Engineering foundation pile detection fixing device
By designing a fixing device with fixed screws, support blocks and drive parts, the problem of poor fixing adaptability of foundation piles in the prior art is solved, and the stability fixation and torsion resistance of foundation piles of different diameters is achieved, and the cross is simplified The disassembly and assembly process of the board group.
Patent Information
- Application Number
- CN202420748567.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-04-11
- Publication Date
- 2024-11-29
- Estimated Expiration
- 2034-04-11
AI Technical Summary
The existing drilling and sampling mechanism has poor adaptability when fixing foundation piles of different diameters, resulting in unstable fixation and difficulty in adapting to foundation piles of different diameters.
A fixing device including a frame, a mounting unit, a fixing screw, a support block and a drive member is designed. The first and second fixing rods are driven to slide and rotate relative to each other through the fixing screw, so as to realize adaptive fixation of the foundation pile, and through The cross plate group increases the contact area with the foundation to improve the torsion resistance.
It improves the adaptability and torsion resistance of the fixture, can effectively fix foundation piles of different diameters, and simplifies the disassembly and assembly and replacement of cross plate groups.
Smart Images

Figure CN222083626U_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of construction engineering, and in particular to a device for detecting and fixing engineering foundation piles. Background Art
[0002] At present, in order to ensure the quality of the pile body and the sediment at the bottom of the pile, it is necessary to test the foundation piles of the project. The current testing methods mainly include static load test, core drilling method, low strain method, high strain method, acoustic wave transmission method, etc. The core drilling method is scientific, intuitive and practical, and is widely used in the detection of concrete cast-in-place piles. The core drilling method uses a drilling sampling mechanism to sample the foundation piles and then analyze the samples.
[0003] The existing drilling sampling mechanism is usually arranged on a frame, which is then fixed to the ground on one hand and to the foundation piles on the other hand. In the fixing of the frame and the foundation piles, a hydraulic cylinder is usually used to drive the arc plate to be pressed and fixed on the foundation piles from two directions. However, for foundation piles of different diameters, the arc plate can only be fixed by line contact, which makes it difficult for the arc plate to be used for fixing foundation piles of different diameters, resulting in poor adaptability of the arc plate. Utility Model Content
[0004] In order to improve the problem of poor adaptability of a fixing device when fixing a frame to foundation piles of different diameters, the present application provides an engineering foundation pile detection fixing device.
[0005] The engineering foundation pile detection and fixing device provided in this application adopts the following technical solution:
[0006] A device for detecting and fixing engineering pile foundations comprises a frame and a drilling and sampling mechanism arranged on the frame, the frame is provided with a plurality of mounting units for inserting into a foundation, the frame is provided with at least two groups of fixing screws, the fixing screws are threadedly connected to the frame and are arranged along the radial direction of the pile foundation, so that at least two groups of fixing screws are opposite to each other, each of the fixing screws is rotatably connected to a support block at one end close to the pile foundation, a first fixing rod for contacting the pile foundation is slidably provided on the support block, a second fixing rod is rotatably provided on the pile foundation, the first fixing rod drives the second fixing rod to rotate through a driving member, so that the second fixing rod is tightly contacted with the pile foundation.
[0007] By adopting the above technical scheme, when installing the drilling sampling mechanism, the frame is first installed on the foundation through the installation unit, and then the fixing screw is rotated to slide toward the foundation pile. The fixing screw first presses the first fixing rod against the foundation pile, and then as the fixing screw continues to move, the first fixing rod and the support block slide relative to each other and rotate toward the foundation pile through the second fixing rod. When the second fixing rod presses against the foundation pile, the fixing screw continues to be rotated, and the support block pushes the first fixing rod and the second fixing rod to press against the foundation pile, completing the fixation of the frame and the foundation pile. In this scheme, the first fixing rod and the second fixing rod can be adaptively fixed according to the different diameters of the foundation pile, thereby improving the adaptability of the fixing device.
[0008] In a specific possible implementation scheme, the driving member includes a driving rod, one end of which is hinged to the second fixed rod, and the other end is hinged to the first fixed rod. The first fixed rod can pull the driving rod through the driving rod to rotate toward the foundation pile and press against the foundation pile.
