Water tank installation pre-positioning structure for photovoltaic panel gap

By using T-shaped connectors and guide parts in the sink installation of photovoltaic panel gaps, combined with buffer silicone pads, the stable installation of the sink and rain water balance are achieved, and the rainwater overflow problem caused by misalignment in the prior art is solved. .

CN222107870UActive Publication Date: 2024-12-03SHANTOU GUOYUAN OPTOELECTRONICS TECHNOLOGY CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202422684932.4
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-11-05
Publication Date
2024-12-03
Estimated Expiration
2034-11-05

AI Technical Summary

Technical Problem

The existing photovoltaic panel sink installation method is prone to overflowing due to misalignment of assembly on rainy days, losing the ability to carry rainwater.

Method used

The connecting parts with the T-shaped structure are combined with the fixing parts, and the left and right guide water balance of the sink is achieved through tightening the studs, and the central position of the studs is ensured through buffering silicone pads and guide parts to avoid increasing water flow on the side of the sink.

Benefits of technology

It effectively avoids the increase in the water flow on the side of the sink caused by assembly problems, ensuring that the sink can carry rainwater normally in heavy rain and prevent overflow.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222107870U_ABST
    Figure CN222107870U_ABST
Patent Text Reader

Abstract

The utility model relates to a water tank installation pre-positioning structure for a photovoltaic panel gap. A connecting piece of a T-shaped structure is arranged in a water tank and detachably connected with a fixing piece through a screw, the fixing piece is of a U-shaped structure, and supporting plates extending inwards are arranged on side plates at the two ends of the fixing piece; the buckling assembly comprises a buckling piece which is of a U-shaped structure, pressing plates extending outwards are arranged on side plates at the two ends of the buckling piece, the upper end and the lower end of the photovoltaic panel abut against the pressing plates and the supporting plate respectively, a lifting and pressing piece is arranged in the fixing piece and abuts against the lower end face of the supporting plate, and a stud sequentially penetrates through the buckling piece and the supporting plate and then is screwed with the lifting and pressing piece. According to the utility model, the connecting piece with the T-shaped structure is pre-arranged in the water tank and is connected to the bottom of the fixing piece, the stud is downwards screwed on the lifting and pressing piece and then is lifted up to fix the photovoltaic panel, the stud which continues to extend downwards abuts against the guide piece, and the fixing piece is aligned by inserting the stud into the guide piece, so that the water tank can be fixed by taking the stud as the center; and the left-right water guide balance is realized.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model belongs to the field of photovoltaic panel auxiliary installation equipment, and in particular relates to a water tank installation pre-positioning structure for photovoltaic panel plate gaps. Background Art

[0002] At present, photovoltaic equipment has entered thousands of households, thanks to the continuous progress of photovoltaic technology and the continuous improvement of the efficiency of photovoltaic modules. At the same time, the increasing maturity of technologies such as energy storage and microgrids has provided strong support for the further development of distributed photovoltaics. With technological progress and large-scale production, the cost of photovoltaic systems has continued to decrease, and grid parity has gradually been achieved, and the dependence on subsidies has gradually decreased. This makes photovoltaic systems more competitive in the market and attracts more users to install them.

[0003] Since the size and specifications of photovoltaic panels have been determined since they leave the factory, installation at different users requires splicing of several photovoltaic panels in a vertical and horizontal distribution. Therefore, a support frame needs to be added at the lower end of the photovoltaic panel for support, and a water gutter needs to be added between the photovoltaic panels to divert rainwater. However, the current installation of the water gutter is fixed at the lower end of the gap between the photovoltaic panels by reverse buckling. However, due to the different operation and proficiency of the assemblers, the water gutter can be installed to align with the gap between the photovoltaic panels. On rainy days, the water flow on the surface of the photovoltaic panel can be timely collected in the water gutter for diversion. However, if it is not aligned during installation, in the case of heavy rain, the water flow on one side of the gutter will increase after the rainwater flows in from the gap, causing the rainwater to overflow from the edge of the gutter on that side, causing the gutter to lose its ability to carry rainwater. Utility Model Content

