By designing the slide chute and screw mechanism to support the concrete pipe, and adjusting the hook position with the lifting and clamping rods, the problems of easy breakage and poor length adaptability of concrete pipes in the prior art are solved, and the safety and cost-effectiveness are improved .

CN222181526UActive Publication Date: 2024-12-17SHENZHEN LUBODE ENG CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420768933.4
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-04-15
Publication Date
2024-12-17
Estimated Expiration
2034-04-15

AI Technical Summary

Technical Problem

The existing concrete pipe spreaders cannot prevent concrete pipes from breaking and cannot adapt to concrete pipe lifting of different lengths, resulting in safety hazards and high usage costs.

Method used

A municipal rainwater pipeline reinforced concrete pipe sling was designed, which uses a chute and a screw mechanism to support the concrete pipe. Combined with the lifting mechanism and the connecting rod, the hook position can be adjusted to prevent the concrete pipe from breaking and adapting to pipes of different lengths.

Benefits of technology

It effectively prevents concrete pipes from breaking, improves safety, reduces usage costs, improves the applicability of spreaders, and allows for flexibly lifting concrete pipes of different lengths.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222181526U_ABST
    Figure CN222181526U_ABST
Patent Text Reader

Abstract

The utility model discloses a reinforced concrete pipe lifting appliance for municipal rainwater pipelines, which is applied to the field of municipal engineering and comprises a fixing column. The crank is rotated to drive the first screw to rotate, the first screw rotates to drive the sliding block to relatively move along the sliding groove, the sliding block moves to drive the fixing rod to move, the fixing rod moves to drive the telescopic rod to move, the telescopic rod moves to drive the supporting rod to move, and the supporting rod moves to support the concrete pipe. The purpose of preventing the concrete pipe from being broken can be achieved, damage to the concrete pipe is avoided, safety is improved, a pull block is moved, the pull block moves to drive a clamping rod to move, the clamping rod is disengaged from a clamping hole, then a sliding barrel is moved to the needed position, the pull block is loosened, the clamping rod is clamped with the clamping hole under the action of a spring, and the concrete pipe is prevented from being broken. The purpose of hoisting concrete pipes with different lengths can be achieved in a mode of fixing the sliding cylinder, so that the use cost is reduced, and the applicability of the hoisting tool is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the field of municipal engineering, in particular to a reinforced concrete pipe hanger for a municipal rainwater pipeline. Background Art

[0002] The government drainage pipeline is composed of multiple sections of large-diameter reinforced concrete pipes buried deep underground. During the construction process, a crane is used to lift the concrete pipes to the installation location section by section. The most important thing for lifting concrete pipes with a crane is a concrete pipe lifter.

[0003] At present, a Chinese utility model with a publication number of CN214456149U discloses a municipal rainwater pipeline reinforced concrete pipe hanger, including a hanger steel plate, a first hanger steel plate is arranged at the bottom of the hanger steel plate, the hanger steel plate and the first hanger steel plate are an integrated structure, a pipe clamping groove is formed at the position between the first hanger steel plate and the hanger steel plate, a first hanging hole is arranged at the position near the upper left corner of the hanger steel plate surface, a second hanging hole is arranged at the position near the upper right corner of the hanger steel plate surface, and a plurality of wire clamping devices are arranged at the rear end surface of the hanger steel plate; the device is simple and convenient to operate when hanging concrete pipes, and can reduce damage to the concrete pipe mouth, which is convenient for recycling between different construction sites. The device greatly reduces the utilization rate of labor and increases work efficiency. The device has low cost, high efficiency, reduces cost, can be recycled, and has a simple manufacturing process (only one person is needed to operate the pipe hanger).

[0004] The existing concrete pipe hoists do not have the function of preventing the concrete pipe from breaking. Generally, the hoists are used to hoist the two ends of the concrete pipe. If the concrete pipe is long, the middle part of the concrete pipe will be subjected to greater force under the action of gravity during hoisting, and it is easy to break, causing losses and posing safety hazards. Concrete pipes of different lengths cannot be hoisted. Generally, hoists can only hoist concrete pipes of fixed lengths. If you want to hoist concrete pipes of different lengths, you need to replace the corresponding hoists, which is very troublesome and increases the cost of use. The applicability is low. In order to solve the above-mentioned problems, we propose a municipal rainwater pipeline reinforced concrete pipe hoist. Utility Model Content

[0005] The utility model aims to provide a municipal rainwater pipeline reinforced concrete pipe hanger, which has the advantages of preventing the concrete pipe from breaking and being able to hang concrete pipes of different lengths.

