballast bed with newly added top-mounted shear hinges, at least one top-mounted shear hinge is arranged between adjacent floating slabs, each top-mounted shear hinge comprises two shear hinge bases, and each top-mounted shear hinge base is provided with a steel spring. The two shear hinge bases are installed on the floating slabs on the two sides through shear hinge anchoring screws correspondingly, and the two shear hinge bases are connected through a hinge rod. The shear hinge anchoring screw is an inverted-cone-shaped screw and anchored into the floating slab, and an anchoring agent is arranged on the periphery of the anchored part. The top-mounted shear hinge has the advantages that the top-mounted shear hinge is mounted, the size can be effectively reduced while the using effect is ensured, and therefore the problem that the mounting space is limited is solved; by arranging the transparent silicon rubber case, a maintainer can quickly observe whether the shear hinge is broken or not, and the working efficiency is improved; the structure is simple and reasonable, installation is convenient and popularization is facilitated.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of floating slab roadbeds, in particular to a floating slab roadbed with built-in shear hinge steel springs and a newly added upper shear hinge. Background Art

[0002] At present, the steel spring floating plate track bed is widely used due to its advantages in performance, especially the advantages of vibration reduction effect. In order to ensure the integrity of the steel spring floating plate track bed, a central shear hinge is generally set between each floating plate, and the load is borne by the shear force transmitted through the central shear hinge, so that each floating plate can bear the force together under the vertical load.

[0003] However, as the operating period increases, the center-mounted shear hinge often fails, such as the shear hinge steel rod breaks. At this time, since the center-mounted shear hinge is embedded in the plate body of the floating plate, it is a difficult technical problem to repair the center-mounted shear hinge. Based on this, the current method is mainly to compensate for the failure of the center-mounted shear hinge by adding an upper shear hinge between the floating plates. However, in the existing steel spring floating plate track bed that has been put into operation, the additional installation of an upper shear hinge on the floating plate often faces the problem of limited installation space. At the same time, how to ensure that the upper shear hinge can effectively replace the center-mounted shear hinge is also a technical problem that needs to be solved urgently. Summary of the invention

[0004] The purpose of the utility model is to provide a steel spring floating plate ballast with an internal shear hinge and a newly added upper shear hinge in accordance with the above-mentioned deficiencies of the prior art. When the internal shear hinge (mid-mounted shear hinge) has failed, an upper shear hinge with optimized structure is added between the floating plates of the steel spring floating plate ballast to realize the transmission of shear force between the floating plates and ensure that the floating plates are subjected to force together.

[0005] The purpose of this utility model is achieved by the following technical solutions:

[0006] A steel spring floating slab track bed with built-in shear hinges and a newly added upper shear hinge comprises a plurality of floating slabs arranged along the line direction, and is characterized in that: at least one set of upper shear hinges is arranged between adjacent floating slabs, and the upper shear hinges comprise two shear hinge bases, the two shear hinge bases are respectively mounted on the floating slabs on both sides through shear hinge anchoring screws, and the two shear hinge bases are connected through a hinge rod; the shear hinge anchoring screw is an inverted conical screw, which is anchored in the floating slab and an anchoring agent is arranged on the periphery of the anchored part.

[0007] The outer sleeve of the hinge rod is provided with a transparent silicone sleeve, and the transparent silicone sleeve is arranged between the two shear hinge bases.

[0008] A leveling steel plate is arranged under the shear hinge base.

[0009] The bottom surface of the leveling steel plate is coated with steel adhesive.

[0010] Two or more sets of the upper shear hinges are arranged along the transverse direction of the floating plate, and the upper shear hinges are arranged at intervals.

[0011] The anchoring agent is a modified vinyl ester anchoring adhesive.

[0012] The shear hinge anchoring screw is fastened by a nut and a disc spring. A pin hole is arranged on the top of the shear hinge anchoring screw. A limiting steel bar with two ends bent downward is arranged in the pin hole.

