Novel rubber concrete damping ballast bed

By using steel fiber rubber concrete vibration-absorbing track beds in rail transit, the problems of unstable quality and complex construction of existing vibration-absorbing pad products are solved, efficient and economical rail vibration-absorbing effects are achieved, and the construction and maintenance process is simplified.

CN222083218UActive Publication Date: 2024-11-29QINGDAO METRO GRP CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420267674.7
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-02-04
Publication Date
2024-11-29
Estimated Expiration
2034-02-04

AI Technical Summary

Technical Problem

The quality of existing vibration damping pads is unstable, easily affected by temperature, complex construction and high cost, and inconvenient maintenance, resulting in weakening or loss of vibration damping effect, making it difficult to achieve efficient track vibration damping.

Method used

Using a new type of rubber concrete vibration-absorbing track bed, by mixing waste rubber powder and steel fibers into C40 concrete, the steel fiber rubber concrete is formed, which eliminates structural reinforcement in the track bed, achieves full coverage vibration reduction, and designs a drainage ditch structure to simplify construction. and maintenance.

Benefits of technology

It improves vibration damping effect and construction progress, reduces costs, simplifies the construction and maintenance process, achieves full coverage vibration damping needs at different sensitive points, and enhances the engineering performance and environmental protection of the materials.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222083218U_ABST
    Figure CN222083218U_ABST
Patent Text Reader

Abstract

The utility model provides a novel rubber concrete vibration reduction ballast bed which comprises a ballast bed body, sleepers and steel rails, the ballast bed body is fixed at the bottom of a circular tunnel, and the sleepers are embedded in the left side and the right side of the upper end of the ballast bed body respectively. The track bed has the advantages that the track bed is basically consistent with a traditional cast-in-place track bed in structural style, construction and performance, the main body structure of the track bed is cast at a time, a foundation leveling layer and a base center ditch do not need to be arranged, construction is convenient and fast, construction organization and later maintenance are facilitated, and the construction efficiency is improved. As a novel energy-saving and environment-friendly concrete material, the rubber concrete has the characteristics of good engineering performance, such as low elastic modulus, low brittleness, good crack resistance, high damping coefficient and the like, in addition, by doping the rubber powder, the recycling of wastes is realized, and the purposes of purifying the environment and turning waste into wealth are realized.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model belongs to the technical field of urban rail transportation, in particular to a novel rubber concrete vibration-damping roadbed. Background Art

[0002] The vibration-damping pad floating plate ballast is a track vibration reduction measure with a high vibration reduction effect. The vibration-damping pad floating plate track system consists of rails, fasteners, ballast bed, isolated elastic ballast bed and foundation leveling layer. It provides elasticity through isolated elastic vibration-damping pads. The vibration-damping pads and ballast bed form a mass-spring system, which greatly attenuates the vibration generated by train operation and then transmits it to the main structure of the tunnel to achieve the purpose of vibration reduction. Its main problems are as follows:

[0003] 1) The quality of vibration damping pads varies greatly. The environment of subway tunnels is relatively complex. During use, vibration damping pads are constantly subjected to vibrations of different frequencies and extrusion by the weight of trains. At the same time, due to the fact that the material of vibration damping pads is easily affected by temperature, the production quality of vibration damping pads is very high. However, the current market competition is fierce, and the production quality of vibration damping pads varies greatly and is difficult to control, which can easily lead to the weakening or even loss of vibration damping effect.

[0004] 2) Blockage and elastic failure Underground tunnels are prone to groundwater leakage. Once the seepage water penetrates into the vibration damping pad, it will have a great impact on the vibration of the roadbed, thereby affecting the vibration damping performance of the system. At the same time, the groundwater carries sand and soil, and the minerals in the water will slowly calcify and condense around the floating plate of the vibration damping pad, causing the elasticity and vibration isolation effect of the vibration damping pad to gradually disappear;

[0005] 3) High requirements for construction accuracy. The floating plate of the vibration damping pad has very high requirements for the flatness of the foundation. When the surface of the foundation is uneven or uneven due to post-construction settlement, the actual bearing capacity of the vibration damping pad will change significantly, and displacement will occur over time, and the vibration damping effect will be lost;

[0006] 4) Complex construction process The construction process of the vibration damping pad floating plate is complex, and the daily track laying progress is 50m / day / working surface, which is 1 / 3 lower than the 75m / day / working surface of the general integral track bed;

[0007] 5) High cost: The cost of a high-quality vibration damping pad floating plate system is high, which is 5 million yuan / km higher than the cost of a general integral track bed.