[0006] The above-mentioned technical objective of the utility model is achieved through the following technical scheme: a municipal rainwater pipeline reinforced concrete pipe hanger, comprising a fixed column, a sliding groove is opened at the bottom of the fixed column, a sliding block is slidably connected inside the sliding groove, the inner wall of the sliding block is threadedly connected with a first screw, and both ends of the first screw are rotatably connected to the inner wall of the sliding groove, a lifting mechanism is arranged at the bottom of the sliding block, a supporting rod is bolted to the bottom of the lifting mechanism, a supporting column is bolted to the surface of the fixed column, a sliding cylinder is slidably sleeved on the surface of the supporting column, a clamping rod is slidably sleeved on the inner wall of the sliding cylinder, a limiting plate is fixed on the surface of the clamping rod, a spring is arranged between the limiting plate and the inner wall of the sliding cylinder, a clamping hole is opened on the surface of the supporting column, and the clamping hole is clamped with the clamping rod, and a hook is bolted to the bottom of the sliding cylinder.

[0007] By adopting the above technical scheme, by turning the crank, the crank rotation drives the first screw rod to rotate, the first screw rotation drives the slider to move relatively along the slide groove, the movement of the slider drives the fixed rod to move, the movement of the fixed rod drives the telescopic rod to move, the movement of the telescopic rod drives the supporting rod to move, and the support rod moves to support the concrete pipe in a way that can prevent the concrete pipe from breaking, avoids damage to the concrete pipe, and improves safety. By moving the pull block, the movement of the pull block drives the connecting rod to move, so that the connecting rod and the connecting hole are disengaged, and then the slide cylinder is moved to the required position, the pull block is released, and the connecting rod is connected to the connecting hole under the action of the spring. The slide cylinder is fixed in a way that can achieve the purpose of hoisting concrete pipes of different lengths, reduces the cost of use, and improves the applicability of the hoist.

[0008] The utility model is further configured as follows: the lifting mechanism includes a fixed rod, a telescopic rod is slidably sleeved inside the fixed rod, and the bottom of the telescopic rod is bolted to one end of the supporting rod, a fixing hole is opened on the surface of the telescopic rod, a second screw rod is slidably sleeved between the fixing hole and the inner wall of the fixed rod, and a nut is threadedly connected to the surface of the second screw rod.

[0009] By adopting the above technical solution and providing an adjustment mechanism, the position of the support rod can be adjusted, which is convenient for use.

[0010] The utility model is further configured as follows: a lifting ring is bolted on the surface of the fixing column.

[0011] By adopting the above technical solution and setting the lifting ring, it is easy to lift.

[0012] The utility model is further configured as follows: scale lines are bolted on the surface of the support column.

[0013] By adopting the above technical solution, the position of the hook can be easily adjusted by setting scale lines.

[0014] The utility model is further configured as follows: a crank is bolted on the surface of the first screw rod.

[0015] By adopting the above technical solution, the first screw rod can be easily rotated by providing a crank.

[0016] The utility model is further configured as follows: one end of the support column is bolted to a limiting head.

[0017] By adopting the above technical solution, the slide tube is prevented from slipping by setting a limit head.

[0018] The utility model is further configured as follows: a rubber pad is bolted on the surface of the hook.

[0019] By adopting the above technical solution, the concrete pipe is protected by arranging a rubber pad.

[0020] The utility model is further configured as follows: a pull block is bolted on the top of the clamping rod.

[0021] By adopting the above technical solution and arranging the pulling block, it is convenient to move the clamping rod.

[0022] In summary, the utility model has the following beneficial effects:

[0023] 1. The utility model rotates the crank, the crank drives the first screw to rotate, the first screw drives the slider to move relatively along the slide slot, the slider moves to drive the fixed rod to move, the fixed rod moves to drive the telescopic rod to move, the telescopic rod moves to drive the support rod to move, the support rod moves to support the concrete pipe, so as to prevent the concrete pipe from breaking, avoid damage to the concrete pipe, and improve safety;

[0024] 2. The utility model moves the pulling block, and the movement of the pulling block drives the clamping rod to move, so that the clamping rod and the clamping hole are disengaged, and then the slide tube is moved to the required position, and the pulling block is released. The clamping rod is clamped with the clamping hole under the action of the spring, and the slide tube is fixed in this way, which can achieve the purpose of hoisting concrete pipes of different lengths, reduce the use cost, and improve the applicability of the hoist. BRIEF DESCRIPTION OF THE DRAWINGS

[0025] Figure 1 It is a three-dimensional diagram of the structure of the utility model;

[0026] Figure 2 It is a cross-sectional view of the structure of the utility model;

[0027] Figure 3 It is a side sectional view of the structure of the utility model;

[0028] Figure 4 This utility model Figure 2 A magnified view of the structure in the middle.

