Fabricated double-wall steel cofferdam universal for weir plate and trestle panel
By using a prefabricated double-walled steel cofferdam structure with vertical layering and horizontal segmentation, combined with mortise and tenon joints and a two-way fastening system, the difficulties and safety risks of underwater cutting during the construction of traditional steel cofferdams have been solved, achieving efficient and low-cost construction and secondary utilization.
Patent Information
- Application Number
- CN202420731586.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-04-10
- Publication Date
- 2024-11-26
- Estimated Expiration
- 2034-04-10
AI Technical Summary
Existing prefabricated steel cofferdams face challenges during construction, including difficult underwater cutting operations, high safety risks, high costs, long construction periods, and the inability to reuse the structures. Furthermore, traditional welding connection methods negatively impact construction efficiency and structural stability.
The prefabricated double-walled steel cofferdam structure adopts vertical layering and horizontal segmentation. Through mortise and tenon joints and a two-way fastening system, combined with flexible waterproof materials and an anchor tensioning system, it achieves vertical connection and lowering after horizontal segmentation and assembly, eliminating welding connections, enhancing structural stability and ease of dismantling.
It reduces underwater cutting time, improves construction safety and efficiency, lowers costs, enables convenient dismantling and reuse of the structure, and enhances construction precision and the structure's shear resistance.
Smart Images

Figure CN222065523U_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of bridge pedestal construction, in particular to an assembled double-wall steel cofferdam common to a weir plate and a trestle deck. Background Art
[0002] With the vigorous development of my country's bridge construction, the development of science and technology, and the continuous accumulation of construction experience, the construction technology of underwater caps is also constantly developing, from caisson and caisson technology to pile foundation, pipe column foundation, and steel sheet pile cofferdam technology. The construction of the bridge substructure is an important part of bridge construction. The cap structure is often underwater, and the underwater construction needs to be converted into a waterless construction environment during the construction process. The cofferdam structure has high overall rigidity, good water-stopping performance, and simple water-stopping form. When constructing the underwater cap of the bridge, steel cofferdams are generally used as water retaining structures to create a dry working environment for the cap construction. The construction technology has also been mature and widely used in the construction of the bridge substructure.
[0003] As a mature technology in the construction of deep-water bridge foundations, double-walled steel cofferdams serve as water retaining structures for cap construction, providing a dry working environment for bridge foundation construction; and the loads they bear include water flow impact, head pressure, and vertical forces from the drilling platform. Due to its high strength, high rigidity, and good waterproof performance, and the fact that it can be removed after the foundation and piers are built out of the water to avoid blocking water flow and waterways, it has been widely used in the construction of many deep-water bridge caps.
[0004] In the prior art, the overall assembly and lowering technology requires setting up an operating platform in the river first, and then assembling the steel cofferdam as a whole on the platform. Due to its large size and deadweight, when using a crane to lower it, the platform bearing capacity and crane performance requirements are high. When using a hanger to lower it, the overall coordination requirements of the hanger are high, and the operation is difficult. In order to reduce the difficulty of the lowering operation, the double-walled steel cofferdam construction adopts on-site welding and assembly in sections. The welding process has high requirements. The double-walled steel cofferdam is an integral structure. When the double-walled steel cofferdam is dismantled, underwater cutting is required, which is easy to cause safety accidents. The underwater operation cofferdam is dismantled irregularly and cannot be transported and reused for a second time. Secondary processing is required, which is costly, low economic benefit, long construction period, and there are many safety risks and high risks. In response to the defects of traditional processes, people have designed prefabricated steel cofferdam structures. Public literature has also reported some prefabricated steel cofferdams, such as:
[0005] 1. Chinese Patent: A square assembled double-walled steel cofferdam and its construction method, application number: 201810696320.3, application date: 2018.06.29, abstract: The present invention relates to a square assembled double-walled steel cofferdam, comprising a plurality of unit modules, which are connected and encircled by locking blocks and locks in sequence; in the top view, the cross section of the locking block is a "V" shape with the opening facing outward, the tip of the "V" shape is connected to the unit module, and the cross section of the lock mouth is a rectangular frame with a notch on the outside, when the locking block and the lock mouth cooperate, the locking block is inserted into the lock mouth, the opening end of the "V" shape of the locking block is close to the lock mouth, and the lock mouth is close to the unit module at the end of the locking block; a water stop cloth is filled between the locking block and the lock mouth. The present invention also relates to a construction method of a square assembled double-walled steel cofferdam. The present invention adopts a locking structure in which a locking block and a locking mouth cooperate, which is simple to construct, reduces underwater installation and dismantling operations, is easy to hoist and insert, does not require large equipment, is convenient and quick to dismantle, and the cofferdam structure can be reused, with little impact on the environment. The present invention belongs to the technical field of construction of underwater steel cofferdams in bridge engineering and water conservancy engineering.
[0006] 2. Chinese Patent: A prefabricated double-wall steel cofferdam structure and construction method for deep-water marine bridges, application number: 201811549888.9, application date: 2018.12.18, abstract: The present invention discloses a prefabricated double-wall steel cofferdam structure and construction method for deep-water marine bridges, including: two diagonal blocks, which are shell-like structures with an L-shaped horizontal cross-section; the two diagonal blocks are arranged opposite to each other and spliced into a square cofferdam structure; the spliced ends of two adjacent corner blocks are connected by at least one locking steel pipe pile. Several horizontal blocks can also be arranged between the spliced ends of two adjacent corner blocks, which are square shell structures; by adjusting the number of horizontal blocks, the length and width of the above-mentioned square cofferdam structure can be adjusted; the horizontal blocks are connected to the adjacent corner blocks by at least one locking steel pipe pile. The present invention has the advantages of good water-stopping effect, reusability, and convenient construction, and can be widely used in the field of bridge construction.
[0007] 3. Chinese Patent: Detachable and recyclable double-wall steel cofferdam, Application No.: 201020241080.7, Application Date: 2010.06.22, Abstract: The utility model discloses a detachable and recyclable double-wall steel cofferdam, which comprises at least a sealed first double-layer wall body and a second sealed double-layer wall body, the sealed first double-layer wall body and the second sealed double-layer wall body are connected to each other by bolts to form a closed double-wall steel cofferdam, a support pipe is connected between the upper parts of the sealed first double-layer wall body and the second sealed double-layer wall body; a disassembly compartment is provided at the connection between the sealed first double-layer wall body and the second sealed double-layer wall body. The cofferdam walls are connected by bolts. After the construction of the foundation is completed, the diver enters the disassembly compartment of the cofferdam box on both sides of the bolt connection to remove the bolts. The detachable and recyclable double-wall steel cofferdam has the characteristics of cost saving, recycling after dismantling, and convenient turnover.
