Metering device for asphalt processing
By calculating the flow rate by utilizing the pressure difference between the shrinkage section and the discharge section in the asphalt processing metering device, and combining the design of locking components and sealing strips, the problems of high installation difficulty and inaccurate measurement of existing devices are solved, and asphalt metering is realized Accuracy and ease of installation.
Patent Information
- Application Number
- CN202420813559.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-04-18
- Publication Date
- 2024-11-26
- Estimated Expiration
- 2034-04-18
AI Technical Summary
The existing asphalt processing metering device is difficult to install and is not tightly sealed. The metering data is inaccurate after long-term use, and the metering meter is difficult to replace and maintain.
A device including the metering device body and the conveying pipe is designed, and the asphalt flow is calculated using the pressure difference between the shrinkage section and the discharge section, and the fast installation and sealing is achieved through locking components and sealing strips. The meter can be quickly rotated and installed and removed. .
It realizes the accuracy of asphalt metering and simplicity of installation, reduces the installation difficulty of the device, and improves the sealing effect, making it easier to maintain and replace the meter.
Smart Images

Figure CN222069778U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the field of asphalt processing, in particular to a metering device for asphalt processing. Background Art
[0002] Asphalt, as an important building material, plays a key role in road paving, waterproofing, etc. However, the quality of asphalt is precisely controlled by the ratio of various raw materials. Too much or too little raw material ratio will affect the quality of asphalt. Therefore, an asphalt processing metering device is needed during the asphalt processing and use to accurately record the amount of asphalt used. The existing asphalt metering devices are not only difficult to install, but also have the problem of poor sealing. At the same time, after long-term use, the metering data will be inaccurate. Therefore, an asphalt processing metering device is needed to solve the problems of high installation difficulty and inaccurate metering data of the existing asphalt processing metering devices.
[0003] A Chinese patent with publication number CN210268795U discloses a metering device for asphalt processing, comprising a main body, transmission pipes are arranged on both sides of the main body, card boxes are fixedly connected to the top and bottom of the surface of the main body, first fixed blocks are fixedly connected to the top and bottom of the transmission pipe, and a first fixed rod is fixedly connected to the side of the first fixed block close to the card box. The device solves the problem that the installation process of the existing asphalt meter is too cumbersome and complicated during use, thereby causing inconvenience to the user. The metering device for asphalt processing has the advantage of easy installation and improves the practicality of the asphalt meter.
[0004] The above patent uses a spring in the card box to fix the card block. After long-term use, the spring loses its elasticity, and the connection between the device body and the pipeline is not tight, causing asphalt leakage. In addition, the meter in the device is integrally formed with the device, which makes it inconvenient to replace and maintain the meter. Utility Model Content
[0005] The utility model aims to provide a metering device for asphalt processing, which has the advantages of simple installation, good connection effect, good sealing effect and convenient maintenance and replacement of the metering meter.
[0006] The utility model aims to provide a metering device for asphalt processing, comprising a metering device body and a conveying pipe, a metering meter is rotatably installed on the top of the metering device body, a feed section, a contraction section and a discharge section are sequentially arranged in the metering device body, wherein the contraction section is arranged between the feed section and the discharge section, flanges are fixedly connected to both ends of the metering device body, a sealing strip is fixedly installed on one side of the flange, a flange is fixedly connected to one end of the conveying pipe, a sealing groove is fixedly installed on one side of the flange, the sealing strip is movably arranged in the sealing groove, the top and bottom of the flanges are movably connected to the flanges, and the locking assembly comprises a locking shaft and a locking block, the locking shafts are fixedly arranged at the top and bottom of the flanges, the locking blocks are fixedly arranged at the top and bottom of the flanges, and the locking shafts are clamped with the locking blocks.
[0007] Furthermore, a threaded hole is provided on the contraction section of the metering device body, a threaded column is fixedly provided on the bottom of the meter, and the meter is rotatably arranged in the threaded hole on the contraction section through the threaded column.