[0029] Figure numerals: 1. fixed column; 2. slide groove; 3. slider; 4. first screw rod; 5. lifting mechanism; 6. support rod; 7. support column; 8. slide cylinder; 9. clamping rod; 10. limit plate; 11. spring; 12. clamping hole; 13. hook; 14. fixed rod; 15. telescopic rod; 16. fixed hole; 17. second screw rod; 18. nut; 19. lifting ring; 20. scale line; 21. crank; 22. limit head; 23. rubber pad; 24. pull block. DETAILED DESCRIPTION

[0030] The utility model is further described in detail below in conjunction with the accompanying drawings.

[0031] Embodiment 1:

[0032] refer to Figure 1 , Figure 2 and Figure 3 A municipal rainwater pipeline reinforced concrete pipe hanger includes a fixed column 1, a slide groove 2 is opened at the bottom of the fixed column 1, a slider 3 is slidably connected inside the slide groove 2, the inner wall of the slider 3 is threadedly connected with a first screw rod 4, and both ends of the first screw rod 4 are rotatably connected to the inner wall of the slide groove 2, a lifting mechanism 5 is arranged at the bottom of the slider 3, and a supporting rod 6 is bolted at the bottom of the lifting mechanism 5. By turning the crank 21, the crank 21 rotates to drive the first screw rod 4 to rotate, and the first screw 4 rotates to drive the slider 3 to move relatively along the slide groove 2, the movement of the slider 3 drives the fixed rod 14 to move, the movement of the fixed rod 14 drives the telescopic rod 15 to move, and the movement of the telescopic rod 15 drives the supporting rod 6 to move. The way in which the supporting rod 6 moves to support the concrete pipe can achieve the purpose of preventing the concrete pipe from breaking, avoids damage to the concrete pipe, and improves safety.

[0033] refer to Figure 3 The lifting mechanism 5 includes a fixed rod 14, a telescopic rod 15 is slidably sleeved inside the fixed rod 14, and the bottom of the telescopic rod 15 is bolted to one end of the supporting rod 6. A fixing hole 16 is opened on the surface of the telescopic rod 15, and a second screw rod 17 is slidably sleeved between the fixing hole 16 and the inner wall of the fixed rod 14. A nut 18 is threadedly connected to the surface of the second screw rod 17. By setting an adjustment mechanism, the position of the supporting rod 6 can be adjusted for easy use.

[0034] refer to Figure 1 , Figure 2 and Figure 3 A lifting ring 19 is bolted on the surface of the fixed column 1, and the lifting ring 19 is provided to facilitate lifting.

[0035] refer to Figure 1 and Figure 3 A crank 21 is bolted to the surface of the first screw rod 4. The crank 21 is provided to facilitate the rotation of the first screw rod 4.

[0036] Embodiment 2:

[0037] refer to Figure 1 , Figure 2 and Figure 4 The surface of the fixed column 1 is bolted with a supporting column 7, and a sliding cylinder 8 is slidably sleeved on the surface of the supporting column 7. A clamping rod 9 is slidably sleeved on the inner wall of the sliding cylinder 8. The surface of the clamping rod 9 is fixedly sleeved with a limiting plate 10, and a spring 11 is arranged between the limiting plate 10 and the inner wall of the sliding cylinder 8. A clamping hole 12 is opened on the surface of the supporting column 7, and the clamping hole 12 is clamped with the clamping rod 9. A hook 13 is bolted on the bottom of the sliding cylinder 8. By moving the pull block 24, the pull block 24 moves to drive the clamping rod 9 to move, so that the clamping rod 9 is disengaged from the clamping hole 12, and then the sliding cylinder 8 is moved to the required position, and the pull block 24 is released. The clamping rod 9 is clamped with the clamping hole 12 under the action of the spring 11. The way of fixing the sliding cylinder 8 can achieve the purpose of hoisting concrete pipes of different lengths, reduce the cost of use, and improve the applicability of the sling.