[0009] By adopting the above technical solution, when the fixing screw pushes the first fixing rod and the support block to slide relative to each other, the first fixing rod slides and pulls the second fixing rod to rotate toward the pile through the driving rod, which facilitates the first fixing rod to drive the second fixing rod.
[0010] In a specific possible implementation mode, a guide rod which is arranged parallel to the fixing screw rod is fixedly provided on the support block, and the guide rod passes through the frame and is slidably arranged with the frame.
[0011] By adopting the above technical solution, the guide rod is used to limit the rotation of the fixed screw rod to drive the rotation of the support block, thereby improving the sliding stability of the support block.
[0012] In a specific possible implementation scheme, the installation unit includes a cross plate group and a mounting rod, the mounting rod is detachably connected to the frame, the cross plate group is arranged on the mounting rod, and is inserted into the foundation along with the mounting rod.
[0013] By adopting the above technical solution, when the frame is installed on the foundation, the cross plate group is first installed on the mounting rod, and then the mounting rod together with the cross plate group is inserted into the foundation, and then the mounting rod and the frame are installed. The cross plate group increases the contact area with the foundation and improves the torsion resistance of the frame.
[0014] In a specific possible implementation manner, the cross plate set includes two plug-in plates plugged into each other, and the two plug-in plates are vertically arranged.
[0015] By adopting the above technical solution, when one of the plug boards of the cross board group is damaged, only the damaged plug board needs to be replaced, and then the two plug boards are plugged together, thereby improving the convenience of replacing the cross board group when it is damaged.
[0016] In a specific possible implementation manner, a cross slot for inserting the cross plate set is provided on the mounting rod, and the cross slot cooperates with the cross plate set to limit the rotation of the cross plate set.
[0017] By adopting the above technical solution, the cross plate group formed by splicing is inserted into the cross slot on the mounting rod, thereby improving the convenience of disassembling and assembling the mounting rod and the cross plate group.
[0018] In a specific possible implementation manner, a tightening sleeve is threadedly sleeved on the mounting rod, and the tightening sleeve is arranged at the end of the mounting rod and is used to restrict the cross plate assembly from sliding out of the cross slot.
[0019] By adopting the above technical solution, when the cross plate group is inserted into the cross slot, the fastening sleeve is screwed onto the mounting rod, and the cross plate group is restricted in the cross slot by the fastening sleeve, so that the cross plate group can be easily pulled out from the foundation.
[0020] In a specific possible implementation manner, the fastening sleeve is provided with a pointed end at an end facing away from the mounting rod.
[0021] By adopting the above technical solution and providing a pointed end, it is convenient for the fastening sleeve to be inserted into the abutment.
[0022] In summary, the present application includes at least one of the following beneficial technical effects:
[0023] 1. When installing the drilling sampling mechanism, the first fixing rod is driven to contact the foundation pile by the fixing screw, and the first fixing rod and the support block slide relative to each other. The first fixing rod pulls the second fixing rod to contact the foundation pile through the driving rod, and the support block pushes the first fixing rod and the second fixing rod to press against the foundation pile, thereby completing the fixing of the frame and the foundation pile. In this embodiment, the first fixing rod and the second fixing rod can be adaptively fixed according to different diameters of the foundation pile, thereby improving the adaptability of the fixing device;
[0024] 2. Before the rack is installed on the foundation, first install the cross plate group on the mounting rod, then insert the mounting rod together with the cross plate group into the foundation, and then install the mounting rod and the rack. The cross plate group increases the contact area with the foundation and improves the torsion resistance of the rack. BRIEF DESCRIPTION OF THE DRAWINGS
[0025] Figure 1 It is a structural schematic diagram of an engineering foundation pile detection and fixing device according to an embodiment of the present application.
[0026] Figure 2 It is a schematic diagram used to show the structure of the drive components.
[0027] Figure 3 is along Figure 2 Section view along line AA.
[0028] Figure 4 yes Figure 1 Enlarged view of part B in the middle.
[0029] Figure 5 It is an exploded view used to show the engagement of two plug-in boards.