[0008] Furthermore, a plurality of clamping blocks are arranged in an array on one side of the flange, and a plurality of clamping slots are arranged in an array on one side of the flange, and the clamping blocks are movably arranged in the clamping slots.
[0009] Furthermore, the locking shaft includes a clamping block 1, which can be provided in two pieces, a rotating shaft is rotatably provided between the two clamping blocks 1, a threaded column 2 is rotatably provided on the rotating shaft, and a chuck is rotatably provided on the threaded column 2.
[0010] Furthermore, the locking block comprises a clamping block 2, which can be provided in number. A connecting block is fixedly provided between the two clamping blocks 2, and a sliding groove is provided on the top of the connecting block.
[0011] The working principle and use principle of the utility model are as follows: by installing the metering device body at two sections of the asphalt conveying pipe, when conveying the processed asphalt, the asphalt enters the device through the feed section of the metering device body, the asphalt entering the device is contracted by the contraction section, and is conveyed to the discharge section. Since the inner diameter of the contraction section is small, when the asphalt is transported to the contraction section of the pipeline, the flow rate will increase due to the decrease in the flow cross-sectional area, resulting in the dynamic pressure reaching a maximum value and the static pressure reaching a minimum value. This pressure change produces a pressure difference, and the pressure difference can be used to increase the asphalt conveying speed, and the flow rate can also be accurately calculated by the pressure difference generated when the asphalt flows through the feed section and the discharge section. Flange plate 1 is arranged at two sections of the device, and flange plate 2 is arranged at one end of the conveying pipe for conveying asphalt. The device realizes the installation of the metering device body by the movable connection between flange plate 1 and flange plate 2, and uses the sealing strip and the sealing groove to increase the sealing between flange plate 1 and flange plate 2. The locking shaft in the locking assembly is rotated and clamped in the locking block to realize the rapid locking connection between flange plate 1 and flange plate 2.
[0012] Compared with the prior art, the beneficial effects of the utility model are: the device utilizes the pressure difference between the contraction section and the discharge section when the asphalt is transported to accurately calculate the amount of asphalt used, which has the advantage of accurate measurement, and the device utilizes a locking assembly to facilitate the rapid installation of the device on the asphalt conveying pipe, reducing the difficulty of installation of the device, and the rotatable meter facilitates timely updating of the metering accuracy of the meter. BRIEF DESCRIPTION OF THE DRAWINGS
[0013] Figure 1 It is a schematic diagram of the overall structure of an embodiment of the utility model;
[0014] Figure 2 This is a cross-sectional view of the main structure of the metering device according to an embodiment of the utility model;
[0015] Figure 3 This is a schematic diagram of the structure of a meter according to an embodiment of the utility model;
[0016] Figure 4 This is a schematic diagram of the structure of a flange according to an embodiment of the utility model;
[0017] Figure 5 This is a schematic diagram of the structure of flange 2 according to an embodiment of the utility model.
[0018] Explanation of the reference numerals in the accompanying drawings: 1. Metering device body; 11. Feed section; 12. Contraction section; 13. Discharge section; 14. Threaded hole; 2. Metering meter; 21. Threaded column one; 3. Flange one; 31. Clamping block; 32. Sealing strip; 4. Flange two; 41. Clamping groove; 42. Sealing groove; 5. Delivery pipe; 6. Locking assembly; 61. Locking shaft; 611. Clamping block one; 612. Rotating shaft; 613. Threaded column two; 614. Chuck; 62. Locking block; 621. Clamping block two; 622. Connecting block; 623. Slide groove. DETAILED DESCRIPTION
[0019] according to Figure 1As shown: a metering device for asphalt processing, including a metering device body 1 and a conveying pipe 5, a metering meter 2 is rotatably installed on the top of the metering device body 1, a feed section 11, a contraction section 12 and a discharge section 13 are sequentially arranged in the metering device body 1, wherein the contraction section 12 is arranged between the feed section 11 and the discharge section 13, both ends of the metering device body 1 are fixedly connected with flanges 3, one side of the flange 3 is fixedly installed with a sealing strip 32, one end of the conveying pipe 5 is fixedly connected with flanges 4, one side of the flanges 4 is fixedly installed with sealing grooves 42, the sealing strip 32 is movably arranged in the sealing groove 42, the flanges 13 and the top and bottom of the flanges 24 are movably connected through a locking assembly 6, the locking assembly 6 includes a locking shaft 61 and a locking block 62, the locking shaft 61 is fixedly arranged at the top and bottom of the flange 13, the locking blocks 62 are fixedly arranged at the top and bottom of the flange 24, and the locking shaft 61 is clamped with the locking block 62.
