Permanent lining construction method for arranging adit in water conveyance tunnel

The method addresses the challenges of constructing branch tunnels in water conveyance tunnels by using laser and ultrasonic detectors, drilling, and backfill grouting with specific sequences and pressures to ensure complete filling and reinforcement, improving grouting uniformity and safety.

CN119084034APending Publication Date: 2024-12-06CHINA RAILWAY CONSTR BRIDGE ENG BUREAU GRP CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411250949.7
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-06
Publication Date
2024-12-06

AI Technical Summary

Technical Problem

The construction of branch tunnels in water conveyance tunnels faces challenges due to complex geological conditions, leading to geological disasters and safety risks, and requires targeted construction methods for permanent lining to ensure stability and air discharge.

Method used

A method involving laser rangefinder and ultrasonic detector cleaning, drilling, backfill grouting with specific sequences and pressures, and sealing to ensure complete filling and reinforcement of tunnel arches, using different water-cement ratios and incorporating exhaust pipes to discharge air.

Benefits of technology

Ensures full filling of tunnel arch gaps, improves grouting uniformity and consistency, facilitates air discharge, and allows accurate monitoring of construction progress, enhancing safety and stability.

✦ Generated by Eureka AI based on patent content.
Patent Text Reader

Abstract

The invention relates to a permanent lining construction method for arranging an adit in a water conveyance tunnel, which is characterized by comprising the following steps of: 1, cleaning and preparing; step 2, drilling holes; step 3, dividing a perfusion area; step 4, backfill grouting monitoring; step 5, grouting; and step 6, plugging and detecting. By deepening the drilling position and arranging the exhaust pipe, air in the top arch is conveniently exhausted through grout during grouting, so that a new cavity is prevented from appearing at the grouting position, the quality of backfill grouting is further improved, through two times of grouting with different water-ash proportions, it is ensured that a gap of the top arch of the tunnel can be fully filled with grouting materials, and the grouting efficiency is improved. And whether the cavity at the position of the top arch is filled or not is observed by detecting the conveying pressure of the grout conveying pipeline, and constructors can conveniently and accurately judge the backfilling progress.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of water conveyance tunnel construction methods, and in particular to a permanent lining construction method for arranging branch tunnels in a horizontal tunnel in a water conveyance tunnel. Background Art

[0002] A water conveyance tunnel refers to a tunnel-type water conveyance structure, which is often used in hydraulic structures. The construction of water conveyance tunnels needs to pass through areas with complex terrain and changeable geological conditions, which brings great difficulties to the construction. Tunnel engineering needs to pass through various geological layers, such as rocks, soil layers, faults, etc. The properties and stability of these geological layers vary greatly, which brings great uncertainty to the construction. The complex geological conditions make the construction process of tunnel engineering prone to geological disasters, such as landslides, water gushing, rock bursts, etc., which seriously threaten the safety of construction workers. At the same time, the construction technology of tunnel engineering is complex, involving excavation, support, lining, ventilation, drainage and other aspects. During the construction process, how to reasonably select the construction method, construction sequence and construction parameters has become a key problem. In addition, the measurement and positioning technology of tunnel engineering is high, and it is necessary to accurately grasp the direction and position of the tunnel to ensure the smooth progress of the tunnel engineering.

[0003] In order to improve the efficiency of tunnel construction and reduce the construction difficulty and construction risk of water conveyance tunnels, several branch tunnels will be set up during the construction of ultra-long-distance water conveyance tunnels. These branch tunnels include flat tunnels and inclined shaft branch tunnels. Generally, in order to reduce the difficulty of branch tunnel construction, flat tunnel branch tunnels are used if possible, and inclined shaft branch tunnels are generally not selected. Moreover, these branch tunnels can not only realize the excavation of water conveyance tunnels from multiple places, but also serve as escape or maintenance passages for the later stage of water conveyance tunnels. Therefore, some of these branch tunnels will be retained as permanent tunnels, and permanent lining construction will be carried out on them. However, since this branch tunnel is a branch tunnel used for water conveyance tunnels, ordinary tunnel support cannot meet its normal construction needs, and more targeted construction methods are required. Summary of the invention

[0004] The object of the present invention is to provide a permanent lining construction method for arranging branch tunnels in a horizontal tunnel of a water conveyance tunnel, which can fully fill the tunnel top arch cavity, ensure the discharge of air therein, and accurately observe the progress of backfill grouting.