[0008] 6) Inconvenient maintenance. The vibration-damping pads under the floating slab roadbed are highly concealed, and it is difficult to repair or replace them in time after the vibration-damping failure problem occurs. This can easily lead to social problems such as vibration and noise complaints at sensitive points along the line. Therefore, we hope to design a vibration-damping roadbed with a new structure to solve this problem. Utility Model Content

[0009] In view of the deficiencies in the prior art, the purpose of the utility model is to provide a new type of rubber concrete vibration-damping ballast to solve the problems raised in the above-mentioned background technology.

[0010] The utility model is realized by the following technical scheme: a novel rubber concrete vibration-damping ballast bed comprises: a ballast bed body, a sleeper and a rail, the ballast bed body is fixed at the bottom of a circular tunnel, sleepers are respectively pre-embedded on the left and right sides of the upper end of the ballast bed body, a rail is buckled on the left side of the upper end of the ballast bed body through sleepers and fasteners, and a rail is buckled on the right side of the upper end of the ballast bed body through sleepers and fasteners;

[0011] The rails are symmetrically buckled on the left and right sides of the upper end of the ballast body through the sleeper axis. The ballast body is cast by mixing C40 concrete, waste rubber powder and steel fiber. In actual use, steel fiber rubber concrete is formed by adding steel fiber to rubber concrete, which can be used as a filler material under the cast-in-place ballast or prefabricated track slab, eliminating the structural reinforcement in the ballast, reducing the steel bar binding process, and further improving the track laying progress.

[0012] The elastic rubber powder is evenly dispersed in the range of the cast-in-place concrete roadbed. The overall stiffness of the cast-in-place concrete roadbed is consistent with the local stiffness, which can achieve full coverage of different vibration reduction levels. Different amounts of rubber powder can be added to meet the vibration reduction requirements of different sensitive points along the line, thereby achieving full coverage of vibration reduction at all sensitive points along the line.

[0013] The structural type, construction and performance of the cast-in-place concrete roadbed are basically the same as those of the traditional cast-in-place roadbed. The cast-in-place concrete roadbed is poured in one go, and there is no need to set up a foundation leveling layer and a central ditch at the base. The construction is convenient, which is conducive to construction organization and future maintenance.

[0014] As a preferred embodiment, the roadbed body is a cast-in-place concrete roadbed structure, the top of which is designed to be horizontal, and drainage ditches formed by downward depressions are arranged on both sides of the top.

[0015] As a preferred embodiment, the cross-section of the drainage ditch is a concave semicircular structure, and the two drainage ditches are designed to be axially symmetrically distributed.

[0016] As a preferred embodiment, the cast-in-place concrete roadbed is fixedly connected to the inner wall of the bottom of the circular tunnel by pouring.

[0017] As a preferred embodiment, the roadbed body is composed of a structure consisting of a concrete filling layer and a prefabricated track slab, wherein the middle of the upper end of the concrete filling layer is recessed downward to form a docking groove with an inverted trapezoidal structure in cross section.

[0018] As a preferred embodiment, the upper surface of the left end of the concrete filling layer is recessed downward to form a drainage groove, and the upper surface of the right end of the concrete filling layer is recessed downward to form a drainage groove, and the two drainage grooves are axially symmetrically arranged.

[0019] As a preferred embodiment, the lower end of the prefabricated track plate is movably mounted in the docking groove on the upper side of the concrete filling layer, and an upwardly inclined inclined surface is respectively provided on the left and right sides of the lower end of the prefabricated track plate, and the inclination and length of the inclined surface are matched with the structures on the left and right sides of the docking groove;

[0020] The height of the upper end of the prefabricated track plate is greater than the height of the upper end of the concrete filling layer. In actual use, rubber concrete, as a new type of energy-saving and environmentally friendly concrete material, has good engineering properties, such as low elastic modulus, low brittleness, good crack resistance, high damping coefficient, etc. In addition, by adding rubber powder, waste recycling and reuse are achieved, and the purpose of purifying the environment and turning waste into treasure is achieved;

[0021] The construction process of the concrete filling layer and precast track slab is consistent with that of the traditional precast ballast bed. Rubber concrete with steel fibers can also be poured at one time. Whether it is a cast-in-place ballast bed or a precast ballast bed, there is no need to make a base concrete leveling layer and a base center ditch. Equipment components such as ditch covers and inspection holes at the center of the track can be eliminated, which greatly simplifies the construction steps, material consumption and the workload of cleaning the ditch in the future.