[0013] The advantages of the utility model are: it can realize the installation of the top-mounted shear hinge, effectively reduce the volume while ensuring the use effect, thereby solving the problem of limited installation space; by providing a transparent silicone sleeve, maintenance personnel can quickly observe whether the shear hinge is broken, thereby improving work efficiency; the structure is simple and reasonable, the installation is convenient, and it is suitable for promotion. BRIEF DESCRIPTION OF THE DRAWINGS

[0014] Figure 1 This is a schematic diagram of the structure of the upper shear hinge of the utility model;

[0015] Figure 2 for Figure 1 AA section view;

[0016] Figure 3 for Figure 1 BB cross-section diagram;

[0017] Figure 4 This is a cross-sectional view of the utility model when applied to an underground rail transit line;

[0018] Figure 5 It is a plan view of the utility model when it is applied to the underground line of rail transit;

[0019] Figure 6 This is a cross-sectional view of the utility model when applied to an elevated rail transit line;

[0020] Figure 7 It is a plan view of the utility model when applied to a rail transit elevated line. DETAILED DESCRIPTION

[0021] The following is a further detailed description of the features of the present invention and other related features through embodiments in conjunction with the accompanying drawings to facilitate understanding by technicians in the same industry:

[0022] like Figure 1-7As shown, the marks 1-10 in the figure respectively represent: shear hinge base 1, shear hinge anchor screw 2, hinge rod 3, transparent silicone sleeve 4, pin hole 5, leveling steel plate 6, steel glue 7, inverted cone screw 8, upper shear hinge 9, floating plate 10.

[0023] Example: Figures 1 to 7 As shown, in this embodiment, a built-in shear hinge steel spring floating slab track bed with a newly added upper shear hinge is used to add an upper shear hinge above the top surface of the floating slab 10 when the built-in middle shear hinge between the floating slabs 10 fails, so that each floating slab 10 can still be connected as a whole, thereby achieving the purpose of common force.

[0024] Specifically, combined Figures 1 to 3 As shown, the top-mounted shear hinge in this embodiment includes two shear hinge bases 1 of the same structure, which are symmetrically arranged and connected to form an integral structure through a hinge rod 3, thereby realizing shear force transmission. The shear hinge base 1 is anchored on the floating plate 10 through four uniformly arranged shear hinge anchor screws 2.

[0025] In this embodiment, the bottom of the shear hinge anchor screw 2 is set as an inverted conical screw 8, which has an inverted conical portion to provide pull-out resistance to the shear hinge anchor screw 2, so that the shear hinge base 1 can be more firmly installed on the floating plate 10, so that the volume of the upper shear hinge can be reduced to a certain extent, and there is no need to use an upper large shear hinge to meet the shear force transmission requirements. At the same time, in this embodiment, when the inverted conical screw 8 is anchored into the borehole of the floating plate 10, the borehole of the floating plate 10 is also filled with a modified vinyl ester anchoring glue as an anchoring agent. The modified vinyl ester anchoring glue itself provides bonding force on the one hand, that is, it can bond the inverted conical screw 8 to the floating plate 10 to form a whole, and on the other hand, the inverted conical portions of the inverted conical screw 8 provide locking force and expansion force, thereby further improving the connection performance between the shear hinge anchor screw 2 and the floating plate 10, and ensuring the installation stability of the shear hinge base 1.

[0026] In this embodiment, the anchoring agent is modified vinyl ester anchoring glue. According to the temperature in the underground tunnel line within the range of 20-25°C, the curing time is 45min-1.5h; the recommended temperature for elevated line construction is greater than 20°C.

[0027] A leveling steel plate 6 is provided below the shear hinge base 1. The leveling steel plate 6 is used to provide a flat mounting surface for the shear hinge base 1, so that the shear hinge base 1 can be mounted on a plane to ensure uniform shear force transmission. At the same time, a steel adhesive 7 is coated on the bottom of the leveling steel plate 6 to connect with the floating plate 10. If the surface of the floating plate 10 is obviously uneven, it is chiseled flat.