[0008] 4. Chinese Patent: Combined Formwork Pile Cofferdam, Application Date: 2008.12.31, Application Number: 200820181623.3, Abstract: The utility model discloses a combined formwork pile cofferdam, including a cofferdam assembly, the cofferdam assembly includes at least three standard formworks and at least three corner special formworks, the two end faces of each cofferdam assembly are respectively detachably fixedly connected with a female lock and a male lock, the female lock and the male lock match each other; each cofferdam assembly is surrounded by a circle and adjacent cofferdam assemblies are plugged into one through the female lock and the male lock, and the lower end face of each cofferdam assembly is either fixedly connected with a cofferdam assembly or a pile tip formwork. The various components of the formwork pile cofferdam of the utility model adopt standardized design, and the production, processing, transportation, insertion and striking are convenient and flexible, and the process is simple, and it is suitable for the construction of various deep water and shallow water high pile or bottom pile caps. The standard formwork can also be used as a construction formwork and cofferdam wall plate, so it can be recycled and reused, which plays a role in saving money. The utility model can adapt to various complex terrains and has the advantage of fast construction speed of steel box cofferdam.
[0009] Although the above documents are all assembled steel cofferdams, they still have corresponding problems. The steel cofferdams disclosed in Documents 1, 2 and 4 are divided into multiple unit modules for insertion. The unit modules are high and are locked only by locks in the unit modules, which easily causes uneven gaps in the unit blocks, resulting in reduced waterproof and water-stopping functions. In addition, Document 2 requires the burial of multiple locking steel pipe piles. In the actual lowering process of the steel cofferdam, the steel cofferdam will be affected by factors such as water flow, waves generated by ships, strong winds, and unbalanced sinking process. A certain horizontal deviation and inclination will occur in the steel cofferdam, which is difficult to insert and will affect the lowering accuracy and safety of the steel cofferdam during the lowering process. The double-walled steel cofferdam of Document 3 is fixed by bolts between each layer of units and pre-assembled and sunk in blocks. Underwater operations cannot be avoided. In addition, the bottom sealing concrete easily makes it difficult to remove some bolts. Excessive vertical stratification easily weakens the vertical stiffness of the steel cofferdam. Divers are used to remove the connecting bolts underwater. Once the cement slurry of the underwater bottom sealing concrete invades the bolts or the underwater bolts rust and expand, it will increase the difficulty of removing the bolts. In addition, applied research has found that vertical stratification and horizontal block division of double-walled steel cofferdams can better reduce the weight of hoisting and facilitate disassembly and assembly for turnover. After horizontal blocks are assembled and then connected and lowered vertically, the construction accuracy of pile foundations or caps can be better guaranteed. In addition, applying tensioning beam stress can ensure that the unit modules are always in a tight state, which can enhance the waterproof and water-stopping functions of the structure. Therefore, it is necessary to design a new assembled steel cofferdam structure that can reduce the amount of underwater cutting work and the difficulty of underwater work without weakening its vertical stiffness, and can also achieve vertical stratification and horizontal block division to reduce the weight of hoisting, so as to facilitate disassembly and assembly for turnover. Summary of the invention
[0010] The purpose of the present invention is to provide an assembled double-wall steel cofferdam which can reduce the difficulty of underwater cutting operations and realize vertical stratification and horizontal block division to reduce the lifting weight. The designed double-wall steel cofferdam structure is installed in an assembled manner through vertical stratification and horizontal block division, and can realize horizontal block assembly and then vertical stratification connection and lowering, thereby ensuring the construction accuracy of pile foundations or pedestals, and can also greatly shorten the construction time and improve the construction efficiency. Moreover, the dismantled and recycled steel cofferdam straight-facing wall panels can be used as single-wall steel cofferdams, double-wall steel cofferdams, steel trestle steel platform bridge panels and various types of plate laying structures, with a high secondary utilization rate, which greatly improves the economic benefits of the double-wall steel cofferdam.
[0011] The present invention is achieved by adopting the following technical solutions:
[0012] An assembled double-walled steel cofferdam commonly used for weir plates and trestle decks comprises a double-walled steel cofferdam welding layer and a double-walled steel cofferdam assembly layer, wherein the double-walled steel cofferdam welding layer is formed by on-site hoisting and welding of four corner modules and a plurality of plane modules, and in order to facilitate hoisting, the double-walled steel cofferdam welding layer is divided into a plurality of segments in the vertical direction, and each segment is formed by on-site hoisting and welding of four corner modules and a plurality of plane modules, and the bottom layer is hoisted, assembled and welded first, and then the upper layer is hoisted and assembled in sequence, and the height of the double-walled steel cofferdam welding layer should not be lower than the height of the pedestal, and the bottom of the double-walled steel cofferdam assembly layer is connected to the top of the double-walled steel cofferdam welding layer by mortise and tenon joints; the double-walled steel cofferdam assembly layer is divided into a plurality of segments connected by mortise and tenon joints in the vertical direction, and each segment is formed by Four corner assembly modules and multiple plane assembly modules are connected by mortise and tenon rings. Each corner assembly module and plane assembly module is equipped with a transverse anchor tensioning system and a vertical anchor tensioning system in the coaming bin. The transverse tensioning fine-rolled threaded steel bars of two adjacent transverse anchor tensioning systems are connected by connectors. The two ends of the transverse tensioning fine-rolled threaded steel bars pass through the outer wall panels of the corner assembly modules at both ends and are tensioned and anchored by transverse tensioning anchors. The vertical tensioning fine-rolled threaded steel bars of two adjacent vertical anchor tensioning systems are connected by connectors. The lower end of the vertical tensioning fine-rolled threaded steel bars is anchored to the horizontal connecting rod in the coaming bin of the double-walled steel coaming dam welding layer. The upper end of the vertical tensioning fine-rolled threaded steel bars is tensioned and anchored to the shoulder beam at the top of the double-walled steel coaming dam assembly layer by vertical tensioning anchors. The joints of the above-mentioned mortise and tenon connections are filled with flexible waterproof materials.
