High-clearance gypsum board suspended ceiling mounting structure

By adopting multiple sets of oblique brace systems and horizontal steel beam structures in the light steel keel ceiling, the bending deformation problem caused by excessive length of the boom is solved, the structure is simplified, and the construction efficiency and stability are improved.

CN222120697UActive Publication Date: 2024-12-06CHINA CONSTR SECOND BUREAU DECORATION ENG CO
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420822404.8
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-04-19
Publication Date
2024-12-06
Estimated Expiration
2034-04-19

AI Technical Summary

Technical Problem

The existing light steel keel ceiling needs to be equipped with reverse support when the length of the boom exceeds 1.5m to prevent bending and deformation, resulting in complex structure and low construction efficiency.

Method used

Multiple groups of oblique bracing systems and horizontal steel beam structures are adopted to shorten the length of the boom, improve installation accuracy and stability through oblique bracing and fixing bolts, and reduce the necessity of counter-support.

Benefits of technology

Simplified steel structure installation is achieved, counter-support is avoided, and the stability and construction efficiency of the suspended ceiling are improved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222120697U_ABST
    Figure CN222120697U_ABST
Patent Text Reader

Abstract

The utility model discloses a high-clearance plasterboard suspended ceiling installation structure which comprises a plurality of sets of inclined strut systems, horizontal steel beams, hanging rods, hanging pieces, main keels, hanging pieces, secondary keels and paper surface plasterboards. The oblique angle support comprises horizontal angle steel fixedly connected with a building structure, vertical angle steel fixedly arranged at one end of the horizontal angle steel and oblique angle steel connected between the horizontal angle steel and the vertical angle steel. The horizontal steel beam is fixedly connected with the vertical angle steel; the suspender is connected with the horizontal steel beam; one end of the hanging piece is connected with the hanging rod, the other end of the hanging piece is connected with the main keel, the secondary keel is connected with the main keel through the hanging piece, and the gypsum plaster board is connected with the secondary keel. The installation structure is simplified, and the stability of the structure is guaranteed.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of suspended ceiling installation, in particular to a high-clearance gypsum board suspended ceiling installation structure. Background Art

[0002] Suspended ceiling refers to a kind of decoration on the top of the living environment of a house. Simply put, it is the decoration of the ceiling, which is one of the important parts of interior decoration.

[0003] The existing Chinese utility model patent with application number CN202321025150.9 discloses a light steel keel ceiling, wherein the light steel keel ceiling structure includes a light steel keel and a gypsum board, wherein the gypsum board is bonded and fixed to the light steel keel through an adhesive layer, wherein the adhesive layer includes a nail-free adhesive layer and an instant adhesive layer. The light steel keel includes a secondary keel and at least two main keels, wherein the secondary keel is connected to at least two main keels, and the side of the secondary keel facing away from the main keel is bonded and fixed to the gypsum board through the adhesive layer. The light steel keel ceiling structure also includes a hanger and a hanger, wherein the hanger is arranged around the main keel, and a connecting hole is provided on the side of the hanger in contact with the hanger, and the hanger is screwed to the hanger through the connecting hole.

[0004] In the above scheme, usually, the light steel keel ceiling adopts φ8mm hanging rods. Due to the long and thin length of the hanging rods, when the hanging rods exceed a certain length, the ceiling will deform upward when the air pressure changes, causing the ceiling to be damaged. According to the construction specifications, when the length of the hanging rod is greater than 1.5m, a counter-support should be set to make the hanging rod and the counter-support form a stable triangular structure. The function of the ceiling hanging rod counter-support is to prevent the hanging rod from being too long and causing bending deformation and affecting the flatness of the ceiling. However, this method requires each hanging rod to be connected to the counter-support, which is complex in structure, huge in workload, and low in construction efficiency. Utility Model Content

[0005] The utility model provides a high-clearance gypsum board ceiling installation structure with simple structure and good stability.

