Hanging basket for building construction

By introducing a load sensing system and control switches into the hanging basket, real-time monitoring and power supply cut-off, the problem of overloading the hanging basket during construction is solved, and construction safety and efficiency are improved.

CN222101415UActive Publication Date: 2024-12-03CHINA CONSTR SILK ROAD CONSTR INVESTMENT CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420391682.2
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-02-29
Publication Date
2024-12-03
Estimated Expiration
2034-02-28

AI Technical Summary

Technical Problem

During construction, hanging baskets often cause safety accidents due to overloading, and it is difficult for existing technology to fundamentally eliminate overloading through management methods.

Method used

A hanging basket including a working basket, lifting device, load sensing system, load display device and control switch is designed to sense the load through a pressure sensor, display and control the motor to cut off the power supply in real time to prevent overload and lift.

Benefits of technology

It effectively eliminates overloading of hanging baskets, improves the efficiency of construction materials and personnel transfers, and ensures construction safety.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222101415U_ABST
    Figure CN222101415U_ABST
Patent Text Reader

Abstract

The utility model discloses a hanging basket for building construction. The hanging basket comprises an operation basket body, a lifting device, a load sensing system, a load display device and a control switch. The lifting device comprises an electric control box, a motor, a rope and a fixing device. The electric control box is used for starting or stopping the motor. The load sensing system comprises a platform plate and a pressure sensor, and the pressure sensor can sense the actual total load in the operation basket body through the platform plate. The control switch is electrically connected with the pressure sensor, the load display device and the electrical control box, the load display device can display the actual total load, and when the actual total load exceeds a preset load limit value, the control switch can control the electrical control box to cut off a power supply. Therefore, when construction materials and operators are transferred into the basket body, the transfer efficiency is improved. In addition, if the total load exceeds a preset load limit value, the electric control box can cut off a power supply, so that the phenomenon of overload operation of the hanging basket can be completely eradicated.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the field of construction technology, and in particular to a hanging basket used in construction. Background Art

[0002] During the construction of the building's exterior, a hanging basket is used. When using a hanging basket, workers first move the construction materials into the working basket, then start the hanging basket, and lift the working basket to the required height under the lifting action of the wire rope to carry out construction work. However, due to the weak safety awareness of some construction workers and the inevitable omissions in safety supervision at the construction site, in order to improve construction efficiency, these construction workers move a large amount of construction materials that exceed the load limit into the working basket at one time, resulting in overloading of the hanging basket, which may lead to safety accidents in the long run.

[0003] In order to solve the above problems, the prior art prevents the phenomenon of overloading of the hanging basket by conducting safety education and safety briefings for on-site construction personnel and assigning full-time safety officers to conduct inspections.

[0004] However, the above-mentioned methods are only solutions through management means, and still cannot fundamentally eliminate the phenomenon of overloading of the hanging basket. Utility Model Content

[0005] The utility model discloses a hanging basket for building construction. The hanging basket is adopted in the construction stage of the building facade, which can fundamentally prevent the phenomenon of overloading of the hanging basket.

[0006] In order to achieve the above-mentioned purpose, the utility model discloses a hanging basket for construction, which comprises: a working basket, a lifting device, a load sensing system, a load display device and a control switch. The lifting device comprises an electrical control box, a motor, a rope and a fixing device, the electrical control box is electrically connected to the motor, the motor can drive the rope to shorten to lift the working basket or extend to lower the working basket when rotating, and the rope is connected to the building body through the fixing device.

[0007] The load sensing system includes a platform plate and a pressure sensor, wherein the platform plate is arranged on the bottom surface of the working basket body, and the pressure sensor is arranged on the lower surface of the platform plate, and the pressure sensor can sense the actual total load of the construction materials and the workers in the working basket body through the platform plate. The control switch is electrically connected to the pressure sensor, the load display device and the electrical control box respectively, and the load display device can display the actual total load in real time. When the actual total load exceeds the preset load limit, the control switch can control the electrical control box to cut off the power supply.

[0008] Optionally, the control switch includes a single chip microcomputer.

[0009] Optionally, the electrical control box is provided with a relay, which can receive the signal transmitted by the control switch and cut off or connect the power supply.

[0010] Optionally, the platform plate includes a plurality of sub-platform plates, and the plurality of sub-platform plates can completely cover the bottom surface of the working basket body. There are a plurality of pressure sensors and the plurality of pressure sensors correspond one-to-one to the plurality of sub-platform plates.

[0011] Optionally, the pressure sensor includes a piezoresistor, and when the load applied to the sub-platform plate changes, the resistance value of the piezoresistor changes accordingly.

