Large-diameter pile wall combined excavation-free anchorage foundation pile foundation steel bar machining jig frame

By designing a large diameter pile wall combination without excavation anchor foundation pile foundation steel tread processing frame, the fast separation of steel cages is achieved using handles, handwheels and articulated structures, the problem of separation of steel cages in the existing technology is solved, and the problem of separation of steel cages is reduced. The labor intensity of workers and the construction efficiency is improved.

CN222332672UActive Publication Date: 2025-01-10GUANGXI CONSTR ENG CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420965920.6
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-05-07
Publication Date
2025-01-10
Estimated Expiration
2034-05-07

AI Technical Summary

Technical Problem

The existing general steel bar processing tire frames are difficult to quickly separate after the steel cage is tied, which increases the labor intensity and construction difficulty of workers.

Method used

A large diameter pile wall combination excavation-free anchoring foundation pile foundation steel steel frame is designed, including bottom pipe assembly, bottom support pipe, side pipe assembly and top hanging plate, and the steel cage is realized through handles, handwheels and articulated structures. The rapid separation reduces the need for workers to split point by point.

Benefits of technology

The rapid separation and lifting of steel cages have been achieved, which reduces the labor intensity of workers and improves construction efficiency and environmental protection effects.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222332672U_ABST
    Figure CN222332672U_ABST
Patent Text Reader

Abstract

The utility model discloses a large-diameter pile wall combined excavation-free anchorage foundation pile foundation reinforcing steel bar processing jig frame, which relates to the technical field of bridge engineering, and comprises a bottom mounting pipe, a pair of bottom supporting pipes, a side mounting pipe and a top hanging plate, a row of bottom mounting plates are welded on the bottom mounting pipe at intervals, and the bottom supporting pipes are welded on the upper sides of the bottom mounting plates in parallel. A pair of first lug plates are welded to the middles of the upper sides of the bottom mounting plates at the two ends, a pair of side mounting pipes are arranged and correspondingly hinged to the first lug plates on the two sides, a plurality of side supporting plates are welded to the inner sides of the side mounting pipes, second lug plates are welded to the outer sides of the side mounting pipes, first hinge seats are hinged to the second lug plates, and side supporting pipes are rotationally connected to the first hinge seats. Second hinge seats are symmetrically mounted on the front side and the rear side of the bottom mounting pipe, third lug plates are hinged to the second hinge seats, side supporting rods are perpendicularly welded to the side faces of the third lug plates, and the side supporting pipes and the side supporting rods located on the same side are in threaded connection. According to the utility model, the rapid dismounting work can be realized through the deflectable side supporting pipes and the detachable top hanging plate.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of bridge engineering, in particular to a large-diameter pile-wall combination excavation-free anchor foundation pile foundation steel bar processing tire frame. Background Art

[0002] The anchor is the main load-bearing component of the suspension bridge, and plays a decisive role in the overall stability and bearing performance of the suspension bridge. At present, the anchor foundation of large domestic suspension bridges generally uses caisson foundation or underground continuous wall foundation. The construction excavation volume is large and has a great impact on the environment.

[0003] The Xunjiang Bridge project of Cangrong Expressway crosses the waters of Xunjiang River, and the surrounding environmental and water conservation requirements are high. During the construction period, it is necessary to minimize the damage to the surrounding environment and strengthen the protection of the surrounding environment. The project crosses the Xunjiang River, and the north and south banks are managed by different counties. The access roads to the anchors on both sides must pass through local villages. The roads along the river on both sides are under construction, and their construction will cause great interference to the construction of the bridge. Therefore, the anchor foundation of the Xunjiang Bridge of Cangrong Expressway adopts a wall foundation of large-diameter pile foundation + milling groove. The foundation structure is novel, and the excavation of the anchor foundation soil is reduced. It has the characteristics of reducing environmental damage, reducing construction difficulty, reducing project cost, and shortening construction period.

[0004] Through the construction experience summary of the milling trench of the Xunjiang Bridge project of Cangrong Expressway, a large-diameter trenchless trench reinforcement construction and connection method was formed. During the construction of the reinforcement cage, the long-line method was adopted, and the special hoist was used to lift and lower it, and the large-diameter trenchless trench reinforcement cage was lowered with special homemade tools. This method serves as a reference for the subsequent large-diameter pile foundation + milling trench wall foundation milling trench reinforcement construction.

