Working foundation pit supporting structure
By using components such as anchor pipes and mesh plates in the foundation pit support structure, the soil landslide and landslide caused by unstable foundation pit support structure is solved, the stability and construction safety of the foundation pit are improved, and the ground is reduced Damage to buildings by settlement.
Patent Information
- Application Number
- CN202323657611.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-12-29
- Publication Date
- 2024-11-26
- Estimated Expiration
- 2033-12-29
AI Technical Summary
The existing foundation pit support structure is prone to instability, resulting in soil landslides or landslides, causing ground settlement and damaging buildings.
Using a structure including support plates, anchor pipes, support plates, support rods and mesh plates, the anchor pipes are fixed to the earth wall to increase stability. The mesh plate provides additional support and uses elastic ropes and rubber rings to improve the stability of the structure. And easy to install and remove.
It effectively increases the stability of the foundation pit, reduces soil landslides and landslides, improves soil bearing capacity and stiffness, improves construction safety, and simplifies the construction process.
Smart Images

Figure CN222065481U_ABST
Abstract
Description
Technical Field
[0001] The utility model belongs to the technical field of civil engineering, in particular to a working foundation pit supporting structure. Background Art
[0002] The foundation pit is an earth pit excavated at the foundation design position according to the base elevation and foundation plane dimensions. The excavation plan needs to be determined in combination with the construction conditions near the site, and waterproofing and drainage work needs to be done well. The excavation needs to stabilize the earth slope, and the slope size must be determined in accordance with relevant construction regulations.
[0003] When the excavation is deep or there are buildings nearby, it is necessary to use foundation pit support structure. The purpose of foundation pit support is to ensure the safety of underground structure construction and the surrounding environment of the foundation pit, and to adopt support, reinforcement and protection measures for the side walls of the foundation pit and the surrounding environment.
[0004] It was found in the foundation pit support structure that the existing foundation pit support retaining wall is prone to instability, which can easily lead to soil landslide or collapse, causing ground settlement and damage to buildings.
[0005] To this end, the utility model provides a working foundation pit supporting structure. Utility Model Content
[0006] In order to make up for the deficiencies of the prior art, at least one technical problem raised in the background technology is solved.
[0007] The technical solution adopted by the utility model to solve its technical problems is: a working foundation pit support structure described in the utility model comprises a support plate; a fixing rod is fixedly connected to the middle part of the two support plates, and a plurality of groups of anchor pipes are slidably connected to the middle part of the support plate, and the plurality of groups of anchor pipes are equidistantly distributed in the middle part of the support plate, and the ends of the plurality of groups of anchor pipes are fixedly connected to a support plate, and the two support plates are arranged oppositely, and two support seats are installed on the side walls of the support plates, and one of the side walls of the support seats is fixedly connected to a first support rod, and the end of the first support rod is threadedly connected to a second support rod, and the end of the second support rod is fixedly connected to another support seat, and the stability of the foundation pit can be effectively increased by fixing the anchor pipes in the earth walls on both sides, and the landslide and collapse of the soil can be reduced, and the safety and integrity of the surrounding buildings can be effectively reduced, and the stability of the foundation pit support structure can be effectively increased to reduce the degree of ground subsidence, effectively reduce the damage to buildings caused by ground subsidence, effectively improve the bearing capacity and rigidity of the soil, and effectively increase the safety of construction.
[0008] Preferably, the side wall of the support plate is fixed with two first hooks, the first hooks are fixed to the side wall of the support plate near the bottom, a first fixing ring is sleeved on the middle part of the first hook, a spring is fixed to the side wall of the first fixing ring, and multiple groups of spring ends are fixed with mesh plates, which can provide additional support and effectively improve the strength and stability of the bottom of the foundation pit, effectively reduce the problem of soil deformation, effectively maintain the stability of the bottom of the foundation pit, and are more convenient to install and disassemble, effectively improve construction efficiency, effectively reduce safety issues caused by soil deformation, and effectively increase the stability and safety of the foundation pit during work.
[0009] Preferably, a fixing seat is fixedly connected to the middle part of the mesh plate, a second hook is fixedly connected to the middle part of the support plate, a second fixing ring is sleeved on the middle part of the second hook, and an elastic rope is fixedly connected to the middle part of the second fixing ring and the end of the fixing seat. The elastic rope connection can effectively increase the supporting force of the middle part of the mesh plate, reduce the deformation of the mesh plate after long-term use, effectively reduce the injuries to the workers caused by the deformation of the mesh plate during work, and make installation and disassembly more convenient, effectively increase the stability of the mesh plate during work, and effectively support the mesh plate to reduce the work difficulties caused by water seepage at the bottom of the foundation pit, effectively increasing the construction progress.