[0030] Explanation of the accompanying drawings: 1. frame; 11. support leg; 12. mounting plate; 2. drilling and sampling mechanism; 21. hydraulic cylinder; 22. driving motor; 23. water drill head; 24. support plate; 3. mounting unit; 31. cross plate group; 311. plug plate; 312. plug-in slot; 32. mounting rod; 33. cross slot; 34. fastening sleeve; 35. tip; 36. fastening nut; 41. fixing screw; 42. support block; 421. slide groove; 43. first fixing rod; 44. second fixing rod; 451. fixing part; 452. connecting part; 461. protrusion; 462. blocking part; 47. driving member; 471. driving rod; 48. guide rod; 5. foundation pile. DETAILED DESCRIPTION
[0031] The following is combined with Figure 1-5 This application is described in further detail.
[0032] The embodiment of the present application discloses an engineering foundation pile detection and fixing device.
[0033] Reference Figure 1 A device for detecting and fixing engineering foundation piles includes a frame 1, on which a drilling sampling mechanism 2 and an installation unit 3 are provided. The drilling sampling mechanism 2 is used to drill into the foundation pile 5 to take out concrete samples of different depths. There are several installation units 3, and the frame 1 is installed and fixed to the foundation through the installation units 3.
[0034] Reference Figure 1 , Figure 2At least two groups of fixing screws 41 are provided on the frame 1. In this embodiment, the number of fixing screws 41 is two groups. Two legs 11 are formed at the bottom of the frame 1. The legs 11 correspond to the fixing screws 41 one by one. The foundation pile 5 is located between the two legs 11. The fixing screws 41 pass through the legs 11 and are threadedly connected to the legs 11. The two fixing screws 41 are arranged opposite to each other along the circumference of the foundation pile 5. Each fixing screw 41 is arranged along the radial direction of the foundation pile 5. Each fixing screw 41 is arranged at one end close to the foundation pile 5. A support block 42 is provided, a fixing screw 41 is inserted into the support block 42 and is rotatably connected to the support block 42, so that the fixing screw 41 can push or pull the support block 42 to move, a first fixing rod 43 and a second fixing rod 44 are provided on the support block 42, and the number of the second fixing rods 44 is two, each of the first fixing rod 43 and the second fixing rod 44 includes a fixing portion 451 and a connecting portion 452, the fixing portion 451 is arranged along the vertical direction, and the connecting portion 452 is arranged perpendicular to the fixing portion 451.
[0035] Reference Figure 2 , Figure 3 The support block 42 is provided with a slide groove 421 for the connecting portion 452 of the first fixing rod 43 to be inserted into. The connecting portion 452 of the first fixing rod 43 is inserted into the slide groove 421 and can slide along the slide groove 421. The connecting portion 452 of the first fixing rod 43 is provided with a protrusion 461 at one end inserted into the slide groove 421. The opening of the slide groove 421 gradually shrinks to form a blocking portion 462 for limiting the protrusion 461 from sliding out of the slide groove 421.
[0036] Reference Figure 1 , Figure 2 , the connecting portion 452 of the second fixing rod 44 is hinged to the support block 42 and rotates along the horizontal plane. The two second fixing rods 44 are located on both sides of the first fixing rod 43. The first fixing rod 43 and each second fixing rod 44 are connected by a driving member 47. The driving member 47 in this embodiment includes a driving rod 471. One end of the driving rod 471 is hinged to the connecting portion 452 of the first fixing rod 43, and the other end is hinged to the connecting portion 452 of the second fixing rod 44. When the support block 42 slides along the connecting portion 452 of the first fixing rod 43, the two second fixing rods 44 can approach each other, and the fixing portion 451 of the second fixing rod 44 is pressed against the foundation pile 5. A guide rod 48 is fixed to the support block 42. The axis of the guide rod 48 is parallel to the axis of the fixing screw 41. The guide rod 48 passes through the leg 11 and is slidably connected to the leg 11. The rotation of the support block 42 is limited by the guide rod 48, thereby improving the sliding stability of the support block 42.
[0037] When installing the frame 1, first install each leg 11 of the frame 1 on the foundation through the installation unit 3, and then rotate the fixing screw 41, the fixing screw 41 pushes the support block 42 to slide toward the foundation pile 5, at this time, the fixing portion 451 of the first fixing rod 43 contacts the foundation pile 5, as the fixing screw 41 continues to rotate, the support block 42 and the first fixing rod 43 slide relative to each other, at this time, while the support block 42 slides toward the foundation pile 5, the driving rod 471 pulls the two second fixing rods 44 closer to each other, when the fixing portions 451 of the two second fixing rods 44 abut against the foundation pile 5, at this time, continue to rotate the fixing screw 41 to move toward the foundation pile 5, the support block 42 presses the fixing portion 451 of the first fixing rod 43 and the fixing portion 451 of the second fixing rod 44 against the foundation pile 5, thereby realizing the fixed connection between the frame 1 and the foundation pile 5, the first fixing rod 43 and the second fixing rod 44 can be adaptively fixed according to the different diameters of the foundation pile 5, thereby improving the adaptability of the fixing device.