[0005] Then, after the existing general steel bar processing frame is used to tie the steel bar cage in the project, it is very inconvenient to separate the steel bar cage from the steel bar processing frame, and workers are required to split it point by point, which increases the labor intensity of the workers. Utility Model Content

[0006] The utility model aims to provide a large-diameter pile-wall combination excavation-free anchor foundation pile foundation reinforcement processing tire frame to solve the above-mentioned defects caused by the prior art.

[0007] The cam is secured to the bottom of the base and is provided with a plurality of flange adapters, the flange adapters being provided with a plurality of flange adapters, the flange adapters being provided with a plurality of flange adapters, the flange adapters being provided with a plurality of flange adapters and the flange adapters being provided with a plurality of flange adapters.

[0008] Preferably, a positioning pin is inserted at the top end of the side-mounted tube, and a U-shaped positioning groove is provided at the lower end of the connecting tube.

[0009] Preferably, a hand wheel is fixedly connected to the lower end of the side support tube.

[0010] Preferably, a C-shaped handle is welded on the side of the connecting pipe.

[0011] Compared with the prior art, the utility model has the following advantages:

[0012] When the steel cage is tied, first lift the top hanging plate with the help of the handle and quickly separate the top layer of steel bars from the top hanging groove, then use the hand wheel to rotate the side support tube and shorten the exposed length of the side support rod, thereby driving the side mounting tube to deflect outward around the ear plate, and quickly separate the steel bars on the left and right sides from the corresponding side support plates, finally lift the steel cage with the lifting equipment and quickly separate the bottom layer of steel bars from the bottom support plate, avoiding the workers from splitting them point by point and reducing the workers' labor intensity. BRIEF DESCRIPTION OF THE DRAWINGS

[0013] Figure 1 It is a schematic structural diagram of the utility model as a whole viewed from the front.

[0014] Figure 2 It is a schematic diagram of the overall three-dimensional structure of the utility model.

[0015] Figure 3 It is a schematic diagram of the structure of the partial explosion of the utility model.

[0016] in:

[0017] 10- bottom-mounted pipe; 11- bottom-mounted plate; 12- bottom-mounted tube; 13- ear plate one; 14- side-mounted pipe; 15- side support plate; 16- ear plate two; 17- positioning pin; 18- hinged seat one; 19- side support pipe; 20- handwheel; 21- hinged seat two; 22- ear plate three; 23- side support rod; 24- connecting pipe; 24a- positioning groove; 25- top hanging plate; 25a- top hanging groove; 26- handle; 30- steel bar. DETAILED DESCRIPTION

[0018] In order to make the technical means, creative features, objectives and effects achieved by the present invention easy to understand, the present invention is further described below in conjunction with specific implementation methods.

[0019] like Figures 1 to 3 As shown, a large-diameter pile-wall combination excavation-free anchor foundation pile foundation reinforcement processing tire frame includes a bottom-mounted pipe 10, a bottom tube 12, a side-mounted pipe 14 and a top hanging plate 25. The bottom-mounted pipe 10 is horizontally fixed on the ground, and a row of bottom-mounted plates 11 are welded at intervals on the upper side of the bottom-mounted pipe 10. The bottom tube 12 is provided with a pair of and parallel welded to the upper side of the row of bottom-mounted plates 11, and a pair of ear plates 13 are welded in the middle of the upper side of the bottom-mounted plates 11 at both ends. The side-mounted pipe 14 is provided with a pair of and correspondingly hinged to the ear plates 13 on both sides, and a plurality of side support plates 15 are welded at intervals on the inner side of the side-mounted pipe 14. An ear plate 2 16 is welded in the center of the outer side of the side-mounted tube 14, an articulated seat 18 is hinged on the ear plate 2 16, and a side support tube 19 is rotatably connected to the articulated seat 18, an articulated seat 21 is symmetrically installed on the front and rear sides of the bottom-mounted tube 10, and an ear plate 3 22 is hinged on the articulated seat 21, a side support rod 23 is vertically welded to the side of the ear plate 3 22, an internal thread is provided on the inner wall of the side support tube 19, and an external thread is provided on the outer wall of the side support rod 23, the side support tube 19 and the side support rod 23 on the same side are threadedly connected, and a pair of connecting tubes 24 are welded at both ends of the top hanging plate 25.