[0004] In order to solve the above technical problems, the utility model provides a water tank installation pre-positioning structure for the gaps of photovoltaic panel parts, by pre-setting a T-shaped structured connector in the water tank, connecting the connector to the bottom of the fixing part, and after the stud on the buckling assembly is screwed downward on the lifting and pressing part, the lifting and pressing part is lifted to fix the photovoltaic panel, and the stud that continues to extend downward will abut against the guide part, and the fixing part can be aligned by inserting it into the guide part, so that the water tank can be fixed with the stud as the center, achieving the balance of water conduction on the left and right sides.

[0005] In order to achieve the above purpose, the technical solution adopted by the utility model is:

[0006] A water tank installation pre-positioning structure for the gap of photovoltaic panel components, comprising a water tank, a fixing component, a buckling assembly and a photovoltaic panel, wherein a T-shaped connecting component is arranged in the water tank, the connecting component and the fixing component are detachably connected by screws, a through hole is arranged on the fixing component, a locking hole is arranged on the connecting component, the fixing component is a U-shaped structure, support plates extending inwards are arranged on the side plates at both ends of the fixing component, a water guide hole is arranged on the bottom of the fixing component, and a plurality of anti-slip teeth are arranged on the lower end surface of the pressing plate;

[0007] The buckling assembly includes a buckling piece, a lifting piece, a stud and a buffer silicone pad, the buckling piece is a U-shaped structure, and the side plates at both ends of the buckling piece are provided with a pressing plate extending outward, and the upper and lower ends of the photovoltaic panel are respectively abutted against the pressing plate and the support plate, the lifting piece is arranged in the fixing piece and abuts against the lower end surface of the support plate, and the stud passes through the buckling piece and the support plate in sequence and is screwed together with the lifting piece; the buffer silicone pad includes a pad and a buffer column, the pad is arranged on the upper end surface of the buffer column, the upper end surface of the pad abuts against the lower end surface of the buckling piece, and the lower end surface of the pad abuts against the support plate, the buffer column extends into the fixing piece, the axis of the buffer column is provided with a through hole for the stud to pass through, and the radial direction of the buffer column is provided with a fixing hole for the lifting piece to pass through; the lifting piece is a horizontally placed plate-like structure, and the edges at both ends of the lifting piece are respectively provided with transition arc portions.

[0008] The water tank installation pre-positioning structure for the gap between photovoltaic panels adopts this structure, and a central connecting piece is set in the middle of the water tank. The connecting piece is a T-shaped structure, and a through hole is provided on the fixing piece. The connecting piece is fixed to the fixing piece by inserting a screw into the through hole and screwing it into the lock hole on the connecting piece. The photovoltaic panel is fixed by a buckling assembly. Specifically, a U-shaped buckling piece is inserted into the gap between two groups of photovoltaic panels, and the pressing plate on the buckling piece presses down the edge of the photovoltaic panel. The anti-slip teeth on the pressing plate can realize position restriction after fixing the photovoltaic panel to prevent the photovoltaic panel from being displaced and falling off. The buckling piece pressed downward presses the photovoltaic panel to the support plate on the fixing piece. On, after the stud passes through the buckling piece, it is inserted into the buffer column until it is screwed into the lifting and pressing piece. At this time, the pad on the buffer silicone pad will be set between the buckling piece and the support plate. Therefore, when the stud is continuously twisted, the lifting and pressing piece will continue to rise until it abuts against the lower end of the support plate, and the support plate will be pressed toward the buckling piece. The function of the pad is to ensure that the lifting and pressing piece and the support plate are elastically connected during the continuous pressing process, so as to maintain a continuous pressing force and prevent the stud from loosening easily. The horizontally placed plate-like structure of the lifting and pressing piece can better make its left and right ends abut against the two groups of support plates respectively, providing sufficient pressing force. The setting of the transition arc portion can facilitate the assembly of the lifting and pressing piece in the fixing piece.

