Net hanging steel bar for diversion tunnel construction
By designing the mesh steel bars of welding and clamping structures in the construction of diversion holes and setting corrosion-resistant and wear-resistant layers on their surfaces, the problem of poor stability of steel bars in the prior art is solved, and a higher service life and Construction safety.
Patent Information
- Application Number
- CN202323610255.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-12-28
- Publication Date
- 2024-11-29
- Estimated Expiration
- 2033-12-28
AI Technical Summary
The existing mesh steel bars for diversion tunnel construction have poor stability and do not have corrosion and wear resistance, so they are easily damaged during use.
A mesh steel bar including vertical mesh hanging parts, arc mesh hanging parts and reinforcement components was designed. The stability of the steel bar is improved through welding and clamping structures, and a waterproof, corrosion-resistant and wear-resistant layer is provided on the surface of the steel bar, and the surface of the steel bar is used. The plug-in rod is in contact with the construction wall of the diversion hole to enhance the fixity and durability of the steel bars.
It improves the stability and service life of the hanging steel bars, avoids corrosion and wear of the steel bars, and enhances the safety and reliability during construction.
Smart Images

Figure CN222083463U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of diversion tunnel construction, in particular to a mesh steel bar for diversion tunnel construction. Background Art
[0002] A diversion tunnel refers to a tunnel used for construction diversion purposes. Tunnel diversion is mainly suitable for mountain rivers with narrow valleys, steep banks and hard rocks. A diversion tunnel is a temporary engineering construction. One of its characteristics is that the construction period is often very tight. If it cannot be completed on time, it will cause the construction period of the entire project to be extended. During the construction period, the original river water flow is diverted from the upstream cofferdam to the tunnel behind the downstream cofferdam. Subjects: Water Conservancy Technology (first-level discipline); Hydraulic Engineering (second-level discipline); Water Conveyance Structures (third-level discipline) When a hydropower station is being built, in order to build a dam, it is necessary to build upper and lower cofferdams to retain water in advance, so before intercepting the flow, the outlet of the river water must be arranged in advance. There are two methods for this arrangement: diversion open channel and diversion tunnel.
[0003] Chinese patent number CN211816112U provides a plugging structure for a diversion tunnel, including a diversion tunnel; a water inlet is provided at one end of the diversion tunnel, and a water outlet is provided at the other end; an annular casting groove is provided on the inner wall of the diversion tunnel, a first steel bar is inserted on the inner wall of the annular casting groove, and an annular concrete ring is cast in the annular casting groove; one end of the first steel bar passes through the annular concrete ring and a concrete connecting ring is cast; a plugging block is cast in the concrete connecting ring, and a second steel bar is provided on the inner wall of the concrete connecting ring; the two sides of the plugging block extend to the water inlet and the water outlet respectively, and are cast on the outer wall of the second steel bar. The new type solves the problems in the prior art that the friction and bonding force between the existing plugging concrete and the rocks around the diversion tunnel are poor in resisting the upstream water pressure, the plugging block is easily offset from the inner wall of the diversion tunnel, and there are great safety hazards.
[0004] In the prior art, mesh steel bars are used for diversion tunnel construction. The mesh steel bars are only connected to the diversion tunnel through concrete, resulting in relatively poor stability of the mesh steel bars. At the same time, the surface of the steel bars is not treated when used, causing the steel bars to be easily damaged. Utility Model Content
[0005] In order to make up for the above shortcomings, the utility model provides a mesh steel bar for diversion tunnel construction, aiming to improve the mesh steel bar for diversion tunnel construction, which has a relatively poor stability under normal circumstances.
[0006] The utility model is achieved in this way:
[0007] The utility model provides a mesh steel bar for diversion tunnel construction, comprising a mesh structure and a reinforcement component.
[0008] The mesh structure includes a vertical mesh member including a horizontal steel bar 1 and an arc-shaped mesh member, the arc-shaped mesh member is installed on the vertical mesh member, the horizontal steel bar 1 includes a steel bar body, the outer wall of the steel bar body is provided with a waterproof layer, the outside of the waterproof layer is provided with a corrosion-resistant layer, and the outside of the corrosion-resistant layer is provided with a wear-resistant layer; the reinforcement component includes a clamping piece and a clamping frame 2, the clamping piece and the clamping frame 2 are clamped at the connection position of the vertical mesh member and the arc-shaped mesh member, the clamping piece includes a clamping frame 1 and a middle clamping frame, the middle clamping frame is located between the clamping frame 1 and the clamping frame 2, a plug-in rod is threadedly installed on one side of the clamping frame 2, a limiting plate is fixed to one end of the plug-in rod, a threaded column is fixed to one side of the limiting plate, and a plug-in nail is fixed to the other end of the plug-in rod.