[0005] The present invention is implemented by the following technical scheme: A permanent lining construction method for arranging branch tunnels in a horizontal tunnel in a water conveyance tunnel, characterized in that it comprises the following steps: Step 1: Cleaning and preparation, i.e. using a laser rangefinder and an ultrasonic detector to inspect the top arch and clean up debris and concrete fragments in the uncast area; Step 2, drilling, i.e. drilling the backfill grouting hole, using a hand drill to drill the hole, and the hole is drilled 10 cm deep into the rock; Step 3: Divide the pouring area, that is, divide the tunnel backfill grouting area according to the length and sequence of concrete pouring, and grouting is carried out with 4 concrete pouring bins as a section. The length of each section is not more than 50m, and the ends of the sections are tightly sealed after the concrete pouring construction; Step 4: Backfill grouting monitoring, that is, install a dial gauge to prevent deformation and lifting, and conduct regular inspections and keep records; Step 5: Grouting, i.e. starting the pressure pump to inject the selected grouting material into the gap of the tunnel top arch through the embedded pipe. During the injection process, the pressure is gradually increased to ensure that the grouting material can fully fill and infiltrate the structure of the tunnel top arch to achieve the effect of reinforcement and strengthening; Step 6: Sealing and testing, i.e. cleaning and sealing the borehole after backfill grouting is completed, and performing a quality inspection on the backfill grouting.

[0006] In order to better implement the method of the present invention, further, the drilling construction is divided according to the type of concrete, the reinforced concrete section is drilled in the embedded pipe, and the plain concrete section is directly drilled.

[0007] In order to better implement the method of the present invention, further, when drilling the pre-buried pipe, the drilling depth is 10 cm in the rock, and the concrete thickness and cavity size are measured and recorded.

[0008] In order to better implement the method of the present invention, further, when the pre-buried pipe is drilled, pre-buried grouting pipes and exhaust pipes are used in the parts of the tunnel with large over-excavation, and the exhaust pipe should be buried in the place with the largest over-excavation, followed by the grouting pipe.

[0009] In order to better implement the method of the present invention, further, step 5 includes the following steps: Step 5. 1. The tunnel backfill grouting construction is carried out in two sequences. The first sequence hole is constructed first, and then the second sequence hole is constructed in the same grouting area. The grouting time interval of each sequence hole is not less than 48 hours; Step 5.2: The first-order holes can be filled with cement slurry with a water-cement ratio of 0.6:1, and the second-order holes can be filled with cement slurries with two ratios of 1:1 and 0.6:1. The parts with large gaps can be filled with cement mortar, but the amount of sand added should not exceed 200% of the weight of cement. ; Step 5.3: The grouting pressure in reinforced concrete can be 0.3 to 0.5 MPa. The grouting pressure in plain concrete lining can be 0.2 to 0.3 MPa.

[0010] In order to better implement the method of the present invention, further, when slurry leakage occurs during the backfill grouting of the first-order hole, it is not necessary to re-grout. When the most concentrated slurry comes out of the hole, it is sealed, and then the second-order hole is carried out. After the slurry leakage in the second-order hole is sealed, the hole is swept and re-grouted.

[0011] In order to better implement the method of the present invention, further, when monitoring the backfill grouting, a pressure gauge needs to be installed and calibrated to control the pressure increase process, thereby facilitating the observation of the lifting and deformation of the concrete.

[0012] In order to better implement the method of the present invention, further, after the backfill grouting is completed, the entire hole is sealed and compacted with hard cement mortar, and the buried pipes leaking out of the lining concrete surface are cut off.

[0013] Compared with the prior art, the present invention has the following advantages and beneficial effects: (1) The present invention ensures that the grouting material can be fully filled in the tunnel arch gap through two groutings with different water-cement ratios, and improves the uniformity and consistency of the grouting effect; (2) The present invention facilitates the discharge of air in the top arch through slurry during grouting by deepening the drilling position and providing an exhaust pipe, thereby avoiding the formation of new cavities at the grouting position and improving the quality of backfill grouting; (3) The present invention provides a pressure gauge to detect the delivery pressure of the slurry delivery pipeline to observe whether the cavity at the top arch position is filled, so as to facilitate construction personnel to accurately judge the backfilling progress. DETAILED DESCRIPTION

[0014] In order to make the purpose, process conditions and advantages of the present invention more clearly understood, the present invention is further described in detail in conjunction with the following embodiments, but the embodiments of the present invention are not limited thereto. Without departing from the above-mentioned technical ideas of the present invention, various substitutions and changes are made according to the common technical knowledge and customary means in the field, which should all be included in the scope of the present invention. The specific embodiments described herein are only used to explain the present invention and are not used to limit the present invention.