[0038] Reference Figure 1 The drilling sampling mechanism 2 in this embodiment includes a hydraulic cylinder 21, a driving motor 22 and a water drill head 23. There are two hydraulic cylinders 21, which are arranged on the top of the frame 1. The output shaft of each hydraulic cylinder 21 faces downward. A support plate 24 is fixedly arranged on the output shafts of the two hydraulic cylinders 21. The driving motor 22 is fixedly arranged on the support plate 24. The output shaft of the driving motor 22 faces vertically downward and passes through the support plate 24. The water drill head 23 is coaxially fixedly arranged on the output shaft of the driving motor 22. The driving motor 22 drives the water drill head 23 to rotate, and then the hydraulic cylinder 21 drives the water drill head 23 to move downward, and the water drill head 23 drills into the foundation pile 5 to perform drilling sampling on the foundation pile 5.
[0039] Reference Figure 1 , Figure 4 , a mounting plate 12 is fixedly provided at the bottom of each leg 11. The mounting unit 3 in this embodiment includes a cross plate group 31 and a mounting rod 32. The cross plate group 31 includes two plug-in plates 311 spliced to each other. Each plug-in plate 311 is provided with a plug-in slot 312. The two plug-in slots 312 are arranged at both ends of different plug-in plates 311. The two plug-in slots 312 are arranged in the same direction. During assembly, one plug-in plate 311 is inserted into another plug-in slot 312 to complete the splicing of the two plug-in plates 311. After the splicing is completed, the two plug-in plates 311 are perpendicular to each other to form a cross plate group 31. When one of the plug-in plates 311 of the cross plate group 31 is damaged, only the damaged plug-in plate 311 needs to be replaced, and then the two plug-in plates 311 are plugged together again, thereby improving the convenience of replacing the cross plate group 31 when it is damaged.
[0040] Reference Figure 4 , Figure 5A cross slot 33 cooperating with the cross plate set 31 is provided on the mounting rod 32, and the cross slot 33 extends to one end of the mounting rod 32, so that the cross plate set 31 can be inserted into the cross slot 33 from one end of the mounting rod 32, and the spliced cross plate set 31 is inserted into the cross slot 33 on the mounting rod 32, thereby improving the convenience of disassembly and assembly of the mounting rod 32 and the cross plate set 31.
[0041] Reference Figure 4 , Figure 5 The length of the cross slot 33 is greater than the length of the cross plate group 31. The end of the mounting rod 32 inserted into the foundation is sleeved with a fastening sleeve 34, which is threadedly connected to the mounting rod 32. The fastening sleeve 34 can tightly fix the cross plate group 31 in the cross slot 33. When the cross plate group 31 is inserted into the cross slot 33, the fastening sleeve 34 is screwed onto the mounting rod 32, and the cross plate group 31 is restricted in the cross slot 33 by the fastening sleeve 34, so that the cross plate group 31 can be easily pulled out of the foundation. The other end of the mounting rod 32 passes through the mounting plate 12. The mounting rod 32 is provided with a fastening nut 36 at one end passing through the mounting plate 12. The fastening nut 36 is threadedly sleeved on the mounting rod 32, and the fastening nut 36 can tightly press the mounting plate 12 against the cross plate group 31. The fastening sleeve 34 is protruded at the end away from the support plate 24 to form a tip 35, which is convenient for the fastening sleeve 34 to be inserted into the foundation. When the frame 1 is installed on the foundation, the cross plate set 31 is first installed on the mounting rod 32, and then the mounting rod 32 together with the cross plate set 31 is inserted into the foundation, and then the fastening nut 36 is screwed to tighten the mounting plate 12 against the cross plate set 31. The cross plate set 31 increases the contact area with the foundation and improves the torsion resistance of the frame 1.