[0010] Preferably, a circular tube is slidably connected to the middle portion of the first support rod, and a circular tube is slidably connected to the middle portion of the second support rod. A plurality of pulleys are fixedly connected inside the circular tube. A plurality of brushes are fixedly connected inside the circular tube. The plurality of brushes are fixedly connected to the middle portion of the circular tube. The surfaces of the first support rod and the second support rod can be effectively cleaned by the brushes, thereby reducing dirt and dust generated on the surfaces, and effectively reducing corrosion and wear on the surfaces of the first support rod and the second support rod caused by dirt and dust, thereby effectively increasing the stability and safety of the first support rod and the second support rod, effectively facilitating the maintenance and inspection of the first support rod and the second support rod, and effectively extending the service life of the first support rod and the second support rod.
[0011] Preferably, two oil bags are fixedly connected to the inside of the circular tube, and the two oil bags are fixedly connected to one side of the inner wall of the circular tube, and the two oil bags are arranged opposite to each other. A connecting pipe is fixedly connected to the side wall of the oil bag, and a sponge block is fixedly connected to the end of the connecting pipe. By applying lubricating oil to the surface of the first support rod and the second support rod, the friction on the surface can be reduced, the wear on the surface of the first support rod and the second support rod can be reduced, and the corrosion and rust on the first support rod and the second support rod after long-term use can be reduced. It can also reduce moisture and the problem of unsmooth movement of the first support rod and the second support rod due to long-term use, thereby increasing their service life and increasing the safety of construction.
[0012] Preferably, a plurality of groups of rubber rings are fixedly connected to the middle part of the elastic rope, and the plurality of groups of rubber rings are equidistantly distributed in the middle part of the elastic rope. The plurality of groups of rubber rings can effectively reduce the contact with the elastic rope and can reduce the damage caused by direct contact between the workers or equipment and the elastic rope, thereby effectively increasing the safety during the construction process, reducing the problem of breakage caused by long-term contact with the elastic rope, and effectively increasing the service life of the elastic rope.
[0013] The beneficial effects of the utility model are as follows:
[0014] 1. The working foundation pit support structure described in the utility model can effectively increase the stability of the foundation pit by fixing anchor pipes in the earth walls on both sides, can reduce soil landslides and collapses, can effectively reduce the safety and integrity of surrounding buildings, and can effectively increase the stability of the foundation pit support structure, reduce the degree of ground subsidence, effectively reduce damage to buildings caused by ground subsidence, effectively improve the bearing capacity and rigidity of the soil, and effectively increase the safety of construction.
[0015] 2. The working foundation pit support structure described in the utility model can provide additional support through the mesh plate, and effectively improve the strength and stability of the bottom of the foundation pit, can effectively reduce the problem of soil deformation, can effectively maintain the stability of the bottom of the foundation pit, and can be more conveniently installed and disassembled, effectively improve construction efficiency, effectively reduce safety problems caused by soil deformation, and effectively increase the stability and safety of the foundation pit during work. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] The utility model will be further described below in conjunction with the accompanying drawings.
[0017] Figure 1 It is a three-dimensional diagram of a working foundation pit support structure in the utility model;
[0018] Figure 2 It is a schematic diagram of the matching structure of the first support rod and the second support rod in the utility model;
[0019] Figure 3 It is a schematic diagram of the matching structure of the elastic rope and the rubber ring in the utility model;
[0020] Figure 4 It is a structural schematic diagram of the spring in the utility model;
[0021] Figure 5 It is a schematic diagram of the matching structure of the brush and the oil bag in the utility model;
[0022] In the figure: 1. support plate; 11. anchor pipe; 12. first support rod; 13. second support rod; 14. support seat; 2. first hook; 21. first fixing ring; 22. spring; 23. mesh plate; 3. fixing seat; 31. elastic rope; 32. second hook; 33. second fixing ring; 4. round tube; 41. pulley; 42. brush; 5. oil bag; 51. connecting pipe; 52. sponge block; 6. rubber ring; 7. rubber plate; 8. support plate; 81. fixing rod. DETAILED DESCRIPTION
[0023] In order to make the technical means, creative features, objectives and effects achieved by the present invention easy to understand, the present invention is further described below in conjunction with specific implementation methods.