[0015] Embodiment 1: This embodiment provides a permanent lining construction method for arranging branch tunnels in a horizontal tunnel of a water conveyance tunnel, comprising the following steps: Step 1: Cleaning and preparation, that is, using a laser rangefinder and an ultrasonic detector to inspect the top arch, and clean up debris and concrete fragments in the uncast area.

[0016] Step 2, drilling, that is, drilling construction of backfill grouting holes, using a hand drill to drill, and the drilling depth is 10 cm in the rock.

[0017] Step 3: Divide the pouring area, that is, divide the tunnel backfill grouting area according to the length and sequence of concrete pouring, and grouting is carried out with 4 concrete pouring bins as a section. The length of each section is not more than 50m, and the ends of the sections are tightly sealed after the concrete pouring construction.

[0018] The tunnel backfill grouting construction is divided into two sequences, and the water-cement ratio and grouting pressure of the backfill grouting are determined.

[0019] Step 4: Backfill grouting monitoring, that is, install a micrometer to prevent deformation and lifting, and conduct regular inspections and keep records.

[0020] Step 5, grouting, that is, starting the pressure pump to inject the selected grouting material into the gap of the tunnel top arch through the embedded pipe. During the injection process, the pressure is gradually increased to ensure that the grouting material can fully fill and infiltrate the structure of the tunnel top arch to achieve the effect of reinforcement and strengthening.

[0021] Step 6: Sealing and testing, i.e. cleaning and sealing the borehole after backfill grouting is completed, and performing a quality inspection on the backfill grouting.

[0022] During construction, first conduct a comprehensive inspection and assessment of the arch to determine the specific location and extent of the unfilled concrete so that appropriate repair measures can be taken. Use professional tools and equipment, such as flashlights, laser rangefinders, etc., to conduct a careful visual inspection of the arch surface. Observe whether there are cracks, depressions or other abnormalities. Use measuring tools, such as ultrasonic detectors and other equipment to test the density and quality of the concrete. After determining the location where backfill grouting is required, remove debris, dust and loose concrete fragments from the unfilled area, clean the surface with a high-pressure water gun or wire brush, and ensure that the repair area is well bonded to the original concrete surface.

[0023] Then a hand drill is used to drill holes through the PVC pipes pre-buried during pouring, and 10 cm deep into the rock to ensure that the cavity can be fully filled during grouting. The backfill grouting area is divided according to the length and sequence of tunnel concrete pouring. A micrometer is installed before grouting, and regular monitoring and records are made to prevent deformation during the grouting process.

[0024] When grouting, it is carried out in two orders. The water-cement ratio of the two groutings is different and the interval is 48 hours. When grouting, the side holes are grouting first and then the top holes. When the grouting hole flows out of the grouting hole, the grouting is continued for a period of time before the grouting is finished. After the grouting is completed, the drilled hole is cleaned and blocked, the hole mouth is smoothed, and the excess pipe is cut off. After 7 days after the grouting is completed, the quality of the backfill grouting is checked.

[0025] Embodiment 2: The drilling construction is divided according to the type of concrete. The reinforced concrete section is drilled in the pre-buried pipe, while the plain concrete section is directly drilled.

[0026] When drilling the pre-buried pipe, the hole is drilled 10 cm deep into the rock, and the concrete thickness and cavity size are measured and recorded.

[0027] When the pre-buried pipe is drilled, the pre-buried grouting pipe and exhaust pipe are used in the part with large over-excavation of the tunnel, and the exhaust pipe should be buried in the place with the largest over-excavation, followed by the grouting pipe.

[0028] During construction, the drilling method is selected according to the inspection results of the tunnel top arch and the concrete structure at that location. When drilling, it is necessary to break through the concrete structure and penetrate 10 cm into the rock to form a filling margin, so as to facilitate the full filling of the cavity and improve the quality of backfill grouting. After drilling, the exhaust pipe needs to be inserted 10 cm into the rock, so that during grouting, the slurry squeezes the air to flow to a higher place, and the 10 cm deep into the rock is the highest point of this part, so that the air is discharged through the exhaust pipe, ensuring that during grouting, no cavity is formed due to residual air, which affects the quality of backfill grouting.

[0029] Embodiment three: The step 5 comprises the following steps: Step 5.1: Tunnel backfill grouting construction is carried out in two sequences. The first sequence hole is constructed first, followed by the second sequence hole in the same grouting area. The time interval between grouting of each sequence hole shall not be less than 48 hours.

