Aluminum nitride crystal growth preparation furnace

The preparation furnace addresses air exposure during material introduction by using a limiting and releasing device to maintain airtightness, enhancing the aluminum nitride crystal synthesis process.

CN222100209UActive Publication Date: 2024-12-03YANGZHOU ZHONGTIANLI NEW MATERIAL
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202323211056.5
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-11-27
Publication Date
2024-12-03
Estimated Expiration
2033-11-27

AI Technical Summary

Technical Problem

Existing preparation furnaces are exposed to external air during the introduction of materials, which can affect the synthesis of aluminum nitride crystals.

Method used

A preparation furnace design with a feeding pipe and barrel system that includes a limiting and releasing device to minimize air exposure by pressing out air through an exhaust system and maintaining airtightness during material transfer.

Benefits of technology

The design effectively reduces the influence of external air on the aluminum nitride crystal preparation process, ensuring a controlled environment for synthesis.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222100209U_ABST
    Figure CN222100209U_ABST
Patent Text Reader

Abstract

The utility model belongs to the technical field of preparation furnaces, and relates to an aluminum nitride crystal growth preparation furnace, which comprises a preparation furnace, a feeding pipe and a feeding barrel, the preparation furnace is provided with the feeding pipe, the feeding barrel slides in the feeding pipe to feed materials into the preparation furnace, and the feeding pipe is internally provided with a limiting device for limiting the movement of a separation disc. A releasing device is arranged in the feeding pipe, the feeding barrel extrudes the releasing device to enable the limiting device to release limiting of the separating disc, materials are placed on the feeding barrel, then the feeding barrel is pushed to move in the feeding pipe, and when the limiting device limits the separating disc, the space between the separating disc and the feeding barrel is continuously reduced; when the feeding barrel makes contact with the extrusion relieving device, the relieving device makes contact with the limitation on the separation disc through the extrusion limiting device, then the space defined by the separation disc and the feeding barrel enters the preparation furnace together for preparation, and when the feeding barrel slides out of the preparation furnace, the leakproofness of the preparation furnace is kept all the time.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model belongs to the technical field of preparation furnaces, and in particular relates to an aluminum nitride crystal growth preparation furnace. Background Art

[0002] Aluminum nitride, a covalent bond compound, has the chemical formula AIN. It is a covalent crystal, belongs to diamond-like nitride, hexagonal system, wurtzite type crystal structure, non-toxic, white or grayish white. Aluminum nitride is a ceramic insulator that gives aluminum nitride a high heat transfer capacity, resulting in aluminum nitride being widely used in microelectronics. Unlike beryllium oxide, aluminum nitride is non-toxic. Aluminum nitride is treated with metal and can replace alumina and beryllium oxide for a large number of electronic instruments. Aluminum nitride can be prepared by the reduction of aluminum oxide and carbon or by direct nitridation of metal aluminum.

[0003] The existing preparation furnace is in contact with the outside world all the time when the materials are put into the furnace for preparation, which may affect the synthesis of aluminum nitride crystals. Utility Model Content

[0004] The utility model aims to provide an aluminum nitride crystal growth preparation furnace to reduce the influence of external air on the preparation of the aluminum nitride crystal during the preparation process.

[0005] To achieve the above purpose, the specific technical scheme of an aluminum nitride crystal growth and preparation furnace of the utility model is as follows:

[0006] A preparation furnace for the growth of aluminum nitride crystals, comprising a preparation furnace, a feeding pipe and a feeding barrel, wherein the preparation furnace is provided with a feeding pipe, and the feeding barrel slides inside the feeding pipe to feed materials into the preparation furnace, and is characterized in that a material changing port is provided on the feeding pipe for changing materials, two connecting bolts are provided on the feeding barrel, a separation disk is provided on the connecting bolt, a limiting device for limiting the movement of the separation disk is provided inside the feeding pipe, a releasing device is provided inside the feeding pipe, and the feeding barrel extrude the releasing device so that the limiting device releases the limit on the separation disk.

[0007] Furthermore, the feeding tube includes a tube body, a sliding cavity and an exhaust hole. The tube body is arranged in communication with the preparation furnace, the sliding cavity is arranged inside the tube body, the tube body is provided with an exhaust hole connected with the sliding cavity, the feeding tube slides inside the sliding cavity, and a limiting device and a releasing device are provided inside the tube body.