[0013] Further preferred: a bolting mechanism is also provided on the bottom outer side of the double-walled steel cofferdam assembly layer and the top outer side of the double-walled steel cofferdam welding layer, the bolting mechanism comprising a transverse bolting ear and a transverse pin, the transverse bolting ear is correspondingly welded and arranged on the bottom outer side of the double-walled steel cofferdam assembly layer and the top outer side of the double-walled steel cofferdam welding layer, after the bottom of the double-walled steel cofferdam assembly layer and the top of the double-walled steel cofferdam welding layer are connected with mortise and tenon joints, the bolting holes of the transverse bolting ears on the double-walled steel cofferdam assembly layer are aligned with the bolting holes of the transverse bolting ears of the double-walled steel cofferdam welding layer and are bolted with transverse pins, which cooperate with the mortise and tenon connection structure to further enhance the shear resistance and ensure the stability of the cofferdam.
[0014] Further preferably, the top of the inner wall plate and the outer wall plate of the double-walled steel cofferdam welding layer is provided with transverse mortise and tenon protrusions and / or transverse mortise and tenon recesses for mortise and tenon connection with the bottom of the inner wall plate and the outer wall plate of the double-walled steel cofferdam assembly layer. The top and bottom of the inner wall plate and the outer wall plate of the double-walled steel cofferdam assembly layer are also correspondingly provided with transverse mortise and tenon protrusions and / or transverse mortise and tenon recesses for mortise and tenon connection.
[0015] Further preferred: an internal support mechanism is provided in the cofferdam at each segment connection of the double-wall steel cofferdam welding layer, the internal support mechanism includes a purlin and a diagonal brace arranged along each segment connection seam, the purlin is divided into multiple sections for connection, two adjacent sections of the purlin are extended by a node plate, the bottom of the purlin is supported and connected to the inner wall plate by a corbel, the purlin is locked and connected to the inner wall plate by riding bolts, the two ends of the diagonal brace are connected to the two purlins at the corners, and the diagonal brace is assembled and connected to the purlin by bolts.
[0016] Further preferred: the riding bolts include double-jointed channel steel at the fixed end in the warehouse, gaskets, bolts, double-jointed channel steel at the fixed end of the purlin and locking nuts. The double-jointed channel steel at the fixed end in the warehouse is located in the warehouse between the inner wall plate and the outer wall plate, and the double-jointed channel steel at the fixed end of the purlin is located in the cofferdam at the end of the purlin. Two bolts pass through the double-jointed channel steel at the fixed end in the warehouse, the inner wall plate and the double-jointed channel steel at the fixed end of the purlin in turn, and are finally locked by locking nuts. The purlin passes through the middle surrounded by the inner wall plate, the bolts and the double-jointed channel steel at the fixed end of the purlin. Gaskets for waterproofing are pierced on the bolts, thereby forming a stable structure to fix the purlin on the panel. During the construction stage, it serves as a screw hole for the riding bolts. After the riding bolts are constructed, the screw is connected to the hole by plug welding; when the cofferdam is subsequently dismantled, it serves as a pre-buried fixing hole for the steel trestle guardrail.
[0017] Further preferred: the corner assembly module includes a corner outer wall panel and a corner inner wall panel, the plane assembly module includes a plane inner wall panel and a plane outer wall panel, the corner outer wall panel and the corner inner wall panel and the plane inner wall panel and the plane outer wall panel are all provided with horizontal cross ribs and vertical ribs, the vertical ribs on the corner outer wall panel and the vertical ribs on the corresponding corner inner wall panel and the vertical ribs on the plane inner wall panel and the vertical ribs on the corresponding plane outer wall panel are respectively connected by bolts through connecting rods, the steel cofferdam wall panel is welded and fixed to the horizontal cross ribs, and the pre-opened steel cofferdam vertical ribs are welded according to the design size to complete the minimum standard unit processing, and the two small units are bolted together through a connecting device to form a consolidation. Double-walled steel cofferdam unit block; multiple transverse anchor tensioning systems and vertical anchor tensioning systems are arranged transversely and vertically between the corner outer wall plate and the corner inner wall plate and between the plane inner wall plate and the plane outer wall plate, respectively; the transverse anchor tensioning system includes a tensioning bundle pipe and transverse tensioning fine-rolled threaded steel bars; the tensioning bundle pipe crosses the vertical ribs, and the transverse tensioning fine-rolled threaded steel bars are passed through the tensioning bundle pipe; the vertical anchor tensioning system includes a support beam and a shoulder pole beam; the support beams are welded between the two vertical ribs of the inner wall plate and the outer wall plate in the warehouse, and the two ends of the shoulder pole beam are respectively connected to the support beams on the inner wall plate and the outer wall plate, the vertical tensioning fine-rolled threaded steel bars pass through the shoulder pole beam and are tensioned and limited by the vertical tensioning anchor. The vertical ribs on the inner wall panel of the plane and the vertical ribs of the corresponding outer wall panel of the plane are connected by bolts through connecting rods. After removing the connecting rods, two independent wall panel structures are formed. The two wall panel structures are laid flat on the Bailey beam and assembled to form the steel trestle bridge deck. The panels are installed in place, and the two adjacent panels are bolted together with pins, and they are fixed to the Bailey beam with riding bolts to form a fixed trestle bridge deck structure. The horizontal cross ribs and vertical ribs of the steel are used as distribution beams of the trestle panel. The two wall panel structures can be converted into the bridge deck of the steel trestle without additional trimming.
[0018] Further preferably, both the corner inner wall plate and the plane inner wall plate are provided with reserved holes for installing riding bolts.
