Water conservancy project construction channel side wall supporting device

By designing a water conservancy engineering construction device including a base plate, a push rod, a mounting plate, a support plate and a first screw, the problem of angle adjustment in the prior art is solved, and flexible support for the side walls of channels with different inclined angles is achieved. , improves the practicality of the device.

CN222477362UActive Publication Date: 2025-02-14HUNAN WATER & ELECTRICITY GATE CONSTR ENG
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202421261479.X
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-06-04
Publication Date
2025-02-14
Estimated Expiration
2034-06-04

AI Technical Summary

Technical Problem

During the construction of existing water conservancy projects, the fixing of concrete formwork makes it difficult to adjust the angle and cannot effectively support the channel side walls of different inclination angles.

Method used

Design a device including a base plate, an electric push rod, a mounting plate, a support plate and a first screw. By rotating the first screw, adjusting the angle of the support plate, combining the sliding cooperation between the electric push rod and the mounting plate, the channel side wall is realized. Flexible support.

Benefits of technology

The support ability of the support plate to the side walls of the channel with different inclination angles is improved, the practicality of the device is enhanced, and the problem of angle adjustment in the prior art is solved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222477362U_ABST
    Figure CN222477362U_ABST
Patent Text Reader

Abstract

The utility model belongs to the technical field of hydraulic engineering construction, and particularly relates to a hydraulic engineering construction channel side wall supporting device which comprises a bottom plate. A plurality of electric push rods are fixedly connected to the side wall of the bottom plate; the electric push rods are uniformly distributed on the side wall of the bottom plate and have the same structure; the end part of the electric push rod is fixedly connected with a mounting plate; by rotating a first screw rod, an ejector rod can push a sliding block to slide in a guide rail, a connecting arm can be driven to move, so that the angle of the connecting arm can be adjusted, an electric push rod can push a mounting plate to move, supporting plates on the two sides get close to and apply pressure to the side wall of a channel, and the defects that an existing supporting device is usually fixedly arranged and cannot be used for supporting the channel are overcome. The angle of the supporting plate is adjusted by rotating the first screw rod, so that the supporting angle of the supporting plate is inconvenient to adjust, the supporting effect on the side walls of the channels with different inclination angles is difficult, at the moment, the angle of the supporting plate is adjusted by rotating the first screw rod, the supporting effect of the supporting plate on the side walls of the channels with different inclination angles is achieved, and the practicability of the supporting plate is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model belongs to the technical field of water conservancy project construction, in particular to a channel side wall supporting device for water conservancy project construction. Background Art

[0002] A water conservancy project refers to a project built to control and allocate natural surface water and groundwater to achieve the purpose of eliminating harm and promoting benefits. It is also called a water project. It involves many aspects such as flood control, drainage, irrigation, power generation, water supply, and water resource protection.

[0003] In the prior art, water conservancy project construction involves opening channels for irrigation and water supply operations. After the opening is completed, the channel side walls also need to be supported, mainly by installing concrete formwork on the channel side walls to reduce damage caused by scouring of the channel side walls by water flow.

[0004] However, in the prior art, in the process of supporting the channel side walls by concrete formwork, it was found that since the concrete formwork is usually fixed, it is difficult to adjust the angle of the concrete formwork when supporting the channel side walls, which makes it difficult to support the channel side walls at different angles. Therefore, a channel side wall support device for water conservancy project construction is proposed to address the above problem. Utility Model Content

[0005] In order to make up for the deficiencies of the prior art and solve at least one technical problem raised in the background technology, the utility model proposes a channel side wall support device for water conservancy project construction.