[0022] As a preferred embodiment, sleepers are pre-embedded on the left and right sides of the upper surface of the prefabricated track slab, and rails are clamped on the left and right sides of the upper end of the prefabricated track slab through sleepers and fasteners.

[0023] After adopting the above technical scheme, the beneficial effects of the utility model are as follows: due to the addition of waste rubber powder into concrete, the cost is slightly increased compared with the traditional cast-in-place ballast, which is much lower than the current cost of the vibration-damping pad floating plate ballast in the high-level vibration-damping section, and the construction progress can reach the daily track-laying progress (75m / day / working surface) consistent with the general overall ballast of the section, which is at least 50% higher than the current construction progress of the vibration-damping pad floating plate. Steel fiber is added to the rubber concrete to form steel fiber rubber concrete, which can be used as a filling layer material under the cast-in-place ballast or prefabricated track slab, eliminating the structural reinforcement in the ballast, reducing the steel bar binding process, and further improving the track-laying progress;

[0024] The elastic rubber powder is evenly dispersed within the ballast bed, and the overall stiffness of the ballast bed is consistent with the local stiffness, which can achieve full coverage of different vibration reduction levels. Different amounts of rubber powder can be added to meet the vibration reduction requirements of different sensitive points along the line, thereby achieving full coverage of vibration reduction at all sensitive points along the line;

[0025] The structural type, construction and performance of the ballast bed are basically the same as those of the traditional cast-in-place ballast bed. The main structure of the ballast bed is cast in one go, and there is no need to set up a foundation leveling layer and a central ditch at the base. The construction is convenient and conducive to construction organization and future maintenance.

[0026] As a new type of energy-saving and environmentally friendly concrete material, rubber concrete has good engineering properties, such as low elastic modulus, low brittleness, good crack resistance, and high damping coefficient. In addition, by adding rubber powder, waste recycling and reuse can be achieved, achieving the purpose of purifying the environment and turning waste into treasure. BRIEF DESCRIPTION OF THE DRAWINGS

[0027] In order to more clearly illustrate the embodiments of the utility model or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the utility model. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative labor.

[0028] Figure 1 This is a diagram of the traditional isolated elastic vibration-damping pad floating slab cast-in-place ballast bed.

[0029] Figure 2 Diagram of the prefabricated ballast bed for the traditional isolated elastic vibration damping pad floating slab.

[0030] Figure 3 It is a schematic diagram of the cast-in-place structure of the new rubber concrete vibration-damping ballast bed of the utility model.

[0031] Figure 4 It is a schematic diagram of the prefabricated structure of the new rubber concrete vibration-damping ballast of the utility model.

[0032] In the figure, 100-circular tunnel, 200-cast-in-place concrete ballast, 300-sleepers, 400-rails, 500-concrete filling layer, 600-precast track slab, 700-ballast body. DETAILED DESCRIPTION

[0033] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments of the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0034] See also Figure 3 to Figure 4The utility model provides a technical solution: a new type of rubber concrete vibration-damping ballast bed, comprising: a ballast bed body 700, a sleeper 300 and a rail 400. The ballast bed body 700 is fixed at the bottom of a circular tunnel 100. The sleepers 300 are respectively pre-buried on the left and right sides of the upper end of the ballast bed body 700. The left side of the upper end of the ballast bed body 700 is buckled with a rail 400 through the sleeper 300 and a fastener. The right side of the upper end of the ballast bed body 700 is buckled with a rail 400 through the sleeper 300 and a fastener.