[0024] like Figure 1 and Figure 2 As shown, a working foundation pit support structure described in an embodiment of the utility model includes a support plate 8; a fixing rod 81 is fixedly connected to the middle of the two support plates 8, and a plurality of groups of anchor pipes 11 are slidably connected to the middle of the support plate 8, and the plurality of groups of anchor pipes 11 are equidistantly distributed in the middle of the support plate 8, and the ends of the plurality of groups of anchor pipes 11 are fixedly connected to a support plate 1, and the two support plates 1 are arranged opposite to each other, and two support seats 14 are installed on the side wall of the support plate 1, and a first support rod 12 is fixedly connected to the side wall of one of the support seats 14, and a second support rod 13 is threadedly connected to the end of the first support rod 12, and another support seat 14 is fixedly connected to the end of the second support rod 13. When working, the two support plates 8 are placed on both sides of the foundation pit, and supported and fixed by the fixing rod 81, and the two support plates 1 are pushed toward one side of the support plate 8 so that the ends of the plurality of groups of anchor pipes 11 are inserted into In the earth walls on both sides of the supporting plate 8, the first support rod 12 and the second support rod 13 are twisted to stretch the first support rod 12 and the second support rod 13, and the support seats 14 on both sides of the first support rod 12 and the second support rod 13 are fitted with the side walls of the supporting plate 1, so that the first support rod 12 and the second support rod 13 support and fix the two support plates 1, and the support plate 1 can be fixed and supported by the first support rod 12 and the second support rod 13, and the stability of the foundation pit can be effectively increased by fixing the anchor pipe 11 in the earth walls on both sides, which can reduce soil landslides and collapses, and can effectively reduce the safety and integrity of surrounding buildings, and can effectively increase the stability of the foundation pit support structure, reduce the degree of ground subsidence, effectively reduce the damage to buildings caused by ground subsidence, effectively improve the bearing capacity and rigidity of the soil, and effectively increase the safety of construction.
[0025] like Figure 1 and Figure 4As shown, the side wall of the supporting plate 8 is fixed with two first hooks 2, and the first hooks 2 are fixed at the side wall of the supporting plate 8 near the bottom. A first fixing ring 21 is sleeved in the middle of the first hook 2, and a spring 22 is fixed to the side wall of the first fixing ring 21. A plurality of groups of the spring 22 ends are fixed with mesh plates 23. When working, the mesh plate 23 is placed between the bottoms of the two supporting plates 8, and the first fixing ring 21 is inserted into the corresponding first hook 2 by stretching the spring 22. The mesh plate 23 is fixed in the middle of the first hook 2 by each first fixing ring 21. The mesh plate 23 can provide additional support, and effectively improve the strength and stability of the bottom of the foundation pit, can effectively reduce the problem of soil deformation, can effectively maintain the stability of the bottom of the foundation pit, and can be more convenient to install and disassemble, effectively improve construction efficiency, effectively reduce safety problems caused by soil deformation, and effectively increase the stability and safety of the foundation pit during work.
[0026] like Figure 1 and Figure 3 As shown, a fixing seat 3 is fixedly connected to the middle part of the mesh plate 23, a second hook 32 is fixedly connected to the middle part of the support plate 1, a second fixing ring 33 is sleeved on the middle part of the second hook 32, and an elastic rope 31 is fixedly connected to the middle part of the second fixing ring 33 and the end of the fixing seat 3. During operation, the elastic rope 31 is stretched upward and the second fixing ring 33 is sleeved on the middle part of the second hook 32 to connect the middle part of the mesh plate 23 with the second support rod 13. The connection through the elastic rope 31 can effectively increase the supporting force of the middle part of the mesh plate 23, reduce the deformation problem of the mesh plate 23 after long-term use, effectively reduce the damage to the staff caused by the deformation of the mesh plate 23 during work, and make it more convenient to install and disassemble, effectively increase the stability of the mesh plate 23 during work, and effectively support the mesh plate 23 to reduce the work difficulties caused by water seepage at the bottom of the foundation pit, and effectively increase the construction progress.