[0020] In the specific implementation, both ends of the metering device body 1 are connected to the asphalt processing conveying pipe 5, and the metering device body 1 is divided into a feed section 11, a contraction section 12 and a discharge section 13 in sequence. The feed section 11 is connected to the discharge end of the conveying pipe 5, and the discharge section 13 is connected to the feed end of another conveying pipe 5. The pressure difference of the asphalt flow rate in the feed section 11 and the contraction section 12 is calculated by the metering table 2 to calculate the flow rate of the asphalt. A flange 1 3 is provided at both ends of the metering device body 1, and flanges 2 4 are provided on the two conveying pipes 5. The metering device body 1 is connected to the flange 1 3 and the flange 2 4. The device body 1 is installed on the conveying pipe 5, and the sealing strip 32 is movably arranged in the sealing groove 42. The sealing strip 32 and the sealing groove 42 improve the sealing degree between the flange 1 3 and the flange 2 4 to avoid asphalt leakage caused by the loose connection between the metering device body 1 and the conveying pipe 5. Both the locking shaft 61 and the locking block 62 can be set to two, and the two locking shafts 61 are symmetrically arranged at the top and bottom ends of the flange 1 3, and the two locking blocks 62 are symmetrically arranged at the top and bottom ends of the flange 2 4. The fixed connection between the metering device body 1 and the conveying pipe 5 is achieved by rotating the locking shaft 61 and clamping it on the locking block 62.
[0021] according to Figure 2 and Figure 3 As shown: a threaded hole 14 is provided on the contraction section 12 of the metering device body 1, a threaded column 21 is fixedly provided on the bottom of the meter 2, and the meter 2 is rotatably arranged in the threaded hole 14 on the contraction section 12 through the threaded column.
[0022] In a specific implementation, the threaded column 21 provided at the bottom of the meter 2 can be rotatably installed in the threaded hole 14 of the contraction section 12 of the metering device body 1. The rotatably installed meter 2 is convenient for quick and easy installation and removal of the meter 2.
[0023] according to Figure 4 and Figure 5 As shown: a plurality of clamping blocks 31 are arranged in an array on one side of the flange 1 3, a plurality of clamping slots 41 are arranged in an array on one side of the flange 2 4, and the clamping blocks 31 are all movably arranged in the clamping slots 41; the locking shaft 61 includes a clamping block 1 611, and the clamping block 1 611 can be set to two, and a rotating shaft 612 is rotatably arranged between the two clamping blocks 1 611, and a threaded column 2 613 is rotatably arranged on the rotating shaft 612, and a chuck 614 is rotatably arranged on the threaded column 2 613; the locking block 62 includes a clamping block 2 621, and the clamping block 2 621 can be set to two, and a connecting block 622 is fixedly arranged between the two clamping blocks 2 621, and a sliding groove 623 is opened on the top of the connecting block 622.
[0024] In the specific implementation, the clamping block 31 can be movably arranged in the clamping groove 41. When the flange 1 3 and the flange 2 4 are fitted and connected, the clamping block 31 slides into the clamping groove 41. The clamping block 31 and the clamping groove 41 are used to prevent the metering device body 1 from being misaligned with the conveying pipe 5 during installation. The threaded column 2 613 can be horizontally rotated between the two clamping blocks 1 611 through the rotating shaft 612. When installing the metering device body 1, first rotate the threaded column 2 613 upward with the rotating shaft 612 as the center, and then align the flange 1 3 with the flange 2 4. The blue plate 24 is fitted, and during the fitting, it is necessary to ensure that the block 31 is engaged in the slot 41, and at the same time ensure that the sealing strip 32 is engaged in the sealing slot 42, and then the threaded column 2 613 is rotated to make the threaded column 2 613 slide into the slot 623 of the connecting block 622, and then the chuck 614 set on the threaded column 2 613 is continuously rotated, and the chuck 614 is continuously rotated toward the bottom end of the threaded column 2 613 to press the connecting block 622 to achieve the installation of the metering device body 1 on the conveying pipe 5.