[0019] Further preferred: the end faces of the inner wall panels and outer wall panels of the corner assembly module and the plane assembly module are correspondingly provided with vertical mortise and tenon grooves and vertical mortise protrusions for mortise and tenon connection, the vertical mortise and tenon protrusions are provided with water stop strip grooves for placing water stop strips on the butt joint surfaces, and the vertical mortise and tenon protrusions are provided with grouting grooves for pouring waterproof polyurea grouting liquid on the side close to the outer wall panel. The vertical mortise and tenon structure is formed by the spatial position of the vertical rib steel and the panel, and the steel plate is fully welded on the inside. The vertical mortise and tenon structure is welded by square steel. The design of the mortise and tenon structure strengthens the ability of the assembled cofferdam to withstand lateral pressure. The gaps reserved in the mortise and tenon structure are filled with flexible waterproof materials, which are used for secondary water isolation with the expansion water stop strip to achieve a better water stopping effect. An expansion water stop strip is fixed on one side of the female joint between the vertical sections of the cofferdam. After the water stop strip expands in water, it can achieve sealing and water stopping. At the same time, a vertical through hole is preset between the male head of the inner and outer wall panels of the vertical section and the outer wall panel of the cofferdam. After the horizontal tensioning bundle is tensioned, waterproof materials (such as polyurea grouting liquid) can be injected to achieve further sealing and water stopping. An expansion water stop strip is fixed on the top of the female joint between the horizontal layers of the cofferdam. After the vertical tightening bundle is tensioned, the water stop strip expands in water to achieve interlayer sealing and water stopping. That is, the water stopping of the gap between the unit blocks is composed of two water stopping structures, namely the expansion water stop strip and the polyurea waterproof grouting liquid. The expansion water stop strip is set at the extrusion of the male and female joints. It expands in water and actively squeezes the connection surface between the unit blocks to achieve a better water stopping effect.
[0020] The inner wall panels and outer wall panels of the corner assembly module and the plane assembly module are welded with corresponding vertical bolting ears on the inner side of the vertical ribs. After the corner assembly module and the plane assembly module are connected by mortise and tenon, and after the plane assembly module and the plane assembly module are connected by mortise and tenon, the bolting holes of the corresponding vertical bolting ears are in a straight line and vertical bolting pins are inserted from top to bottom. The vertical ribs on both sides are combined to form a space for pouring clay waterproofing materials, and the space also surrounds the vertical bolting ears and the vertical bolting pins in the middle, that is, the bolting ears are welded on the belly of the steel section at the end face, and the welding is full at a spacing of 50cm. After the unit block cofferdam is installed, the bolting pins are inserted, which can enhance the shear resistance of the assembled steel cofferdam at the joints and better ensure the stability of the structure.
[0021] After the completion of the main bridge, all the steel cofferdams above the top surface of the compartment concrete need to be removed. Since the cofferdam removal part adopts an assembled design, no underwater cutting is required. According to the vertical five-section design, the main demolition construction process is as follows: construction preparation → installation of the pier anti-overturning pulley block → water injection inside the double-walled steel cofferdam to ensure that the water level inside and outside the cofferdam is consistent → removal of the fourth and third internal supports and purlins → loosening the fifth section vertical tensioning bundle → pulling out the vertical pins between blocks → loosening the fifth section horizontal tensioning bundle → lifting off one by one → removal of the second internal support and purlins → loosening the fourth section vertical tensioning bundle → pulling out the vertical pins between blocks → loosening the fourth section horizontal tensioning bundle → lifting off one by one → removal of the first internal support and purlins → pulling out the pins of the pin-jointed plate connecting the second and third sections → loosening the third section vertical tensioning bundle → pulling out the vertical pins between blocks → loosening the third section horizontal tensioning bundle → lifting off one by one → removal of material operation and turnover use. A single wall is lifted by a crawler crane arranged on the platform, and then transported to a designated location for stacking by a flatbed truck waiting on the platform.
[0022] The assembled double-wall steel cofferdam with common weir plate and trestle deck has the following advantages:
[0023] 1. This prefabricated double-walled steel cofferdam eliminates the welding connection process of the cofferdam. Both the internodes and interlayers are connected as a whole by bidirectional fastening bundles, which is convenient for subsequent disassembly, saves welding operation time in the assembly stage, greatly reduces the operation time of deep-water cutting wall panels in the demolition stage, improves operation safety, and greatly improves construction efficiency; and uses fine-rolled threaded steel as a fastening bundle to connect the vertical interlayers and horizontal internodes as a whole. The traditional double-walled steel cofferdam is connected as a whole by welding. In recent years, some vertical internodes have been connected by bolts, mortise and tenon connections, CO type, CV type and CT type connectors, but the layers are generally still connected by welding, and the overall "prefabricated" connection has not been fully realized. The technology of this application uses a bidirectional fastening bundle system, which is a domestic first, and there is no similar structural system.
[0024] 2. The cofferdam is connected as a whole by a two-way fastening bundle. The cofferdam can be dismantled later by loosening the fastening bundle and cooperating with a crane. The dismantling is convenient and quick, and the cofferdam wall panels will not be damaged due to the dismantling, avoiding the need to cut the cofferdam during the welding process, which would damage its overall integrity. After the cofferdam is dismantled and recycled, the ribbed wall panels can be transferred to the steel trestle and steel platform for use as bridge panels by removing the bolts between the vertical ribs of the inner and outer wall panels. The vertical bolting ears and vertical bolting pin structures provided on the inner and outer wall panels of the plane assembly module can be quickly connected to form a steel trestle and a steel platform for use as bridge panels, that is, the vertical ribs on the plane inner wall panels and the corresponding vertical ribs on the plane outer wall panels are bolted together through connecting rods. After removing the connecting rods, two independent wall panel structures are formed. The two wall panel structures are laid flat on the Bailey beam for assembly. To form the steel trestle deck, the panels are installed in place, two adjacent panels are bolted together with latches, and mounted bolts are used to fix them to the Bailey beam. The mounted bolts are installed on the vertical rib steel sections, which is convenient for the installation and disassembly of the trestle construction and avoids opening holes in the bridge deck. The integrity of the bridge deck can be maintained for turnover use. The horizontal cross ribs and vertical rib steel sections are used as distribution beams for the trestle deck. The two wall panel structures do not require additional repairs to be converted into the bridge deck of the steel trestle. The reserved holes for the mounted bolts on the wall panels on the outside of the bridge deck can be used as uprights for inserting railings during the conversion to the steel trestle stage. The double-walled steel cofferdam is easy to operate to convert the trestle deck. Only the horizontal connection needs to be removed to form a standard bridge panel block structure. No secondary processing and welding and cutting operations are required, which saves costs and improves the efficiency of conversion construction.