[0027] like Figure 1 and Figure 5As shown, the middle of the first support rod 12 is slidably connected to a round tube 4, the middle of the second support rod 13 is slidably connected to a round tube 4, the inside of the round tube 4 is fixedly connected with multiple groups of pulleys 41, the inside of the round tube 4 is fixedly connected with multiple groups of brushes 42, and multiple groups of the brushes 42 are fixedly connected to the middle of the round tube 4. When working, the round tube 4 is slid in the middle of the first support rod 12 and the second support rod 13 through the multiple groups of pulleys 41, and the ends of the multiple groups of brushes 42 are in contact with the first support rod 12 and the second support rod 13. In the process of sliding of the round tube 4, the ends of the first support rod 12 and the second support rod 13 are used to push the ends of the brushes 42 ... The surface of the rod 12 and the second support rod 13 are cleaned. The surface of the first support rod 12 and the second support rod 13 can be effectively cleaned by the brush 42, reducing the dirt and dust generated on the surface, effectively reducing the corrosion and wear on the surface of the first support rod 12 and the second support rod 13 caused by dirt and dust, effectively increasing the stability and safety of the first support rod 12 and the second support rod 13, and can effectively facilitate the maintenance and inspection of the first support rod 12 and the second support rod 13, and can effectively extend the service life of the first support rod 12 and the second support rod 13.
[0028] like Figure 5 As shown, two oil bags 5 are fixedly connected to the inside of the circular tube 4, and the two oil bags 5 are fixedly connected to one side of the inner wall of the circular tube 4. The two oil bags 5 are arranged opposite to each other, and the side wall of the oil bag 5 is fixedly connected to a connecting pipe 51, and the end of the connecting pipe 51 is fixedly connected to a sponge block 52. During operation, when the circular tube 4 slides, the oil bag 5 is filled with lubricating oil, and the lubricating oil enters the sponge block 52 through one end of the connecting pipe 51, and the sponge block 52 is in contact with the surface of the first support rod 12 and the second support rod 13, so that the lubricating oil is applied to the surface of the first support rod 12 and the second support rod 13. By applying the lubricating oil to the surface of the first support rod 12 and the second support rod 13, the friction of the surface can be reduced, the wear on the surface of the first support rod 12 and the second support rod 13 can be reduced, and the corrosion and rust on the first support rod 12 and the second support rod 13 after long-term use can be reduced, and moisture can be reduced, and the problem of unsmooth movement of the surface of the first support rod 12 and the second support rod 13 caused by long-term use can be reduced, thereby increasing their service life and increasing the safety of construction.
[0029] like Figure 1 and Figure 3As shown, a plurality of groups of rubber rings 6 are fixedly connected to the middle of the elastic rope 31, and the plurality of groups of rubber rings 6 are equidistantly distributed in the middle of the elastic rope 31. When working, the rubber ring 6 is fixedly connected to the middle of the elastic rope 31, and the rubber ring 6 is used to separate the elastic rope 31 from direct contact. The plurality of groups of rubber rings 6 can effectively reduce the contact with the elastic rope 31, and can reduce the damage caused by direct contact between the staff or equipment and the elastic rope 31, effectively increase the safety during the construction process, reduce the breakage problem caused by long-term contact with the elastic rope 31, and can effectively increase the service life of the elastic rope 31.
[0030] like Figure 1 As shown, two rubber plates 7 are fixedly connected to the side wall of the support plate 1, and the rubber plates 7 are fixedly connected to the side wall of the support plate 1 close to the supporting plate 8. During operation, when the support plate 1 is pushed to contact the supporting plate 8, the rubber plates 7 are in contact with the side wall of the supporting plate 8. The rubber plates 7 can effectively reduce the friction on the surface of the supporting plate 8 when the support plate 1 is pushed, reduce the wear problem caused by the friction, and increase the stability of the support plate 1, thereby effectively improving the supporting effect of the support plate 1 and effectively improving the safety of the construction.