[0009] In an embodiment of the utility model, the arc-shaped mesh hanging member includes an arc-shaped steel bar and a second transverse steel bar, and the arc-shaped steel bar is welded to one side of the second transverse steel bar.
[0010] In an embodiment of the utility model, a vertical steel bar is welded to one side of the horizontal steel bar, and the top end of the vertical steel bar is connected to the arc-shaped steel bar.
[0011] In an embodiment of the utility model, a fixing hole is formed on one side of the clamping frame, a transverse clamping groove is formed on one side of the clamping frame, and the transverse steel bar is clamped in the transverse clamping groove.
[0012] In one embodiment of the utility model, a horizontal clamping groove II is opened on one side of the middle clamping frame, and the horizontal steel bar I is clamped in the horizontal clamping groove II. A vertical clamping groove I is opened on the other side of the middle clamping frame, and the vertical steel bar is clamped in the vertical clamping groove I. A fixing hole II is opened on one side of the middle clamping frame.
[0013] In an embodiment of the utility model, a second vertical clamping groove is formed on one side of the second clamping frame, and the vertical steel bar is clamped in the second vertical clamping groove. A third fixing hole is formed on the other side of the second clamping frame.
[0014] In an embodiment of the utility model, a thread groove is formed on one side of the second clamping frame, and the threaded column is threaded inside the thread groove.
[0015] The beneficial effects of the utility model are as follows: the utility model obtains a mesh steel bar for diversion hole construction through the above-mentioned design. When in use, the plug-in rod is arranged, and the plug-in rod can be installed on the clamping piece through the threaded column, which is convenient for the installation of the plug-in rod. The plug-in rod is plugged into the diversion hole construction wall. Since the mesh steel bar is in contact and connected with the diversion hole through the concrete through the plug-in rod, the stability of the fixing of the mesh steel bar is improved. The clamping piece includes a clamping frame 1, a middle clamping frame and a clamping frame 2, which can be clamped on the contact between the horizontal steel bar 1 and the vertical steel bar and the arc steel bar and the horizontal steel bar 2. Then the mesh steel bar is fixed by the plug-in rod, which improves the stability of the mesh steel bar for diversion hole construction. A corrosion-resistant layer is arranged on the steel bar body to improve the corrosion resistance of the steel bar and avoid corrosion of the steel bar. The wear-resistant layer can avoid wear on the surface of the steel bar and improve the service life of the steel bar. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] In order to more clearly illustrate the technical solution of the implementation mode of the utility model, the drawings required for use in the implementation mode will be briefly introduced below. It should be understood that the following drawings only show certain embodiments of the utility model and therefore should not be regarded as limiting the scope. For ordinary technicians in this field, other relevant drawings can be obtained based on these drawings without paying creative work.
[0017] Figure 1 It is a schematic diagram of the overall structure of the mesh steel bars used for diversion tunnel construction provided by the embodiment of the utility model;
[0018] Figure 2 A schematic diagram of the local structure of mesh steel bars for diversion tunnel construction provided by the embodiment of the utility model;
[0019] Figure 3 A schematic diagram of the explosion structure of mesh reinforcement bars for diversion tunnel construction provided by the embodiment of the utility model;
[0020] Figure 4 A schematic diagram of the structural layers of mesh steel bars for diversion tunnel construction provided in an embodiment of the utility model.
[0021] In the figure: 100-mesh structure; 110-vertical mesh; 111-horizontal steel bar one; 1110-steel body; 1111-waterproof layer; 1112-corrosion-resistant layer; 1113-wear-resistant layer; 112-vertical steel bar; 120-arc-shaped mesh; 121-arc-shaped steel bar; 122-horizontal steel bar two; 200-reinforcement assembly; 210-clamping piece; 211-clamping frame one; 212-middle clamping frame; 213-fixing hole one; 214-horizontal clamping groove one; 215-horizontal clamping groove two; 216-vertical clamping groove one; 217-fixing hole two; 220-clamping frame two; 221-vertical clamping groove two; 222-fixing hole three; 223-threaded groove; 230-plug-in rod; 231-limiting plate; 232-threaded column; 233-plug-in nail. DETAILED DESCRIPTION
[0022] In order to make the purpose, technical solution and advantages of the implementation of the utility model clearer, the technical solution in the implementation of the utility model will be clearly and completely described below in conjunction with the drawings in the implementation of the utility model. Obviously, the described implementation is a part of the implementation of the utility model, not all of the implementations. Based on the implementation of the utility model, all other implementations obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0023] Example
[0024] See also Figure 1-4 The utility model provides a technical solution: a mesh steel bar for diversion tunnel construction, including a mesh structure 100 and a reinforcement component 200.