[0030] Step 5.2: The first-order holes can be filled with cement slurry with a water-cement ratio of 0.6:1, and the second-order holes can be filled with cement slurries with two ratios of 1:1 and 0.6:1. The parts with large gaps can be filled with cement mortar, but the amount of sand added should not exceed 200% of the weight of cement.

[0031] Step 5.3: The grouting pressure in reinforced concrete can be 0.3-0.5 MPa. The grouting pressure in plain concrete lining can be 0.2-0.3 MPa.

[0032] When grouting of the first-order hole occurs, it is not necessary to re-grout. When the most concentrated slurry comes out of the hole, it is sealed and then the second-order hole is made. After the slurry leakage in the second-order hole is sealed, the hole is swept and re-grouted.

[0033] The main reason for the tunnel backfill grouting construction to be carried out in two sequence holes is to ensure that the grouting material is fully filled in the entire tunnel or cave, and to achieve the effect of uniform infiltration and reinforcement. When grouting the first sequence hole, it is mainly to fill the gaps and cracks in the surface layer, enhance the stability and bearing capacity of the surface, and by grouting the surface layer first, the pressure and resistance during subsequent grouting can be reduced. This helps to better control the flow and filling effect of the grouting material, and avoid excessive pressure causing the grouting material to flow and accumulate too quickly in the tunnel. When grouting the second sequence hole, it can ensure that the grouting material is evenly infiltrated in the entire tunnel or cave, and fully fill all spaces and gaps. This helps to improve the uniformity and consistency of the grouting effect and ensure the overall strength and stability of the structure.

[0034] First grout the first sequence hole, and then grout the second sequence hole after 48 hours. At the same time, the side holes should be grouted first, and then the top holes. The specific operation is to start from the bottom layer, grouting in layers, select two holes with the same height and symmetry on both sides for grouting in sequence, and open the other holes. When the grout flows out of the other holes at the same height, control the grouting pressure to fully exhaust the gas, and seal the pipe when the specific gravity of the grouting is the same as that of the grouting, and the same applies to the rest. When the grouting hole in the upper layer flows out slurry, the grouting pipe is replaced to this grouting hole, and grouting is performed from the grouting hole. The grouting method is the same as above. In addition, if there are holes with or without slurry, grouting is performed separately. This backfill grouting adopts "pure pressure" grouting, and a pressure gauge is installed at the grouting pipe at the orifice to control the grouting pressure between 0.3 and 0.5 MPa. Under the designed pressure, the grouting hole stops absorbing slurry and continues for 10 minutes before the grouting of the hole is finished.

[0035] When monitoring the backfill grouting, a pressure gauge needs to be installed and calibrated to control the pressure increase process, thereby facilitating the observation of the lifting and deformation of the concrete.

[0036] During backfill grouting, the delivery pressure of the injected slurry is detected by a pressure gauge. When the pressure gauge reaches the specified pressure, it means that the cavity has been filled. Because when there is a cavity in the top arch and it is not filled, the slurry will not encounter resistance during the delivery process. However, when the cavity is filled, it becomes difficult to continue to deliver the slurry in the delivery pipeline to the top arch. Therefore, stop absorbing new slurry at this time, and continue to use the pressure pump to continue to deliver the remaining slurry in the pipeline to the top arch. Continue to grout for 10 minutes. If there is no obvious change in pressure, the grouting can be stopped and the slurry is allowed to solidify.

[0037] 8. A permanent lining construction method for arranging branch tunnels in a horizontal tunnel in a water diversion tunnel according to claim 1, characterized in that: after the backfill grouting is completed, the entire hole is sealed and densely filled with hard cement mortar, and the buried pipes leaking out of the lining concrete surface are cut off.

[0038] After backfill grouting is completed, remove the accumulated water and dirt in the borehole, use hard cement mortar to seal the entire hole tightly, smooth the hole mouth, and cut off the buried pipe exposed on the surface of the lining concrete.

[0039] The quality inspection of backfill grouting shall be carried out 7 days after the grouting of the part is completed. The single-hole grouting test or double-hole connection test can be used for quality inspection of backfill grouting by drilling grouting method. The water pressure test adopts the single-point method and the water permeability is determined according to the provisions of Appendix B of "Technical Specifications for Cement Grouting Construction of Hydraulic Structures" (SL62-2014). The water pressure test shall be carried out by drilling and water pressure 7 days after the consolidation grouting of the part is completed. The number of inspection holes shall not be less than 5% of the total number of grouting holes in the part. The water pressure test data shows that the number of holes less than 3Lu is not less than 90% of the number of inspection holes, and the water permeability value of unqualified holes does not exceed 50% of the above-mentioned specified value, and is not concentrated, which is considered qualified.