[0031] During operation, the two supporting plates 8 are placed on both sides of the foundation pit and supported and fixed by the fixing rods 81, and the two supporting plates 1 are pushed toward one side of the supporting plates 8 so that the ends of the multiple groups of anchor pipes 11 are inserted into the earth walls on both sides of the supporting plates 8, and the first supporting rod 12 and the second supporting rod 13 are twisted to lengthen the first supporting rod 12 and the second supporting rod 13, and the supporting seats 14 on both sides of the first supporting rod 12 and the second supporting rod 13 are fitted with the side walls of the supporting plate 1, so that the first supporting rod 12 and the second supporting rod 13 support and fix the two supporting plates 1, and the supporting plate 1 can be fixed and supported by the first supporting rod 12 and the second supporting rod 13, and the mesh plate 23 is placed between the bottoms of the two supporting plates 8, and the first fixing ring 21 is inserted into the corresponding first hook 2 by stretching the spring 22, and the mesh plate 23 is fixed in the middle of the first hook 2 by each first fixing ring 21, and the elastic rope 31 is stretched upward, and the second fixing The ring 33 is inserted into the middle part of the second hook 32, so that the middle part of the mesh plate 23 is connected to the second support rod 13, and the circular tube 4 is slid in the middle part of the first support rod 12 and the second support rod 13 through multiple sets of pulleys 41, and the ends of multiple sets of brushes 42 are in contact with the first support rod 12 and the second support rod 13. During the sliding process of the circular tube 4, the surfaces of the first support rod 12 and the second support rod 13 are cleaned by the ends of the brushes 42. When the circular tube 4 slides, the oil bag 5 is filled with lubricating oil, and the lubricating oil enters the sponge block 52 through one end of the connecting pipe 51, and the sponge block 52 is in contact with the surfaces of the first support rod 12 and the second support rod 13, so that the lubricating oil is applied to the surfaces of the first support rod 12 and the second support rod 13, and the rubber ring 6 is fixed to the middle part of the elastic rope 31, and the rubber ring 6 is used to make a barrier and direct contact with the elastic rope 31. When the support plate 1 is pushed to contact the supporting plate 8, the rubber plate 7 contacts the side wall of the supporting plate 8.
[0032] The above shows and describes the basic principles, main features and advantages of the utility model. Those skilled in the art should understand that the utility model is not limited by the above embodiments. The above embodiments and descriptions are only for explaining the principles of the utility model. Without departing from the spirit and scope of the utility model, the utility model may have various changes and improvements, which fall within the scope of the utility model to be protected. The scope of protection claimed by the utility model is defined by the attached claims and their equivalents.
Claims
1. A working foundation pit support structure, comprising a support plate (8); characterized in that: A fixing rod (81) is fixedly connected in the middle of the two support plates (8), and a plurality of groups of anchor pipes (11) are slidably connected in the middle of the support plates (8). The plurality of groups of anchor pipes (11) are evenly distributed in the middle of the support plates (8), and the ends of the plurality of groups of anchor pipes (11) are fixedly connected to a support plate (1). The two support plates (1) are arranged opposite to each other, and two support seats (14) are installed on the side walls of the support plates (1), wherein a first support rod (12) is fixedly connected to the side wall of one of the support seats (14), and a second support rod (13) is threadedly connected to the end of the first support rod (12), and another support seat (14) is fixedly connected to the end of the second support rod (13).
2. A working foundation pit support structure according to claim 1, characterized in that: The side wall of the support plate (8) is fixedly connected to two first hooks (2), the first hooks (2) are fixedly connected to the side wall of the support plate (8) near the bottom end, a first fixing ring (21) is sleeved on the middle of the first hook (2), a spring (22) is fixedly connected to the side wall of the first fixing ring (21), and a plurality of groups of the springs (22) are fixedly connected to the ends of mesh plates (23).
3. A working foundation pit support structure according to claim 2, characterized in that: A fixing seat (3) is fixedly connected to the middle of the mesh plate (23), a second hook (32) is fixedly connected to the middle of the support plate (1), a second fixing ring (33) is sleeved on the middle of the second hook (32), and an elastic rope (31) is fixedly connected to the middle of the second fixing ring (33) and the end of the fixing seat (3).
4. A working foundation pit support structure according to claim 3, characterized in that: The middle part of the first support rod (12) is slidably connected to a circular tube (4), the middle part of the second support rod (13) is slidably connected to a circular tube (4), a plurality of groups of pulleys (41) are fixedly connected inside the circular tube (4), a plurality of groups of brushes (42) are fixedly connected inside the circular tube (4), and the plurality of groups of brushes (42) are fixedly connected to the middle part of the circular tube (4).
5. A working foundation pit support structure according to claim 4, characterized in that: Two oil bags (5) are fixedly connected inside the circular tube (4). The two oil bags (5) are fixedly connected to one side of the inner wall of the circular tube (4). The two oil bags (5) are arranged opposite to each other. A connecting pipe (51) is fixedly connected to the side wall of the oil bag (5). A sponge block (52) is fixedly connected to the end of the connecting pipe (51).
6. A working foundation pit support structure according to claim 5, characterized in that: A plurality of groups of rubber rings (6) are fixedly connected to the middle of the elastic rope (31), and the plurality of groups of rubber rings (6) are evenly distributed in the middle of the elastic rope (31).