[0035] The rails 400 are axially symmetrically buckled on the left and right sides of the upper end of the ballast body 700 through the sleepers 300. The ballast body 700 is cast by mixing C40 concrete, waste rubber powder and steel fiber. In actual use, steel fiber rubber concrete is formed by adding steel fiber to rubber concrete, which can be used as a filling layer material under the cast-in-place ballast or prefabricated track slab 600, eliminating the structural reinforcement in the ballast, reducing the steel bar binding process, and further improving the track laying progress;

[0036] The elastic rubber powder is evenly dispersed within the range of the cast-in-place concrete roadbed 200. The overall stiffness of the cast-in-place concrete roadbed 200 is consistent with the local stiffness, which can achieve full coverage of different vibration reduction levels. Different amounts of rubber powder can be added to meet the vibration reduction requirements of different sensitive points in combination with the vibration reduction requirements of sensitive points along the line, thereby achieving full coverage of vibration reduction at all sensitive points along the line.

[0037] The structural type, construction and performance of the cast-in-place concrete roadbed 200 are basically the same as those of the traditional cast-in-place roadbed. The cast-in-place concrete roadbed 200 is poured in one go, and there is no need to set up a foundation leveling layer and a base center ditch. The construction is convenient, which is conducive to construction organization and future maintenance.

[0038] See also Figure 3 The roadbed body 700 is a cast-in-place concrete roadbed 200 structure, the top of which is horizontally designed, and drainage ditches formed by downward depressions are arranged on both sides of the top.

[0039] The cross section of the drainage ditch is a concave semicircular structure, and the two drainage ditches are designed to be axially symmetrical.

[0040] The cast-in-place concrete roadbed 200 is fixedly connected to the bottom inner wall of the circular tunnel 100 by pouring.

[0041] As the first embodiment of the utility model, in actual use, C40 concrete, waste rubber powder and steel fiber are uniformly mixed so that the waste rubber powder and steel fiber are evenly distributed in the C40 concrete, and then the uniformly mixed C40 concrete, waste rubber powder and steel fiber are poured into the cast-in-place formwork arranged in advance at the bottom of the circular tunnel 100. The cast-in-place process is the same as the cast-in-place process of the traditional isolated elastic vibration damping pad floating plate cast-in-place ballast bed (see the attached manual for details). Figure 1 and attached Figure 3);

[0042] After the waste rubber is ground into rubber powder, it is mixed into concrete to form rubber concrete, and the rubber concrete is used as the cast-in-place concrete roadbed 200. Its elastic function can replace the elastic pads or vibration-damping fasteners in the current subway projects;

[0043] Different levels of vibration reduction effects can be achieved by combining different demands of vibration and noise sensitive points along the rail transit line (according to the different demands of vibration and noise sensitive points at different positions of the line, the content of rubber powder can be appropriately increased during pouring to improve the vibration reduction and noise reduction performance of this section of cast-in-place concrete ballast 200).

[0044] See also Figure 4 The roadbed body 700 is composed of a concrete filling layer 500 and a prefabricated track plate 600, wherein the middle of the upper end of the concrete filling layer 500 is recessed downward to form a docking groove with an inverted trapezoidal cross-section.

[0045] The upper surface of the left end of the concrete filling layer 500 is concave downward to form a drainage groove, and the upper surface of the right end of the concrete filling layer 500 is concave downward to form a drainage groove, and the two drainage grooves are axially symmetrically arranged.

[0046] The lower end of the prefabricated track plate 600 is movably mounted in the docking groove on the upper side of the concrete filling layer 500. The left and right sides of the lower end of the prefabricated track plate 600 are respectively provided with an upwardly inclined inclined surface, and the inclination and length of the inclined surface are matched with the structures on the left and right sides of the docking groove;

[0047] The height of the upper end of the prefabricated track plate 600 is greater than the height of the upper end of the concrete filling layer 500. In actual use, rubber concrete, as a new type of energy-saving and environmentally friendly concrete material, has good engineering properties, such as low elastic modulus, low brittleness, good crack resistance, high damping coefficient, etc. In addition, by adding rubber powder, waste recycling is achieved, and the purpose of purifying the environment and turning waste into treasure is achieved;

[0048] The construction process of the concrete filling layer 500 and the precast track slab 600 is consistent with that of the traditional precast ballast bed, and the rubber concrete with steel fibers can also be poured at one time. No matter it is a cast-in-place ballast bed or a precast ballast bed, there is no need to make a base concrete leveling layer and a base center ditch, and equipment components such as ditch covers and inspection holes at the center of the road can be eliminated, which greatly simplifies the construction steps, material consumption and the workload of cleaning the ditch in the future.

