Pile foundation reinforcing and repairing mechanism for wharf reconstruction

Through the combined structure of sleeve, compression sealing strip, stirrup, planting reinforcement and epoxy sealing glue, a grouting cavity is formed for the dock pile foundation reinforcement, which solves the problem of undustration of pile foundation repair in the existing technology and achieves a higher Carrying capacity and durability.

CN222083628UActive Publication Date: 2024-11-29CCCC THIRD HARBOR ENGINEERING CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420750155.6
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-04-11
Publication Date
2024-11-29
Estimated Expiration
2034-04-11

AI Technical Summary

Technical Problem

The existing dock pile foundation repair technology is difficult to restore its bearing capacity and is not durable, and is prone to secondary damage, resulting in safety hazards and waste of resources in the dock.

Method used

A combined structure of sleeves, compression seal strips, multi-layer stirrups, planting reinforcement and epoxy sealing glue is adopted to form a grouting cavity for reinforcement, and the internal and external layers are jointly supported, increasing the horizontal and height directions and improving the bearing capacity.

Benefits of technology

It significantly improves the reinforcement and repair strength and durability of the pile foundation, extends the service life, enhances the bearing capacity of the dock, and avoids slurry leakage and corrosion.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222083628U_ABST
    Figure CN222083628U_ABST
Patent Text Reader

Abstract

The utility model discloses a pile foundation reinforcing and repairing mechanism for wharf reconstruction. Comprising a sleeve surrounding the outer side of a damaged position of a pile foundation, a compression sealing strip arranged at the bottom of the sleeve and used for sealing a gap between the pile foundation and the sleeve, a grouting cavity formed by the gap between the pile foundation and the sleeve, and multiple layers of stirrups arranged in the grouting cavity and formed by stacking around the outer side of the pile foundation. The embedded steel bars are vertically inserted into the grouting cavity. The outer side of the pile foundation can be conveniently grouted and reinforced through the grouting cavity formed by the sleeve, and the reinforced pile foundation is jointly supported by the inner-layer grouting and the outer-layer sleeve, so that the pile foundation is more durable; the multiple layers of stirrups formed by stacking can reinforce and optimize the pile foundation from all horizontal sections, and the multiple vertically-inserted embedded steel bars can reinforce and optimize the pile foundation from the height direction, so that the reinforcing and repairing strength is further enhanced, and the pile foundation has higher bearing capacity.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of dock construction, in particular to a pile foundation reinforcement and repairing mechanism for transforming a dock. Background Art

[0002] A dock is a building at the seaside or by the river for passengers to get on and off and for cargo to be loaded and unloaded. With the growing development of dock transportation in my country, the traffic volume is increasing and the number of overloaded and limited-load vehicles is increasing, which brings certain safety hazards to the docks. Some docks that cannot meet modern transportation needs or have reached their design life need to be demolished and rebuilt. However, the demolition and reconstruction of docks not only wastes resources and generates a lot of construction waste, but also requires a lot of manpower and financial resources.

[0003] Therefore, compared with demolishing and rebuilding the wharf, a more economical and environmentally friendly way is to transform the old wharf and repair the damage and cracks. After the existing pile foundation is damaged, the broken parts are repaired with common cement mortar, or reinforced with hoops and other reinforcements. It is difficult to restore its bearing capacity after repair, and it is not durable and prone to secondary damage. Summary of the invention

[0004] In view of this, the utility model provides a pile foundation reinforcement and repair mechanism for transforming a dock, which has the characteristics of high reinforcement and repair strength, good effect, and simple and easy operation.

[0005] The utility model solves the above problems through the following technical means:

[0006] The utility model discloses a pile foundation reinforcement and repair mechanism for renovating a dock, comprising a sleeve surrounding the outside of a damaged part of the pile foundation, a compression sealing strip arranged at the bottom of the sleeve and used to seal the gap between the pile foundation and the sleeve, a grouting cavity formed by the gap between the pile foundation and the sleeve, multiple layers of stirrups arranged inside the grouting cavity and stacked around the outside of the pile foundation, and multiple embedded bars vertically inserted into the grouting cavity.

[0007] The pile foundation reinforcement and repair mechanism for transforming a dock of the utility model also includes a plurality of limiters arranged on the inner side of the sleeve for limiting the distance between the sleeve and the pile foundation, and an underwater epoxy sealing strip arranged on the top of the sleeve for sealing the pile foundation and the top of the sleeve.

[0008] The pile foundation reinforcement and repairing mechanism for transforming a dock of the utility model also comprises a bottom underwater epoxy sealing adhesive injected into the upper part of the compression sealing strip from the bottom of the grouting cavity.

[0009] Preferably, the top underwater epoxy sealing strip is an upper inclined structure.

[0010] Preferably, the sleeve is a composite fiber sleeve.