[0042] The implementation principle of the engineering foundation pile detection and fixing device of the embodiment of the present application is as follows: when installing the frame 1, first insert the cross plate group 31 together with the installation rod 32 into the foundation, and then screw the fastening nut 36 onto the installation rod 32, so that the installation plate 12 is pressed against the cross plate group 31, and the frame 1 and the foundation are fixed. Then, the fixing screw 41 is rotated, and the fixing screw 41 pushes the support block 42 to slide toward the foundation pile 5. At this time, the fixing portion 451 of the first fixing rod 43 contacts the foundation pile 5. As the fixing screw 41 continues to rotate, the support block 42 and the first fixing rod 43 slide relative to each other. At this time, when the support block 42 slides toward the foundation pile 5, the driving rod 471 pulls the two second fixing rods 44 closer to each other. When the fixing parts 451 of the two second fixing rods 44 abut against the foundation pile 5, the fixing screw 41 continues to be rotated to move toward the foundation pile 5, and the support block 42 presses the fixing parts 451 of the first fixing rod 43 and the fixing parts 451 of the second fixing rod 44 against the foundation pile 5, thereby realizing the fixed connection between the frame 1 and the foundation pile 5. The first fixing rod 43 and the second fixing rod 44 can be adaptively fixed according to the different diameters of the foundation pile 5, thereby improving the adaptability of the fixing device.
[0043] The above are all preferred embodiments of the present application, and the protection scope of the present application is not limited thereto. Therefore, any equivalent changes made according to the structure, shape, and principle of the present application should be included in the protection scope of the present application.
Claims
1. A construction pile detection and fixing device, comprising a frame (1) and a drilling sampling mechanism (2) arranged on the frame (1), characterized in that: The frame (1) is provided with a plurality of mounting units (3) for inserting into the foundation, and the frame (1) is provided with at least two groups of fixing screws (41), the fixing screws (41) are threadedly connected to the frame (1), and are arranged along the radial direction of the foundation pile (5), so that at least two groups of fixing screws (41) are opposite to each other, each of the fixing screws (41) is rotatably connected to a support block (42) at one end close to the foundation pile (5), and a first fixing rod (43) for contacting the foundation pile (5) is slidably provided on the support block (42), and a second fixing rod (44) is rotatably provided on the foundation pile (5), and the first fixing rod (43) drives the second fixing rod (44) to rotate through a driving member (47), so that the second fixing rod (44) is tightly contacted with the foundation pile (5).
2. The engineering foundation pile detection and fixing device according to claim 1 is characterized in that: The driving member (47) comprises a driving rod (471), one end of the driving rod (471) being hinged to the second fixing rod (44), and the other end of the driving rod (471) being hinged to the first fixing rod (43), and the first fixing rod (43) can pull the driving rod (471) through the driving rod (471) to rotate toward the foundation pile (5) and press against the foundation pile (5).
3. The engineering foundation pile detection and fixing device according to claim 1 is characterized in that: A guide rod (48) is fixedly provided on the support block (42) and is arranged parallel to the fixing screw rod (41); the guide rod (48) passes through the frame (1) and is slidably arranged with the frame (1).
4. The engineering foundation pile detection and fixing device according to claim 1 is characterized in that: The mounting unit (3) comprises a cross plate group (31) and a mounting rod (32); the mounting rod (32) is detachably connected to the frame (1); the cross plate group (31) is arranged on the mounting rod (32) and is inserted into the foundation along with the mounting rod (32).
5. The engineering foundation pile detection and fixing device according to claim 4 is characterized in that: The cross plate group (31) comprises two plug-in plates (311) plugged into each other, and the two plug-in plates (311) are arranged vertically.
6. The engineering foundation pile detection and fixing device according to claim 4 is characterized in that: The mounting rod (32) is provided with a cross slot (33) for the cross plate group (31) to be inserted into, and the cross slot (33) cooperates with the cross plate group (31) to limit the rotation of the cross plate group (31).
7. The engineering foundation pile detection and fixing device according to claim 6 is characterized in that: A tightening sleeve (34) is threadedly sleeved on the mounting rod (32). The tightening sleeve (34) is arranged at the end of the mounting rod (32) and is used to restrict the cross plate group (31) from sliding out of the cross slot (33).
8. The engineering foundation pile detection and fixing device according to claim 7 is characterized in that: The fastening sleeve (34) is provided with a tip (35) at an end facing away from the mounting rod (32).