[0006] The technical problem to be solved is: usually, light steel keel ceilings use φ8mm hanging rods. Due to the slenderness of the hanging rods, when the hanging rods exceed a certain length, the ceiling will deform upward when the air pressure changes, causing damage to the ceiling. According to the construction specifications, when the length of the hanging rod is greater than 1.5m, a counter-support should be set to form a stable triangular structure with the hanging rod and the counter-support. The function of the ceiling hanging rod counter-support is to prevent the hanging rod from being too long and causing bending deformation, which affects the flatness of the ceiling. However, this method requires each hanging rod to be connected to the counter-support, which is complex in structure, huge in workload, and low in construction efficiency.

[0007] In order to solve the above technical problems, the utility model adopts the following technical solutions:

[0008] The utility model discloses a high-clearance gypsum board ceiling installation structure, comprising a plurality of groups of diagonal bracing systems, horizontal steel beams, suspension rods, suspension pieces, main keels, hangers, secondary keels and gypsum boards, each group of the diagonal bracing systems comprises a pair of diagonal supports, the diagonal supports comprise horizontal angle steels fixed to the building structure, vertical angle steels fixed to one end of the horizontal angle steels and diagonal angle steels connected between the horizontal angle steels and the vertical angle steels; the horizontal steel beams are fixed to the vertical angle steels; the suspension rods are connected to the horizontal steel beams; one end of the suspension piece is connected to the suspension rod, and the other end is connected to the main keel; the secondary keel is connected to the main keel through the hangers, and the gypsum boards are connected to the secondary keels.

[0009] The utility model discloses a high-clearance gypsum board ceiling installation structure. Further, the vertical angle steel is provided with fixing bolts at the bottom of the horizontal steel beam, and the horizontal steel beam is supported on the fixing bolts.

[0010] The utility model discloses a high-clearance gypsum board ceiling installation structure. Furthermore, the horizontal steel beam is angle steel.

[0011] The utility model provides a high-clearance gypsum board ceiling installation structure. Further, the suspension rod passes through the horizontal steel beam and is fastened by nuts located on both sides of the horizontal steel beam.

[0012] The utility model discloses a high-clearance gypsum board ceiling installation structure. Further, the hanging member comprises a vertical plate member, an upper horizontal plate is fixedly provided at one end of the vertical plate member, and a lower horizontal plate is fixedly provided at the other end, a vertical plate parallel to the vertical plate member is fixedly provided on the lower horizontal plate, the hanging rod is connected to the upper horizontal plate, the main keel is placed in a U-shaped space enclosed by the vertical plate member, the lower horizontal plate and the vertical plate and supported on the lower horizontal plate, and a limiting bolt is connected between the vertical plate member and the vertical plate.

[0013] The utility model discloses a high-clearance gypsum board ceiling installation structure. Further, the secondary keel is a groove-shaped structure and the opening ends of the secondary keel are respectively formed with L-shaped clamping parts bent toward the inner direction of the groove, and the hanger is formed with clamping teeth that can be buckled on the clamping parts.

[0014] The utility model discloses a high-clearance gypsum board ceiling installation structure. Further, the hanger is in a U-shaped structure, buckled on the main keel, and a latch is formed at the open end thereof, and an installation space is provided between the latch and the hanger.

[0015] Compared with the prior art, the utility model has the following beneficial effects:

[0016] 1. This application aims at the high-clearance ceiling structure, and installs a simplified steel structure conversion system on the building structure. Multiple sets of diagonal bracing systems are used as the main force-bearing structure, and multiple parallel horizontal steel beams are connected at the bottom as the installation base of the hanger, thereby shortening the length of the hanger to less than 1.5m, avoiding the setting of counter-support, and having a simple structure and good stability;

[0017] 2. Arranging the angled supports in pairs can reduce the number of angled supports and improve the fixing effect on the horizontal steel beams;

[0018] 3. By setting fixing bolts, the fixing bolts are used to temporarily fix and position the horizontal steel beam before the horizontal steel beam is fixed, so as to ensure the installation accuracy and stability of the horizontal steel beam.