[0025] See also Figure 1-Figure 4 The mesh structure 100 includes a vertical mesh member 110, a horizontal steel bar 111 and an arc mesh member 120. The arc mesh member 120 is installed on the vertical mesh member 110. The horizontal steel bar 111 includes a steel bar body 1110. The outer wall of the steel bar body 1110 is provided with a waterproof layer 1111. The outer part of the waterproof layer 1111 is provided with a corrosion-resistant layer 1112. The corrosion-resistant layer 1112 improves the corrosion resistance of the steel bar and avoids corrosion of the steel bar. The outer part of the corrosion-resistant layer 1112 is provided with a wear-resistant layer 1113. The wear-resistant layer 1113 can avoid wear on the surface of the steel bar and improve the service life of the steel bar.
[0026] The arc-shaped mesh member 120 includes an arc-shaped steel bar 121 and a second horizontal steel bar 122 . The arc-shaped steel bar 121 is welded to one side of the second horizontal steel bar 122 . A vertical steel bar 112 is welded to one side of the first horizontal steel bar 111 . The top of the vertical steel bar 112 is connected to the arc-shaped steel bar 121 .
[0027] See also Figure 2 and Figure 3The reinforcement component 200 includes a clamping member 210 and a clamping frame 220. The clamping member 210 and the clamping frame 220 are clamped at the connection position of the vertical mesh member 110 and the arc mesh member 120. The clamping member 210 includes a clamping frame 1 211 and a middle clamping frame 212. The clamping member 210 includes a clamping frame 1 211, a middle clamping frame 212 and a clamping frame 220 that can be clamped at the contact between the horizontal steel bar 111 and the vertical steel bar 112 and the arc steel bar 121 and the horizontal steel bar 2 122, and then the mesh steel bars are fixed by the plug-in rod 230 to improve the diversion hole. In order to ensure the stability of the mesh steel bars used in construction, the middle clamping frame 212 is located between the clamping frame 1 211 and the clamping frame 220. A plug-in rod 230 is threadedly installed on one side of the clamping frame 220. The plug-in rod 230 is plugged into the construction wall of the diversion tunnel. Since the mesh steel bars are in contact and connected with the diversion tunnel through the concrete through the plug-in rod 230, the stability of the fixation of the mesh steel bars is improved. A limiting plate 231 is fixed to one end of the plug-in rod 230, a threaded column 232 is fixed to one side of the limiting plate 231, and a plug-in nail 233 is fixed to the other end of the plug-in rod 230.
[0028] A fixing hole 213 is provided on one side of the clamping frame 211, a horizontal clamping groove 214 is provided on one side of the clamping frame 211, and a horizontal steel bar 111 is clamped in the horizontal clamping groove 214. A horizontal clamping groove 215 is provided on one side of the middle clamping frame 212, and a horizontal steel bar 111 is clamped in the horizontal clamping groove 215. A vertical clamping groove 216 is provided on the other side of the middle clamping frame 212, and the vertical steel bar 112 is clamped in the vertical clamping groove 216. A fixing hole 217 is provided on one side, a vertical clamping groove 221 is provided on one side of the clamping frame 220, and the vertical steel bar 112 is clamped in the vertical clamping groove 221. A fixing hole 3 222 is provided on the other side of the clamping frame 220, and a threaded groove 223 is provided on one side of the clamping frame 220. A threaded column 232 is threaded inside the threaded groove 223. The plug-in rod 230 can be installed on the clamping part 210 through the threaded column 232, which facilitates the installation of the plug-in rod 230.