[0025] 3. Compared with the traditional welded cofferdam, the prefabricated double-wall steel cofferdam of the present application replaces the 12mm horizontal ring plate of the traditional welded cofferdam with a horizontal I10 I-steel, and the vertical rib angle steel 80*80*5 is replaced with an H-steel HW175*175*7.5 / 11, and at the same time replaces the inner and outer wall panel connecting parts, that is, the horizontal diagonal bracing rods, with H-steel bolt connections. Although the steel consumption of a single component is increased, the bearing capacity of a single component is greatly improved and the spacing between components is increased. Therefore, the overall steel consumption is reduced by about 20%, greatly reducing the construction cost.
[0026] 4. The structural force system is optimized, and the welding of the inner and outer wall trusses of the cofferdam is optimized to bolt connection, which avoids the additional stress caused by welding and affects the overall bearing capacity of the structure; at the same time, the operation time and number of welding horizontal diagonal braces in the compartment (generally less than 1m in width and height) are reduced, and the overall construction efficiency is improved; the connection method between the structural nodes and layers is optimized. The nodes and layers of the traditional cofferdam are connected as a whole by welding technology, while the technology of this application adds mortise and tenon joints to the vertical nodes of the cofferdam, and the two sides of the mortise and tenon joints are supported by the wall panels and vertical ribs respectively, and finally the structure is further strengthened and fixed by the shear pins arranged inside; Yin-yang mortise and tenon joints are also added to the horizontal layers, and the two sides of the mortise and tenon joints are supported by the wall panels and the limit channel steels respectively. When converted to steel trestle panels, the mortise and tenon structure can also enhance the shear resistance of the bridge deck system. The vertical pin connection structure is used to form a transverse pin connection structure of the assembled trestle panel. The connection between the trestle bridge panel blocks is enhanced through the pin connection, making the structure more complete and further enhancing the shear resistance of the bridge deck structure.
[0027] 5. The internal support system is installed in advance to improve the structural safety. The internal purlin is installed before the cofferdam is lowered so that it can participate in the cofferdam stress. It plays a vital supporting role during the lowering and pumping operations. It serves as the main stress-bearing structure of the entire cofferdam at the moment of transient stress, ensuring the safety of the cofferdam construction. BRIEF DESCRIPTION OF THE DRAWINGS
[0028] Figure 1 This is a schematic diagram of the installation structure of the assembled double-wall steel cofferdam;
[0029] Figure 2 It is a structural schematic diagram of the assembled corner plate;
[0030] Figure 3 It is a structural schematic diagram of the assembled flat plate;
[0031] Figure 4 It is a schematic diagram of the exploded structure of the assembled flat panel;
[0032] Figure 5 It is a schematic diagram of the exploded structure of the horizontal internode connection;
[0033] Figure 6 It is a schematic diagram of the connection structure at the horizontal internode connection;
[0034] Figure 7 It is a schematic diagram of the decomposed structure of the vertical interlayer connection;
[0035] Figure 8 It is a structural schematic diagram of the vertical anchor tensioning system;
[0036] Fig. 9 It is a schematic diagram of the installation structure of the inner support mechanism;
[0037] Fig.10 This is a schematic diagram of the structure of a riding bolt;
[0038] Fig.11 Installation diagram for converting double-walled steel cofferdam panels into trestle decks;
[0039] The names corresponding to the numbers in the figure are:
[0040] 1. Double-wall steel cofferdam welding layer; 2. Bolting mechanism; 3. Horizontal anchor tensioning system; 4. Double-wall steel cofferdam assembly layer; 5. Vertical anchor tensioning system; 6. Purlin; 7. Diagonal brace; 8. Riding bolt; 9. Corbel; 10. Horizontal tensioning anchor; 11. Horizontal tensioning fine-rolled threaded steel; 12. Vertical mortise and tenon; 13. Vertical bolting ear; 14. Corner outer wall plate; 15. Horizontal transverse rib; 16. Vertical rib; 17. Connecting rod; 18. Corner inner wall plate; 19. Vertical mortise and tenon; 20. Reserved hole; 21. Plane inner wall plate ; 22. Plane outer wall panel; 23. Vertical bolting pin; 24. Tensioning bundle pipe; 25. Horizontal bolting ear; 26. Horizontal mortise and tenon; 27. Horizontal mortise and tenon; 28. Support beam; 29. Shoulder beam; 30. Vertical tensioning anchor; 31. Vertical tensioning fine-rolled threaded steel; 32. Node plate; 33. Double-jointed channel steel at the fixed end in the warehouse; 34. Gasket; 35. Bolt; 36. Double-jointed channel steel at the fixed end of the purlin; 37. Locking nut; 38. Grouting groove; 39. Waterstop strip groove; 40. Space for pouring clay waterproofing material 40. DETAILED DESCRIPTION
[0041] In order to describe the present technology more clearly, the present technology is further described in detail below with reference to the accompanying drawings and embodiments. Example
[0042] A prefabricated double-walled steel cofferdam commonly used for weir plates and trestle decks, comprising a double-walled steel cofferdam welding layer 1 and a double-walled steel cofferdam assembly layer 4, wherein the double-walled steel cofferdam welding layer 1 is formed by on-site hoisting and welding of four corner modules and a plurality of plane modules, and in order to facilitate hoisting, the double-walled steel cofferdam welding layer 1 is divided into a plurality of segments in the vertical direction, and each segment is formed by on-site hoisting and welding of four corner modules and a plurality of plane modules, and the bottom layer is hoisted, assembled and welded first, and then the upper layer is hoisted and assembled in sequence, and the height of the double-walled steel cofferdam welding layer 1 should not be lower than the height of the pedestal, and the bottom of the double-walled steel cofferdam assembly layer 4 is connected to the top of the double-walled steel cofferdam welding layer 1 by mortise and tenon joints; the double-walled steel cofferdam assembly layer 4 is divided into a plurality of segments connected by mortise and tenon joints in the vertical direction, and each segment is formed by four corner assembly modules The block and a plurality of plane assembly modules are connected by mortise and tenon rings. Each corner assembly module and plane assembly module is provided with a transverse anchor tensioning system 3 and a vertical anchor tensioning system 5 in the coaming bin. The transverse tensioning fine rolled threaded steel bars 11 of two adjacent transverse anchor tensioning systems 3 are connected by a connector. The two ends of the transverse tensioning fine rolled threaded steel bars 11 pass through the outer wall panels of the corner assembly modules at both ends and are tensioned and anchored by transverse tensioning anchors 10. The vertical tensioning fine rolled threaded steel bars 31 of two adjacent vertical anchor tensioning systems 5 are connected by a connector. The lower end of the vertical tensioning fine rolled threaded steel bars 31 is anchored to the horizontal connecting rod in the coaming bin of the double-walled steel coaming welding layer 1. The upper end of the vertical tensioning fine rolled threaded steel bars 31 is tensioned and anchored to the shoulder beam 29 at the top of the double-walled steel coaming assembly layer 4 by vertical tensioning anchors 30. The joints of the above-mentioned mortise and tenon connection are filled with flexible waterproof materials.