[0049] The sleepers 300 are pre-embedded on the left and right sides of the upper surface of the prefabricated track slab 600, and the rails 400 are buckled by the sleepers 300 and fasteners on the left and right sides of the upper end of the prefabricated track slab 600.

[0050] As a second embodiment of the present utility model, based on the above-mentioned first embodiment, in actual use, a cast-in-place concrete filling layer 500 is formed at the bottom of the circular tunnel by mixing C40 concrete, waste rubber powder and steel fiber evenly, and a prefabricated track plate 600 is made in advance by a special mold (the length and structure of the prefabricated track plate 600 need to be set according to the length and structure of the actual installation position of the circular tunnel 100 to ensure that it can fit during on-site installation). After the prefabrication of the prefabricated track plate 600 is completed, it is transported to the position where the circular tunnel 100 needs to be laid, and a concrete filling layer 500 is poured under the prefabricated track plate 600. The construction process of the prefabricated track plate 600 is consistent with that of the traditional prefabricated roadbed (see the attached manual for details). Figure 2 and attached Figure 4 );

[0051] Steel fiber rubber concrete is formed by adding steel fiber into rubber concrete, which can be used as the material of concrete filling layer 500, eliminating the structural reinforcement in the roadbed, reducing the steel bar binding process, and further improving the construction speed.

[0052] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the protection scope of the present invention.

Claims

1. New rubber concrete vibration-damping ballast bed, including: A ballast body (700), a sleeper (300) and a rail (400), characterized in that the ballast body (700) is fixed to the bottom of a circular tunnel (100), sleepers (300) are pre-buried on the left and right sides of the upper end of the ballast body (700), the rail (400) is buckled on the left side of the upper end of the ballast body (700) through the sleeper (300) and fasteners, and the rail (400) is buckled on the right side of the upper end of the ballast body (700) through the sleeper (300) and fasteners; The steel rails (400) are axially symmetrically buckled on the left and right sides of the upper end of the ballast body (700) through the sleepers (300).

2. The novel rubber concrete vibration damping ballast as claimed in claim 1 is characterized in that: The ballast body (700) is a cast-in-place concrete ballast (200) structure, the top of which is designed to be horizontal, and drainage ditches formed by depressions are arranged on both sides of the top.

3. The novel rubber concrete vibration damping ballast as claimed in claim 2 is characterized by: The cross section of the drainage ditch is a concave semicircular structure, and the two drainage ditches are designed to be axially symmetrically distributed.

4. The novel rubber concrete vibration damping ballast as claimed in claim 3 is characterized by: The cast-in-place concrete ballast (200) is fixedly connected to the inner wall of the bottom of the circular tunnel (100) by pouring.

5. The novel rubber concrete vibration damping ballast as claimed in claim 1 is characterized by: The ballast body (700) is a structure consisting of a concrete filling layer (500) and a prefabricated track slab (600), wherein the middle of the upper end of the concrete filling layer (500) is recessed downward to form a docking groove with an inverted trapezoidal structure in cross section.

6. The novel rubber concrete vibration damping ballast as claimed in claim 5 is characterized by: The upper surface of the left end of the concrete filling layer (500) is concave downward to form a drainage groove, and the upper surface of the right end of the concrete filling layer (500) is concave downward to form a drainage groove, and the two drainage grooves are axially symmetrically arranged.

7. The novel rubber concrete vibration damping ballast as claimed in claim 6 is characterized by: The lower end of the prefabricated track plate (600) is movably mounted in a docking groove on the upper side of the concrete filling layer (500), and an upwardly inclined inclined surface is respectively provided on the left and right sides of the lower end of the prefabricated track plate (600), and the inclination and length of the inclined surface are matched with the structures on the left and right sides of the docking groove; The height of the upper end of the prefabricated track slab (600) is greater than the height of the upper end of the concrete filling layer (500).

8. The novel rubber concrete vibration-damping ballast bed as claimed in claim 7 is characterized in that: The left and right sides of the upper surface of the prefabricated track plate (600) are respectively pre-embedded with sleepers (300), and the left and right sides of the upper end of the prefabricated track plate (600) are respectively fastened with rails (400) through sleepers (300) and fasteners.