[0009] Therefore, when the photovoltaic panels using this connection structure are hit by heavy rain, rainwater will enter the fixings through the gaps between the photovoltaic panels. Since there is no sealing design between the fixings and the photovoltaic panels, the rainwater will seep out from the gaps between them. Therefore, the gutter at the lower end of the fixings can catch the rainwater seeping from the fixings and accommodate it. Since the T-shaped structure connector is maintained in the middle of the fixings, the incoming rainwater can be well distributed on the left and right ends of the connector, thereby avoiding an increase in water flow on one side of the gutter due to assembly problems, causing rainwater to overflow from the edge of the gutter on that side, resulting in the gutter losing its ability to carry rainwater.

[0010] Furthermore, the crimping assembly also includes a guide piece, which is a U-shaped structure that opens upward and faces the stud, and a fixing plate extending outward is provided on the lower end of the guide piece, and a through hole is provided on the fixing plate, and the screw passes through the through hole and the through hole in sequence and is screwed into the lock hole; guide plates that are inclined upward and extend outward are provided on the side plates at both ends of the guide piece, and an opening is provided at the bottom of the guide piece for the stud to pass through, and an entry hole is provided at the bottom of the fixing piece for the stud to pass through, and a notch is provided on the connecting piece for the stud to extend into; the fixing plate, through hole, through hole and lock hole each include two groups and are symmetrical front and back with the stud as the center of symmetry.

[0011] Compared with the prior art, the advantage of the utility model is that the photovoltaic panel can be clamped and fixed by screwing the clamping piece and the lifting piece by the studs, and the T-shaped connecting piece can not only achieve a more stable assembly and tightening effect, but also allow workers to screw the connecting piece to the fixing piece in sequence during the assembly and installation process, so that the water tank is installed and positioned first, and then the lifting piece is inserted from the fixing piece, and the stud on the clamping piece is screwed into the lifting piece first, and then the photovoltaic panel is inserted between the pressing plate and the support plate. After tightening the studs, the photovoltaic panel can be fixed. Since the T-shaped connecting piece is maintained in the middle of the fixing piece, the incoming rainwater can be well distributed on the left and right ends of the connecting piece, avoiding the increase of water flow on one side of the water tank due to assembly problems, causing rainwater to overflow from the edge of the water tank on that side, causing the water tank to lose its ability to carry rainwater. BRIEF DESCRIPTION OF THE DRAWINGS

[0012] In order to more clearly illustrate the embodiments of the utility model or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the utility model. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0013] Figure 1 It is a three-dimensional diagram of the utility model;

[0014] Figure 2 It is an explosion diagram of the utility model;

[0015] Figure 3 For the utility model Figure 2 A local enlarged view of point A;

[0016] Figure 4 It is a top view of the utility model;

[0017] Figure 5 For the utility model Figure 4 BB cross-sectional view;

[0018] Figure 6 For the utility model Figure 5 A partial enlarged view of point C;

[0019] Figure 7 It is a three-dimensional diagram of the fixing member of the utility model;

[0020] Figure 8 It is a three-dimensional diagram of the buffer silicone pad and the lifting and pressing member of the utility model.

[0021] Among them: 1. water tank; 11. connecting piece; 111. lock hole; 112. notch; 12. screw; 2. fixing piece; 21. support plate; 22. perforation; 23. inlet hole; 24. water guide hole; 3. buckling assembly; 31. buckling piece; 311. pressing plate; 312. anti-slip teeth; 32. lifting and pressing piece; 321. transition arc portion; 33. stud; 34. buffer silicone pad; 341. pad; 342. buffer column; 343. through hole; 344. fixing hole; 35. guide piece; 351. fixing plate; 352. through hole; 353. guide plate; 354. opening; 4. photovoltaic panel. DETAILED DESCRIPTION

[0022] In order to make the purpose, technical solution and advantages of the utility model clearer, the technical solution of the utility model will be described clearly and completely below. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments of the utility model, all other embodiments obtained by ordinary technicians in this field without creative work belong to the scope of protection of the utility model.