[0043] A bolting mechanism 2 is also provided on the outer side of the bottom of the double-walled steel cofferdam assembly layer 4 and the outer side of the top of the double-walled steel cofferdam welding layer 1. The bolting mechanism 2 includes a transverse bolting ear 25 and a transverse pin. The transverse bolting ear 25 is correspondingly welded and arranged on the outer side of the bottom of the double-walled steel cofferdam assembly layer 4 and the outer side of the top of the double-walled steel cofferdam welding layer 1. After the bottom of the double-walled steel cofferdam assembly layer 4 and the top of the double-walled steel cofferdam welding layer 1 are connected by mortise and tenon joints, the bolting holes of the transverse bolting ears 25 on the double-walled steel cofferdam assembly layer 4 are aligned with the bolting holes of the transverse bolting ears 25 of the double-walled steel cofferdam welding layer 1 and are bolted by transverse pins.
[0044] The top of the inner wall plate and the outer wall plate of the double-walled steel cofferdam welding layer 1 is provided with a transverse tenon protrusion 26 and / or a transverse tenon recess 27 for tenon-tenon connection with the bottom of the inner wall plate and the outer wall plate of the double-walled steel cofferdam assembly layer 4. The top and bottom of the inner wall plate and the outer wall plate of the double-walled steel cofferdam assembly layer 4 are also correspondingly provided with a transverse tenon protrusion 26 and / or a transverse tenon recess 27 for tenon-tenon connection.
[0045] An internal support mechanism is provided in the cofferdam at each segment connection of the double-walled steel cofferdam welding layer 1, and the internal support mechanism includes a purlin 6 and a diagonal brace 7 arranged along each segment connection seam. The purlin 6 is divided into multiple sections for connection, and two adjacent sections of the purlin 6 are extended by a node plate 32. The bottom of the purlin 6 is supported and connected to the inner wall plate through a corbel 9. The purlin 6 is locked and connected to the inner wall plate through a riding bolt 8, and the two ends of the diagonal brace 7 are connected to the two purlins 6 at the corners.
[0046] The riding bolt 8 includes a double-piece channel steel 33 at the fixed end in the warehouse, a gasket 34, a bolt 35, a double-piece channel steel 36 at the fixed end of the purlin and a locking nut 37. The double-piece channel steel 33 at the fixed end in the warehouse is located in the warehouse between the inner wall plate and the outer wall plate, and the double-piece channel steel 36 at the fixed end of the purlin is located in the cofferdam at the end of the purlin. The two bolts 35 pass through the double-piece channel steel 33 at the fixed end in the warehouse, the inner wall plate and the double-piece channel steel 36 at the fixed end of the purlin in turn, and are finally locked by the locking nut 37. The purlin 6 passes through the middle surrounded by the inner wall plate, the bolt 35 and the double-piece channel steel 36 at the fixed end of the purlin, and a gasket 34 for waterproofing is pierced on the bolt 35.
[0047] The corner assembly module includes a corner outer wall panel 14 and a corner inner wall panel 18, and the plane assembly module includes a plane inner wall panel 21 and a plane outer wall panel 22. The corner outer wall panel 14 and the corner inner wall panel 18 and the plane inner wall panel 21 and the plane outer wall panel 22 are all provided with horizontal transverse ribs 15 and vertical ribs 16. The vertical ribs 16 on the corner outer wall panel 14 and the corresponding vertical ribs 16 on the corner inner wall panel 18 and the vertical ribs 16 on the plane inner wall panel 21 and the corresponding vertical ribs 16 on the plane outer wall panel 22 are respectively connected by bolts through connecting rods 17. The steel cofferdam wall panels are welded and fixed to the horizontal transverse ribs, and the pre-opened steel cofferdam vertical ribs are welded according to the design size to complete the minimum standard unit processing, and the two small units are bolted together through a connecting device to form a consolidated double-wall steel cofferdam unit. Element block; multiple transverse anchor tensioning systems 3 and vertical anchor tensioning systems 5 are arranged transversely and vertically between the corner outer wall panel 14 and the corner inner wall panel 18 and between the plane inner wall panel 21 and the plane outer wall panel 22, respectively. The transverse anchor tensioning system 3 includes a tensioning bundle pipe 24 and a transverse tensioning fine-rolled threaded steel bar 11. The tensioning bundle pipe 24 crosses the vertical ribs 16, and the transverse tensioning fine-rolled threaded steel bar 11 is passed through the tensioning bundle pipe 24; the vertical anchor tensioning system 5 includes a support beam 28 and a shoulder pole beam 29. The support beam 28 is welded between the two vertical ribs 16 of the inner wall panel and the outer wall panel in the warehouse, and the two ends of the shoulder pole beam 29 are respectively connected to the support beams 28 on the inner wall panel and the outer wall panel, and the vertical tensioning fine-rolled threaded steel bar 31 passes through the shoulder pole beam 29 and is tensioned and limited by the vertical tensioning anchor 30.
[0048] The corner inner wall plate 18 and the plane inner wall plate 21 are both provided with reserved holes 20 for installing the riding bolts 8 .
[0049] The end faces of the inner wall panels and outer wall panels of the corner assembly module and the plane assembly module are provided with vertical mortise and tenon recesses 12 and vertical mortise protrusions 19 for mortise and tenon connection. The vertical mortise and tenon recesses 12 are formed by the vertical rib steel and the spatial position of the panel, and the steel plate is fully welded on the inside. The vertical mortise and tenon protrusions 19 are welded by square steel. The vertical mortise and tenon recesses 12 and the vertical mortise and tenon protrusions 19 are directly connected with the surface reserved for water stop strips. The vertical mortise and tenon protrusions 19 are reserved for the side close to the outer wall panel. The grouting groove 38 for pouring waterproof polyurea grouting liquid. The design of the mortise and tenon structure strengthens the ability of the assembled cofferdam to withstand lateral pressure. In the gaps reserved in the mortise and tenon structure, flexible waterproof materials are filled, and secondary water isolation is performed with the expansion water stop strips to achieve a better water stop effect.