[0019] The utility model will be further described below in conjunction with the accompanying drawings. BRIEF DESCRIPTION OF THE DRAWINGS

[0020] Figure 1 This is a schematic diagram of the installation structure of the utility model;

[0021] Figure 2 It is a structural schematic diagram of the utility model hanging part;

[0022] Figure 3 It is a structural schematic diagram of the pendant of the utility model.

[0023] Reference numerals:

[0024] 1. Building structure; 2. Angled support; 2.1. Horizontal angle steel; 2.2. Vertical angle steel; 2.3. Oblique angle steel; 3. Horizontal steel beam; 4. Fixing bolts; 5. Hanging rod; 6. Hanging fittings; 6.1. Vertical plate; 6.2. Upper horizontal plate; 6.3. Lower horizontal plate; 6.4. Vertical plate; 6.5. Limiting bolts; 7. Secondary purlin; 7.1. Clamping part; 8. Hanging fittings; 8.1. Clamping teeth; 8.2. Installation space; 9. Gypsum board; 10. Main purlin. DETAILED DESCRIPTION

[0025] like Figure 1-Figure 3As shown, the utility model is a high-clearance gypsum board ceiling installation structure, including multiple groups of diagonal bracing systems, horizontal steel beams 3, hangers 5, hangers 6, main keels 10, hangers 8, secondary keels 7 and paper-faced gypsum boards 9, the multiple groups of diagonal bracing systems are arranged in rows, each group of diagonal bracing systems includes a pair of diagonal supports 2, the diagonal supports 2 include horizontal angle steels 2.1, vertical angle steels 2.2 fixed at one end of the horizontal angle steels 2.1, and diagonal angle steels 2.3 connected between the horizontal angle steels 2.1 and the vertical angle steels 2.2, the horizontal angle steels 2.1, the vertical angle steels 2.2 and the diagonal angle steels 2.3 are combined to form a triangular stable structure, the horizontal angle steel 2.1 is installed on the building structure 1 and is fixed to the building structure 1 through expansion bolts.

[0026] The horizontal steel beam 3 is made of galvanized angle steel. Multiple horizontal steel beams 3 are arranged in a row. The horizontal steel beam 3 is fixedly connected to the vertical angle steel 2.2. The vertical angle steel 2.2 is provided with fixing bolts 4 at the bottom of the horizontal steel beam 3. The horizontal steel beam 3 is supported on the fixing bolts 4. The fixing bolts 4 are used to temporarily fix and position the horizontal steel beam 3 before the horizontal steel beam 3 is fixed, so as to ensure the installation accuracy and stability of the horizontal steel beam 3.

[0027] The upper end of the suspension rod 5 passes through the horizontal steel beam 3 and is fastened by nuts located on both sides of the horizontal steel beam 3 , and the lower end is connected to the suspension piece 6 .

[0028] The hanger 6 includes a vertical plate 6.1, an upper horizontal plate 6.2 fixed at one end of the vertical plate 6.1, a lower horizontal plate 6.3 fixed at the other end of the vertical plate 6.1, and a vertical plate 6.4 fixed on the lower horizontal plate 6.3 and parallel to the vertical plate 6.1, wherein the height of the vertical plate 6.4 is shorter than the vertical plate 6.1, so that a space for passing the main keel 10 can be formed between the vertical plate 6.4 and the upper horizontal plate 6.2, the lower end of the hanger 5 passes through the upper horizontal plate 6.2 and is locked by a double nut, the main keel 10 is placed in a U-shaped space enclosed by the vertical plate 6.1, the lower horizontal plate 6.3 and the vertical plate 6.4 and supported on the lower horizontal plate 6.3, and a limiting bolt 6.5 is connected between the vertical plate 6.1 and the vertical plate 6.4, and the limiting bolt 6.5 closes the U-shaped space and has a fixing effect on the main keel 10.