[0006] The technical solution adopted by the utility model to solve its technical problems is as follows: a side wall support device for a water conservancy project construction channel described in the utility model comprises a bottom plate; a plurality of electric push rods are fixedly connected to the side wall of the bottom plate; the electric push rods are evenly distributed on the side wall of the bottom plate and have the same structure; a mounting plate is fixedly connected to the end of the electric push rod; the mounting plate and the bottom plate are in sliding cooperation; a support plate is hingedly connected to the side wall of the mounting plate; a bracket is fixedly connected to the side wall of the mounting plate; a first screw is threadedly connected to the side wall of the bracket; the first screw penetrates the bracket wall and is threadedly connected thereto; a pair of push rods are symmetrically hinged to the end of the first screw; a pair of guide rails are fixedly connected to the side wall of the mounting plate; the guide rails are symmetrically arranged on both sides of the mounting plate and have the same structure; a slider is slidably connected to the inner side wall of the guide rail; the push rod and the slider are in a hinged relationship; the side wall of the slider is hingedly connected to a connecting arm; the connecting arm is in a hinged relationship with the support plate; at this time, the angle of the support plate is adjusted by rotating the first screw, so as to play a supporting role of the support plate on the channel side wall with different inclination angles, thereby improving the practicality of the support plate.

[0007] Preferably, a plurality of universal wheels are evenly fixed to the bottom of the base plate; a pair of fixed plates are provided on the side walls of the base plate; the fixed plates are symmetrically arranged on both sides of the base plate and have the same structure; a second screw is threadedly connected to the side walls of the fixed plate; the second screw penetrates the fixed plate wall body and is threadedly connected thereto; an extrusion plate is rotatably connected to the end of the second screw; a plurality of barbs are evenly fixed to the side walls of the extrusion plate; at this time, the universal wheels are arranged, thereby facilitating the movement and adjustment of the base plate, and the barbs can also fix the base plate after the movement is completed.

[0008] Preferably, the side walls of the bottom plate are provided with a pair of slide grooves; the slide grooves are symmetrically arranged on both sides of the bottom plate and have the same structure; the side walls of the slide grooves are slidably connected to plug blocks; the side walls of the plug blocks are fixedly connected to rubber pads; the plug blocks are fixedly connected to the fixed plate; the side walls of the bottom plate are rotatably connected to a pair of first spring rods; the first spring rods are symmetrically arranged on both sides of the bottom plate and have the same structure; the ends of the first spring rods are fixedly connected to plug rods; the side walls of the plug blocks are provided with slots; at this time, the plug blocks are fixed by inserting them into the slide grooves, thereby facilitating the disassembly and maintenance of the second screw rod, and at the same time, the rubber pads can play a pre-fixing role when fixing the plug blocks, reducing the possibility of the plug blocks slipping out of the side walls of the slide grooves.

[0009] Preferably, a pair of through holes are symmetrically provided on the side wall of the guide rail; a pair of second spring rods are fixedly connected to the side wall of the slider; the second spring rods are symmetrically arranged on both sides of the slider and have the same structure; a scraper is fixedly connected to the end of the second spring rod; at this time, the dirt is scraped off by the scraper, thereby cleaning the dirt attached to the guide rail, improving the smoothness of the sliding between the guide rail and the slider, and at the same time, the second spring rod can increase the sufficient contact between the scraper and the guide rail, thereby improving the cleaning effect.

[0010] Preferably, the scraper side wall is evenly fixed with multiple cleaning brushes; the cleaning brush side wall is fixed with a connecting rod; the connecting rod passes through the cleaning brush wall body and is fixed thereto; at this time, the cleaning brush is provided to further increase the cleaning effect of the dirt attached to the inner wall of the guide rail, and the cleaning effect of the cleaning brush during cleaning can be improved by the connecting rod.

[0011] Preferably, the side walls of the fixed plate are hinged with a pair of clamping blocks; the clamping blocks are symmetrically arranged on both sides of the fixed plate and have the same structure; the side walls of the bottom plate are evenly provided with a plurality of clamping slots; the positions of the clamping blocks correspond to the positions of the clamping slots; at this time, the clamping blocks are clamped into the side walls of the clamping slots, thereby further increasing the fixing effect of the plug in the slide slot.