[0050] The vertical ribs 16 on the inner side of the inner wall panels and the outer wall panels of the corner assembly module and the plane assembly module are welded with vertical bolting ears 13, and the vertical ribs 16 are made of I-beams. After the corner assembly module and the plane assembly module are connected by mortise and tenon joints, and after the plane assembly module and the plane assembly module are connected by mortise and tenon joints, the bolting holes of the corresponding vertical bolting ears 13 are in a straight line and vertical bolting pins 23 are inserted from top to bottom. The vertical ribs 16 on both sides enclose a space 40 for pouring clay waterproofing material, and the space also encloses the vertical bolting ears 13 and the vertical bolting pins 23 in the middle.
[0051] The installation and construction steps of the assembled double-walled steel cofferdam common to the above-mentioned weir plate and trestle deck are as follows:
[0052] Step 1: According to the design drawings, the corner modules and plane modules of the double-walled steel cofferdam welding layer 1 and the corner assembly modules and plane assembly modules of the double-walled steel cofferdam assembly layer 4 are respectively manufactured.
[0053] Step 2: hoist and weld the corner modules and plane modules of the double-walled steel cofferdam welding layer 1 in layers. After the corner modules and plane modules of the next section of the double-walled steel cofferdam welding layer 1 are hoisted and welded and lowered to a suitable height, hoist and weld the next section.
[0054] Step three: After the double-wall steel cofferdam welding layer 1 is hoisted, welded and lowered, the first section of the double-wall steel cofferdam assembly layer 4 is installed. According to the principle of symmetry, the corner assembly module of the double-wall steel cofferdam assembly layer 4 is hoisted first, and then the plane assembly module of the double-wall steel cofferdam assembly layer 4 is hoisted. The waterstop strips are placed in the waterstop strip grooves reserved on the vertical tenon recesses 12 and vertical tenon protrusions 19 of the inner wall panels and outer wall panels of the corner assembly module and the plane assembly module. During hoisting, the corresponding transverse tensioning fine-rolled threaded steel bars 11 and vertical tensioning fine-rolled threaded steel bars 31 are inserted in advance. The lower end of the vertical tensioning fine-rolled threaded steel bars 31 is anchored to the transverse connecting rod in the cofferdam bin of the double-wall steel cofferdam welding layer 1, and the transverse bolting ears 25 are bolted with transverse pins, and the flexible waterproof material is filled at the connecting seam between the double-wall steel cofferdam welding layer 1 and the first section of the double-wall steel cofferdam assembly layer 4.
[0055] Step 4: After the double-walled steel cofferdam assembly layer 4 of the previous step is hoisted, the transverse anchor tensioning system 3 of the double-walled steel cofferdam assembly layer 4 is tensioned, and the tensioning is symmetrical at both ends. After the tensioning of the transverse anchor tensioning system 3 is completed, the vertical anchor tensioning system 5 is tensioned. The vertical tensioning adopts a single-end tensioning and single-end anchoring process, that is, tensioning and anchoring at the upper end. A grouting groove for pouring waterproof polyurea grouting liquid is reserved on the side of the vertical tenon 19 close to the outer wall panel, and the space enclosed by the vertical ribs 16 on both sides is poured with clay waterproof material.
[0056] Step 5: Install the inner support. The purlin extension is connected with node plate bolts and fixed with riding bolts. After the overall purlin installation is completed, install the diagonal brace. The diagonal brace and the purlin are connected with bolts, and the vertical bolt pins 23 are inserted, and then the whole is lowered to a suitable height.
[0057] Step 6: Follow steps 3 to 5 to complete the hoisting of the double-wall steel cofferdam assembly layer 4 in the previous section to complete the construction of the entire assembled double-wall steel cofferdam.
[0058] The above description is not a limitation of the present application, and the present application is not limited to the above examples. Any changes, modifications, additions or substitutions made by ordinary technicians in this technical field within the essential scope of the present application should fall within the scope of protection of the present application.
Claims
1. An assembled double-walled steel cofferdam commonly used for weir plates and trestle decks, comprising a double-walled steel cofferdam welding layer (1), wherein the double-walled steel cofferdam welding layer (1) is formed by on-site hoisting and welding of four corner modules and a plurality of plane modules, Features: It also includes a double-walled steel cofferdam assembly layer (4), the bottom of the double-walled steel cofferdam assembly layer (4) is connected to the top of the double-walled steel cofferdam welding layer (1) by mortise and tenon joints; the double-walled steel cofferdam assembly layer (4) is divided into a plurality of segments connected by mortise and tenon joints in the vertical direction, each segment is composed of four corner assembly modules and a plurality of plane assembly modules connected by mortise and tenon joints in a circular manner, and a transverse anchor tensioning system (3) and a vertical anchor tensioning system (5) are arranged in the coaming bin of each corner assembly module and the plane assembly module, and the transverse tensioning fine-rolled threaded steel bars (11) of two adjacent transverse anchor tensioning systems (3) are connected by a plurality of mortise and tenon joints. The connector is used to extend the length of the horizontal tensioned fine-rolled threaded steel bar (11), and the two ends of the horizontal tensioned fine-rolled threaded steel bar (11) are respectively passed through the outer wall panels of the corner assembly modules at the two ends and tensioned and anchored through the horizontal tensioning anchor (10). The vertical tensioned fine-rolled threaded steel bars (31) of the two adjacent vertical anchor tensioning systems (5) are extended through the connector. The lower end of the vertical tensioned fine-rolled threaded steel bar (31) is anchored to the horizontal connecting rod in the coaming bin of the double-walled steel cofferdam welding layer (1), and the upper end of the vertical tensioned fine-rolled threaded steel bar (31) is tensioned and anchored to the shoulder beam (29) at the top of the double-walled steel cofferdam assembly layer (4) through the vertical tensioning anchor (30).