[0029] The secondary keel 7 is a groove-shaped structure, and the open ends of the secondary keel 7 are respectively formed with L-shaped clamping parts 7.1 bent toward the groove. The secondary keel 7 is connected to the main keel 10 through a hanger 8. The hanger 8 is a U-shaped structure and is buckled on the main keel 10. A clamping tooth 8.1 is formed at its open end. An installation space 8.2 is provided between the clamping tooth 8.1 and the hanger 8. The gypsum board 9 is fixed to the secondary keel 7 by screws.

[0030] The embodiments described above are merely descriptions of preferred implementation modes of the present invention, and are not intended to limit the scope of the present invention. Without departing from the design spirit of the present invention, various modifications and improvements made to the technical solutions of the present invention by ordinary technicians in this field should all fall within the protection scope determined by the claims of the present invention.

Claims

1. A high clearance gypsum board ceiling installation structure, characterized in that: The invention comprises a plurality of diagonal bracing systems, horizontal steel beams (3), suspension rods (5), suspension fittings (6), main keels (10), hanging fittings (8), secondary keels (7) and gypsum boards (9), each of which comprises a pair of diagonal bracing systems, wherein the diagonal bracing systems comprise a pair of diagonal bracings (2), and the diagonal bracings (2) comprise a horizontal angle steel (2.1) fixed to a building structure (1), a vertical angle steel (2.2) fixed to one end of the horizontal angle steel (2.1), and a vertical angle steel (2.3) connected to the horizontal angle steel ( 2.1) and the oblique angle steel (2.3) between the vertical angle steel (2.2); the horizontal steel beam (3) is fixed to the vertical angle steel (2.2); the suspension rod (5) is connected to the horizontal steel beam (3); one end of the suspension member (6) is connected to the suspension rod (5), and the other end is connected to the main keel (10); the secondary keel (7) is connected to the main keel (10) through the hanger (8); and the gypsum board (9) is connected to the secondary keel (7).

2. A high clearance gypsum board ceiling installation structure according to claim 1, characterized in that: The vertical angle steel (2.2) is provided with a fixing bolt (4) at the bottom of the horizontal steel beam (3), and the horizontal steel beam (3) is supported on the fixing bolt (4).

3. A high clearance gypsum board ceiling installation structure according to claim 1, characterized in that: The horizontal steel beam (3) is made of angle steel.

4. A high clearance gypsum board ceiling installation structure according to claim 3, characterized in that: The suspension rod (5) passes through the horizontal steel beam (3) and is fastened by nuts located on both sides of the horizontal steel beam (3).

5. The high clearance gypsum board ceiling installation structure according to claim 1, characterized in that: The hanging member (6) comprises a vertical plate member (6.1), an upper horizontal plate (6.2) is fixedly provided at one end of the vertical plate member (6.1), and a lower horizontal plate (6.3) is fixedly provided at the other end, a vertical plate (6.4) parallel to the vertical plate member (6.1) is fixedly provided on the lower horizontal plate (6.3), the hanging rod (5) is connected to the upper horizontal plate (6.2), the main keel (10) is placed in a U-shaped space enclosed by the vertical plate member (6.1), the lower horizontal plate (6.3) and the vertical plate (6.4) and supported on the lower horizontal plate (6.3), and a limiting bolt (6.5) is connected between the vertical plate member (6.1) and the vertical plate (6.4).

6. The high clearance gypsum board ceiling installation structure according to claim 1, characterized in that: The secondary keel (7) is a groove-shaped structure, and the opening ends of the secondary keel (7) are respectively formed with L-shaped clamping parts (7.1) bent toward the inside of the groove, and the hanging piece (8) is formed with clamping teeth (8.1) that can be buckled on the clamping parts (7.1).

7. A high clearance gypsum board ceiling installation structure according to claim 6, characterized in that: The hanging piece (8) is in a U-shaped structure and is buckled on the main keel (10). A latching tooth (8.1) is formed at the open end of the hanging piece. An installation space (8.2) is provided between the latching tooth (8.1) and the hanging piece (8).