[0028] like Figure 2As shown, the hinge rod 3 between the shear hinge bases 1 is covered with a transparent silicone sleeve 4 on its outer periphery. The transparent silicone sleeve 4 protects the hinge rod 3 to a certain extent and is also convenient for observing whether the shear hinge is broken.

[0029] like Figure 2 As shown, the top of the shear hinge anchoring screw 2 is fastened to the shear hinge base 1 by a nut and a disc spring. A pin hole 5 is provided at the top of the shear hinge anchoring screw 2, and a steel bar with both ends bent downward and a matching steel bar sleeve are inserted into the pin hole 5 to prevent the nut from falling off.

[0030] In this embodiment, the upper shear hinge 9 can be applied to underground lines or elevated lines commonly used in rail transit. Figure 4 and Figure 5 The top shear hinge 9 is shown to be applied to underground rail transit lines. Figure 6 and Figure 7 The top-mounted shear hinge 9 is applied to the elevated line of rail transit. Whether it is applied to the underground line or elevated line of rail transit, the top-mounted shear hinge 9 should avoid the existing roadbed structure or related lines during installation. If it is impossible to avoid, then consider rectification and relocation.

[0031] In the specific implementation of this embodiment: when the floating plates 10 on both sides exist in the height direction, the shear hinge bases 1 on both sides should be leveled by the leveling steel plates 6, and at the same time, the shear hinge anchor screws 2 with the required length should be configured to ensure that the hinge rods 3 are arranged horizontally so as to effectively and evenly transmit the shear force.

[0032] Although the above embodiments have described the concepts and embodiments of the purpose of the utility model in detail with reference to the accompanying drawings, ordinary technicians in this field can recognize that various improvements and modifications can still be made to the utility model without departing from the scope of the claims, so they are not described one by one here.

Claims

1. A steel spring floating slab track bed with built-in shear hinges and newly added upper shear hinges, comprising a plurality of floating slabs arranged along the track direction, characterized in that: At least one set of upper shear hinges is arranged between adjacent floating plates, and the upper shear hinges include two shear hinge bases, which are respectively installed on the floating plates on both sides through shear hinge anchoring screws, and the two shear hinge bases are connected by a hinge rod; the shear hinge anchoring screw is an inverted cone screw, which is anchored in the floating plate and an anchoring agent is arranged on the periphery of the anchored part.

2. The internal shear hinge steel spring floating slab track bed with newly added upper shear hinge according to claim 1 is characterized by: The outer sleeve of the hinge rod is provided with a transparent silicone sleeve, and the transparent silicone sleeve is arranged between the two shear hinge bases.

3. The internal shear hinge steel spring floating slab track bed with newly added upper shear hinge according to claim 1 is characterized by: A leveling steel plate is arranged under the shear hinge base.

4. The internal shear hinge steel spring floating slab track bed with newly added upper shear hinge according to claim 3 is characterized by: The bottom surface of the leveling steel plate is coated with steel adhesive.

5. The internal shear hinge steel spring floating slab track bed with newly added upper shear hinge according to claim 1 is characterized by: Two or more sets of the upper shear hinges are arranged along the transverse direction of the floating plate, and the upper shear hinges are arranged at intervals.

6. The internal shear hinge steel spring floating slab track bed with newly added upper shear hinge according to claim 1 is characterized by: The anchoring agent is a modified vinyl ester anchoring adhesive.

7. The internal shear hinge steel spring floating slab track bed with newly added upper shear hinge according to claim 1 is characterized by: The shear hinge anchoring screw is fastened by a nut and a disc spring. A pin hole is arranged on the top of the shear hinge anchoring screw. A limiting steel bar with two ends bent downward is arranged in the pin hole.