Foundation pile
By designing structures such as screws, nut seats, side baffles and traction rods in the foundation piles, combined with the limit guidance of the slide and guide strips, the safety hazards of positioning the foundation piles and artificial straightening are solved, and the foundation piles are realized Stable vertical installation and efficient positioning.
Patent Information
- Application Number
- CN202420463071.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-11
- Publication Date
- 2024-12-10
- Estimated Expiration
- 2034-03-11
AI Technical Summary
The existing positioning foundation piles are prone to tilt during construction, which affects the positioning effect. There are safety hazards and poor results in manual assisted straightening.
A foundation pile is designed, including pile body, screw, nut seat, side baffle, pull rod, positioning ring and L-shaped rod. Through the rotation of the screw and the deflection of the pull rod, the limit guide of the slide and the guide bar are combined with the limit guide of the slide and guide bar. , ensure that the pile body is buried vertically in the soil to avoid tilting.
The stable vertical installation of foundation piles is achieved, which reduces the difficulty of breaking soil and construction risks, and improves the reliability and safety of positioning effects.
Smart Images

Figure CN222140009U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of foundation pile structures, in particular to a foundation pile used for building construction and water conservancy. Background Art
[0002] During the construction of building water conservancy, it is necessary to locate the building at the construction site. During the positioning process, the positioning pile is indispensable. However, the current positioning pile does not have a certain guiding structure on its surface during use, which causes the pile body to tilt easily during the process of being nailed into the ground, affecting the overall positioning effect. Or, it is easy to cause injuries to construction workers by using manual assistance to straighten the pile, and the effect is not good, which needs to be improved. To this end, we proposed a pile. Utility Model Content
[0003] The purpose of the utility model is to provide a foundation pile to overcome the technical problems existing in the prior art.
[0004] In order to achieve the above technical objectives and the above technical effects, the utility model provides the following technical solutions:
[0005] A foundation pile comprises a pile body, wherein the bottom of the pile body is connected to a pile tip, a accommodating cavity is arranged in the pile body, a screw is rotatably connected to the center of the accommodating cavity, a nut seat is symmetrically screwed on the outer wall of the screw, a through groove is opened around the cavity wall of the accommodating cavity, a side baffle is inserted in the through groove, a traction rod is hinged between the side baffle and the nut seat, a positioning ring is sleeved on the outside of the pile body, and an L-shaped rod is connected around the outer wall of the positioning ring.
[0006] Preferably, in a foundation pile, a stepped hole is provided on the top of the pile body, a screw is rotatably connected to the lower part of the stepped hole through a bearing, a hexagonal countersunk hole is provided on the upper end of the screw, a hexagonal steel rod is detachably inserted in the hexagonal countersunk hole, and an operating rod is connected to the upper end of the hexagonal steel rod.
[0007] Preferably, in a foundation pile, the inner wall of the positioning ring is connected with guide strips around, the outer wall of the pile body is provided with a slideway matched with the guide strip, and the position of the slideway is staggered with the through groove.
[0008] Preferably, in a foundation pile, the outer wall of the side baffle extending into the accommodating cavity is connected to a stopper, and the side baffle extending out of the accommodating cavity is provided with a tip structure.
[0009] Preferably, in a foundation pile, the length dimension of the upper end of the through groove from the upper end of the pile body is greater than the thickness dimension of the positioning ring.
[0010] Preferably, in a foundation pile, the threads of the upper and lower sections of the screw are arranged in opposite directions.
[0011] The beneficial effects of the utility model are:
[0012] The utility model discloses the pile body is convenient to install and can prevent the pile body from tilting, and the pile body is convenient to install and can be used for pile maintenance ... BRIEF DESCRIPTION OF THE DRAWINGS
[0013] In order to more clearly illustrate the technical solution of the present invention, the drawings required for use in the description of the specific implementation methods will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.
[0014] Figure 1 It is a schematic diagram of the overall structure of the utility model;
[0015] Figure 2 It is a schematic diagram of the internal structure of the pile body in the utility model;
[0016] Figure 3 It is a structural schematic diagram of the positioning ring in the utility model;
[0017] Figure 4 It is a structural schematic diagram of the side baffle in the utility model.
[0018] In the figure: 1, pile body; 2, pile tip; 3, accommodating cavity; 4, screw; 5, nut seat; 6, through groove; 7, side baffle; 8, traction rod; 9, positioning ring; 10, L-shaped rod; 11, stepped hole; 12, slideway; 41, hexagonal countersunk hole; 42, hexagonal steel rod; 43, operating rod; 71, block; 91, guide strip. DETAILED DESCRIPTION
[0019] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments of the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0020] See also Figure 1-4As shown, this embodiment is a foundation pile, including a pile body 1, a pile tip 2 is connected to the bottom of the pile body 1, a receiving chamber 3 is arranged in the pile body 1, a screw rod 4 is rotatably connected to the center of the receiving chamber 3, a nut seat 5 is symmetrically screwed on the upper and lower outer walls of the screw rod 4, a through groove 6 is opened around the cavity wall of the receiving chamber 3, a side baffle plate 7 is inserted in the through groove 6, a traction rod 8 is hinged between the side baffle plate 7 and the nut seat 5, a positioning ring 9 is sleeved on the outside of the pile body 1, and an L-shaped rod 10 is connected around the outer wall of the positioning ring 9.