[0012] Optionally, the load display device is arranged on the side wall of the working basket.

[0013] Optionally, a leveling device is provided on the bottom surface of the working basket body, and the leveling device is used to level the working basket body so that the platform plate is in a horizontal state.

[0014] Optionally, the leveling device includes a plurality of vertical telescopic members, and the plurality of vertical telescopic members are arranged on the edge of the bottom surface of the working basket body.

[0015] Optionally, the vertical telescopic member is an automatic hydraulic jack.

[0016] Optionally, the rope comprises a steel wire rope.

[0017] Compared with the related art, the beneficial effects of the present application are at least:

[0018] Since the pressure sensor can sense the actual total load of the construction materials and operators in the working basket through the platform plate, the control switch is electrically connected to the pressure sensor and the load display device respectively. In the process of transferring the construction materials and operators into the working basket, the control switch can obtain the information of the actual total load from the pressure sensor in real time and transmit the information of the actual total load to the load display device. After obtaining the information of the actual total load, the load display device can display the actual total load in real time. In this way, when transporting construction materials and operators into the basket, the load display device can display the actual total load of the construction materials and operators placed in the basket in real time, and can observe the changes in the actual total load more intuitively, which is convenient for the operators to complete the transportation of construction materials and operators more quickly under the premise that the actual total load does not exceed the preset load limit, thereby improving the transportation efficiency.

[0019] Then, since the control switch is electrically connected to the pressure sensor and the electrical control box respectively, when the actual total load exceeds the preset load limit, the control switch can control the electrical control box to cut off the power supply. In this way, when transporting construction materials and workers into the basket, if the total load exceeds the preset load limit, the electrical control box can cut off the power supply, and then the motor cannot be started, and the basket cannot be lifted, so the phenomenon of overloading the hanging basket can be eliminated. BRIEF DESCRIPTION OF THE DRAWINGS

[0020] In order to more clearly illustrate the technical solutions in the embodiments of the present application, the drawings required for use in the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present application. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0021] Figure 1 It is a structural schematic diagram of a hanging basket for construction provided in an embodiment of the present application, excluding a fixing device;

[0022] Figure 2 It is a structural diagram of connecting a hanging basket used for construction to the main body of a building;

[0023] Figure 3 It is a schematic diagram of the connection relationship between the load sensing system and the control switch;

[0024] Figure 4 yes Figure 3 Schematic diagram of the structure of the platform plate.

[0025] Description of reference numerals:

[0026] 1-Working basket;

[0027] 2-lifting device; 21-electrical control box; 211-relay; 22-motor; 23-rope; 231-wire rope; 24-fixing device;

[0028] 3- load sensing system; 31- platform plate; 311- sub-platform plate; 32- pressure sensor; 321- piezoresistor;

[0029] 4- Load display device;

[0030] 5-control switch; 51-single chip microcomputer;

[0031] 6-leveling device; 61-vertical telescopic member;

[0032] 100- Suspended basket for building construction;

[0033] A-Main building. DETAILED DESCRIPTION

[0034] The following will be combined with the drawings in the embodiments of the present application to clearly and completely describe the technical solutions in the embodiments of the present application. Obviously, the described embodiments are only part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of this application.

[0035] In the present application, the terms "upper", "lower", "left", "right", "front", "back", "top", "bottom", "inner", "outer", "middle", "vertical", "horizontal", "lateral", "longitudinal" and the like indicate positions or positional relationships based on the positions or positional relationships shown in the drawings. These terms are mainly used to better describe the present application and its embodiments, and are not used to limit the indicated devices, elements or components to have a specific orientation, or to be constructed and operated in a specific orientation.

[0036] In addition, some of the above terms may be used to express other meanings in addition to indicating orientation or positional relationship. For example, the term "on" may also be used to express a certain dependency or connection relationship in some cases. For those of ordinary skill in the art, the specific meanings of these terms in this application can be understood according to specific circumstances.

[0037] In addition, the terms "installed", "set", "provided with", "connected", and "connected" should be understood in a broad sense. For example, it can be a fixed connection, a detachable connection, or an integral structure; it can be a mechanical connection, or an electrical connection; it can be a direct connection, or an indirect connection through an intermediate medium, or it can be an internal connection between two devices, elements, or components. For those of ordinary skill in the art, the specific meanings of the above terms in this application can be understood according to specific circumstances.

[0038] In addition, the terms "first", "second", etc. are mainly used to distinguish different devices, elements or components (the specific types and structures may be the same or different), and are not used to indicate or imply the relative importance and quantity of the indicated devices, elements or components. Unless otherwise specified, "plurality" means two or more.