[0012] Preferably, a buckle plate is fixedly connected to the side wall of the card block; the buckle plate is arranged in an arc shape; at this time, the buckle plate is arranged to facilitate the card block to be pulled open.

[0013] Beneficial effects of the utility model:

[0014] 1. The utility model provides a channel side wall support device for water conservancy project construction. By setting a first screw rod and a sliding block, the existing support device is usually fixed, which makes it inconvenient to adjust the supported angle, thereby making it difficult to support the channel side walls with different inclination angles. At this time, the angle of the support plate is adjusted by rotating the first screw rod, so that the support plate can support the channel side walls with different inclination angles, thereby improving the practicality of the support plate.

[0015] 2. The utility model provides a channel side wall support device for water conservancy project construction. By setting universal wheels and barbs, it can reduce the inconvenience of moving the bottom plate due to its certain weight, which makes the process of adjusting the position of the bottom plate more cumbersome for the staff. At this time, the universal wheels are set to facilitate the movement and adjustment of the bottom plate, and the barbs can fix the bottom plate after the movement is completed. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] The drawings described herein are used to provide a further understanding of the present invention and constitute a part of the present application. The exemplary embodiments of the present invention and their descriptions are used to explain the present invention and do not constitute an improper limitation on the present invention. In the drawings:

[0017] Figure 1 It is a three-dimensional diagram of the utility model;

[0018] Figure 2 yes Figure 1 A partial enlarged view of the middle part;

[0019] Figure 3 It is a three-dimensional diagram of the guide rail in the utility model;

[0020] Figure 4 It is a three-dimensional diagram of the scraper in the utility model;

[0021] Figure 5 It is a three-dimensional diagram of the cleaning brush in the utility model.

[0022] Legend:

[0023] 1. Bottom plate; 11. Electric push rod; 12. Mounting plate; 13. Support plate; 14. Bracket; 15. First screw rod; 16. Push rod; 17. Guide rail; 18. Slider; 19. Connecting arm; 2. Universal wheel; 21. Fixing plate; 22. Second screw rod; 23. Extrusion plate; 24. Barb; 3. Slide groove; 31. Insert block; 32. Rubber pad; 33. First spring rod; 34. Insert rod; 35. Slot; 4. Through hole; 41. Second spring rod; 42. Scraper; 5. Cleaning brush; 51. Connecting rod; 6. Block; 61. Slot; 7. Buckle plate. DETAILED DESCRIPTION

[0024] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments of the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0025] Specific examples are given below.

[0026] See also Figure 1-Figure 5 The utility model provides a side wall support device for a water conservancy project construction channel, comprising a bottom plate 1; a plurality of electric push rods 11 are fixedly connected to the side wall of the bottom plate 1; the electric push rods 11 are evenly distributed on the side wall of the bottom plate 1 and have the same structure; a mounting plate 12 is fixedly connected to the end of the electric push rod 11; the mounting plate 12 and the bottom plate 1 are in sliding fit; a support plate 13 is hingedly connected to the side wall of the mounting plate 12; a bracket 14 is fixedly connected to the side wall of the mounting plate 12; a first screw 15 is threadedly connected to the side wall of the bracket 14 ; The first screw rod 15 passes through the wall of the bracket 14 and is threadedly connected thereto; a pair of push rods 16 are symmetrically hinged at the ends of the first screw rod 15; a pair of guide rails 17 are fixedly connected to the side walls of the mounting plate 12; the guide rails 17 are symmetrically arranged on both sides of the mounting plate 12 and have the same structure; a slider 18 is slidably connected to the inner side wall of the guide rail 17; the push rod 16 and the slider 18 are in an articulated relationship; a connecting arm 19 is hinged to the side wall of the slider 18; the connecting arm 19 is in an articulated relationship with the support plate 13; When in use, the staff puts the bottom plate 1 into the channel, and then holds and rotates the first screw 15. By rotating the first screw 15, the top rod 16 can push the slider 18 to slide in the guide rail 17. At this time, the sliding of the slider 18 can drive the connecting arm 19 to move, and a certain force is applied to the support plate 13 through the connecting arm 19, so that its angle can be adjusted. When the adjustment is completed, by starting the electric push rod 11, the electric push rod 11 can push the mounting plate 12 to move, so that the support plates 13 on both sides approach and press on the channel side walls, thereby supporting the channel side walls. In this process, the existing support device is usually fixed, which makes it inconvenient to adjust the angle it supports, thereby making it difficult to support the channel side walls with different inclination angles. At this time, the angle of the support plate 13 is adjusted by rotating the first screw 15, so that the support plate 13 plays a supporting role on the channel side walls with different inclination angles, thereby improving the practicality of the support plate 13.