[0038] refer to Figure 1 The surface of the support column 7 is bolted with scale lines 20, and the position of the hook 13 is easily adjusted by setting the scale lines 20.

[0039] refer to Figure 1 and Figure 2 One end of the support column 7 is bolted to a limit head 22, and the limit head 22 is provided to prevent the slide tube 8 from slipping.

[0040] refer to Figure 1 , Figure 2 and Figure 3 A rubber pad 23 is bolted to the surface of the hook 13, and the rubber pad 23 is provided to protect the concrete pipe.

[0041] refer to Figure 1 and Figure 4 A pull block 24 is bolted to the top of the clamping rod 9. By setting the pull block 24, it is convenient to move the clamping rod 9.

[0042] A brief description of the usage process: turn the crank 21, the crank 21 drives the first screw 4 to rotate, the first screw 4 drives the slider 3 to move relatively along the slide slot 2, the slider 3 moves and drives the fixed rod 14 to move, the fixed rod 14 moves and drives the telescopic rod 15 to move, the telescopic rod 15 moves and drives the support rod 6 to move, the support rod 6 moves to support the concrete pipe, which can achieve the purpose of preventing the concrete pipe from breaking, move the pull block 24, the pull block 24 moves and drives the clamping rod 9 to move, so that the clamping rod 9 and the clamping hole 12 are disengaged, and then the slide 8 is moved to the required position, release the pull block 24, the clamping rod 9 is clamped with the clamping hole 12 under the action of the spring 11, and the slide 8 is fixed, which can achieve the purpose of hoisting concrete pipes of different lengths.

[0043] This specific embodiment is merely an explanation of the present invention and is not a limitation of the present invention. After reading this specification, those skilled in the art may make non-creative modifications to the present embodiment as needed, but such modifications are protected by patent law as long as they are within the scope of the claims of the present invention.

Claims

1. A reinforced concrete pipe hanger for a municipal rainwater pipeline, comprising a fixing column (1), characterized in that: The bottom of the fixed column (1) is provided with a slide groove (2), the interior of the slide groove (2) is slidably connected with a slider (3), the inner wall of the slider (3) is threadedly connected with a first screw rod (4), and both ends of the first screw rod (4) are rotatably connected to the inner wall of the slide groove (2), a lifting mechanism (5) is provided at the bottom of the slider (3), a supporting rod (6) is bolted to the bottom of the lifting mechanism (5), a supporting column (7) is bolted to the surface of the fixed column (1), and the A slide cylinder (8) is slidably sleeved on the surface of the support column (7), a clamping rod (9) is slidably sleeved on the inner wall of the slide cylinder (8), a limit plate (10) is fixedly sleeved on the surface of the clamping rod (9), a spring (11) is arranged between the limit plate (10) and the inner wall of the slide cylinder (8), a clamping hole (12) is opened on the surface of the support column (7), and the clamping hole (12) is clamped with the clamping rod (9), and a hook (13) is bolted to the bottom of the slide cylinder (8).

2. A municipal rainwater pipeline reinforced concrete pipe hanger according to claim 1, characterized in that: The lifting mechanism (5) comprises a fixed rod (14), a telescopic rod (15) is slidably sleeved inside the fixed rod (14), and the bottom of the telescopic rod (15) is bolted to one end of the supporting rod (6), a fixing hole (16) is opened on the surface of the telescopic rod (15), a second screw rod (17) is slidably sleeved between the fixing hole (16) and the inner wall of the fixed rod (14), and a nut (18) is threadedly connected to the surface of the second screw rod (17).

3. A municipal rainwater pipeline reinforced concrete pipe hanger according to claim 1, characterized in that: A lifting ring (19) is bolted to the surface of the fixing column (1).

4. A municipal rainwater pipeline reinforced concrete pipe hanger according to claim 1, characterized in that: The surface of the support column (7) is bolted with scale lines (20).

5. A municipal rainwater pipeline reinforced concrete pipe hanger according to claim 1, characterized in that: A crank (21) is bolted to the surface of the first screw rod (4).

6. A municipal rainwater pipeline reinforced concrete pipe hanger according to claim 1, characterized in that: One end of the support column (7) is bolted to a limit head (22).

7. A municipal rainwater pipeline reinforced concrete pipe hanger according to claim 1, characterized in that: A rubber pad (23) is bolted to the surface of the hook (13).

8. A municipal rainwater pipeline reinforced concrete pipe hanger according to claim 1, characterized in that: A pull block (24) is bolted to the top of the clamping rod (9).