[0039] The technical solution of the present application will be further described below in conjunction with specific embodiments and drawings.

[0040] Figure 1 1 is a schematic structural diagram of a hanging basket 100 for construction provided in an embodiment of the present application, except for the fixing device 24. Figure 2 It is a structural schematic diagram of a hanging basket 100 used for construction connected to a building body A. Figure 3It is a schematic diagram of the connection relationship between the load sensing system 3 and the control switch 5.

[0041] See also Figure 1 , Figure 2 and Figure 3 The hanging basket 100 for construction includes: a working basket body 1, a lifting device 2, a load sensing system 3, a load display device 4 and a control switch 5. The working basket body 1 is used to accommodate construction materials and workers. The lifting device 2 includes an electrical control box 21, a motor 22, a rope 23 and a fixing device 24. The electrical control box 21 is electrically connected to the motor 22 and is used to connect the power supply to start the motor 22 or cut off the power supply to shut down the motor 22. When the motor 22 rotates, it can drive the rope 23 to shorten to lift the working basket body 1 or extend to lower the working basket body 1. The rope 23 is connected to the building body A through the fixing device 24. The fixing device 24 is used to fix the hanging basket 100 for construction to the building body A.

[0042] The load sensing system 3 includes a platform plate 31 and a pressure sensor 32. The platform plate 31 is arranged on the bottom surface of the working basket body 1, and the pressure sensor 32 is arranged on the lower surface of the platform plate 31. The pressure sensor 32 can sense the actual total load of the construction materials and workers in the working basket body 1 through the platform plate 31. The control switch 5 is electrically connected to the pressure sensor 32, the load display device 4 and the electrical control box 21 respectively. In the process of transferring the construction materials and workers into the working basket body 1, the control switch 5 can obtain the information of the actual total load from the pressure sensor 32 in real time and transmit the information of the actual total load to the load display device 4. After obtaining the information of the actual total load, the load display device 4 can display the actual total load in real time. When the actual total load exceeds the preset load limit, the control switch 5 can control the electrical control box 21 to cut off the power supply.

[0043] In this embodiment, since the pressure sensor 32 can sense the actual total load of the construction materials and operators in the working basket 1 through the platform plate 31, the control switch 5 is electrically connected to the pressure sensor 32 and the load display device 4 respectively. In the process of transferring the construction materials and operators to the working basket 1, the control switch 5 can obtain the information of the actual total load from the pressure sensor 32 in real time and transmit the information of the actual total load to the load display device 4. After obtaining the information of the actual total load, the load display device 4 can display the actual total load in real time. In this way, when transporting the construction materials and operators into the basket, the load display device 4 can display the actual total load of the construction materials and operators placed in the basket in real time, and can observe the changes of the actual total load more intuitively, which is convenient for the operators to complete the transportation of the construction materials and operators more quickly under the premise that the actual total load does not exceed the preset load limit, thereby improving the transportation efficiency.

[0044] Next, since the control switch 5 is electrically connected to the pressure sensor 32 and the electrical control box 21, when the actual total load exceeds the preset load limit, the control switch 5 can control the electrical control box 21 to cut off the power supply. In this way, when transporting construction materials and workers into the basket, if the total load exceeds the preset load limit, the electrical control box 21 can cut off the power supply, and then the motor 22 cannot be started, and the basket cannot be lifted, so the phenomenon of overloading of the hanging basket 100 can be eliminated.

[0045] It should be noted that when the above-mentioned fixing device 24 fixes the hanging basket 100 to the building body A, it can be fixedly connected to the roof of the building body A, or it can be fixedly connected to the structure of a certain layer of the building body A. The embodiment of the present application does not limit this.

[0046] It should also be noted that the construction material can be an exterior wall insulation board, mortar, paint and curtain wall glass, or other types of building materials, which is not limited in the embodiments of the present application.

[0047] It should also be noted that the above-mentioned real-time refers to timely feedback of changed data or information at any time.

[0048] See also Figure 1 , Figure 2 and Figure 3 When the preset load limit of the hanging basket 100 is set to 1000 kg, when the construction materials and workers are transferred to the hanging basket 100, the basket is first placed on the ground, and then the construction materials and workers are successively transferred to the platform plate 31 in the hanging basket 100. During the transfer process, the pressure sensor 32 can sense the actual total load of the construction materials and workers in the working basket 1 through the platform plate 31, and the load display device 4 can display the actual total load in real time. When the actual total load reaches 900 kg, the speed of transferring the construction materials and workers is reduced until the actual total load is close to but does not exceed 1000 kg, and the transfer is stopped, and then the motor 22 is started to make the lifting device 2 lift the basket to the height required for construction for construction.