[0008] Furthermore, the limiting device includes a baffle, a slope, a first rack and a first gear. The baffle is arranged on the first rack. The baffle and the first rack slide inside the tube body. The first rack is meshed with the first gear arranged inside the tube body. The first gear is connected to the releasing device. The baffle is provided with a slope, and the baffle limits the upward movement of the separation plate.

[0009] Further, the releasing device includes a storage chamber, a movable ring, a ball head column, a spring, a first inclined plate, a second inclined plate, a pushing rack and a second gear. The storage chamber is arranged inside the tube body, the movable ring slides inside the storage chamber, the ball head column is arranged on the moving ring, the spring is arranged between the storage chamber and the moving ring, the first inclined plate is arranged on the moving ring, the second inclined plate slides inside the tube body, the second inclined plate is provided with a pushing rack, the first inclined plate squeezes the second inclined plate, and the second gear meshing with the pushing rack is arranged on the first gear.

[0010] Furthermore, the connecting bolt includes a connecting column, a first limiting ring and a second limiting ring, the connecting column is arranged on the feeding barrel, the first limiting ring and the second limiting ring are arranged on the connecting column, the limiting separation disk is arranged on the connecting column, and the limiting separation disk is placed between the first limiting ring and the second limiting ring.

[0011] The advantages of the utility model are:

[0012] The utility model places the material on the feeding barrel and then pushes the feeding barrel to move inside the feeding tube. At that time, due to the restriction of the separation disc by the limiting device, the space between the separation disc and the feeding barrel is continuously reduced, and the air inside the space is pressed out. When the feeding barrel contacts the extrusion releasing device, the releasing device contacts the restriction of the separation disc by the extrusion limiting device, and then the space enclosed by the separation disc and the feeding barrel enters into the preparation furnace for preparation together. When the feeding barrel is moved out of the preparation furnace, the airtightness of the preparation furnace is also maintained. BRIEF DESCRIPTION OF THE DRAWINGS

[0013] Figure 1 It is a schematic diagram of the overall structure of the utility model;

[0014] Figure 2 It is an overall cross-sectional view of the utility model;

[0015] Figure 3 for Figure 2 A partial enlarged schematic diagram;

[0016] Figure 4 This is a schematic diagram of the structure of the feeding pipe of the utility model;

[0017] Figure 5 A schematic diagram of the connecting bolt structure of the utility model;

[0018] Figure 6 A schematic diagram of the structure of the release device of the utility model;

[0019] Description of the markings in the figure:

[0020] Preparation furnace 1; feed pipe 2; tube body 2-1; sliding cavity 2-2; exhaust hole 2-3; material change port 3; feed barrel 4; separation plate 5; baffle 6-1; inclined surface 6-2; first rack 6-3; first gear 6-4; release device 7; storage cavity 7-1; moving ring 7-2; ball head column 7-3; spring 7-4; first inclined panel 7-5; second inclined panel 7-6; push rack 7-7; second gear 7-8; connecting bolt 8; connecting column 8-1; first limit ring 8-2; second limit ring 8-3. DETAILED DESCRIPTION

[0021] The technical solution of the utility model will be described clearly and completely below in conjunction with the accompanying drawings. Obviously, the described embodiments are part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments of the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0022] In the description of the present invention, it should be noted that the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer", etc., indicating the orientation or positional relationship, are based on the orientation or positional relationship shown in the drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present invention. In addition, the terms "first", "second", and "third" are used for descriptive purposes only, and cannot be understood as indicating or implying relative importance.

[0023] like Figure 1-6 As shown, a furnace for preparing aluminum nitride crystal growth comprises a preparation furnace 1, a feeding pipe 2 and a feeding barrel 4, wherein the preparation furnace 1 is provided with a feeding pipe 2, and the feeding barrel 4 slides inside the feeding pipe 2 to feed materials into the preparation furnace 1, and is characterized in that a material changing port 3 for changing materials is provided on the feeding pipe 2, two connecting bolts 8 are provided on the feeding barrel 4, and a separation disk 5 is provided on the connecting bolt 8, a limiting device 6 for limiting the movement of the separation disk 5 is provided inside the feeding pipe 2, a releasing device 7 is provided inside the feeding pipe 2, and the feeding barrel 4 squeezes the releasing device 7 so that the limiting device 6 releases the limiting of the separation disk 5.