[0011] Preferably, the grouting cavity is filled with epoxy resin grouting material or cement-based grouting material.

[0012] Preferably, the plurality of embedded bars are located outside the stirrups and are evenly distributed around the periphery of the stirrups.

[0013] Preferably, a fastening belt for temporarily fixing the sleeve is provided at an upper portion of the outer side of the sleeve.

[0014] Preferably, the compression sealing strip is located 25 mm away from the bottom of the sleeve.

[0015] It can be seen from the above technical solution that the utility model has the following beneficial effects:

[0016] The utility model provides a pile foundation reinforcement and repair mechanism for a renovated dock. The grouting cavity is formed by the sleeve, so the outer side of the pile foundation can be conveniently reinforced by grouting. The reinforced pile foundation is supported by the inner grouting and the outer sleeve, so it is more durable. The compression sealing strip at the bottom is sealed to prevent leakage. The stacked multi-layer stirrups can strengthen and optimize the pile foundation from each horizontal section, and the vertically inserted multiple embedded bars can strengthen and optimize the pile foundation from the height direction, thereby further enhancing the reinforcement and repair strength and making it have a stronger bearing capacity. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] Figure 1 It is a structural cross-sectional view of the pile foundation reinforcement and repair mechanism for transforming a dock according to the utility model;

[0018] Figure 2 It is a structural schematic diagram of the pile foundation reinforcement and repair mechanism for transforming a wharf in Example 1;

[0019] Figure 3 This is a structural schematic diagram of the pile foundation reinforcement and repair mechanism for the renovated dock in Example 2.

[0020] like Figure 1-Figure 3 , sleeve-1, compression sealing strip-2, grouting cavity-3, stirrups-4, embedded bars-5, limiter-6, top underwater epoxy sealing strip-7, bottom underwater epoxy sealing glue-8, pile body-9, pile head-10, pile foundation-11. DETAILED DESCRIPTION

[0021] In the description of the present invention, it should be understood that the terms "center", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", etc., indicating directions or positional relationships, are based on the directions or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific direction, be constructed and operated in a specific direction, and therefore should not be understood as a limitation on the present invention.

[0022] The terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Therefore, a feature defined as "first" or "second" may explicitly or implicitly include one or more of the features. In the description of the present utility model, unless otherwise specified, "plurality" means two or more.

[0023] Example 1

[0024] The pile body 9 reinforcement and repair mechanism for transforming the wharf in this embodiment is mainly aimed at the reinforcement and repair of the pile body 9. The utility model will be described in detail below in conjunction with the accompanying drawings. Figure 2 As shown: the reinforcement and repair mechanism for the pile body 9 of the renovated dock described in this embodiment includes a sleeve 1 surrounding the outside of the damaged part of the pile body 9, a compression sealing strip 2 arranged at the bottom of the sleeve 1 for sealing the gap between the pile body 9 and the sleeve 1, a grouting cavity 3 formed by the gap between the pile body 9 and the sleeve 1, a multi-layer stirrup 4 arranged inside the grouting cavity 3 and stacked around the outside of the pile body 9, and a plurality of embedded bars 5 vertically inserted into the grouting cavity 3, and also includes a plurality of limiters 6 arranged on the inner side of the sleeve 1 for limiting the distance between the sleeve 1 and the pile body 9, and an underwater epoxy sealing strip 7 arranged on the top of the sleeve 1 for sealing the pile body 9 and the top of the sleeve 1.

[0025] The pile body 9 reinforcement and repair mechanism for the modified dock described in this embodiment limits the sleeve 1 by multiple limiters 6, ensuring that the grouting cavity 3 is evenly surrounded by the outside of the pile body 9. The sleeve 1 forms a grouting cavity 3, which can conveniently grout and reinforce the outside of the pile body 9. The reinforced pile body 9 is supported by the inner layer of grouting and the outer layer of the sleeve 1, which is more durable. The compression sealing strip 2 at the bottom is sealed to prevent leakage; the stacked multi-layer stirrups 4 can strengthen and optimize the pile body 9 from each horizontal section, and the vertically inserted multiple embedded bars 5 can strengthen and optimize the pile body 9 from the height direction, thereby further strengthening the reinforcement and repair strength and making it have a stronger bearing capacity; the underwater epoxy sealing strip 7 arranged on the top of the sleeve 1 can separate the slurry in the grouting cavity 3 from the outside, avoid the corrosion of the slurry by river water or sea water, and extend the service life.

[0026] As a preferred implementation of this embodiment, the sleeve 1 is a composite fiber sleeve 1.

[0027] As a preferred implementation of this embodiment, the grouting cavity 3 is filled with epoxy resin grouting material or cement-based grouting material.

[0028] In order to facilitate the operation and construction, as a further improvement of the above technical solution, the plurality of embedded bars 5 are located outside the stirrups 4 and are evenly distributed around the periphery of the stirrups 4 .