[0040] Although the embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the claims and their equivalents.

Claims

1. A permanent lining construction method for arranging branch tunnels in a horizontal tunnel of a water conveyance tunnel, characterized in that: The following steps are involved: Step 1: Cleaning and preparation, i.e. using a laser rangefinder and an ultrasonic detector to inspect the top arch and clean up debris and concrete fragments in the uncast area; Step 2, drilling, i.e. drilling the backfill grouting hole, using a hand drill to drill the hole, and the hole is drilled 10 cm deep into the rock; Step 3: Divide the pouring area, that is, divide the tunnel backfill grouting area according to the length and sequence of concrete pouring, and grouting is carried out with 4 concrete pouring bins as a section. The length of each section is not more than 50m, and the ends of the sections are tightly sealed after the concrete pouring construction; Step 4: Backfill grouting monitoring, that is, install a dial gauge to prevent deformation and lifting, and conduct regular inspections and keep records; Step 5: Grouting, i.e. starting the pressure pump to inject the selected grouting material into the gap of the tunnel top arch through the embedded pipe. During the injection process, the pressure is gradually increased to ensure that the grouting material can fully fill and infiltrate the structure of the tunnel top arch to achieve the effect of reinforcement and strengthening; Step 6: Sealing and testing, i.e. cleaning and sealing the borehole after backfill grouting is completed, and performing a quality inspection on the backfill grouting.

2. The permanent lining construction method for arranging branch tunnels in a horizontal tunnel in a water diversion tunnel according to claim 1 is characterized in that: The drilling construction is divided according to the type of concrete. The reinforced concrete section is drilled in the pre-buried pipe, while the plain concrete section is directly drilled.

3. The permanent lining construction method for arranging branch tunnels in a horizontal tunnel in a water diversion tunnel according to claim 2 is characterized in that: When drilling the pre-buried pipe, the hole is drilled 10 cm deep into the rock, and the concrete thickness and cavity size are measured and recorded.

4. The permanent lining construction method for arranging branch tunnels in a horizontal tunnel in a water diversion tunnel according to claim 3 is characterized in that: When the pre-buried pipe is drilled, the pre-buried grouting pipe and exhaust pipe are used in the part with large over-excavation of the tunnel, and the exhaust pipe should be buried in the place with the largest over-excavation, followed by the grouting pipe.

5. The permanent lining construction method for arranging branch tunnels in a horizontal tunnel in a water diversion tunnel according to claim 1 is characterized in that: The step 5 comprises the following steps: Step 5.

1. The tunnel backfill grouting construction is carried out in two sequences. The first sequence hole is constructed first, and then the second sequence hole is constructed in the same grouting area. The grouting time interval of each sequence hole is not less than 48 hours; Step 5.2: The first-order holes can be filled with cement slurry with a water-cement ratio of 0.6:1, and the second-order holes can be filled with cement slurries with two ratios of 1:1 and 0.6:

1. The parts with large gaps are filled with cement mortar, but the amount of sand added is not more than 200% of the weight of cement; Step 5.

3. The grouting pressure in reinforced concrete can be 0.3 to 0.5 MPa; The grouting pressure in plain concrete lining can be 0.2 ~ 0.3Mpa.

6. A permanent lining construction method for arranging branch tunnels in a horizontal tunnel in a water diversion tunnel according to claim 5, characterized in that: When grouting of the first-order hole occurs, it is not necessary to re-grout. When the most concentrated slurry comes out of the hole, it is sealed and then the second-order hole is made. After the slurry leakage in the second-order hole is sealed, the hole is swept and re-grouted.

7. The permanent lining construction method for arranging branch tunnels in a horizontal tunnel in a water diversion tunnel according to claim 1 is characterized in that: When monitoring the backfill grouting, a pressure gauge needs to be installed and calibrated to control the pressure increase process, thereby facilitating the observation of the lifting and deformation of the concrete.

8. The permanent lining construction method for arranging branch tunnels in a horizontal tunnel in a water diversion tunnel according to claim 1 is characterized in that: After the backfill grouting is completed, the entire hole is sealed and filled tightly with hard cement mortar, and the buried pipes leaking out of the lining concrete surface are cut off.