Claims
1. A metering device for asphalt processing, comprising a metering device body (1) and a delivery pipe (5), characterized in that: A metering meter (2) is rotatably mounted on the top of a metering device body (1), a feed section (11), a contraction section (12) and a discharge section (13) are sequentially arranged in the metering device body (1), wherein the contraction section (12) is arranged between the feed section (11) and the discharge section (13), both sections of the metering device body (1) are fixedly connected to a flange plate 1 (3), one side of the flange plate 1 (3) is fixedly mounted to a sealing strip (32), one end of a conveying pipe (5) is fixedly connected to a flange plate 2 (4), and the flange plate 2 (4) is fixedly connected to the conveying pipe (5). A sealing groove (42) is fixedly installed on one side, and a sealing strip (32) is movably arranged in the sealing groove (42). The top and bottom of the flange plate 1 (3) and the flange plate 2 (4) are movably connected through a locking assembly (6). The locking assembly (6) comprises a locking shaft (61) and a locking block (62). The locking shaft (61) is fixedly arranged at the top and bottom of the flange plate 1 (3), and the locking block (62) is fixedly arranged at the top and bottom of the flange plate 2 (4). The locking shaft (61) is clamped with the locking block (62).
2. A metering device for asphalt processing according to claim 1, characterized in that: A threaded hole (14) is provided on the contraction section (12) of the metering device body (1), a threaded column (21) is fixedly provided on the bottom of the metering meter (2), and the metering meter (2) is rotatably arranged in the threaded hole (14) on the contraction section (12) through the threaded column.
3. A metering device for asphalt processing according to claim 1 or 2, characterized in that: A plurality of clamping blocks (31) are arranged in an array on one side of the first flange (3), and a plurality of clamping slots (41) are arranged in an array on one side of the second flange (4), wherein the clamping blocks (31) are all movably arranged in the clamping slots (41).
4. A metering device for asphalt processing according to claim 1 or 2, characterized in that: The locking shaft (61) comprises a clamping block 1 (611), which can be provided in two pieces. A rotating shaft (612) is rotatably provided between the two clamping blocks 1 (611), a threaded column 2 (613) is rotatably provided on the rotating shaft (612), and a chuck (614) is rotatably provided on the threaded column 2 (613).
5. The metering device for asphalt processing according to claim 3, characterized in that: The locking shaft (61) comprises a clamping block 1 (611), which can be provided in two pieces. A rotating shaft (612) is rotatably provided between the two clamping blocks 1 (611), a threaded column 2 (613) is rotatably provided on the rotating shaft (612), and a chuck (614) is rotatably provided on the threaded column 2 (613).
6. A metering device for asphalt processing according to claim 1, 2 or 5, characterized in that: The locking block (62) comprises a clamping block 2 (621), which can be provided in two pieces. A connecting block (622) is fixedly provided between the two clamping blocks 2 (621), and a sliding groove (623) is provided on the top of the connecting block (622).
7. The metering device for asphalt processing according to claim 3, characterized in that: The locking block (62) comprises a clamping block 2 (621), which can be provided in two pieces. A connecting block (622) is fixedly provided between the two clamping blocks 2 (621), and a sliding groove (623) is provided on the top of the connecting block (622).
8. A metering device for asphalt processing according to claim 4, characterized in that: The locking block (62) comprises a clamping block 2 (621), which can be provided in two pieces. A connecting block (622) is fixedly provided between the two clamping blocks 2 (621), and a sliding groove (623) is provided on the top of the connecting block (622).