[0027] Further, such as Figure 1 , Figure 2As shown, a plurality of universal wheels 2 are evenly fixed to the bottom of the bottom plate 1; a pair of fixing plates 21 are provided on the side walls of the bottom plate 1; the fixing plates 21 are symmetrically arranged on both sides of the bottom plate 1 and have the same structure; a second screw 22 is threadedly connected to the side wall of the fixing plate 21; the second screw 22 penetrates the wall of the fixing plate 21 and is threadedly connected thereto; an extrusion plate 23 is rotatably connected to the end of the second screw 22; a plurality of barbs 24 are evenly fixed to the side wall of the extrusion plate 23; when in use, the bottom plate 1 is pushed by a staff member to make the universal wheel 2 roll in the channel to adjust the position of the bottom plate 1, and when the adjustment is completed, the staff member The operator holds and rotates the second screw 22, and the second screw 22 can push the extrusion plate 23 down to make it close to the ground. At this time, the extrusion plate 23 applies pressure to the barb 24, which can make the barb 24 insert into the soil and fix the bottom plate 1 to reduce the rolling of the universal wheel 2. In this process, the bottom plate 1 can be reduced. Due to the certain weight of the bottom plate 1, it is inconvenient to move it, which makes the process of adjusting the position of the bottom plate 1 more cumbersome for the operator. At this time, the universal wheel 2 is set, which makes it convenient to move and adjust the bottom plate 1. At the same time, the barb 24 can fix the bottom plate 1 after the movement is completed.

[0028] Further, such as Figure 2 As shown, the side wall of the bottom plate 1 is provided with a pair of slide grooves 3; the slide grooves 3 are symmetrically arranged on both sides of the bottom plate 1 and have the same structure; the side wall of the slide groove 3 is slidably connected with an insert block 31; the side wall of the insert block 31 is fixedly connected with a rubber pad 32; the insert block 31 is fixedly connected to the fixed plate 21; the side wall of the bottom plate 1 is rotatably connected with a pair of first spring rods 33; the first spring rods 33 are symmetrically arranged on both sides of the bottom plate 1 and have the same structure; the end of the first spring rod 33 is fixedly connected with an insert rod 34; the side wall of the insert block 31 is provided with a slot 35; when in use, the staff holds the fixed plate 21 and inserts the insert block 31 into the slide groove 3. At this time, a certain friction force will be generated due to the contact between the rubber pad 32 and the slide groove 3, so that the insert block 31 is pre-fixed, and then The staff will hold and rotate the insertion rod 34, and when the insertion rod 34 is rotated to the position corresponding to the slot 35, by loosening the insertion rod 34, a certain reaction force will be applied under the elastic force of the first spring rod 33, so that the insertion rod 34 is inserted into the slot 35, and the insertion block 31 is fixed, thereby completing the installation of the fixing plate 21. In this process, the second screw rod 22 can be reduced to be inconvenient to disassemble and replace when rusted after long-term use, thereby increasing a certain amount of workload. At this time, the insertion block 31 is inserted into the slide groove 3 to fix it, thereby facilitating the disassembly and maintenance of the second screw 22. At the same time, the rubber pad 32 can play a pre-fixing role when fixing the insertion block 31, reducing the possibility of the insertion block 31 sliding out of the side wall of the slide groove 3.