[0049] However, if the operator has a weak sense of safety, he or she may ignore the limitation of the preset load limit on the total load when transferring construction materials and operators into the working basket body 1. When the actual total load exceeds 1000 kg, the control switch 5 can obtain the information that the actual total load exceeds 1000 kg from the pressure sensor 32, and then control the electrical control box 21 to cut off the power supply. At this time, the operator cannot start the motor 22, and then cannot lift the hanging basket 100, so the phenomenon of overloading the hanging basket 100 is eliminated.

[0050] In some embodiments, see Figure 1 and Figure 3The control switch 5 includes a single chip microcomputer 51. Since the single chip microcomputer 51 has strong data processing and computing capabilities and strong control capabilities, the control capability of the control switch 5 is improved, thereby making the automatic control capability of the hanging basket 100 stronger and more convenient to use.

[0051] In some embodiments, see Figure 1 and Figure 3 The electrical control box 21 is provided with a relay 211, which can receive the signal transmitted by the control switch 5 and cut off or connect the power supply. In this way, when the total load exceeds the preset load limit, the relay 211 can cut off the power supply and thus prevent the lifting of the hanging basket 100. When some construction materials or operators are unloaded from the hanging basket 100 to reduce the actual total load, the relay 211 can connect the power supply again and thus lift the hanging basket 100. Therefore, the relay 211 can connect the cut-off power supply again, so that the hanging basket 100 can be repeatedly used, thereby improving the construction efficiency.

[0052] When transporting construction materials and workers into the basket, it is generally difficult to evenly distribute the construction materials and workers on the platform 31. As a result, the platform 31 deforms unevenly at different positions, which leads to a large numerical error in the actual total load. In order to solve this problem, in some embodiments, see Figure 1 , Figure 3 and Figure 4 The platform plate 31 includes a plurality of sub-platform plates 311, and the plurality of sub-platform plates 311 can completely cover the bottom surface of the working basket body 1. There are a plurality of pressure sensors 32, and the plurality of pressure sensors 32 correspond to the plurality of sub-platform plates 311 one by one. Each pressure sensor 32 can sense the corresponding local load through the corresponding sub-platform plate 311 alone, and the total load is the sum of the corresponding local loads sensed by all the sub-platform plates 311. In this way, compared with setting the platform plate 31 as a whole plate, the actual total load finally sensed by the pressure sensor 32 is more accurate.

[0053] In some embodiments, see Figure 1 and Figure 3The pressure sensor 32 includes a piezoresistor 321. When the load applied to the sub-platform plate 311 changes, the resistance value of the corresponding piezoresistor 321 changes. Since the current flowing through the piezoresistor 321 and the voltage applied to both ends of the piezoresistor 321 will change when the piezoresistor 321 changes, the change of the local load applied to the corresponding sub-plate can be reflected by the change of the current flowing through the piezoresistor or the voltage applied to both ends of the piezoresistor 321, and the current or voltage is more sensitive when changing. In this way, compared with other types of pressure sensors 32, the local load sensed by the pressure sensor 32 including the piezoresistor 321 is more accurate, thereby making the total load more accurate.

[0054] In order to make it easier for operators to read the total load value of the load display device 4, in some embodiments, see Figure 1 and Figure 3 The load display device 4 is arranged on the side wall of the working basket body 1. In this way, the operator can more easily observe the value of the actual total load on the load display device 4 when transferring construction materials and operators.

[0055] It should be noted that the value of the actual total load can be directly expressed by numbers or indirectly expressed by graphics or symbols, and the embodiments of the present application do not limit this.

[0056] The ground at the actual construction site is generally uneven, so it is difficult to make the platform board 31 in a horizontal state when the basket is placed on the ground at the construction site. When the platform board 31 is not in a horizontal state, the gravity of the construction materials and construction workers placed on the platform board 31 cannot be fully converted into the pressure applied to the pressure sensor 32 by the platform board 31. Specifically, the pressure applied to the pressure sensor 32 is less than the gravity of the construction materials and construction workers, which leads to the actual total load being greater than the total load value on the load display device 4. Therefore, there is still a risk of overloading the hanging basket 100. In order to make the actual total load sensed by the pressure sensor 32 more accurate, in some embodiments, see Figure 1 and Figure 3 The bottom surface of the working basket body 1 is provided with a leveling device 6, which is used to level the working basket body 1 so that the platform board 31 is in a horizontal state. In this way, the leveling device 6 is used to make the platform board 31 in a horizontal state, and the gravity of the construction materials and construction workers placed on the platform board 31 can be completely converted into the pressure applied to the pressure sensor 32 by the platform board 31, so that the total load value sensed by the pressure sensor 32 can be more accurate, thereby further avoiding the phenomenon of overloading of the hanging basket 100.