[0021] A stepped hole 11 is provided at the top of the pile body 1, and the lower part of the stepped hole 11 is rotatably connected to the screw rod 4 through a bearing. A hexagonal countersunk hole 41 is provided at the upper end of the screw rod 4, and a hexagonal steel rod 42 is detachably inserted in the hexagonal countersunk hole 41. An operating rod 43 is connected to the upper end of the hexagonal steel rod 42 to facilitate the control of the rotation of the screw rod 4.
[0022] The inner wall of the positioning ring 9 is connected with guide strips 91 around it, and the outer wall of the pile body 1 is provided with a slideway 12 matched with the guide strips 91. The slideway 12 is staggered with the through groove 6 to ensure that the pile body 1 extends vertically into the soil.
[0023] The outer wall of the side baffle plate 7 extending into the accommodating cavity 3 is connected with a stopper 71, and the side baffle plate 7 extending out of the accommodating cavity 3 is provided with a tip structure to facilitate extending into the soil layer.
[0024] The length dimension of the upper end of the through groove 6 from the upper end of the pile body 1 is greater than the thickness dimension of the positioning ring 9 to avoid interference with the extension of the side baffle 7.
[0025] The upper and lower threads of the screw rod 4 are arranged in opposite directions, and the two nut seats 5 can move closer after rotation.
[0026] The specific implementation of the utility model is:
[0027] When the device is in use, the vertical end of the L-shaped rod 10 is extended into the soil surface so that the positioning ring 9 remains horizontal, and the pile body 1 is extended into the soil along the opening of the positioning ring 9. The pile tip 2 is used to reduce the difficulty of breaking the ground. The slideway 12 is used in conjunction with the guide strip 91 for limiting guidance to ensure that the pile body 1 can be buried vertically downward in the soil. When the upper end of the pile body 1 is flush with the upper end of the positioning ring 9, the hexagonal steel rod 42 is extended into the hexagonal countersunk hole 41 along the stepped hole 11, and the hexagonal steel rod 42 is driven to rotate by the operating rod 43. After the screw rod 4 rotates synchronously, the two nut seats 5 move closer, and after the upper and lower sets of traction rods 8 are deflected, the side baffle plate 7 extends out of the pile body 1 along the through groove 6. The end of the side baffle plate 7 adopts a pointed end structure, which is convenient for extending into the surrounding soil layer, which can further prevent the pile body 1 from tilting and ensure the use effect. After the foundation pile installation is completed, the hexagonal steel rod 42 and the positioning ring 9 can be removed.
[0028] In the description of this specification, the description with reference to the terms "one embodiment", "example", "specific example", etc. means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the utility model. In this specification, the schematic representation of the above terms does not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described can be combined in any one or more embodiments or examples in a suitable manner.
[0029] The preferred embodiments of the utility model disclosed above are only used to help explain the utility model. The preferred embodiments do not describe all the details in detail, nor do they limit the utility model to the specific implementation methods described. Obviously, many modifications and changes can be made according to the content of this specification. This specification selects and specifically describes these embodiments in order to better explain the principles and practical applications of the utility model, so that technicians in the relevant technical field can well understand and use the utility model. The utility model is limited only by the claims and their full scope and equivalents.
Claims
1. A pile foundation, comprising a pile body (1), Features: The bottom of the pile body (1) is connected to a pile tip (2), a receiving cavity (3) is provided in the pile body (1), a screw rod (4) is rotatably connected to the center of the receiving cavity (3), a nut seat (5) is symmetrically screwed to the outer wall of the screw rod (4) in upper and lower directions, a through groove (6) is provided around the cavity wall of the receiving cavity (3), a side baffle plate (7) is inserted into the through groove (6), a traction rod (8) is hinged between the side baffle plate (7) and the nut seat (5), a positioning ring (9) is sleeved on the outside of the pile body (1), and an L-shaped rod (10) is connected to the outer wall of the positioning ring (9).
2. A foundation pile according to claim 1, Features: The top of the pile body (1) is provided with a stepped hole (11), the lower part of the stepped hole (11) is rotatably connected to a screw rod (4) via a bearing, the upper end of the screw rod (4) is provided with a hexagonal countersunk hole (41), a hexagonal steel rod (42) is detachably inserted into the hexagonal countersunk hole (41), and the upper end of the hexagonal steel rod (42) is connected to an operating rod (43).
3. A foundation pile according to claim 1, Features: The inner wall of the positioning ring (9) is connected with guide strips (91) all around, and the outer wall of the pile body (1) is provided with a slideway (12) matched with the guide strip (91), and the position of the slideway (12) is staggered with the through groove (6).
4. A foundation pile according to claim 1, Features: The outer wall of the side baffle (7) extending into the accommodating cavity (3) is connected to a stopper (71), and the side baffle (7) extending out of the accommodating cavity (3) is provided with a tip structure.
5. A foundation pile according to claim 1, Features: The length dimension of the upper end of the through groove (6) from the upper end of the pile body (1) is greater than the thickness dimension of the positioning ring (9).
6. A foundation pile according to claim 1, Features: The upper and lower sections of the screw (4) are arranged with threads having opposite rotation directions.