[0029] Further, such as Figure 4 , Figure 5 As shown, the side wall of the guide rail 17 is symmetrically provided with a pair of through holes 4; the side wall of the slider 18 is fixedly connected with a pair of second spring rods 41; the second spring rods 41 are symmetrically arranged on both sides of the slider 18 and have the same structure; the end of the second spring rod 41 is fixedly connected with a scraper 42; when in use, when the slider 18 slides in the guide rail 17, the dirt attached to the inner wall of the guide rail 17 can be scraped off by the contact between the scraper 42 and the inner wall of the guide rail 17, and then pushed out to the outside through the through hole 4, and at the same time, the contact between the scraper 42 and the guide rail 17 will cause a certain amount of wear on the scraper 42, so that the distance between the two is increased, and at this time, the scraper 42 is pushed out to the outside through the through hole 4. The elastic force of the second spring rod 41 will push the scraper 42 so that the scraper 42 is in full contact with the inner wall of the guide rail 17. In this process, the guide rail 17 can be reduced to be easily attached to the inner wall after long-term use, which makes it difficult to clean it, thereby causing a certain impact on the sliding effect between the guide rail 17 and the slider 18. At this time, the scraper 42 is used to scrape off the dirt, thereby playing a cleaning role on the dirt attached to the guide rail 17, improving the smoothness of the sliding between the guide rail 17 and the slider 18. At the same time, the second spring rod 41 can increase the full contact between the scraper 42 and the guide rail 17, thereby improving the cleaning effect.

[0030] Further, such as Figure 5 As shown, a plurality of cleaning brushes 5 are evenly fixedly connected to the side wall of the scraper 42; a connecting rod 51 is fixedly connected to the side wall of the cleaning brush 5; the connecting rod 51 passes through the wall of the cleaning brush 5 and is fixedly connected thereto; when in use, while the scraper 42 is used to scrape off the dirt, the cleaning brush 5 can be used to clean the position after the scraper 42 has scraped off the remaining dirt, and in the process of cleaning by the cleaning brush 5, a plurality of cleaning brushes 5 can be fixedly connected by the connecting rod 51 so that they are concentrated together during cleaning. In this process, the poor cleaning effect of the scraper 42 can be reduced, resulting in some dirt still remaining on the inner wall of the guide rail 17 after the scraper 42 has scraped, which will have a certain impact on the sliding effect of the guide rail 17 and the slider 18. At this time, the cleaning brush 5 is provided to further increase the cleaning effect of the dirt attached to the inner wall of the guide rail 17, and the cleaning effect of the cleaning brush 5 during cleaning can be improved by the connecting rod 51.

[0031] Further, such as Figure 2As shown, a pair of blocks 6 are hinged on the side wall of the fixing plate 21; the blocks 6 are symmetrically arranged on both sides of the fixing plate 21 and have the same structure; a plurality of slots 61 are evenly opened on the side wall of the bottom plate 1; the blocks 6 correspond to the positions of the slots 61; when in use, the block 6 is first held and pulled by the staff, and when the block 6 is pulled open, the insertion block 31 is then fixed, and finally the block 6 corresponds to the position of the slot 61. At this time, the block 6 is released, and it will automatically reset under the action of the internal torsion spring at the hinge of the block 6, so that it is stuck in the side wall of the slot 61. In this process, it can reduce the risk of foreign objects accidentally pulling the insertion rod 34, causing the insertion rod 34 to easily slide out of the side wall of the slot 35, thereby affecting the fixing effect of the insertion block 31 to a certain extent. At this time, the block 6 is stuck in the side wall of the slot 61, thereby further increasing the fixing effect of the insertion block 31 in the slide groove 3.