[0057] In some embodiments, see Figure 1 and Figure 3The leveling device 6 includes a plurality of vertical telescopic members 61, and the plurality of vertical telescopic members 61 are arranged at the edge of the bottom surface of the working basket body 1. In this way, the platform plate 31 can be placed in a horizontal state by simply adjusting the height of the plurality of vertical telescopic members 61 arranged at the edge of the bottom surface of the working basket body 1, thereby making the leveling process simpler, thereby improving the transfer efficiency.

[0058] In some embodiments, see Figure 1 and Figure 3 The vertical telescopic member 61 is an automatic hydraulic jack. Since the automatic hydraulic jack has a relatively large load capacity and can automatically extend or shorten, on the one hand, the load capacity of the basket body during leveling can be increased, and on the other hand, the leveling process can be simplified, thereby improving the transfer efficiency.

[0059] In some embodiments, see Figure 1 The rope 23 includes a steel wire rope 231. Since the steel wire rope 231 has a large load safety factor and a high tensile strength, and has good fatigue strength, impact toughness and corrosion resistance, the safety and durability of the rope 23 are improved, thereby improving the safety of the hanging basket 100 and extending the service life of the hanging basket 100.

[0060] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present application, rather than to limit it. Although the present application has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or replace some or all of the technical features therein with equivalents. However, these modifications or replacements do not cause the essence of the corresponding technical solutions to deviate from the scope of the technical solutions of the embodiments of the present application.

Claims

1. A hanging basket for construction. It is characterized in that include: Working basket body (1); A lifting device (2), the lifting device (2) comprising an electrical control box (21), a motor (22), a rope (23) and a fixing device (24), the electrical control box (21) being electrically connected to the motor (22), the motor (22) being able to drive the rope (23) to shorten to lift the working basket (1) or to lengthen to lower the working basket (1) when rotating, the rope (23) being connected to the building body A via the fixing device (24); A load sensing system (3), the load sensing system (3) comprising a platform plate (31) and a pressure sensor (32), the platform plate (31) being arranged on the bottom surface of the working basket (1), the pressure sensor (32) being arranged on the lower surface of the platform plate (31), the pressure sensor (32) being able to sense the actual total load of the construction materials and the operators in the working basket (1) through the platform plate (31); Load display device (4); A control switch (5), wherein the control switch (5) is electrically connected to the pressure sensor (32), the load display device (4) and the electrical control box (21), respectively; the load display device (4) is capable of displaying the actual total load in real time; when the actual total load exceeds a preset load limit, the control switch (5) is capable of controlling the electrical control box (21) to cut off power supply.

2. The hanging basket for construction according to claim 1, It is characterized in that The control switch (5) comprises a single chip microcomputer (51).

3. The hanging basket for construction according to claim 1, It is characterized in that The electrical control box (21) is provided with a relay (211), and the relay (211) is capable of receiving a signal transmitted by the control switch (5) and cutting off or connecting the power supply.

4. The hanging basket for construction according to claim 1, It is characterized in that The platform plate (31) comprises a plurality of sub-platform plates (311), and the plurality of sub-platform plates (311) can completely cover the bottom surface of the working basket body (1). There are a plurality of pressure sensors (32), and the plurality of pressure sensors (32) correspond one-to-one to the plurality of sub-platform plates (311).

5. The hanging basket for construction according to claim 4, It is characterized in that The pressure sensor (32) comprises a piezoresistor (321), and when the load applied to the sub-platform plate (311) changes, the resistance value of the corresponding piezoresistor (321) changes.

6. The hanging basket for construction according to claim 1, It is characterized in that The load display device (4) is arranged on the side wall of the working basket body (1).

7. The hanging basket for construction according to claim 1, It is characterized in that The bottom surface of the working basket body (1) is provided with a leveling device (6), and the leveling device (6) is used to level the working basket body (1) so that the platform plate (31) is in a horizontal state.

8. The hanging basket for construction according to claim 7, It is characterized in that The leveling device (6) comprises a plurality of vertical telescopic members (61), and the plurality of vertical telescopic members (61) are arranged on the edge of the bottom surface of the working basket body (1).

9. The hanging basket for construction according to claim 8, It is characterized in that The vertical telescopic member (61) is an automatic hydraulic jack.

10. The hanging basket for construction according to claim 1, It is characterized in that The rope (23) comprises a steel wire rope (231).