Drainage structure applied to planted roof

By setting up a water circulation system and drainage pipe at the bottom of the planting roof, combined with waterproof sealing paste and isolation layer, the problems of poor drainage and leakage of traditional planting roofs are solved, and the drainage effect with stable structure and convenient construction is achieved.

CN222362691UActive Publication Date: 2025-01-17GUANGDONG XIANGSHUN CONSTR ENG CO LTD
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202421039065.2
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-05-13
Publication Date
2025-01-17
Estimated Expiration
2034-05-13

AI Technical Summary

Technical Problem

The drainage structure of traditional planted roofs has poor stability, making it difficult to ensure that there is no leakage within the service period, resulting in poor drainage.

Method used

A structure including water circulation system, masonry, drainage pipes, drainage plates and filter layers was designed. By setting drainage ditches and drainage pipes at the bottom of the planting roof, waterproof sealing paste and isolation layer prevent leakage, and through hole-mounted covers Plates and angle iron enable rapid discharge and collection of rainwater.

Benefits of technology

It achieves smooth drainage of the planted roof, prevents long-term accumulation and leakage of rainwater, has a simple structure, convenient construction, and has the advantages of prefabricated production and convenient installation.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222362691U_ABST
    Figure CN222362691U_ABST
Patent Text Reader

Abstract

The utility model discloses a drainage structure applied to a planting roof. The drainage structure comprises a structural layer, a water circulation system arranged on the structural layer, brickworks piled on the two sides of the water circulation system, and drainage pipes embedded in the bottoms of the brickworks. The drainage pipes are communicated with the two sides of the masonry; planting soil is filled in the pits on the side surfaces of the masonry, and plants are planted on the surface of the planting soil. The brickworks are piled on the two sides of the water circulation system to form the drainage ditches, redundant rainwater in planting soil is drained into the drainage ditches through the drainage pipes and collected by the water circulation system, and a unified structure of planting and drainage is formed. The drainage structure is arranged at the bottom of the planting roof, the planting roof and the drainage structure are connected through the built decorative surface, and the planting roof has the advantages of being simple in structure, convenient to construct, capable of being shaped and prefabricated in advance, stable and reliable.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to a drainage structure, in particular to a drainage structure applied to a planting roof. Background Art

[0002] With the development of cities, urban greening issues have attracted more and more attention. As a new type of greening method, green roofs can not only beautify cities, but also protect the environment, save energy and reduce emissions.

[0003] Green roofs can effectively isolate outdoor natural factors such as high temperature, low temperature, wind, rain, etc., improve the insulation performance of houses, and extend the life of houses. Therefore, they are widely used in the construction industry. However, with traditional construction methods, the structural stability of green roofs is poor, and it is difficult to ensure that there will be no leakage during the service life. Therefore, there is a need for a drainage structure that can ensure smooth drainage of green roofs to prevent blockage and leakage. Utility Model Content

[0004] The utility model aims to solve the problems of poor drainage and leakage of existing planting roofs, and to provide a drainage structure for planting roofs which is simple in structure, convenient in construction, stable and reliable.

[0005] The purpose of the utility model can be achieved by adopting the following technical solutions:

[0006] A drainage structure for a planted roof comprises a structural layer, a water circulation system arranged on the structural layer, masonry stacked on both sides of the water circulation system, and a drainage pipe buried at the bottom of the masonry; the drainage pipe is connected to both sides of the masonry; the pit on the side of the masonry is filled with planting soil, and plants are planted on the surface of the planting soil.

[0007] As a preferred solution, the upper ends of the masonry on both sides of the water circulation system are provided with cover plates with holes for rainwater to flow into the drainage ditch.

[0008] As a preferred solution, the water circulation system is arranged on the structural layer through a waterproof sealing paste.

[0009] As a preferred solution, a drainage board is provided at the outer bottom of the masonry body, and the drainage board is provided on the upper part of the drainage pipe.

[0010] As a preferred solution, an isolation layer is provided between the drainage board and the planting soil.

[0011] As a preferred solution, graded stones are provided between the drainage board and the planting soil.

[0012] As a preferred solution, a filter layer is provided at one end of the drainage pipe which is identical to the outer side of the masonry body.

[0013] As a preferred solution, an angle iron is fixed to the upper end of the masonry, and the cover plate with holes can be opened or closed on the angle iron.

[0014] As a preferred solution, the angle iron is fixed to the upper end of the masonry through steel bars.

[0015] The implementation of this utility model has the following beneficial effects:

[0016] The utility model piles masonry on both sides of the water circulation system to form a drainage ditch, so that excess rainwater in the planting soil is discharged into the drainage ditch through the drainage pipe and collected by the water circulation system, forming a unified system of planting and drainage. By setting a drainage structure at the bottom of the planting roof, the two are connected through the masonry decorative surface, which has the advantages of simple structure, convenient construction, prefabrication and convenient on-site installation and construction. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] In order to more clearly illustrate the embodiments of the utility model or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the utility model. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0018] Figure 1 The utility model is a structural schematic diagram of a drainage structure applied to a planting roof.

[0019] Figure 2 It is a structural schematic diagram of the utility model using spaced-distributed masonry on the same side of a water circulation system of a drainage structure of a planting roof. DETAILED DESCRIPTION

[0020] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0021] Example

[0022] Reference Figure 1 and Figure 2The present embodiment relates to a drainage structure applied to a green roof, including a structural layer 1, a water circulation system 2 arranged on the structural layer 1, masonry 3 stacked on both sides of the water circulation system 2, and a drainage pipe 4 buried at the bottom of the masonry 3; the drainage pipe 4 is connected to both sides of the masonry 3; the pit on the side of the masonry 3 is filled with planting soil 5, and plants are planted on the surface of the planting soil 5.