[0032] Further, such as Figure 2 As shown, the side wall of the card block 6 is fixedly connected with a buckle plate 7; the buckle plate 7 is arranged in an arc shape; when in use, the staff puts the finger on the side wall of the buckle plate 7, and the finger can be hooked under the arc effect of the buckle plate 7, and then a certain force is applied to the buckle plate 7 to pull the card block 6 open. In this process, it can reduce the inconvenience of the staff in holding the card block 6, which makes it easy for the staff to slip off the side wall when pulling. At this time, the buckle plate 7 is set, which makes it convenient to pull the card block 6 open.

[0033] Working principle: When in use, the staff puts the bottom plate 1 into the channel, and then holds and rotates the first screw 15. By rotating the first screw 15, the top rod 16 can push the slider 18 to slide in the guide rail 17. At this time, the sliding of the slider 18 can drive the connecting arm 19 to move, and a certain force is applied to the support plate 13 through the connecting arm 19, so that its angle can be adjusted. When the adjustment is completed, the electric push rod 11 is started, and the electric push rod 11 can push the mounting plate 12 to move, so that the support plates 13 on both sides approach and press on the side walls of the channel, so as to support the side walls of the channel. When in use, the staff pushes the bottom plate 1 to make the universal wheel 2 roll in the channel to push the bottom plate 1 is adjusted. When the adjustment is completed, the staff holds and rotates the second screw rod 22, and the second screw rod 22 can push the extrusion plate 23 down to make it close to the ground. At this time, the extrusion plate 23 applies pressure to the barb 24, which can be inserted into the soil to fix the bottom plate 1 to reduce the rolling of the universal wheel 2. When in use, the staff holds the fixing plate 21 and inserts the plug block 31 into the slide groove 3. At this time, a certain friction force will be generated due to the contact between the rubber pad 32 and the slide groove 3, so as to pre-fix the plug block 31. Then, the staff holds and rotates the insertion rod 34. When the insertion rod 34 is rotated to the position corresponding to the slot 35, the insertion rod 34 is released under the elastic force of the first spring rod 33. The scraper 42 is pressed against the guide rail 17 to remove dirt from the guide rail 17, and the dirt is then removed from the guide rail 17 through the cleaning brush 5. The position scraped by the scraper 42 is cleaned to sweep away the remaining dirt, and during the cleaning process of the cleaning brush 5, multiple cleaning brushes 5 can be fixedly connected by the connecting rod 51 so that they can be concentrated together during cleaning. When in use, the staff first holds and pulls the block 6, and when the block 6 is pulled open, the plug block 31 is then fixed, and finally the block 6 will correspond to the position of the slot 61. At this time, the block 6 is released, and it will automatically reset under the action of the internal torsion spring at the hinge of the block 6, so that it is stuck in the side wall of the slot 61. When in use, the staff places their fingers on the side wall of the buckle plate 7, and the fingers can be hooked under the arc action of the buckle plate 7, and then a certain force is applied to the buckle plate 7 to pull the block 6 open.

[0034] The above shows and describes the basic principle, main features and advantages of the utility model. Those skilled in the art should understand that the utility model is not limited by the above embodiments, and the above embodiments and descriptions are only for explaining the principle of the utility model. Without departing from the spirit and scope of the utility model, the utility model may have various changes and improvements, and these changes and improvements fall within the scope of the utility model to be protected.