[0024] By placing the material on the feeding barrel 4, and then pushing the feeding barrel 4 to move inside the feeding pipe 2, due to the restriction of the separation disc 5 by the limiting device 6, the space between the separation disc 5 and the feeding barrel 4 is continuously reduced, and the air inside the space is pressed out, when the feeding barrel 4 contacts the extrusion releasing device 7, the releasing device 7 contacts the restriction on the separation disc 5 by the extrusion limiting device 6, and then the space enclosed by the separation disc 5 and the feeding barrel 4 enters the preparation furnace 1 together for preparation, and the feeding barrel 4 keeps the preparation furnace 1 airtight when it is pulled out of the preparation furnace 1.

[0025] Among them, Figure 1-6 As shown, the feeding tube 2 includes a tube body 2-1, a sliding cavity 2-2 and an exhaust hole 2-3. The tube body 2-1 is arranged in communication with the preparation furnace 1, the sliding cavity 2-2 is arranged inside the tube body 2-1, and the tube body 2-1 is provided with an exhaust hole 2-3 which is connected with the sliding cavity 2-2. The feeding tube 4 slides inside the sliding cavity 2-2, and a limiting device 6 and a releasing device 7 are provided inside the tube body 2-1.

[0026] The material to be prepared is placed on the feeding barrel 4 through the material changing port 3, and then the feeding barrel 4 is moved, and the air in the separation disc 5 and the feeding barrel 4 is gradually discharged from the exhaust holes 2-3 to avoid the influence of excessive air on the preparation.

[0027] Among them, Figure 1-6 As shown, the limiting device 6 includes a baffle 6-1, a slope 6-2, a first rack 6-3 and a first gear 6-4. The baffle 6-1 is arranged on the first rack 6-3. The baffle 6-1 and the first rack 6-3 slide inside the tube body 2-1. The first rack 6-3 is meshed with the first gear 6-4 arranged inside the tube body 2-1. The first gear 6-4 is connected to the releasing device 7. The baffle 6-1 is provided with a slope 6-2. The baffle 6-1 limits the upward movement of the separation plate 5.

[0028] When the feed tube 4 moves, the pressure between the feed tube 4 and the separation disk 5 will increase. In order to ensure the discharge of air between the feed tube 4 and the separation disk 5, the separation disk 5 needs to be fixed, and the baffle 6-1 limits the movement of the separation disk 5.

[0029] Among them, Figure 1-6As shown, the releasing device 7 includes a storage chamber 7-1, a moving ring 7-2, a ball head column 7-3, a spring 7-4, a first inclined panel 7-5, a second inclined panel 7-6, a pushing rack 7-7 and a second gear 7-8. The storage chamber 7-1 is arranged inside the tube body 2-1, the moving ring 7-2 slides inside the storage chamber 7-1, the ball head column 7-3 is arranged on the moving ring 7-2, the spring 7-4 is arranged between the storage chamber 7-1 and the moving ring 7-2, the first inclined panel 7-5 is arranged on the moving ring 7-2, the second inclined panel 7-6 slides inside the tube body 2-1, the second inclined panel 7-6 is provided with a pushing rack 7-7, the first inclined panel 7-5 squeezes the second inclined panel 7-6, and the second gear 7-8 meshing with the pushing rack 7-7 is arranged on the first gear 6-4.

[0030] When the feeding tube 4 moves to the position of the ball head column 7-3, it will push the ball head column 7-3 to move, and the ball head column 7-3 will drive the first inclined panel 7-5 to move, and the first inclined panel 7-5 will squeeze the second inclined panel 7-6 to move, and the second inclined panel 7-6 will drive the pushing rack 7-7 to move, and the pushing rack 7-7 will drive the second gear 7-8 to rotate, and the second gear 7-8 will drive the first gear 6-4 to rotate, and the rotation will cause the first rack 6-3 to move, and the first rack 6-3 will drive the baffle 6-1 to retract into the inside of the tube body 2-1 to contact the restriction on the separation plate 5, and then the separation plate 5 and the feeding tube 4 will move together to the inside of the preparation furnace 1 for preparation.

[0031] Among them, Figure 1-6 As shown, the connecting bolt 8 includes a connecting column 8-1, a first limiting ring 8-2 and a second limiting ring 8-3, the connecting column 8-1 is arranged on the feeding tube 4, the first limiting ring 8-2 and the second limiting ring 8-3 are arranged on the connecting column 8-1, and the limiting separation disk 5 is arranged on the connecting column 8-1, and the limiting separation disk 5 is placed between the first limiting ring 8-2 and the second limiting ring 8-3.