[0029] Specifically, the working principle of the mesh steel bar for diversion tunnel construction is as follows: when in use, the horizontal steel bar 111 of the mesh steel bar is welded to the vertical steel bar 112, the arc steel bar 121 is welded to the horizontal steel bar 122, and then the clamping frame 1 211, the middle clamping frame 212 and the clamping frame 220 are clamped to the horizontal steel bar 111 and the vertical steel bar 112 and the arc steel bar 121 and the horizontal steel bar 122. The clamping frame 1 211, the middle clamping frame 212 and the clamping frame 220 are fixed by bolts, and then the plug-in rod 230 is threaded into the thread groove 223 through the threaded column 232. , which is convenient for the installation of the plug-in rod 230. The plug-in rod 230 is plugged into the construction wall of the diversion tunnel. Since the mesh steel bars are in contact with the diversion tunnel through the concrete through the plug-in rod 230, the stability of the mesh steel bars is improved. The mesh steel bars are fixed by the plug-in rod 230 to improve the stability of the mesh steel bars used in the diversion tunnel construction. A corrosion-resistant layer 1112 is provided on the steel bar body 1110 to improve the corrosion resistance of the steel bars and avoid corrosion of the steel bars. The wear-resistant layer 1113 avoids wear on the surface of the steel bars and increases the service life of the steel bars. Then concrete is injected into the mesh steel bars.
[0030] It should be noted that the specific models and specifications of the waterproof layer 1111, the corrosion-resistant layer 1112 and the wear-resistant layer 1113 need to be selected and determined according to the actual specifications of the device, and the specific selection and calculation method adopts the existing technology in this field, so it will not be described in detail.
[0031] The above description is only the preferred implementation of the utility model, and is not intended to limit the utility model. For those skilled in the art, the utility model can have various modifications and changes. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the utility model shall be included in the protection scope of the utility model.
Claims
1. A mesh steel bar for diversion tunnel construction, characterized in that: include A mesh structure (100), the mesh structure (100) comprising a vertical mesh member (110) comprising a horizontal steel bar (111) and an arc-shaped mesh member (120), the arc-shaped mesh member (120) being mounted on the vertical mesh member (110), the horizontal steel bar (111) comprising a steel bar body (1110), the outer wall of the steel bar body (1110) being provided with a waterproof layer (1111), the outer surface of the waterproof layer (1111) being provided with a corrosion-resistant layer (1112), and the outer surface of the corrosion-resistant layer (1112) being provided with a wear-resistant layer (1113); A reinforcement component (200), the reinforcement component (200) comprising a clamping member (210) and a second clamping frame (220), the clamping member (210) and the second clamping frame (220) being clamped at the connection position between the vertical hanging mesh member (110) and the arc-shaped hanging mesh member (120), the clamping member (210) comprising a first clamping frame (211) and a middle clamping frame (212), the middle clamping frame (212) being located between the first clamping frame (211) and the second clamping frame (220), a plug-in rod (230) being threadedly mounted on one side of the second clamping frame (220), a limiting plate (231) being fixed on one end of the plug-in rod (230), a threaded column (232) being fixed on one side of the limiting plate (231), and a plug-in nail (233) being fixed on the other end of the plug-in rod (230).
2. The mesh steel bar for diversion tunnel construction according to claim 1, characterized in that: The arc-shaped mesh hanging member (120) comprises an arc-shaped steel bar (121) and a second transverse steel bar (122), wherein the arc-shaped steel bar (121) is welded to one side of the second transverse steel bar (122).
3. A mesh steel bar for diversion tunnel construction according to claim 2, characterized in that: A vertical steel bar (112) is welded to one side of the horizontal steel bar (111), and the top end of the vertical steel bar (112) is connected to the arc-shaped steel bar (121).
4. The mesh steel bar for diversion tunnel construction according to claim 1, characterized in that: A fixing hole (213) is provided on one side of the clamping frame (211), and a transverse clamping groove (214) is provided on one side of the clamping frame (211), wherein the transverse steel bar (111) is clamped in the transverse clamping groove (214).
5. The mesh steel bar for diversion tunnel construction according to claim 3, characterized in that: A second horizontal clamping groove (215) is provided on one side of the middle clamping frame (212), and the first horizontal steel bar (111) is clamped in the second horizontal clamping groove (215). A first vertical clamping groove (216) is provided on the other side of the middle clamping frame (212), and the vertical steel bar (112) is clamped in the first vertical clamping groove (216). A second fixing hole (217) is provided on one side of the middle clamping frame (212).
6. The mesh steel bar for diversion tunnel construction according to claim 3, characterized in that: A second vertical clamping groove (221) is provided on one side of the second clamping frame (220), and the vertical steel bar (112) is clamped in the second vertical clamping groove (221). A third fixing hole (222) is provided on the other side of the second clamping frame (220).
7. The mesh steel bar for diversion tunnel construction according to claim 1, characterized in that: A thread groove (223) is formed on one side of the second clamping frame (220), and the threaded column (232) is threaded inside the thread groove (223).