[0023] The structure piles up masonry 3 on both sides of the water circulation system 2 to form a drainage ditch 23, so that excess rainwater in the planting soil 5 is discharged into the drainage ditch 23 through the drainage pipe 4 and is collected by the water circulation system 2, thereby preventing the problem of excessive rainwater in the planting soil 5 remaining for a long time and causing leakage.

[0024] The upper ends of the masonry 3 on both sides of the water circulation system 2 are provided with perforated covers 6 for rainwater to flow into the gutter. Rainwater can flow into the gutter through the perforated covers 6 and be collected by the water circulation system 2, thereby preventing excessive rainwater from accumulating on the upper surface of the plants, allowing the rainwater to be quickly discharged to prevent leakage problems.

[0025] The water circulation system 2 is arranged on the structural layer 1 through the waterproof sealing paste 7 to prevent rainwater in the drainage ditch from leaking through the gap between the water circulation system 2 and the structural layer 1.

[0026] A drainage board 8 is provided at the outer bottom of the masonry 3, and the drainage board 8 is provided on the upper part of the drainage pipe 4. The drainage board 8 is used to receive excess rainwater in the planting soil 5, so that the rainwater is collected by the drainage board 8 and discharged into the drainage ditch 23 through the drainage pipe 4, and recycled by the water circulation system 2.

[0027] An isolation layer 9 is provided between the drainage board 8 and the planting soil 5. The isolation layer 9 serves to prevent the root system from damaging the structure and to protect the roof layer.

[0028] A graded stone 10 is provided between the drainage board 8 and the planting soil 5. The graded stone 10 has good water permeability, which can make rainwater flow onto the drainage board 8 more easily, thereby better collecting excess rainwater in the planting soil 5.

[0029] One end of the drain pipe 4 which is the same as the outer side of the masonry 3 is provided with a filter layer 11. The filter layer 11 can prevent the drain pipe 4 from being blocked by mud.

[0030] An angle iron 12 is fixed to the upper end of the masonry 3, and the cover plate 6 with holes can be opened or covered on the angle iron 12. A plurality of angle irons 12 form a wellhead, and the cover plate 6 with holes can be opened or covered on the wellhead. The cover plate 6 with holes can be a grate.

[0031] The angle iron 12 is fixed to the upper end of the masonry 3 through the steel bar 13. One end of the steel bar 13 is embedded in the upper end of the masonry 3, and the other end is connected to the angle iron 12, so that the angle iron 12 is fixed to the masonry 3.

[0032] The construction process of this utility model is as follows:

[0033] Before the construction of the planted roof, the water circulation system 2 is constructed according to the characteristics of the site. First, the building structure layer 100 is completed, and then the water circulation system 2 is waterproofed and sealed with a waterproof sealant. When installing the embedded drain pipe 4, the drainage board 8 is first installed on the upper part of the drain pipe 4 to receive excess rainwater so that the rainwater can be recycled. After the water circulation system 2 itself is waterproofed, the masonry 3 is built on both sides, and the drain pipe 4 is embedded; after reaching the height of the masonry, the masonry is stopped, and then the masonry structure is waterproofed; graded stones 10 are added at the contact surface with the planting soil 5 for drainage treatment, and an isolation layer 9 is added for differentiation and isolation; the filter layer 11 is used for filtration, and after the treatment is completed, it is connected with the embedded drain pipe 4 to realize the collection of rainwater. The built drainage ditch 23 has pre-embedded angle irons 12 and steel bars 13 on the top, and is connected to the upper capping material 16 with concrete 14 and cement mortar 15; after the entire structure is completed, the decorative surface can be constructed, and finally the planting soil 5 is piled and leveled; after the construction is completed, the vegetation can be planted.

[0034] The above disclosure is only a preferred embodiment of the present invention, and certainly cannot be used to limit the scope of rights of the present invention. Therefore, equivalent changes made according to the claims of the present invention are still within the scope covered by the present invention.

Claims

1. A drainage structure applied to a planted roof, characterized in that: It includes a structural layer, a water circulation system arranged on the structural layer, masonry stacked on both sides of the water circulation system, and a drainage pipe buried at the bottom of the masonry; the drainage pipe is connected with both sides of the masonry; the pit on the side of the masonry is filled with planting soil, and plants are planted on the surface of the planting soil.

2. The drainage structure applied to a green roof according to claim 1, characterized in that: The upper ends of the masonry on both sides of the water circulation system are provided with perforated covers for rainwater to flow into the drainage ditch.

3. The drainage structure applied to a green roof according to claim 1, characterized in that: The water circulation system is arranged on the structural layer through a waterproof sealing paste.

4. The drainage structure applied to a green roof according to claim 1, characterized in that: A drainage board is arranged at the outer bottom of the masonry body, and the drainage board is arranged on the upper part of the drainage pipe.

5. The drainage structure applied to a green roof according to claim 4, characterized in that: An isolation layer is provided between the drainage board and the planting soil.

6. The drainage structure applied to a green roof according to claim 5, characterized in that: Graded stones are arranged between the drainage board and the planting soil.

7. The drainage structure applied to a green roof according to claim 1, characterized in that: A filter layer is provided at one end of the drain pipe which is identical to the outer side of the masonry.

8. The drainage structure applied to a green roof according to claim 2, characterized in that: An angle iron is fixed on the upper end of the masonry body, and the cover plate with holes can be opened or closed on the angle iron.

9. The drainage structure applied to a green roof according to claim 8, characterized in that: The angle iron is fixed to the upper end of the masonry through steel bars.

Citation Information

Cited By

  • A landscape drainage system for a planted roof

    CN224834203U