[0023] The specific implementation of the utility model will be described below in conjunction with the accompanying drawings:

[0024] like Figure 1-8As shown, a water tank 1 for installing a pre-positioning structure of a gap between panels of a photovoltaic panel comprises a water tank 1, a fixing member 2, a pressing assembly 3 and a photovoltaic panel 4. A T-shaped connecting member 11 is provided in the water tank 1. The connecting member 11 and the fixing member 2 are detachably connected by screws 12. A through hole 22 is provided on the fixing member 2. A locking hole 111 is provided on the connecting member 11. The fixing member 2 is a U-shaped structure. Support plates 21 extending inward are provided on the side plates at both ends of the fixing member 2. A water guide hole 24 is provided on the bottom of the fixing member 2. A plurality of anti-slip teeth 312 are provided on the lower end surface of the pressing plate 311.

[0025] The buckling assembly 3 includes a buckling piece 31, a lifting piece 32, a stud 33 and a buffer silicone pad 34. The buckling piece 31 is a U-shaped structure. The side plates at both ends of the buckling piece 31 are provided with a pressing plate 311 extending outward. The upper and lower ends of the photovoltaic panel 4 are respectively abutted against the pressing plate 311 and the support plate 21. The lifting piece 32 is arranged in the fixing part 2 and abuts against the lower end surface of the support plate 21. The stud 33 passes through the buckling piece 31 and the support plate 21 in turn and is screwed with the lifting piece 32; the buffer silicone pad 34 includes a pad 341 and a buffer The column 342, the pad 341 is arranged on the upper end surface of the buffer column 342, the upper end surface of the pad 341 abuts on the lower end surface of the buckling member 31, and the lower end surface of the pad 341 abuts on the support plate 21. The buffer column 342 extends into the fixing member 2, and the axis of the buffer column 342 is provided with a through hole 343 for the stud 33 to pass through, and the radial direction of the buffer column 342 is provided with a fixing hole 344 for the lifting and pressing member 32 to pass through; the lifting and pressing member 32 is a horizontally placed plate-like structure, and the edges of both ends of the lifting and pressing member 32 are respectively provided with transition arc portions 321.

[0026] Furthermore, the buckling assembly 3 also includes a guide member 35, which is a U-shaped structure that opens upward and faces the stud 33. A fixing plate 351 extending outward is provided on the lower end of the guide member 35, and a through hole 352 is provided on the fixing plate 351. The screw 12 passes through the through hole 352 and the through hole 22 in sequence and is screwed into the lock hole 111; guide plates 353 that are inclined upward and extend outward are provided on the side plates at both ends of the guide member 35, and an opening 354 for the stud 33 to pass through is provided at the bottom of the guide member 35, an entry hole 23 for the stud 33 to pass through is provided at the bottom of the fixing member 2, and a notch 112 for the stud 33 to extend into is provided on the connecting member 11; the fixing plate 351, the through hole 352, the through hole 22 and the lock hole 111 each include two groups and are symmetrical front and back with the stud 33 as the center of symmetry.

[0027] Description of the working method of this utility model:

[0028] The water tank 1 for installing the pre-positioning structure of the gap between the photovoltaic panels adopts this structure, and a central connecting piece 11 is set in the middle of the water tank 1. The connecting piece 11 is a T-shaped structure, and a through hole 22 is provided on the fixing piece 2. The connecting piece 11 is fixed to the fixing piece 2 by inserting the screw 12 into the through hole 22 and screwing it into the lock hole 111 on the connecting piece 11, and the photovoltaic panel 4 is fixed by the buckling assembly 3. Specifically, a U-shaped buckling piece 31 is inserted into the gap between the two groups of photovoltaic panels 4, and the pressing plate 311 on the buckling piece 31 presses down the edge of the photovoltaic panel 4. The anti-slip teeth 312 on the pressing plate 311 can realize position restriction after fixing the photovoltaic panel 4, so as to prevent the photovoltaic panel 4 from being displaced and falling off, and the buckling piece 31 pressed downward presses the photovoltaic panel 4 onto the supporting plate 21 on the fixing piece 2. After the stud 33 passes through the buckling piece 31, it is inserted into the buffer column 342 until it is screwed into the lifting and pressing piece 32. At this time, the pad 341 on the buffer silicone pad 34 will be set between the buckling piece 31 and the support plate 21. Therefore, when the stud 33 is continuously twisted, the lifting and pressing piece 32 continues to rise until it abuts against the lower end of the support plate 21, which will press the support plate 21 toward the buckling piece 31. The function of the pad 341 is to ensure that the lifting and pressing piece 32 and the support plate 21 are elastically connected during the continuous pressing process, and the continuous pressing force can be maintained to prevent the stud 33 from loosening easily. The horizontal plate structure of the lifting and pressing piece 32 can better make its left and right ends abut against the two groups of support plates 21 respectively, providing sufficient pressing force. The setting of the transition arc portion 321 can facilitate the assembly of the lifting and pressing piece 32 in the fixing piece 2.

[0029] Therefore, when the photovoltaic panels 4 with this connection structure are used and encounter heavy rain, rainwater will enter the fixing parts 2 through the gaps between the photovoltaic panels 4. Since there is no sealing design between the fixing parts 2 and the photovoltaic panels 4, the rainwater will seep out from the gaps between them. Therefore, the water tank 1 at the lower end of the fixing parts 2 can catch the rainwater seeping from the fixing parts 2 and accommodate it. Since the T-shaped structure connector 11 is maintained in the middle of the fixing parts 2, the incoming rainwater can be well distributed on the left and right ends of the connector 11, avoiding an increase in water flow on one side of the water tank 1 due to assembly problems, causing rainwater to overflow from the edge of the water tank 1 on that side, causing the water tank 1 to lose its ability to carry rainwater.

[0030] Due to this connection method, it is still difficult to ensure that the fixing member 2 remains in the center of the stud 33. Once it is deflected, it is still difficult to ensure that the water tank 1 can maintain the ability to carry rainwater and prevent overflow. Therefore, the fixing member 2 needs to be straightened, that is, the pipe is straightened in the center of the stud 33. Therefore, a guide member 35 is added. The guide member 35 is a U-shaped structure, and the side plates at both ends thereof are provided with guide plates 353 that are inclined upward and extend outward. The purpose is to abut against the guide plate 353 during the process of screwing the stud 33 downward, and then enter the guide member 35 along the inclined direction to perform left and right direction correction. Then the guide member 35 must be at the center line of the fixing member 2. Therefore, a through hole 352 is opened in the fixing plate 351 on the guide member 35, and the fixing plate 351 is placed on the fixing member 2, so that the screw 12 passes through the through hole 352 and the through hole 22 in sequence and is screwed into the lock hole 111. In particular, in the case of two sets of fixing plates 351, through holes 352, through holes 22 and lock holes 111, the guide member 35 can be more effectively fixed in the fixing member 2. Therefore, when the stud 33 is screwed downward, the guide member 35 is abutted and the fixing member 2 is forced to be aligned, so that the sink 1 can be completely centered. In order to avoid interference with the stud 33 being screwed downward, an opening 354 for the stud 33 to pass through is provided at the bottom of the guide member 35, an inlet hole 23 for the stud 33 to pass through is provided at the bottom of the fixing member 2, and a notch 112 for the stud 33 to extend into is provided on the connecting member 11, so that the stud 33 will not be hindered in the process of being screwed downward.