Claims

1. A channel side wall support device for water conservancy project construction, comprising a bottom plate (1); characterized in that: The side wall of the bottom plate (1) is fixedly connected to a plurality of electric push rods (11); the electric push rods (11) are evenly distributed on the side wall of the bottom plate (1) and have the same structure; the end of the electric push rod (11) is fixedly connected to a mounting plate (12); the mounting plate (12) and the bottom plate (1) are in sliding fit; the side wall of the mounting plate (12) is hingedly connected to a support plate (13); the side wall of the mounting plate (12) is fixedly connected to a bracket (14); the side wall of the bracket (14) is threadedly connected to a first screw rod (15); the first screw rod (15) passes through the bracket (14) ) wall and is threadedly connected thereto; a pair of push rods (16) are symmetrically hinged at the ends of the first screw rod (15); a pair of guide rails (17) are fixedly connected to the side walls of the mounting plate (12); the guide rails (17) are symmetrically arranged on both sides of the mounting plate (12) and have the same structure; a slider (18) is slidably connected to the inner wall of the guide rail (17); the push rod (16) and the slider (18) are in an articulated relationship; the side wall of the slider (18) is hinged with a connecting arm (19); the connecting arm (19) and the support plate (13) are in an articulated relationship.

2. A channel side wall support device for water conservancy project construction as claimed in claim 1, characterized in that: The bottom of the base plate (1) is evenly fixed with a plurality of universal wheels (2); the side walls of the base plate (1) are provided with a pair of fixing plates (21); the fixing plates (21) are symmetrically arranged on both sides of the base plate (1) and have the same structure; the side walls of the fixing plates (21) are threadedly connected with a second screw rod (22); the second screw rod (22) penetrates the wall of the fixing plate (21) and is threadedly connected thereto; the end of the second screw rod (22) is rotatably connected with an extrusion plate (23); the side walls of the extrusion plate (23) are evenly fixed with a plurality of barbs (24).

3. A channel side wall support device for water conservancy project construction as claimed in claim 2, characterized in that: The side wall of the bottom plate (1) is provided with a pair of slide grooves (3); the slide grooves (3) are symmetrically arranged on both sides of the bottom plate (1) and have the same structure; the side wall of the slide groove (3) is slidably connected with an insert block (31); the side wall of the insert block (31) is fixedly connected with a rubber pad (32); the insert block (31) and the fixed plate (21) are in a fixed relationship; the side wall of the bottom plate (1) is rotatably connected with a pair of first spring rods (33); the first spring rods (33) are symmetrically arranged on both sides of the bottom plate (1) and have the same structure; the end of the first spring rod (33) is fixedly connected with an insert rod (34); the side wall of the insert block (31) is provided with a slot (35).

4. A channel side wall support device for water conservancy project construction as claimed in claim 1, characterized in that: A pair of through holes (4) are symmetrically formed on the side wall of the guide rail (17); a pair of second spring rods (41) are fixedly connected to the side wall of the slider (18); the second spring rods (41) are symmetrically arranged on both sides of the slider (18) and have the same structure; and a scraper (42) is fixedly connected to the end of the second spring rod (41).

5. A channel side wall support device for water conservancy project construction as claimed in claim 4, characterized in that: A plurality of cleaning brushes (5) are evenly fixedly connected to the side wall of the scraper (42); a connecting rod (51) is fixedly connected to the side wall of the cleaning brush (5); and the connecting rod (51) penetrates the wall of the cleaning brush (5) and is fixedly connected thereto.

6. A channel side wall support device for water conservancy project construction as claimed in claim 2, characterized in that: A pair of clamping blocks (6) are hingedly connected to the side wall of the fixing plate (21); the clamping blocks (6) are symmetrically arranged on both sides of the fixing plate (21) and have the same structure; a plurality of clamping grooves (61) are evenly arranged on the side wall of the bottom plate (1); and the positions of the clamping blocks (6) and the clamping grooves (61) correspond to each other.

7. A channel side wall support device for water conservancy project construction as claimed in claim 6, characterized in that: A gusset plate (7) is fixedly connected to the side wall of the clamping block (6); the gusset plate (7) is arranged in an arc shape.

Citation Information

Cited By

  • Groove excavation supporting device for water conservancy and hydropower construction

    CN120311716A