[0029] In order to facilitate fixed installation, as a further improvement of the above technical solution, a fastening belt (not shown in the figure) for temporarily fixing the sleeve 1 is provided at the upper outer side of the sleeve 1 .

[0030] As a preferred implementation of this embodiment, the compression sealing strip 2 is located 25 mm away from the bottom of the sleeve 1.

[0031] It can be seen from the above technical solution that the utility model has the following beneficial effects:

[0032] Example 2

[0033] The pile head 10 reinforcement and repair mechanism for transforming the wharf in this embodiment is mainly aimed at the pile head 10 reinforcement and repair. The utility model will be described in detail below with reference to the accompanying drawings. Figure 3As shown: the reinforcement and repair mechanism for the pile head 10 of the renovated dock described in this embodiment includes a sleeve 1 surrounding the outside of the damaged part of the pile head 10, a compression sealing strip 2 arranged at the bottom of the sleeve 1 for sealing the gap between the pile head 10 and the sleeve 1, a grouting cavity 3 formed by the gap between the pile head 10 and the sleeve 1, a multi-layer stirrup 4 arranged inside the grouting cavity 3 and stacked around the outside of the pile head 10, and a plurality of embedded bars 5 vertically inserted into the grouting cavity 3, and also includes a bottom underwater epoxy sealing glue 8 injected from the bottom of the grouting cavity 3 into the upper part of the compression sealing strip 2.

[0034] The pile head 10 reinforcement and repair mechanism for the renovated dock described in this embodiment can only be fixed from the bottom when the pile head 10 is reinforced. Therefore, the bottom underwater epoxy sealant 8 injected from the bottom of the grouting cavity 3 can not only fix the sleeve 1, but also further seal the bottom to avoid leakage. The grouting cavity 3 formed by the sleeve 1 can conveniently be used to grout and reinforce the outside of the pile head 10. The reinforced pile head 10 is supported by the inner layer of grouting and the outer layer of the sleeve 1, which is more durable. The compression sealing strip 2 at the bottom is sealed to prevent leakage. The stacked multi-layer stirrups 4 can strengthen and optimize the pile head 10 from each horizontal section, and the vertically inserted multiple embedded bars 5 can strengthen and optimize the pile head 10 from the height direction, thereby further strengthening the reinforcement and repair strength, so that it has a stronger bearing capacity.

[0035] Finally, it should be noted that the above embodiments are only used to illustrate the technical solution of the utility model rather than to limit it. Although the utility model has been described in detail with reference to the preferred embodiments, ordinary technicians in the field should understand that the technical solution of the utility model can be modified or replaced by equivalents without departing from the purpose and scope of the technical solution of the utility model, which should be included in the scope of the claims of the utility model.

Claims

1. A pile foundation reinforcement and repair mechanism for transforming a dock, characterized by: It includes a sleeve surrounding the outside of the damaged part of the pile foundation, a compression sealing strip arranged at the bottom of the sleeve for sealing the gap between the pile foundation and the sleeve, a grouting cavity formed by the gap between the pile foundation and the sleeve, multiple layers of stirrups arranged inside the grouting cavity and stacked around the outside of the pile foundation, and multiple embedded bars vertically inserted into the grouting cavity.

2. The pile foundation reinforcement and repair mechanism for transforming a dock according to claim 1, characterized in that: It also includes a plurality of limiters arranged on the inner side of the sleeve for limiting the distance between the sleeve and the pile foundation, and an underwater epoxy sealing strip arranged on the top of the sleeve for sealing the pile foundation and the top of the sleeve.

3. The pile foundation reinforcement and repair mechanism for transforming a dock according to claim 1, characterized in that: The method also includes injecting bottom underwater epoxy sealing glue into the upper part of the compression sealing strip from the bottom of the grouting cavity.

4. The pile foundation reinforcement and repair mechanism for transforming a dock according to claim 2, characterized in that: The top underwater epoxy sealing strip is an upper inclined structure.

5. The pile foundation reinforcement and repair mechanism for transforming a dock according to claim 1, characterized in that: The sleeve is a composite fiber sleeve.

6. The pile foundation reinforcement and repair mechanism for transforming a dock according to claim 1, characterized in that: The grouting cavity is filled with epoxy resin grouting material or cement-based grouting material.

7. The pile foundation reinforcement and repair mechanism for transforming a dock according to claim 1, characterized in that: The plurality of embedded bars are all located outside the stirrups and are evenly distributed around the periphery of the stirrups.

8. The pile foundation reinforcement and repair mechanism for transforming a dock according to claim 1, characterized in that: A fastening belt for temporarily fixing the sleeve is provided at the upper outer side of the sleeve.

9. The pile foundation reinforcement and repair mechanism for transforming a dock according to claim 1, characterized in that: The compression seal strip is located 25 mm from the bottom of the sleeve.