[0031] The beneficial effect of the utility model is that the photovoltaic panel 4 can be clamped and fixed by screwing the clamping piece 31 and the lifting piece 32 by the stud 33, and the T-shaped structure connecting piece 11 can not only achieve a more stable assembly and tightening effect, but also allow workers to screw the connecting piece 11 to the fixing piece 2 in sequence during the assembly and installation process, so that the water tank 1 is first installed and positioned, and then the lifting piece 32 is inserted from the fixing piece 2, and the stud 33 on the clamping piece 31 is first screwed into the lifting piece 32, and then the photovoltaic panel 4 is inserted between the pressing plate 311 and the support plate 21. After tightening the stud 33, the photovoltaic panel 4 can be fixed. Since the T-shaped structure connecting piece 11 is maintained in the middle of the fixing piece 2, the incoming rainwater can be well distributed at the left and right ends of the connecting piece 11, avoiding the increase of water flow on one side of the water tank 1 due to assembly problems, causing rainwater to overflow from the edge of the water tank 1 on that side, causing the water tank 1 to lose its ability to carry rainwater.

[0032] The above embodiments are only used to illustrate the technical solution of the utility model, rather than to limit it. Although the utility model is described in detail with reference to the above embodiments, ordinary technicians in this field should understand that they can still modify the technical solutions recorded in the above embodiments, or replace some or all of the technical features therein with equivalents. These modifications or replacements do not make the essence of the corresponding technical solutions deviate from the scope of the technical solutions of the embodiments of the utility model.

Claims

1. A water tank installation pre-positioning structure for the gap between photovoltaic panels. Features: It includes a water tank, a fixing part, a buckling assembly and a photovoltaic panel. A T-shaped connecting part is provided in the water tank. The connecting part and the fixing part are detachably connected by screws. The fixing part is a U-shaped structure. The side plates at both ends of the fixing part are provided with support plates extending inwards. The buckling assembly includes a buckling part, a lifting part and a stud. The buckling part is a U-shaped structure. The side plates at both ends of the buckling part are provided with pressing plates extending outwards. The upper and lower ends of the photovoltaic panel are respectively abutted against the pressing plate and the support plate. The lifting part is arranged in the fixing part and abuts against the lower end surface of the support plate. The stud passes through the buckling part and the support plate in turn and is screwed to the lifting part.

2. The water tank installation pre-positioning structure for the gap of photovoltaic panels according to claim 1, Features: The buckling assembly also includes a buffer silicone pad, which includes a pad and a buffer column. The pad is arranged on the upper end surface of the buffer column, the upper end surface of the pad abuts against the lower end surface of the buckling member, and the lower end surface of the pad abuts against the support plate. The buffer column extends into the fixing member, the axis of the buffer column is provided with a through hole for the stud to pass through, and the radial direction of the buffer column is provided with a fixing hole for the lifting and pressing member to pass through.

3. The water tank installation pre-positioning structure for the gap of photovoltaic panels according to claim 2, Features: The lifting and pressing member is a transverse plate-shaped structure, and transition arc portions are respectively provided at the edges of both ends of the lifting and pressing member.

4. The water tank installation pre-positioning structure for the gap of photovoltaic panels according to claim 1, Features: The crimping assembly also includes a guide piece, which is a U-shaped structure that opens upward and faces the stud. A fixing plate extending outward is provided on the lower end of the guide piece, and a through hole is provided on the fixing plate. A through hole is provided on the fixing piece, and a lock hole is provided on the connecting piece. The screw passes through the through hole and the through hole in turn and is screwed into the lock hole.

5. The water tank installation pre-positioning structure for the gap of photovoltaic panels according to claim 4, Features: The side plates at both ends of the guide member are provided with guide plates which are inclined upward and extend outward, the bottom of the guide member is provided with an opening for the stud to pass through, the bottom of the fixing member is provided with an entry hole for the stud to pass through, and the connecting member is provided with a notch for the stud to extend into.

6. The water tank installation pre-positioning structure for the gap of photovoltaic panels according to claim 5, Features: The fixing plate, through holes, through holes and lock holes all include two groups and are front-to-back symmetrical with the stud as the symmetry center.

7. The water tank installation pre-positioning structure for the gap of photovoltaic panels according to claim 1, Features: A water guide hole is arranged on the bottom of the fixing piece.

8. The water tank installation pre-positioning structure for the gap of photovoltaic panels according to claim 1, Features: A plurality of anti-slip teeth are arranged on the lower end surface of the pressing plate.