[0020] In this embodiment, a positioning pin 17 is inserted at the top of the side-mounted pipe 14, and a U-shaped positioning groove 24a is provided at the lower end of the connecting pipe 24. The cooperation between the positioning pin 17 and the positioning groove 24a facilitates positioning the top hanging plate 25 between the side-mounted pipes 14 on the left and right sides.

[0021] In this embodiment, a hand wheel 20 is fixedly connected to the lower end of the side support tube 19. The hand wheel 20 is convenient for rotating the side support tube 19, thereby conveniently driving the side mounting tube 14 to deflect.

[0022] In this embodiment, a C-shaped handle 26 is welded to the side of the connecting pipe 24. The handle 26 facilitates lifting or lowering the top hanging plate 25.

[0023] In this embodiment, the steel bars on the upper and lower sides of the steel cage are distributed in a straight line, and the steel bars on the left and right sides are distributed in a curve.

[0024] The working principle of this large diameter pile wall combination excavation-free anchor foundation pile foundation reinforcement processing tire frame:

[0025] The bottom layer of steel bars 30 are placed on the upper side of the bottom support tube 12 at intervals, the left and right sides of the steel bars 30 are placed on the side support plates 15 respectively, and the top layer of steel bars 30 are placed in the top hanging grooves 25 a on the top hanging plate 25 respectively.

[0026] When the steel cage is tied, first lift the top hanging plate 25 with the help of the handle 26 to quickly separate the top layer of steel bars 30 from the top hanging groove 25a, then use the hand wheel 20 to rotate the side support tube 19 and shorten the exposed length of the side support rod 23, thereby driving the side mounting tube 14 to deflect outward around the ear plate 13, and quickly separate the steel bars 30 on the left and right sides from the corresponding side support plates 15, finally lift the steel cage through the lifting equipment and quickly separate the bottom layer of steel bars 30 from the bottom support plate 12.

[0027] Therefore, the embodiments disclosed above are only illustrative in all aspects and are not exclusive. All changes within the scope of the present invention or within the scope equivalent to the present invention are included in the present invention.

Claims

1. A large diameter pile-wall combination excavation-free anchor foundation pile foundation reinforcement processing tire frame, characterized in that: The invention comprises a bottom-mounted pipe (10), a bottom-mounted tube (12), a side-mounted pipe (14) and a top hanging plate (25), wherein the bottom-mounted pipe (10) is horizontally fixed on the ground, and a row of bottom-mounted plates (11) are welded at intervals on the upper side of the bottom-mounted pipe (10), the bottom-mounted tube (12) is provided with a pair of bottom-mounted plates (11) welded in parallel to the upper side of the row of bottom-mounted plates (11), and a pair of ear plates (13) are welded in the middle of the upper side of the bottom-mounted plates (11) at both ends, the side-mounted pipe (14) is provided with a pair of ear plates (13) hinged to the two sides, and a plurality of side support plates (15) are welded at intervals on the inner side of the side-mounted pipe (14). ), an ear plate 2 (16) is welded in the center of the outer side of the side-mounted tube (14), an articulated seat 1 (18) is hinged on the ear plate 2 (16), and a side support tube (19) is rotatably connected to the articulated seat 1 (18), an articulated seat 2 (21) is symmetrically installed on the front and rear sides of the bottom-mounted tube (10), and an ear plate 3 (22) is hinged on the articulated seat 2 (21), a side support rod (23) is vertically welded on the side of the ear plate 3 (22), and the side support tube (19) and the side support rod (23) on the same side are threadedly connected, and a pair of connecting tubes (24) are welded at both ends of the top hanging plate (25).

2. The large-diameter pile-wall combination trenchless anchor foundation reinforcement processing tire frame according to claim 1 is characterized by: A positioning pin (17) is inserted into the top end of the side-mounted tube (14), and a U-shaped positioning groove (24a) is provided at the lower end of the connecting tube (24).

3. The large-diameter pile-wall combination trenchless anchor foundation reinforcement processing tire frame according to claim 1 is characterized by: A hand wheel (20) is fixedly connected to the lower end of the side support tube (19).

4. The large-diameter pile-wall combination trenchless anchor foundation reinforcement processing tire frame according to claim 1 is characterized by: A C-shaped handle (26) is welded to the side of the connecting pipe (24).