[0032] The first limiting ring 8-2 and the second limiting ring 8-3 control the distance between the maximum and minimum holes of the separation disc 5 and the feeding barrel 4, so as to discharge the separation disc 5 and the feeding barrel 4 as much as possible while ensuring the airtightness of the separation disc 5 and the feeding barrel 4.

[0033] It is understood that the present invention is described by some embodiments, and those skilled in the art are aware that various changes or equivalent substitutions may be made to these features and embodiments without departing from the spirit and scope of the present invention. In addition, under the teachings of the present invention, these features and embodiments may be modified to adapt to specific circumstances and materials without departing from the spirit and scope of the present invention. Therefore, the present invention is not limited to the specific embodiments disclosed herein, and all embodiments falling within the scope of the claims of this application are within the scope of protection of the present invention.

Claims

1. A furnace for preparing aluminum nitride crystal growth, comprising a preparation furnace (1), a feeding pipe (2) and a feeding cylinder (4), wherein the preparation furnace (1) is provided with a feeding pipe (2) for feeding materials, and the feeding cylinder (4) slides inside the feeding pipe (2) to feed materials into the preparation furnace (1), It is characterized in that The feeding pipe (2) is provided with a material changing port (3) for changing materials, the feeding cylinder (4) is provided with two connecting bolts (8), a separation disk (5) is provided on the connecting bolts (8), a limiting device (6) for limiting the movement of the separation disk (5) is provided inside the feeding pipe (2), a releasing device (7) is provided inside the feeding pipe (2), and the feeding cylinder (4) squeezes the releasing device (7) so that the limiting device (6) releases the limiting of the separation disk (5).

2. The aluminum nitride crystal growth preparation furnace according to claim 1, It is characterized in that The feeding tube (2) comprises a tube body (2-1), a sliding cavity (2-2) and an exhaust hole (2-3); the tube body (2-1) is arranged in the preparation furnace (1) and is connected to the preparation furnace (1); the sliding cavity (2-2) is arranged inside the tube body (2-1); the tube body (2-1) is provided with an exhaust hole (2-3) connected to the sliding cavity (2-2); the feeding cylinder (4) slides inside the sliding cavity (2-2); and a limiting device (6) and a releasing device (7) are provided inside the tube body (2-1).

3. The aluminum nitride crystal growth preparation furnace according to claim 2, It is characterized in that The limiting device (6) comprises a baffle (6-1), an inclined surface (6-2), a first rack (6-3) and a first gear (6-4); the baffle (6-1) is arranged on the first rack (6-3); the baffle (6-1) and the first rack (6-3) slide inside the tube body (2-1); the first rack (6-3) is meshed with a first gear (6-4) arranged inside the tube body (2-1); the first gear (6-4) is connected to a releasing device (7); the baffle (6-1) is provided with an inclined surface (6-2); and the baffle (6-1) limits the separation disc (5) from moving upward.

4. The aluminum nitride crystal growth preparation furnace according to claim 3, It is characterized in that The releasing device (7) comprises a receiving chamber (7-1), a moving ring (7-2), a ball head column (7-3), a spring (7-4), a first inclined plate (7-5), a second inclined plate (7-6), a pushing rack (7-7) and a second gear (7-8); the receiving chamber (7-1) is arranged inside the tube body (2-1); the moving ring (7-2) slides inside the receiving chamber (7-1); the ball head column (7-3) is arranged on the moving ring (7-2); and the spring (7-4) is arranged on the first inclined plate (7-5), the second inclined plate (7-6), a pushing rack (7-7) and a second gear (7-8); The spring (7-4) is arranged between the storage chamber (7-1) and the moving ring (7-2), the first inclined plate (7-5) is arranged on the moving ring (7-2), the second inclined plate (7-6) slides inside the tube body (2-1), the second inclined plate (7-6) is provided with a pushing rack (7-7), the first inclined plate (7-5) presses the second inclined plate (7-6), and the second gear (7-8) meshing with the pushing rack (7-7) is arranged on the first gear (6-4).

5. The aluminum nitride crystal growth preparation furnace according to claim 4, It is characterized in that The connecting bolt (8) comprises a connecting column (8-1), a first limiting ring (8-2) and a second limiting ring (8-3); the connecting column (8-1) is arranged on the feeding cylinder (4); the first limiting ring (8-2) and the second limiting ring (8-3) are arranged on the connecting column (8-1); the limiting separation disk (5) is arranged on the connecting column (8-1); and the limiting separation disk (5) is placed between the first limiting ring (8-2) and the second limiting ring (8-3).