2. The assembled double-walled steel cofferdam with common weir plate and trestle deck according to claim 1, Features: The outer side of the bottom of the double-walled steel cofferdam assembly layer (4) and the outer side of the top of the double-walled steel cofferdam welding layer (1) are further provided with a bolting mechanism (2), the bolting mechanism (2) comprising a transverse bolting ear (25) and a transverse pin, the transverse bolting ear (25) being correspondingly welded and arranged on the outer side of the bottom of the double-walled steel cofferdam assembly layer (4) and the outer side of the top of the double-walled steel cofferdam welding layer (1), after the bottom of the double-walled steel cofferdam assembly layer (4) and the top of the double-walled steel cofferdam welding layer (1) are connected by mortise and tenon joints, the bolting holes of the transverse bolting ears (25) on the double-walled steel cofferdam assembly layer (4) are aligned with the bolting holes of the transverse bolting ears (25) on the double-walled steel cofferdam welding layer (1) and are bolted by the transverse pin.
3. The assembled double-walled steel cofferdam with a common weir plate and trestle deck according to claim 1 or 2, Features: The tops of the inner wall plates and the outer wall plates of the double-walled steel cofferdam welding layer (1) are provided with transverse mortise protrusions (26) and / or transverse mortise recesses (27) for mortise and tenon connection with the bottom mortise and tenon joints of the inner wall plates and the outer wall plates of the double-walled steel cofferdam assembly layer (4).
4. The assembled double-walled steel cofferdam with common weir plate and trestle deck according to claim 1, Features: An internal support mechanism is provided in the cofferdam at each segment connection of the double-walled steel cofferdam welding layer (1), and the internal support mechanism comprises a purlin (6) and a diagonal brace (7) arranged along each segment connection seam, the purlin (6) is divided into multiple sections for connection, two adjacent sections of the purlin (6) are extended by a node plate (32), the bottom of the purlin (6) is supported and connected to the inner wall plate by a corbel (9), the purlin (6) is locked and connected to the inner wall plate by a riding bolt (8), and the two ends of the diagonal brace (7) are connected to the two purlins (6) at the corners.
5. The assembled double-walled steel cofferdam with common weir plate and trestle deck according to claim 4, Features: The riding bolt (8) comprises a double-jointed channel steel (33) at a fixed end in the warehouse, a gasket (34), a bolt (35), a double-jointed channel steel (36) at a fixed end of the surrounding purlin and a locking nut (37). The double-jointed channel steel (33) at a fixed end in the warehouse is located in the warehouse between the inner wall plate and the outer wall plate. The double-jointed channel steel (36) at a fixed end of the surrounding purlin is located in the cofferdam at the end of the surrounding purlin. Two bolts (35) pass through the double-jointed channel steel (33) at a fixed end in the warehouse, the inner wall plate and the double-jointed channel steel (36) at a fixed end of the surrounding purlin in sequence, and are finally locked by the locking nut (37). The surrounding purlin (6) passes through the middle of the inner wall plate, the bolt (35) and the double-jointed channel steel (36) at a fixed end of the surrounding purlin. A gasket (34) for waterproofing is passed through the bolt (35).
6. The assembled double-walled steel cofferdam with a common weir plate and trestle deck according to claim 1, Features: The corner assembly module comprises a corner outer wall panel (14) and a corner inner wall panel (18), and the plane assembly module comprises a plane inner wall panel (21) and a plane outer wall panel (22). The corner outer wall panel (14) and the corner inner wall panel (18) as well as the plane inner wall panel (21) and the plane outer wall panel (22) are all provided with horizontal transverse ribs (15) and vertical ribs (16). The vertical ribs (16) on the corner outer wall panel (14) and the corresponding vertical ribs (16) on the corner inner wall panel (18) and the vertical ribs (16) on the plane inner wall panel (21) and the corresponding vertical ribs (16) on the plane outer wall panel (22) are respectively connected by bolts via connecting rods (17). A plurality of transverse anchor tensioning systems (3) and a vertical anchor tensioning system (5) are respectively provided on the corner outer wall panel (14) and the corner inner wall panel (18). The horizontal and vertical arrangements are arranged between the corner inner wall panels (18) and between the plane inner wall panels (21) and the plane outer wall panels (22). The horizontal anchor tensioning system (3) comprises a tensioning bundle pipe (24) and a horizontal tensioning fine-rolled threaded steel bar (11). The tensioning bundle pipe (24) crosses the vertical ribs (16), and the horizontal tensioning fine-rolled threaded steel bar (11) is passed through the tensioning bundle pipe (24). The vertical anchor tensioning system (5) comprises a support beam (28) and a shoulder beam (29). The support beam (28) is welded between two vertical ribs (16) of the inner wall panels and the outer wall panels in the warehouse, respectively. The two ends of the shoulder beam (29) are respectively connected to the support beams (28) on the inner wall panels and the outer wall panels. The vertical tensioning fine-rolled threaded steel bar (31) passes through the shoulder beam (29) and is tensioned and limited by a vertical tensioning anchor (30).
7. The assembled double-walled steel cofferdam with common weir plate and trestle deck according to claim 6, Features: The corner inner wall plate (18) and the plane inner wall plate (21) are both provided with reserved holes (20) for installing riding bolts (8).
8. The assembled double-walled steel cofferdam with common weir plate and trestle deck according to claim 6, Features: The end faces of the inner wall panels and the outer wall panels of the corner assembly module and the plane assembly module are respectively provided with vertical tenon recesses (12) and vertical tenon protrusions (19) for mortise and tenon connection, and a water stop strip attachment groove for placing a water stop strip is reserved on the butt joint surface of the vertical tenon recesses (12) and the vertical tenon protrusions (19), and a pouring groove for pouring a waterproof polyurea grouting liquid is reserved on the side of the vertical tenon protrusions (19) close to the outer wall panel.
9. The assembled double-walled steel cofferdam with a common weir plate and trestle deck according to claim 6 or 8, Features: The inner side vertical ribs (16) of the inner wall panels and the outer wall panels of the corner assembly module and the plane assembly module are welded with corresponding vertical bolting ears (13). After the corner assembly module and the plane assembly module are connected by mortise and tenon and after the plane assembly module and the plane assembly module are connected by mortise and tenon, the bolting holes of the corresponding vertical bolting ears (13) are in a straight line and vertical bolting pins (23) are inserted from top to bottom. The vertical ribs (16) on both sides enclose a space for pouring clay waterproof material, and the space also encloses the vertical bolting ears (13) and the vertical bolting pins (23) in the middle.